Schedule management in an industrial electrical assembly project for a “pet food” company
Schedule Management in an Industrial Electrical Assembly Project of a “Pet Food” Company
Vinícius Garcia da Silva Gonçalves; Emilio Antonio Amstalden
DOI: 10.22167/2675-6528-202602405
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The growing complexity of industrial projects has highlighted the importance of time management for delivery predictability and execution efficiency, particularly in environments with operational constraints. The difficulty in maintaining alignment between planning and execution motivated this study, considering the impacts on project performance. The effectiveness of schedule management was evaluated in an industrial electrical assembly project, carried out in a manufacturing unit of the food sector. For this purpose, an applied research, qualitative and descriptive in nature, structured as action research, was employed. Data collection occurred through the researcher’s active participation and documentary analysis, covering the schedule and activity execution records. The results showed deviations between planned and executed durations, indicating limitations in schedule control during project execution, especially in activities with high operational variability. It was observed that, despite consistent planning, the absence of continuous monitoring with performance indicators compromised the anticipation of deviations. It was concluded that the implementation of more structured control practices contributes to increasing predictability, improving decision-making, and enhancing project management maturity in industrial environments.
Keywords: Industrial environment; Deadline control; Activity performance; Project execution; Project planning.
1. Introduction
The growing demand for efficiency and competitiveness in industrial environments drives organizations to adopt structured management approaches to ensure predictability and control in the execution of their projects. In this scenario, project management has established itself as a fundamental component for the coordination of resources, activities, and deadlines, especially in ventures involving high technical and operational complexity (Kerzner, 2022).
In the industrial sector, electrical assembly and automation projects present significantly amplified management challenges, particularly concerning Time Management. The need to integrate technical activities in active production environments, often with restricted intervention windows, demands detailed planning and a high level of coordination among the involved teams (Project Management Institute, 2021).
Complexity is intensified by the presence of multiple interfaces, the interdependence between activities, and the influence of external variables, such as material availability, access conditions, and the release of productive areas. Schedule predictability becomes more critical as the number of uncontrollable variables in the project environment increases (Meredith and Mantel Jr., 2017).
Given this panorama, the schedule assumes a central role in project management, being responsible for translating the scope into a structured set of activities with logical sequencing and estimated durations. The quality of this planning depends directly on the ability to decompose the work adequately and estimate the duration of activities based on realistic premises (Heldman, 2021).
Among the most used approaches for duration estimation in industrial projects, bottom-up and parametric techniques stand out. These techniques combine detailed activity decomposition with the use of historical productivity data. They contribute to the standardization of planning, but their effectiveness is conditioned by the reliability of the databases used (Fleming and Koppelman, 2016).
However, even with planning elaborated with methodological rigor, the execution of projects frequently exhibits deviations from the established baseline. Such deviations can be attributed both to limitations in the initial estimates and to factors inherent in operational dynamics, such as unforeseen field events, scope changes, and unforeseen constraints (Flyvbjerg, 2014).
In this context, continuous schedule monitoring is fundamental for the early identification of deviations and for corrective decision-making. Earned Value Management (EVM) stands out as one of the main tools for this purpose, as it allows for integrated analysis between planning and execution through objective performance indicators (Kerzner, 2017).
Indicators such as the Schedule Performance Index (SPI) and Schedule Variance (SV) allow for the evaluation of the project’s efficiency in relation to the planned timeline. They provide quantitative subsidies for schedule management, contributing to more data-driven management and reducing subjectivity in progress evaluation (Vargas, 2021).
Despite the relevance of these practices, their application in industrial projects does not always occur in a structured manner. In many cases, schedule control is limited to visual monitoring of physical progress, without the systematic use of performance metrics. This compromises the ability to anticipate problems and improve the quality of future planning (Hillson and Murray-Webster, 2017).
This reality is even more critical in projects executed in environments with operational restrictions, such as those carried out during scheduled factory shutdowns. In these situations, the time available for execution is limited, and any deviation can directly impact the resumption of production, increasing the operational and financial risks of the undertaking (Silva and Zafalon, 2019).
Given this context, the need arises to understand, in an applied manner, how schedule planning and control practices behave in the execution of industrial projects, as well as which factors influence the adherence between the planned and the executed. Thus, this work is justified by the search for proposing practical improvements that increase the predictability and reliability of planning in similar projects, and aims to evaluate the effectiveness of schedule management in an industrial electrical assembly project, through the comparison between planned and executed durations, the application of temporal performance indicators, and the identification of the main causes of deviations.
2. Material and Methods
To achieve the proposed objective, a methodological approach of an applied nature was adopted, according to Gil (2019), aiming to generate knowledge directed towards the resolution of a practical problem in the context of schedule management in industrial projects. Regarding the objectives, the research was characterized as descriptive, seeking to analyze and interpret phenomena observed in the real context of the project, without the intention of manipulating them, according to Vergara (2016).
Regarding the approach, the study employed a qualitative and quantitative character, as it sought, simultaneously, to interpret the processes, practices, and behaviors involved in schedule management, as well as to analyze measurable data related to project performance. The integration between qualitative and quantitative approaches enabled a comprehensive understanding of the phenomenon studied (Minayo, 2017; Creswell, 2014).
Additionally, the method used was action research, characterized by the researcher’s direct participation in the studied context, with involvement in planning activities and schedule monitoring. This approach allowed for an understanding of reality and, simultaneously, the promotion of practical improvements in the analyzed context, according to Thiollent (2011) and Tripp (2005).
The unit of analysis consisted of an industrial electrical assembly project, executed in a manufacturing unit in the food sector, located in the interior of the state of São Paulo. The organization studied is a medium-sized Brazilian company, active in the industrial engineering and automation segment, with approximately 1000 employees. Its projects are characterized by high operational complexity and execution in active production environments.
The specific project analyzed was executed in the period from November 17, 2025, to January 04, 2026, including a scheduled plant shutdown window for the execution of critical activities. This active industrial environment, with operational restrictions and high demands for quality and deadline compliance, reinforced the criticality of schedule planning and control.
The project execution mobilized a multidisciplinary team composed of approximately 25 professionals. These included a construction coordinator, field supervisor, project analyst, safety technicians, administrative staff, and operational professionals, such as electricians, assemblers, and assistants. The integration between these roles was fundamental to enable the execution of activities within the established deadline.
Data collection was carried out through two complementary strategies: the researcher’s active participation and documentary analysis. Active participation occurred in the context of the analyzed project, in which the researcher directly acted as Project Analyst III, performing functions related to schedule planning and control.
This performance allowed for continuous monitoring of activities, observation of practices adopted in duration estimation and progress monitoring, as well as identification of deviations between planning and execution. The researcher’s direct participation in the studied environment is a fundamental characteristic of action research, enabling a deep understanding of phenomena from practical experience (Thiollent, 2011).
Complementarily, documentary analysis was performed, based on formal project records. The baseline schedule, developed in Microsoft Project, the Work Breakdown Structure (WBS), and the Daily Site Reports (RDO) were used. These documents allowed for the acquisition of objective data on the planned and executed durations of activities, as well as evidence of physical progress and the causes of identified deviations (Gil, 2019).
In the initial planning, the WBS (Work Breakdown Structure) was used for the decomposition of the scope into manageable activities, favoring the detailing of the work and the organization of the schedule (PMI, 2021). For duration estimation, the “bottom-up” and parametric approaches were employed. The “bottom-up” estimating was used from the detailing of the activities (Heldman, 2021), and the parametric was based on historical productivity indices (Fleming and Koppelman, 2016).
The consolidation of the planning was carried out using Microsoft Project software, which was used for structuring the schedule, defining predecessors, logical sequencing of activities, and identifying the critical path. The use of computational tools contributed to greater precision in planning and better schedule control (PMI, 2021).
During execution, progress monitoring was carried out through the Daily Operational Reports (RDO), used as a tool for recording executed activities, field occurrences, and factors that impacted schedule performance. Additionally, the temporal performance analysis was structured based on Earned Value Management (EVM).
For the project performance evaluation, the Schedule Variance (SV) and Schedule Performance Index (SPI) indicators were used as metrics. These indicators allowed for an objective assessment of the adherence between planning and execution, enabling the identification of deviations and supporting decision-making throughout the project (Kerzner, 2017; Vargas, 2021).
The data analysis steps were structured to reflect the phases of the analyzed project, establishing a correspondence between the research development and the practical execution of field activities. Initially, the structuring of the baseline schedule was analyzed, including the decomposition of activities by the WBS (Work Breakdown Structure), duration estimation techniques, and the definition of the baseline.
Next, the physical progress of the activities and the deviations between the planned and the actual were assessed, based on data from the Daily Site Reports (RDO). Subsequently, the EVM performance indicators (SPI and CPI) were applied to quantitatively evaluate the project’s temporal efficiency. Finally, the findings were discussed in light of the project management literature, allowing for the identification of convergences and divergences in relation to recommended practices.
3. Results and Discussion
The analysis of the results revealed important insights into schedule management in the industrial electrical assembly project, highlighting the complexity inherent in manufacturing environments with operational constraints. The study sought to evaluate the effectiveness of time management practices, comparing planning with actual execution and applying performance indicators. Initial findings focused on the planning phase, examining the structuring of the baseline schedule, the assumptions adopted, and the level of detail of the activities, crucial elements for project consistency and clarity in its execution.
Schedule Planning Analysis
Initially, the structuring of the baseline schedule was consolidated from the decomposition of the main project activities. The identified macro-activities included infrastructure assembly (beds), cable removal and relocation, cable laying, cable preparation and connection, and testing and commissioning. Each of these activities had specific execution characteristics, duration estimation methods, and critical dependencies, demonstrating a systematic approach to organizing the scope of work, according to the guidelines of the Work Breakdown Structure (WBS).
Regarding duration estimation methods, the combined application of “bottom-up” and parametric approaches was observed. Activities that demanded greater technical detail, such as cable preparation and connection, were estimated using the “bottom-up” method, which is based on a meticulous decomposition of the work. On the other hand, activities with greater operational repetitiveness, such as cable laying, used parametric estimation, based on historical productivity data. This combination of techniques is consistent with good project management practices, which advocate adapting the estimation methodology to the specific nature of each activity (Fleming and Koppelman, 2016).
The analysis of the premises that underpinned the schedule planning revealed critical factors with potential impact on project performance. Team productivity was based on historical company data, classified with high impact on the schedule. Material availability was considered according to the supply plan, with medium impact. The release of manufacturing areas, dependent on client operation, and plant operational conditions, considered stable, were identified as high-impact factors, while standard working hours, with the possibility of overtime, had a medium impact. These elements, especially those with high dependence on external factors, represented significant risks to schedule compliance, as they were not under the direct control of the project team.
In general, the schedule planning demonstrated technical coherence and the application of adequate project management tools and techniques. The logical decomposition of activities and the coherent chaining of dependencies contributed to the schedule’s consistency. However, the high dependence on critical assumptions, such as the release of factory areas and the plant’s operational conditions, introduced a degree of variability in the execution environment. This dependence on external factors, which are not directly controllable by the project team, suggested the possibility of deviations during execution, reinforcing the need for rigorous monitoring.
Analysis of Execution and Deviations
The second stage of the research focused on the analysis of the project execution, comparing the planned durations with those actually carried out. Data extracted from the baseline schedule and the Daily Site Reports (RDO) allowed for the identification of significant deviations. The infrastructure assembly activity, planned for 10 days, was executed in 12 days, resulting in a 2-day delay. The cable laying and relocation, with a planned duration of 6 days, extended to 7 days, a 1-day delay. Cable pulling, scheduled for 12 days, took 15 days to complete, representing the largest deviation, with a 3-day delay.
The preparation and connection of cables, planned for 8 days, was executed in 9 days, with a 1-day delay. The only activity that remained as planned was testing and commissioning, with a duration of 5 days in both planning and execution. These results showed a predominance of delays in most operational activities, particularly in cable laying, which presented the greatest variation compared to the plan. This sensitivity of operational activities to deviations can be attributed to the high volume of execution and dependence on field conditions, which introduce greater variability in productivity.
The difference observed between the planned and the executed highlighted the influence of unforeseen factors in the initial planning. Operational constraints, interferences in the factory environment, and variations in team productivity were identified as elements that impacted execution. These aspects reinforce the limitation of deterministic estimates when applied in dynamic industrial environments, where unpredictability is a constant. The difficulty in anticipating and mitigating these factors contributed directly to the temporal deviations, compromising adherence to the original schedule.
Schedule Monitoring and Controlling
The third stage of the research involved a quantitative analysis of schedule performance through Earned Value Management (EVM), using the Schedule Variance (SV) and Schedule Performance Index (SPI) indicators. The SV, which indicates the deviation between planned value and earned value, was predominantly negative for most activities, confirming the delays already observed. The SPI, which measures schedule efficiency (SPI > 1 ahead of schedule, SPI < 1 behind schedule), corroborated this trend.
For infrastructure assembly, the SPI was 0.83, indicating a delay. The removal and relocation of cables presented an SPI of 0.86, also delayed. The cable laying activity registered the lowest SPI, at 0.80, evidencing the lowest efficiency in execution compared to planning. Cable preparation and connection had an SPI of 0.89, while testing and commissioning reached an SPI of 1.00, being the only activity executed as planned. These results demonstrate that most activities presented performance below planned, with SPI values consistently below 1.
The low performance, especially in the cable-laying activity, can be associated with its high execution volume and dependence on operational conditions of the manufacturing environment, factors that tend to increase productivity variability. Although the planning was structured based on adequate techniques, the project execution was impacted by factors not fully foreseen, resulting in performance lower than expected. This behavior reinforces the need for continuous use of performance indicators throughout execution, allowing for early identification of deviations and the adoption of corrective actions, as recommended by Kerzner (2017).
The analysis also revealed a limitation in the integration between planning and schedule control. Despite the existence of execution data in the RDOs, the systematic application of indicators such as IDP during the project’s progress was not observed. The absence of continuous monitoring with performance indicators compromised the ability to anticipate problems and improve the quality of future planning (Hillson and Murray-Webster, 2017). The use of EVM as a continuous control tool is fundamental to increasing predictability and efficiency in time management, which was not fully explored in the analyzed project.
Discussion and Improvement Proposals
The significant deviations from the planned schedule, evidenced by negative Schedule Variance (SV) values and Schedule Performance Index (SPI) below 1 in most activities, are aligned with the literature on industrial projects. The variability of the execution environment, dependence on external factors, and limitations of deterministic estimates are elements that contribute to the occurrence of deviations, as highlighted by Flyvbjerg (2014). The underestimation of deadlines and overestimation of productivity are recurring factors in complex and dynamic projects, which was clearly manifested in the case studied.
The absence of structured monitoring during execution was a crucial factor that hindered the early identification of deviations. Effective schedule management requires not only adequate planning but also the continuous use of control tools that allow real-time performance tracking (Project Management Institute, 2021). Although the project utilized consistent practices in the planning phase, the gaps identified in the monitoring and controlling stage represent significant opportunities for improvement in future projects in industrial environments.
Given the identified gaps, improvements applicable to similar projects are proposed. The first improvement consists of the systematic adoption of Earned Value Management (EVM) during project execution, and not just as a post-analysis tool. The continuous application of indicators such as SPI and BCWP would allow for early identification of deviations, enabling the implementation of corrective actions in a timely manner. According to Kerzner (2017), the continuous use of EVM significantly increases the ability to forecast and control the schedule, contributing to more proactive and data-driven management.
Another relevant improvement is the use of a formally controlled and updated baseline throughout the project. Active baseline management allows for comparing schedule versions and evaluating the impact of changes, contributing to greater traceability and control of alterations. According to the Project Management Institute (2021), baseline management is essential to ensure the integrity of the plan and provide a clear reference for progress evaluation. This practice ensures that any change in scope or schedule is duly recorded and analyzed.
Additionally, the adoption of responsibility management tools, such as the RACI matrix, is recommended, as it allows for a clear definition of the roles and responsibilities of the teams involved. This practice contributes to reducing communication failures and rework, factors that directly impact schedule performance, as highlighted by Kerzner (2022). Clarity in responsibilities minimizes ambiguities and optimizes coordination among team members, promoting a more efficient and collaborative work environment, essential for the execution of complex projects.
Another improvement proposal consists of implementing structured follow-up routines, such as periodic control meetings focused on performance indicators and constraint analysis. According to Hillson and Murray-Webster (2017), proactive risk and constraint management is fundamental to reducing uncertainty and improving project performance. These meetings allow the project team to discuss progress, identify potential problems, and make collective decisions to keep the project on track, promoting a culture of continuous monitoring.
Finally, the use of visual monitoring tools is recommended, such as physical progress curves (S-curve), which allow for a clear visualization of the project’s evolution in relation to the plan. This approach facilitates communication among stakeholders and contributes to more transparent and results-oriented management. The analysis of the results shows that, although the project was conducted based on adequate planning practices, the absence of a structured control system throughout its execution limited the efficiency of schedule management. The proposed improvements aim precisely to reduce this gap, contributing to increased predictability, operational efficiency, and project management maturity in industrial contexts.
In summary, the study demonstrated that, despite consistent initial planning and the use of adequate estimation techniques, the execution of the industrial electrical assembly project was marked by significant deviations from the schedule. The main cause of these deviations was the absence of continuous and systematic monitoring, with the application of performance indicators, which prevented the early identification of problems and the taking of corrective decisions. Dependence on external factors and the variability of the operational environment also contributed to the ineffectiveness of control. The improvement proposals, focused on the integration between planning and control, aim to enhance predictability and efficiency in future projects, responding directly to the objective of evaluating the effectiveness of schedule management.
4. Conclusion
This study sought to evaluate the effectiveness of schedule management in an industrial electrical assembly project, by comparing planned and executed durations, applying temporal performance indicators, and identifying the main causes of deviations. It was found that, although the initial planning was structured consistently, using techniques such as “bottom-up” and parametric, the project execution was marked by significant deviations. It was observed that the dependence on critical assumptions, such as the release of factory areas and the plant’s operational conditions, introduced a degree of variability that impacted performance. Quantitative analysis, through earned value management, showed predominantly negative Schedule Variances and Schedule Performance Indices below one in most activities, indicating delays. The main cause of these deviations was the absence of continuous and systematic monitoring with performance indicators, which compromised the early identification of problems and corrective decision-making. As a contribution, the work reinforces the importance of integration between planning and control, proposing the systematic adoption of earned value management, baseline formalization, implementation of monitoring routines, and the use of visual tools, aiming to increase predictability and efficiency in industrial projects.
However, the study presented limitations arising from the focus on a single project, the restricted period of data collection, and limited access to consolidated productivity histories, in addition to the reliance on participant observation and documentary analysis, which restricts the generalization of the findings. The dynamics of the industrial environment may also have influenced the results. For future research, it is recommended to broaden the analysis to multiple projects, use more robust databases, and explore the continuous use of real-time indicators to deepen the understanding of schedule management in industrial contexts.
Bibliographic References
Creswell, J. W. 2014. Research design: qualitative, quantitative, and mixed methods approaches. 4ed. Sage Publications, Thousand Oaks, CA, Estados Unidos.
Fleming, Q. W.; Koppelman, J. M. 2016. Earned Value Project Management. 4ed. Project Management Institute, Newtown Square, PA, USA.
Flyvbjerg, B. 2014. What you should know about megaprojects and why: An overview. Project Management Journal. 45(2): 6–19.
Gil, A. C. 2019. Métodos e técnicas de pesquisa social. 7ed. Atlas, São Paulo, SP, Brasil.
Heldman, K. 2021. Project Management JumpStart. 4ed. Wiley, Indianapolis, IN, USA.
Hillson, D.; Murray-Webster, R. 2017. Understanding and Managing Risk Attitude. 2ed. Routledge, London, UK.
Kerzner, H. 2017. Project Management Metrics, KPIs, and Dashboards. 2ed. Wiley, Hoboken, NJ, USA.
Kerzner, H. 2022. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 13ed. Wiley, Hoboken, NJ, USA.
Meredith, J. R.; Mantel Jr., S. J. 2017. Project Management: A Managerial Approach. 9ed. Wiley, Hoboken, NJ, USA.
Minayo, M. C. S. 2017. O desafio do conhecimento: pesquisa qualitativa em saúde. 14ed. Hucitec, São Paulo, SP, Brasil.
Project Management Institute [PMI]. 2021. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 7ed. Project Management Institute, Newtown Square, PA, USA.
Silva, R.; Zafalon, L. 2019. Gestão de paradas industriais e seus impactos operacionais. Revista Produção Industrial. 19(2): 45–60.
Thiollent, M. 2011. Metodologia da pesquisa-ação. 18ed. Cortez, São Paulo, SP, Brasil.
Tripp, D. 2005. Action research: a methodological introduction. Education and Action Research. 13(3): 443–466.
Vargas, R. V. 2021. Gerenciamento de Projetos: Estabelecendo Diferenciais Competitivos. 9ed. Brasport, Rio de Janeiro, RJ, Brasil.
Vergara, S. C. 2016. Projetos e relatórios de pesquisa em administração. 16ed. Atlas, São Paulo, SP, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq