Risk Management in Contracting and Tendering at a Support Foundation
Alexandre Gomes de Macedo; Gabriela Fernanda Mandro
DOI: 10.22167/2675-6528-202600489
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Risk management has consolidated itself as an essential tool for strengthening governance and administrative efficiency in organizational contexts. This study aimed to identify, describe, and analyze the main risks associated with the purchasing and contracting processes in a support foundation linked to a federal university, and to propose treatment measures to mitigate them. The research was characterized as applied, with a qualitative approach and descriptive nature, developed through a case study. For data collection, techniques of bibliographic research, documentary analysis, process observation, and brainstorming meetings with a focus group of involved professionals were used. Risk analysis was based on the methodology of the Comptroller General of the Union, evaluating probability, impact, and control effectiveness. The results showed relevant risks of an operational, regulatory, and organizational nature, highlighting failures in document preparation, inconsistencies in quotations, absence of internal regulations, and limitations in knowledge management. After proposing treatment measures, a significant reduction in risk criticality levels was observed. It was found that the application of risk management contributes to the improvement of contracting processes, promoting greater control, efficiency, and legal certainty. The study offers practical subsidies for the improvement of management in support foundations and organizations with similar characteristics.
Keywords: Internal control; Administrative efficiency; Organizational governance; Bidding.
1. Introduction
Risk management has established itself as a fundamental pillar for strengthening governance and promoting administrative efficiency in various organizational contexts. Within the scope of Public Administration, the relevance of this topic is accentuated by the complexity of purchases and contracts. These procedures, governed by legal frameworks such as Law No. 14.133/2021 (Brazil, 2021), are designed to ensure the selection of the most advantageous proposal, adherence to the public interest, and the promotion of sustainable national development. However, the inherent nature of these operations exposes organizations to a constant range of uncertainties, both of internal and external origin, demanding the continuous improvement of process management and analysis tools.
In the contemporary organizational scenario, risk management plays a crucial role in supporting the integrity and quality of decision-making processes. The Comptroller General of the Union [CGU] (2021) emphasizes that the planning and actions necessary for risk management, formalized in a Risk Management Plan, are essential. Such practices aim at the proactive identification of vulnerabilities and the implementation of preventive measures, thus contributing to the strengthening of institutional governance. This systematic approach is vital for public entities and their supporting foundations to navigate complex regulatory environments, minimizing exposures and optimizing resource allocation.
The concept of risk, as outlined by the Project Management Institute [PMI] (2027), encompasses two main dimensions. Individual risk refers to uncertain events or conditions that may positively or negatively impact the objectives of a specific project. On the other hand, overall risk comprises the aggregate effect of uncertainties that permeate the project as a whole, resulting from the combination of multiple risk sources and potentially influencing overall performance and variations in expected outcomes. Kaplan and Mikes (2012) complement this view, arguing that risk management should transcend mere compliance control, adopting a strategic perspective that allows for differentiation between avoidable, strategic, and external risks. Hillson (2009) reinforces the idea that a structured analysis of risks transforms uncertainties into valuable information for management, promoting continuous process improvement.
Despite the growing awareness of the importance of risk management, many organizations, especially those linked to the public sector such as support foundations, still face significant challenges in the effective implementation of control mechanisms. The complexity of bidding and contracting processes, the need for compliance with constantly evolving legislation, and the pressure for efficiency and transparency create an environment conducive to the materialization of operational, regulatory, and organizational risks. The absence of formal process mapping, the lack of clear internal regulations, high staff turnover, and deficient institutional knowledge management are examples of gaps that can compromise the effectiveness of contracting and the legal security of operations.
In this context, risk management emerges as an indispensable tool for decision-making, providing a reasonable level of security in achieving organizational objectives. It acts as a robust mechanism for strengthening governance, improving projects and initiatives, and ensuring the effective delivery of value. The application of risk management methodologies can, therefore, substantially contribute to enhancing organizational processes, especially in the contracting and bidding environment, which is marked by uncertainties and rigorous regulatory requirements. Its practical relevance lies in the ability to identify vulnerabilities, propose treatment measures, and consequently mitigate negative impacts, ensuring greater control and efficiency.
The need to improve risk management in entities that deal with public resources and large-scale projects justifies in-depth studies. Understanding the particularities and challenges inherent in these processes is fundamental to developing effective strategies that promote compliance, transparency, and resource optimization. Given the foregoing, this study aims to identify, describe, and analyze the risks present in the bidding and contracting processes of a support foundation linked to a federal university, considering how these risks manifest in daily operations, in order to support reflections and proposals for improving control mechanisms.
2. Material and Methods
This research was characterized as a study of an applied nature, seeking to observe, analyze, and propose solutions for practical problems related to bidding and contracting processes. A qualitative approach was adopted, focused on the interpretation of information obtained through documents, observations, and surveys with participants. Regarding its objectives, the study was descriptive in nature, aiming to evaluate the characteristics of a specific phenomenon, in this case, risk management within the context of the analyzed institution. The research design was framed as a case study, allowing for an in-depth analysis of the organizational reality.
The empirical object of the study was a support foundation linked to a federal university, a non-profit organization that manages academic, scientific, and outreach projects. The investigation focused on the Purchasing and Services Department, the unit responsible for the procurement of goods and contracting of services essential for the execution of projects under the foundation’s management. This department operates in integration with the project sector, processing acquisition demands according to the established work plans.
The analyzed operational flow begins with the request for purchases or contracting by the responsible researcher to the Projects Department. After analysis and approval, the demand is formally forwarded to the Purchasing and Services Department. This department, through the Purchasing Planning Sector, analyzes the request, carries out quotations, defines the applicable modality, and prepares the terms of reference. After legal analysis and execution of the contract, the process is forwarded to the Contract Oversight Sector for monitoring of contract execution and verification of supplier obligations.
For the acquisition of information and data, techniques and instruments were applied sequentially. Initially, a literature review was carried out to theoretically ground risk management and public procurement. Next, documentary research was conducted, which enabled the analysis of manuals, regulations, and document templates used in the sector. Subsequently, operational flows were observed, aiming for a better understanding of the activities performed.
Subsequently, brainstorming meetings were held with a focus group, composed of five participants directly involved in the analyzed processes. The selection was based on experience and performance in the purchasing management areas. The meetings took place over three months, with a semi-structured nature, conducted by the researcher using a guiding script previously defined based on the list of identified risks.
The meetings aimed to stimulate the identification and discussion of the main risks associated with the studied activities. The brainstorming process included the initial free listing of perceived risks, collective discussion for clarification and deepening of the situations, and the proposal of measures to mitigate the impacts. The information obtained was recorded in a structured spreadsheet, allowing for the organization, categorization, and subsequent analysis of the risks.
The risk analysis was based on the Risk Management Methodology of the General Comptroller’s Office of the Union [CGU] (2019), aligned with the guidelines of ABNT NBR ISO 31000:2018 and the COSO Enterprise Risk Management [ERM] framework (2017). This systematic and structured approach was adopted to integrate the analysis with organizational objectives, in accordance with good governance and internal control practices (Brasil, 2018).
The identification of risks marked the beginning of the analysis, understanding their causes and consequences. The assessment was carried out by jointly estimating the probability of occurrence and the impact associated with each event. Probability referred to the chance of materialization in a given period, using a five-level ordinal scale. Impact expressed the degree of compromise of the process objectives, also assessed on a five-level ordinal scale. The risk level was calculated by multiplying the assigned values, resulting in a classification ranging from low risk to extreme risk.
The assessment was carried out considering two scenarios: inherent risk, which represents exposure in the absence of controls, and residual risk, which reflects the remaining level after considering existing controls. For residual risk, a reduction factor was applied according to the effectiveness of the controls. Risk treatment involved choosing alternatives such as avoiding, mitigating, transferring, or accepting (Vieira et al., 2019; Brasil, 2018), based on the classification of risks into extreme, high, medium, and low levels (Tribunal Superior do Trabalho, 2015).
3. Results and Discussion
The analysis of purchasing and contracting processes in the support foundation revealed a complex scenario, marked by the presence of several risks that impact operational efficiency, regulatory compliance, and organizational governance. The initial identification of risks was carried out through a multifaceted approach, which included a detailed analysis of the workflow, a review of internal documents, and the collection of qualified insights from involved professionals, using brainstorming techniques with a focus group. This stage was crucial for mapping the uncertainties inherent in the studied activities, allowing for an in-depth understanding of their causes and potential consequences.
The identified risks were categorized into three main groups: operational, regulatory, and organizational. Within the operational scope, failures in the formulation of demands were highlighted, such as requests with incomplete or excessively specific descriptions, which generate rework and delays. The occurrence of inconsistent or incomplete quotations, resulting from inadequate market research, was also observed, which can lead to the incorrect choice of contracting modalities and inefficiency in execution. Errors in the elaboration of essential documents, such as terms of reference and public notices, were equally noted, implying legal risks and the need for constant corrections.
Still within the operational spectrum, the research pointed to delays in order fulfillment, attributed to bureaucracy and a lack of process and deadline control. The inadequate definition of contracting modalities, often resulting from deficient procurement planning, was also a relevant risk, causing delays and inefficiency. Deficient contract oversight, in turn, was associated with workload overload and failures in control and training mechanisms, resulting in inadequate execution and losses. Non-compliance by suppliers, although partially mitigated by existing controls, still represents a significant risk for the foundation.
Regarding regulatory and organizational risks, the research highlighted the difficulty collaborators have in interpreting legislation, due to the complexity of the norms and low training, which can lead to procedural errors and legal uncertainty. The absence of adequate organization and planning of requests, as well as the lack of standardization of purchasing plans, were identified as causes of emergency delays and rework. The risk of expense fragmentation, arising from the incorrect definition of the nature of the acquisition, was also an important finding, with implications for institutional accountability.
The absence of clear internal regulations defining the foundation’s methods, combined with regulatory gaps, contributes to procedural and legal insecurity. At the organizational level, high employee turnover, driven by uncompetitive salaries and a high workload, results in the loss of institutional knowledge. Poor knowledge management, characterized by the absence of Standard Operating Procedures (SOPs) and mapped processes, leads to repeated errors. Finally, poor data analysis, due to a deficient operational system, culminates in poorly substantiated decisions, compromising the foundation’s strategic management.
Analysis of Raised Risks
The risk assessment was carried out based on the methodology of the Comptroller General of the Union (CGU), which considers the probability of occurrence and the impact on the process objectives. Initially, the analysis of inherent risks, i.e., without considering the effectiveness of existing controls, revealed a scenario with a predominance of risks classified as medium, high, and extreme. This initial distribution underscored the foundation’s vulnerability and the urgency of strategic interventions to strengthen governance and the efficiency of procurement processes.
Among the inherent risks of greatest criticality, three were classified as extreme, demanding immediate management attention. The first was the lack of organization and planning of orders (R9), which generates delays and rework. The second, the risk of fragmentation arising from the incorrect definition of the nature of the acquisition (R10), with serious legal and institutional implications. The third extreme risk was the absence of internal regulations defining the foundation’s methods (R11), evidencing a structural gap that compromises the standardization and legal security of operations.
Additionally, several risks were classified as high in the inherent scenario, indicating significant fragilities that could compromise efficiency and compliance. This category included failures in the quotation process (R2), errors in document preparation (R3), delays in meeting demands (R4), deficient oversight (R6), and difficulties in interpreting legislation (R8). These findings reinforce the need for improvement in internal controls and team training to mitigate the negative impacts associated with these uncertainties.
Risks classified as medium, although of lower relative criticality, also require continuous monitoring and improvement actions. In this category, the following were identified: requests with inadequate descriptions (R1), incorrect adoption of contracting modalities (R5), non-compliance with contracts by suppliers (R7), high employee turnover (R12), low knowledge management (R13), and limitations in data analysis (R14). The presence of these medium and low risks, according to the inherent risk matrix, reinforces the need for a comprehensive approach to risk management, as recommended by ISO 31000 (2018).
After evaluating the existing controls, the analysis of residual risks, which represent the remaining exposure level, was carried out. A general reduction in criticality levels was observed, indicating that the implemented controls have some effectiveness. However, the persistence of risks at high and extreme levels demonstrates that the current mechanisms are still insufficient to guarantee an acceptable level of security, according to the guidelines of the Comptroller General of the Union (CGU, 2019) and the COSO Enterprise Risk Management framework (COSO, 2017).
The risk related to the absence of regulations defining foundation methods (R11) remained at an extreme level, even after considering existing controls, underscoring a critical structural fragility. The risks of lack of organization and planning of orders (R9) and of fragmentation (R10) were reduced from extreme to high, but still require priority attention. Risks such as quotation failures (R2), delays in meeting demands (R4), and difficulty understanding legislation (R8) also remained at a high level, indicating that current controls were not effective in significantly mitigating these issues.
On the other hand, some risks showed a more significant reduction, moving to the medium level. This includes risks related to document preparation (R3) and contractual oversight (R6), suggesting that the existing controls in these areas have partial effectiveness. The other risks, such as requests with inadequate descriptions (R1), adoption of contracting modalities (R5), high staff turnover (R12), and low data analysis (R14), were classified as medium or low, but still require continuous monitoring to prevent their materialization.
Treatment of Raised Risks
Based on the analysis of inherent and residual risks, treatment measures were proposed aiming at the mitigation, transfer, or acceptance of risks, according to the strategies outlined by Vieira et al. (2019). The choice of actions considered the organizational context of the foundation, seeking viable and effective solutions to reduce exposure to uncertainties. The proposals were structured based on the observed weaknesses and the contributions of the focus group, focusing on the standardization of procedures, training, and improvement of control instruments.
For the risk of requests with incomplete or excessively specific descriptions (R1), it was proposed to hold alignment meetings with project analysts and coordinators. The objective is to improve the initial filtering of requests, avoiding the forwarding of requests with insufficient information to the procurement department. This measure aims to reduce rework and optimize the flow of demands, ensuring that requests reach the procurement department with the necessary clarity for the continuation of processes.
Regarding incorrect, inaccurate, or incomplete quotations (R2), one of the sector’s main bottlenecks, the proposal under review by the executive board is that project coordinators submit at least three quotations along with the request. This measure seeks to accelerate the quotation process, which is currently handled by a small and overburdened team, and ensure greater speed and accuracy in supplier selection, contributing to the efficiency and cost-effectiveness of contracts.
To mitigate errors in document preparation (R3), an action under development involves the foundation’s legal department for the analysis and reformulation of draft models, contracts, and other documents. The objective is to standardize the use of these documents in purchasing and contracting processes, reducing legal risks and the need for corrections. Assertive team training, along with the reformulation of drafts, is expected to decrease the turnaround time for requests (R4), which are currently hampered by bureaucracy and lack of control.
The inadequate adoption of contracting modalities (R5) will be mitigated by the definition of new regulations, which will also address the absence of regulations defining the foundation’s methods (R11). These new guidelines, under development with the Legal Counsel and the Executive Directorate, aim to redesign obsolete and bureaucratic processes, creating more optimized and agile workflows. This action is crucial to ensure that procurement is carried out in compliance with legality and efficiently, avoiding the splitting of expenses (R10) and legal uncertainty.
Deficient oversight (R6) will be addressed through training of contract supervisors and improvement of the task management panel, focusing on deadline control, addendums, and monitoring of contractual compliance. For contractual non-compliance by suppliers (R7), it is proposed to reformulate the penalty process, with updated regulations and team training. The difficulty in understanding legislation (R8) will be addressed by aligning with current legislation and continuous employee training, in conjunction with the Legal Department and the Executive Directorate.
The lack of organization and planning of orders (R9) will be mitigated by the prior development of a semi-annual or annual purchasing plan for the projects, aligned with the coordinators. For low knowledge management (R13), the reformulation of documents and the creation of a training program, including the reuse of materials such as recorded meetings, are the proposed actions. Low data analysis (R14) will be improved with the creation of new integrated dashboards, consolidating data from the tools used and the task manager, which has already enabled better visualization of deadlines and identification of bottlenecks, although limitations still exist due to the outsourced system.
After the proposition and consideration of the new mitigation actions, a reclassification of residual risks was performed, evidencing an expressive reduction in criticality levels. Risks previously classified as extreme, such as the absence of regulations (R11), lack of demand planning (R9), and the risk of fragmentation (R10), were reclassified to the medium level. This demonstrates the potential effectiveness of the suggested actions, indicating a significant advancement in the maturity of the foundation’s control processes, according to the guidelines of the Superior Labor Court (2015) for risk classification.
Additionally, the risks that were at a high level, such as quotation failures (R2), delays in service (R4), deficient inspection (R6), and difficulties in interpreting legislation (R8), also showed a consistent reduction, mostly moving to medium or low levels. This transition reflects the effectiveness of the proposed actions, such as the standardization of procedures, team training, and improvement of control mechanisms. However, the risk related to non-compliance with contracts by suppliers (R7) remained at a medium level, suggesting inherent limitations in organizational control over external factors, demanding continuous monitoring and complementary strategies.
In summary, the application of the risk management methodology allowed for the identification and analysis of the main vulnerabilities in the foundation’s purchasing and contracting processes, revealing operational, regulatory, and organizational risks of varying criticality. The proposition of risk treatment measures, based on detailed analysis and focus group collaboration, demonstrated significant potential to reduce exposure to these risks, promoting greater control, efficiency, and legal certainty, especially in those of an organizational and regulatory nature, which showed the most expressive improvements.
4. Conclusion
The present study aimed to identify, describe, and analyze the main risks associated with the purchasing and contracting processes in a support foundation linked to a federal university, as well as to propose treatment measures to mitigate them. The presence of relevant operational, regulatory, and organizational risks was verified, with emphasis on flaws in document preparation, inconsistencies in quotations, absence of internal regulations, and limitations in knowledge management. The initial analysis of inherent risks revealed a scenario with a predominance of medium, high, and extreme criticality, evidencing the foundation’s vulnerability. After proposing treatment measures, a significant reduction in risk criticality levels was observed. Risks previously classified as extreme, such as the absence of regulations defining the foundation’s methods, the lack of organization and planning of orders, and the risk of expense splitting, were reclassified to the medium level. This transition demonstrates the potential of the suggested actions to promote greater control, efficiency, and legal certainty, especially in the organizational and regulatory aspects, which showed the most significant improvements.
Despite the advances observed, it was found that the risk related to non-compliance by suppliers remained at a medium level, evidencing limitations inherent in organizational control over external factors. Additionally, the organization’s environment of high bureaucracy and regulatory rigidity may hinder the full implementation of the proposed solutions, requiring additional institutional and legal validations that may impact the time needed for the consolidation of improvements. As a practical contribution, this study offers subsidies for the improvement of risk management in support foundations and organizations with similar characteristics, strengthening governance and administrative efficiency. For future studies, it is recommended to define and implement periodic cycles of verification and monitoring of the proposed solutions, in order to evaluate their effectiveness over time and promote continuous adjustments in control mechanisms.
Bibliographic References
Associação Brasileira de Normas Técnicas [ABNT]. 2018. NBR ISO 31000:2018 – Gestão de riscos: diretrizes. ABNT, Rio de Janeiro, RJ, Brasil.
Brasil. 2016. Instrução Normativa Conjunta CGU/MP nº 01, de 10 de maio de 2016. Diário Oficial da União, Brasília, 11 maio 2016. Seção 1, p. 14-17.
Brasil. 2021. Lei nº 14.133, de 1º de abril de 2021. Lei de Licitações e Contratos Administrativos. Diário Oficial da União, Brasília, 1 abr. 2021. Seção 1, p. 1–114.
Brasil. Controladoria-Geral da União [CGU]. 2019. Metodologia de Gestão de Riscos. CGU, Brasília, DF, Brasil.
Brasil. Tribunal Superior do Trabalho [TST]. 2015. Plano de Gestão de Riscos da Secretaria do Tribunal Superior do Trabalho. Tribunal Superior do Trabalho, Brasília, DF, Brasil.
Committee of Sponsoring Organizations of the Treadway Commission [COSO]. 2017. Enterprise Risk Management: Integrating with Strategy and Performance. COSO, New York, NY, USA.
Hillson, D. 2009. Managing Risk in Projects. Gower, Aldershot, UK.
Kaplan, R.S.; Mikes, A. 2012. Managing risks: a new framework. Harvard Business Review 90(6): 48-60.
PMI, 2027 [Referência completa não encontrada no documento original]
Vieira, J.B.; et al. 2019. Governança, gestão de riscos e integridade: opções de tratamento de riscos conforme ABNT ISO 31000. Enap, Brasília, DF, Brasil. Disponível em: <https://bibliotecadigital.enap.gov.br/bitstream/1/4281/1/5_Livro_Governança%20Gestão%20de%20Riscos%20e%20Integridade.pdf>. Acesso em: 05 fev. 2026.