October 26, 2026
Schedule management for deadline optimization in laboratory service subcontracting
Murilo Butarelli Miuci; Beatriz Garcia Altafin
DOI: 10.22167/2675-6528-202601248
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The complexity of managing schedules in subcontracting laboratory services was addressed, aiming to optimize deadlines and mitigate uncertainties. A methodology was developed and applied for defining and controlling deadlines in subcontracted tests, using the PERT technique and schedule management tools. A mixed approach was adopted, including documentary analysis of historical records, direct observation, and meetings with collaborators from a materials laboratory in São Carlos, SP. The methodology was structured based on the PMBOK guide, the Work Breakdown Structure (WBS), the Precedence Diagramming Method (PDM), and the PERT technique with three-point estimation, as well as a risk matrix for sample preparation. The results revealed that the previous deadline definition process was informal and disregarded crucial internal steps and logistical factors. The proposed methodology structured the process, incorporating neglected variables such as the complexity of sample preparation and logistical conditions, resulting in more consistent estimates. A simulation demonstrated the potential to increase deadline predictability and reduce delays, suggesting more realistic and operationally coherent deadlines. It was concluded that the methodology improved the control of activities and the identification of critical steps, contributing to the continuous improvement of deadline management, and its integration into the company’s system for automation was recommended.
Keywords: Project management; Testing laboratory; Methodology; PERT; Predictability.
1. Introduction
Project management, in its essence, seeks the optimization of resources and the delivery of value within scope, cost, and time constraints (Project Management Institute [PMI], 2017). However, the inherent complexity of service delivery environments, especially those involving subcontracting, intensifies the challenges related to schedule management. The dependence on third parties and the interconnection of internal and external stages introduce variables that can compromise predictability and operational efficiency. In an increasingly competitive global scenario, the ability to accurately estimate and control deadlines becomes a strategic differentiator, directly impacting customer satisfaction and business sustainability (Fernandes, 2017).
In the laboratory services sector, outsourcing assays is a common practice, driven by the need for access to specific technologies or by the optimization of internal costs and capacity. However, this practice entails a series of challenges in time management, as the total project schedule becomes influenced not only by internal activities but also by the processes and deadlines of partner laboratories (Brazilian Agricultural Research Corporation [EMBRAPA], 2019). The lack of a structured methodology for defining and controlling these deadlines can lead to frequent delays, rework, and consequently, customer dissatisfaction, compromising the company’s reputation and profitability. Empirical data indicate that inefficient schedule management is one of the main causes of project failures, with significant financial impacts and loss of market credibility (Rodrigues et al., 2019).
To mitigate such uncertainties, schedule management relies on a set of established tools and techniques. The PMBOK Guide (PMI, 2017) sets forth best practices for project schedule planning, development, monitoring, and control. Among the most effective tools for dealing with variability and uncertainty in activity durations, the PERT (Program Evaluation and Review Technique) stands out, which uses three-point estimation (optimistic, most likely, and pessimistic) to calculate the expected duration of each task (Kerzner, 2013). This probabilistic approach is particularly valuable in contexts where durations are not fixed, allowing for a more realistic analysis of deadlines and the identification of critical paths.
Complementarily, the Work Breakdown Structure (WBS) is fundamental for decomposing the scope of work into manageable packages, while the Precedence Diagramming Method (PDM) allows for visualizing the interdependencies between activities, establishing a logical sequence for project execution (PMI, 2017). The combination of these tools offers a robust foundation for building a detailed and realistic schedule, capable of incorporating the particularities of each stage and the associated risks. The application of these theoretical concepts in laboratory service subcontracting environments is crucial for transforming informal processes into predictive and controllable systems, where communication among stakeholders is enhanced and risks are proactively managed (Thamhain and Wilemon, 1975).
In the context of a materials laboratory in São Carlos, SP, it was observed that the process of defining deadlines for subcontracted tests was predominantly informal and lacked standardized criteria. The analysis of historical records from 2025 revealed that factors such as the complexity of sample preparation, logistical conditions of transport, and the operational particularities of external suppliers were not systematically considered. This gap resulted in inconsistent deadline estimations, often underestimated, and contributed to a high rate of delays in delivering results to clients. Tests such as capillary rheometry and moisture content determination by the Karl Fischer method, for example, registered significant delays, often attributed to the geographical location of partner laboratories and the inadequate assessment of transport time. Client dissatisfaction with the non-compliance of deadlines was a key performance indicator that required intervention.
Given the complexity of managing schedules in subcontracting laboratory services and the need to optimize deadlines and mitigate uncertainties, this study is justified by the search for a practical and replicable solution to the identified challenges, aiming to improve predictability and operational efficiency. Thus, the present work aimed to develop and apply a methodology for defining and controlling deadlines in subcontracted tests in a materials laboratory, using the PERT technique and schedule management tools, evaluating its contribution to improving predictability and reducing delays.
2. Material and Methods
The research was classified as applied, seeking to generate practical knowledge to solve a real problem in deadline management in laboratory services, according to Kauark et al. (2010). Action research was adopted as the technical procedure, with direct researcher participation to propose and implement improvements, aligning with Thiollent (2025). The methodological approach was mixed, combining quantitative techniques for historical deadline data analysis and qualitative techniques to understand influencing factors (Neves, 1996). The study was exploratory, reviewing literature on schedule management and techniques such as PERT, and descriptive, characterizing the current deadline setting process in the company (Kauark et al., 2010).
The study was conducted in a service-providing laboratory for materials, located in São Carlos, São Paulo. The analysis period included historical company records referring to subcontracted tests performed in 2025, with specific data from October 2025 for the pilot test. The unit of analysis focused on the process of defining and controlling deadlines for subcontracted tests. This focus allowed for a detailed analysis of the operational and logistical particularities that impacted deadline predictability, seeking to identify the intervening steps, limitations, and variables.
The population of interest consisted of approximately one hundred outsourced trials, distributed among about twenty-five suppliers. For the analysis, a sample of fifteen recurring trials was selected, based on consolidated data from 2025. The selection criteria prioritized statistical representativeness and analytical feasibility of the cases. For confidentiality reasons, the names of the partner laboratories were not presented, and the data were treated in an aggregated and representative manner, ensuring the methodological integrity of the research without compromising sensitive company information.
Data collection was carried out through documentary analysis, direct observation, and technical meetings. Historical company records related to subcontracted tests from 2025 were examined, including deadline control spreadsheets, delay history, and supplier information. Internal documents such as commercial proposals and operational procedures were also analyzed. Meetings with heads of the commercial, purchasing, processing, laboratory, and finishing departments validated the information and identified factors influencing the duration of activities. Direct observation of operational routines complemented the survey, providing insights into the workflow.
The proposed methodology was structured in six successive stages, aligned with the good project management practices described in the PMBOK guide (PMI, 2017). This framework provided the basis for the planning, development, and control of the schedule, covering everything from activity definition to deadline monitoring. The organization into phases allowed for a systematic and coherent approach, ensuring that all relevant aspects of schedule management were considered. Each stage was designed to build upon the previous one, ensuring the integrity and effectiveness of the methodology applied to the context of subcontracted trials.
The first stage, “Plan Schedule Management”, focused on defining procedures, guidelines, and records. Documentary analysis of internal records, previous schedules, and data from partner laboratories was performed to understand the current process. Meetings with managers and collaborators identified causes of delay and influencing factors. A literature review on schedule management, PERT, and three-point estimation theoretically supported the proposal. The result was the elaboration of the Schedule Management Plan, a fundamental document for the subsequent phases of the research (Kerzner, 2013; PMI, 2017).
In the “Activity Definition” and “Activity Sequencing” steps, the tasks necessary for the outsourced trials were identified and documented. The decomposition technique, based on the Work Breakdown Structure (WBS), was used to break down generic work packages into specific and manageable activities (PMI, 2017). Subsequently, the Precedence Diagramming Method (PDM) was adopted to establish the dependency relationships between tasks, predominantly Finish-to-Start (FS). This approach allowed for the construction of a logical sequence of activities, highlighting the process flow and the critical steps for defining deadlines (Kerzner, 2013).
In the “Activity Duration Estimation” stage, the PERT technique with three-point estimation (optimistic, most likely, pessimistic) was employed, calculating the expected duration (tE) using the formula tE = (tO + 4tM + tP) / 6. The estimates were based on historical data, partner information, and the experience of those responsible (PMI, 2017; Vargas, 2009). For sample preparation, a risk matrix was developed considering material type, sample, operation, finishing, and quantity, classifying complexity into seven levels. Additionally, one business day was added to the deadline for every five additional samples of the same test.
The fifth stage, “Schedule Development”, consisted of structuring a spreadsheet. This tool consolidated all process activities, their precedence relationships, and the automatic calculation of expected durations, including optimistic, most likely, and pessimistic estimates. The spreadsheet served as a preliminary tool for evaluating the methodology with collaborators and managers. It was foreseen that the developed logic would be incorporated into the organization’s computerized system, which was under development, to provide the total expected timeframe and the completion dates for each stage, facilitating monitoring and traceability (PMI, 2017).
Finally, the sixth stage, “Schedule Control”, involved comparing estimated deadlines with those actually observed. Indicators such as the percentage of trials completed on time, ahead of schedule, or delayed, and the magnitude of deviations were used for this analysis (PMI, 2017). The methodology was validated through a pilot study involving the company’s most recurrent trials, using consolidated data from 2025. Previously practiced deadlines were compared with those obtained by the developed methodology, evaluating its contribution to predictability and delay reduction (Kerzner, 2013).
The collected data were treated and analyzed through a combination of quantitative and qualitative techniques. Quantitative analysis involved calculating the expected durations of activities using the PERT technique, based on three-point estimates. The Work Breakdown Structure (WBS) and the Precedence Diagramming Method (PDM) were employed to structure and sequence the activities. A risk matrix was developed for sample preparation, allowing for deadline adjustments. Qualitative analysis interpreted information from meetings and documents, identifying influencing factors and causes of delays, validating the methodology by comparing estimated and actual deadlines.
Regarding the ethical aspects, the research ensured the confidentiality of information from the company and partner laboratories, treating the data in an aggregated and representative manner. As a methodological limitation, it should be noted that the official performance indicators after the full implementation of the methodology were not available at the time this work was prepared. Therefore, the observed effects and the comparisons presented should be interpreted as a projection based on historical data and the proposed criteria, and not as results already proven by the company. Definitive validation will depend on the monitoring of indicators after implementation.
3. Results and Discussion
The analysis of the results began with an in-depth evaluation of the current scenario of deadline definition and control practiced by the company, revealing a panorama that lacked formalization and detail. The commercial department manager was asked for access to historically practiced deadlines for subcontracted tests, which allowed for a critical analysis of the criteria underlying the commercialization of these services. This initial survey was crucial for identifying significant flaws in the current model, highlighting the imperative need for a comprehensive review of the schedule planning process. The informality and lack of detail in the pre-existing schedule represented a substantial deviation from good project management practices, as advocated by the Project Management Institute (PMI, 2017), which emphasizes the importance of robust and well-documented planning for project predictability and success.
It was found that the schedule then in use had a predominantly informal character and was insufficiently detailed, failing to adequately address both the internal and external stages of the subcontracting process. Critical factors, such as the time spent transporting samples, the operational particularities inherent to each supplier, and the complexities involved in sample preparation, were not systematically incorporated into the deadline estimation. This planning gap is particularly concerning because, as Thamhain and Wilemon (1975) point out, Procurement Management and dependence on external suppliers introduce risks that can significantly compromise deadlines and delivery quality. The neglect of these elements resulted in unrealistic deadline estimations, increasing the probability of delays and customer dissatisfaction. Furthermore, crucial stages such as data processing and the preparation of the final report, which have a direct impact on customer delivery, were not formally integrated into the planning, leading to a fragmented and incomplete view of the service lifecycle.
Another relevant finding was that the commercial deadline frequently did not consider the quantity of samples to be analyzed, being applied uniformly regardless of the workload. This practice, which disregarded the direct influence of the “quantity of samples” variable on the total execution time, significantly contributed to delays. The absence of a detailed description of activities and a clearly defined logical sequence in the schedule made it difficult to monitor progress, identify bottlenecks early, and allocate resources efficiently. Such a scenario contrasts with the principles of Kerzner (2013), who emphasizes the need for a project breakdown structure and a logical sequencing of activities for effective schedule management. The lack of clarity and formality in the previous process not only compromised operational efficiency but also undermined client confidence due to the unpredictability of deliveries.
To deepen the analysis and quantify the impact of these deficiencies, a pilot test was conducted with ten of the company’s most recurring trials, using data from October 2025. This study compared the marketed deadline with the time effectively elapsed until the report’s completion and submission to the client. The results, presented synthetically to preserve confidentiality, showed significant discrepancies between what was promised and what was delivered.
Table 1. Comparison between marketed deadlines and the time effectively elapsed until the completion of the work, in business days
|
Essay |
Marketable Term |
Elapsed Time |
|
Traction |
20 |
23 |
|
Traction |
20 |
19 |
|
Traction |
20 |
25 |
|
Traction |
20 |
21 |
|
Traction |
20 |
20 |
|
ICP-OES |
12 |
11 |
|
ICP-OES |
12 |
10 |
|
ICP-OES |
12 |
14 |
|
ICP-OES |
12 |
12 |
|
ICP-OES |
12 |
12 |
|
Flexion |
20 |
22 |
|
Flexion |
20 |
19 |
|
Flexion |
20 |
19 |
|
Flexion |
20 |
24 |
|
Moisture Content via Karl Fischer |
15 |
17 |
|
Moisture Content via Karl Fischer |
15 |
17 |
|
Moisture Content via Karl Fischer |
15 |
19 |
|
Moisture Content via Karl Fischer |
15 |
15 |
|
Poisson’s ratio |
15 |
23 |
|
Poisson’s ratio |
15 |
22 |
|
Poisson’s ratio |
15 |
20 |
|
Granulometric Distribution |
12 |
12 |
|
Granulometric Distribution |
12 |
11 |
|
Granulometric Distribution |
12 |
14 |
|
X-ray Diffraction |
10 |
11 |
|
X-ray Diffraction |
10 |
9 |
|
X-ray Diffraction |
10 |
8 |
|
Capillary Rheometry |
20 |
24 |
|
Capillary Rheometry |
20 |
25 |
|
Rockwell Hardness |
12 |
12 |
|
Rockwell Hardness |
12 |
11 |
|
UV-Vis |
15 |
14 |
|
UV-Vis |
15 |
16 |
Source: Original research results
As presented in Table 1, the analysis of historical data allowed for the identification of relevant differences in the behavior of deadlines according to the type of subcontracted test. It was observed that the most significant delays were associated with tests such as capillary rheometry and determination of moisture content by the Karl Fischer method, which registered considerable delays. These delays were mainly attributed to the geographical location of the responsible laboratories, which implied longer and more complex transportation times. In these cases, the sample transportation time was not adequately evaluated during the definition of deadlines, directly impacting the total execution time. This finding reinforced the need to incorporate more precise and detailed logistical criteria into schedule planning, an aspect that the proposed methodology sought to address systematically. The lack of consideration for transportation logistics, as highlighted by Vargas (2009), is a common error in projects that depend on third parties, and its correction is fundamental for the accuracy of deadline estimates.
Given this diagnosis, the need to formally structure the schedule management through the development of a Schedule Management Plan became evident. This plan was developed to consolidate the guidelines, responsibilities, process steps, and criteria adopted for planning, monitoring, and controlling project deadlines, aligning with the recommendations of the PMBOK (PMI, 2017) for more mature and effective project management.
Source: Original research results
Figure 1. Project Schedule Management Plan
As presented in Figure 1, the Schedule Management Plan was developed with the purpose of replacing the empirical model previously adopted with a more systematic approach aligned with project management best practices. This plan established clear technical criteria and well-defined responsibilities for each stage of the process. The consolidation of this document represented a significant advance in the company’s time management maturity, providing the necessary foundation for the application of the techniques and tools presented in subsequent topics. The formalization of planning, as advocated by Fernandes (2017), is an essential step in transforming deadline management from a reactive to a proactive activity, allowing for greater control and predictability.
The first stage of the proposed methodology, “Plan Schedule Management,” focused on defining procedures, guidelines, and records. This phase involved a documentary analysis of internal records, previous schedules, and data provided by partner laboratories, aiming to understand the current process of defining deadlines for subcontracted assays. In parallel, meetings were held with managers and collaborators from the involved sectors to identify the main causes of delay, operational particularities, and factors influencing activity duration. A literature review on schedule management, PERT technique, and three-point estimation theoretically grounded the proposed methodology, resulting in the elaboration of the Schedule Management Plan, a fundamental document for the subsequent research phases and for the implementation of the proposed improvements (Kerzner, 2013; PMI, 2017). The integration of these information sources – historical data, tacit knowledge from collaborators, and specialized literature – is a differential that confers robustness to the planning, allowing the methodology to be adapted to the laboratory’s specificities.
After the development of the Schedule Management Plan, it became imperative to detail in a structured manner all activities involved in the execution of subcontracted tests. This “Activity Definition” aimed to enable more precise duration estimates and effective deadline control, transforming the established guidelines into identifiable and controllable operational activities. To this end, the decomposition technique was adopted, through the Work Breakdown Structure (WBS), with the objective of breaking down the subcontracted testing process into progressively more detailed and manageable work packages (PMI, 2017). The WBS was developed based on the analysis of the company’s internal processes, external stages associated with suppliers, and the most recurrent tests identified in the initial survey, ensuring a faithful representation of the actual execution flow of the subcontracted tests.
Source: Original research results
Figure 2. Analytical structure of the project for the outsourced trials
As illustrated in Figure 2, the WBS (Work Breakdown Structure) was structured hierarchically, encompassing everything from the initial client contact stages to the delivery of the final technical report. At the first level, the macro-stages of the process were defined, which included service contracting and formalization, sample management and preparation, execution of subcontracted tests, treatment and validation of results, and the issuance of the final report. At the second level, each macro-stage was subdivided into specific activities, such as budget preparation, purchase requisition, sample registration and preparation, shipment to the partner laboratory, monitoring of test execution, receipt of results, and technical data analysis. This decomposition allowed for the identification of all critical interfaces of the process, including stages often overlooked in deadline definition, such as sample transportation, waiting times between stages, and post-data treatment activities. As a result, the WBS provided a more integrated and detailed view of the project scope, serving as a basis for activity sequencing and for the application of duration estimation techniques. The WBS approach, by detailing the scope, mitigates the risk of neglected activities, which are common sources of delays and rework, as highlighted by Rodrigues and Leiva (2014) and Rodrigues, Jesus, and Oliveira (2019), who emphasize the importance of detailed planning for project success.
Based on the WBS (Work Breakdown Structure), the sequencing of activities was performed with the objective of establishing the logical order of execution of the process and identifying the interdependencies between the project stages. This step was fundamental to ensure the coherence of the operational flow of the subcontracted tests and create the necessary basis for duration estimation and schedule development. The sequencing was carried out based on the precedence diagramming method (PDM), considering the dependency relationships between the activities identified in the WBS. Due to the characteristics of the analyzed process, it was observed that most activities were directly dependent on the completion of the previous stage, making parallel execution unfeasible without compromising the technical quality of the tests. Therefore, the Finish-to-Start (FS) relationship was predominantly adopted, in which an activity can only begin after the completion of its predecessor (PMI, 2017). This methodological choice is consistent with the sequential and often irreversible nature of laboratory processes, where the quality of one stage is a prerequisite for the next.
Source: Original research results
Figure 3. Precedence diagram
The definition of these relationships, as illustrated in Figure 3, made it possible to clearly identify the predecessor and successor activities throughout the process, as well as to highlight stages that are more sensitive to delays, especially at the interfaces between the laboratory and external suppliers. The sequencing of activities provided the necessary basis for estimating activity durations and for developing the project schedule. The clarity of dependencies is crucial for identifying the project’s critical path, allowing managers to focus their efforts on activities that have the greatest potential to impact the final deadline, a central practice in schedule management (Kerzner, 2013).
The estimation of the duration of activities was developed from the definition of the initial milestone of the schedule, considered as the moment when the budget is approved by the client or when the sample is received by the company, whichever occurs last. This definition allowed the schedule planning to be aligned with the effective start of service execution, avoiding distortions between the commercialized deadline and the operational deadline. From this point, and based on information provided by the commercial and purchasing departments, approximately 100 subcontracted tests currently performed by the company were identified, distributed among about 25 distinct suppliers. Although the proposed methodology is applicable to this entire set, it was decided to concentrate the analysis on the 15 most recurrent tests, selected based on consolidated data from 2025, ensuring statistical representativeness and analytical feasibility. For confidentiality reasons, the names of the partner laboratories were not presented, with the data being treated in an aggregated and representative manner, without compromising the methodological consistency of the study.
With the trials defined, the durations of the internal stages of the process were estimated. Initial technical evaluation and sample management constitute the first stage that directly impacts the schedule and represents the formal start of the operational process. Based on the company’s history and consultations with the leaders of the involved sectors, a deadline of one business day was set for internal sample registration and an additional two business days for the technical entry of the work. In this phase, the characteristics of the requested trial are analyzed, as well as the analysis conditions and additional information related to the preparation methods are defined, establishing the technical basis for subsequent stages. The standardization of these internal deadlines, although seemingly simple, is a significant advancement compared to the previous informality, contributing to the reduction of variability and the increase of predictability in the initial phases of the project.
Sample preparation, a historically overlooked step in defining deadlines, begins immediately after the completion of the technical input stage and has been treated with greater detail. Considering the variability associated with preparation methods, influenced by factors such as the quantity of samples, material type, sample type, required preparation method, and finishing requirements, a risk matrix was developed as a support tool for estimating this phase. This approach was chosen because it is already used in other company sectors and is widely understood by employees, facilitating its application and acceptance.
Source: Original research results
Figure 4. Risk matrix applied to estimate the duration of sample preparation
As illustrated in Figure 4, the risk matrix for sample preparation jointly assesses factors such as material type, sample type, preparation method, finishing requirement, and sample quantity, classifying complexity into seven distinct levels. This classification allows for the representation of the technical impact of each variable on execution time, offering a robust tool for adjusting the estimated duration according to the work’s complexity (PMI, 2017; Vargas, 2009). The incorporation of a risk matrix is a clear example of how the proposed methodology integrates risk management into schedule planning, a fundamental aspect for dealing with the uncertainty inherent in complex projects, such as subcontracted laboratory tests. By quantifying risk and assigning proportional deadlines, the company can avoid underestimating the necessary effort, a common problem in environments with high variability (EMBRAPA, 2019).
Based on the definition of complexity levels, execution times proportional to each score range of the risk matrix were assigned, so that higher levels reflected greater technical effort and, consequently, longer estimated durations. These times were defined based on the history of previous work and the experience of the processing sector manager, considering the recurrence of operational difficulties, the need for rework, and the additional consumption of resources in more complex preparations.
Source: Original research results
Figure 5. Preparation times attributed to each risk level
Figure 5 details the preparation times assigned for each risk level, ranging from 1 to 2 hours for the simpler levels (score 1 to 5) to 4 to 5 days for the more complex ones (score >30). Additionally, one business day was added to the deadline for every five additional samples of the same assay, recognizing the impact of workload on the total time required for assay completion. This granularity in estimation, which considers both technical complexity and volume, is a significant advancement over the previous practice of uniform deadlines, promoting more realistic and accurate estimates.
Once the preparation was completed, the estimate moved to the stage of checking and sending the samples to partner laboratories. As this is an operationally simpler process, a deadline of one business day was defined for the final check. The transport time was estimated according to the supplier’s location, the type of shipment adopted, and the information provided by the contracted carriers, allowing for greater adherence between the planned deadline and the time actually needed for this stage. The explicit inclusion of transport time, which was previously a source of delays, demonstrates the comprehensiveness of the new methodology in covering all critical stages of the process.
Subsequently, deadlines for the outsourced tests were estimated. For this stage, information provided by partner laboratories was considered the most likely estimate. The optimistic and pessimistic estimates were defined based on each supplier’s historical performance, considering records of advances and delays observed in previous work. Additionally, a deadline adjustment criterion was established based on the quantity of samples analyzed, determining that for every five additional samples of the same test, one business day should be added to the execution deadline. This three-point estimation approach (PERT), as described by Vargas (2009), is fundamental to incorporating the uncertainty and variability inherent in supplier deadlines, allowing for a more probabilistic and realistic view of the timelines.
Finally, the estimation included the stage of reviewing the results and issuing the final technical report. The deadlines associated with this phase were defined based on the company’s history and the technical knowledge of the finalization team, considering the particularities of each type of test, the volume of data generated, and the complexity of the analyses. The inclusion of these final stages in the schedule, which were previously often ignored, ensures that the total deadline communicated to the client is a complete and accurate representation of the entire service cycle.
Source: Original research results
Figure 6. Spreadsheet section with the duration estimates for the outsourced testing process steps
In Figure 6, the spreadsheet section containing the consolidation of duration estimates assigned to each process step is presented, expressed in business days, from sample entry to report submission to the client. This section serves as the basis for the project schedule development, detailing the deadlines for registration, technical entry, verification, submission, and the optimistic, probable, and pessimistic estimates from suppliers. The detailed visualization of each step allows for a clear understanding of where deadlines are generated and how different variables contribute to the total time.
From these individual estimates, the deadlines were consolidated by type of test, resulting in the final values corresponding to the optimistic, most likely, and pessimistic scenarios, expressed in business days.
Source: Original research results
Figure 7. Spreadsheet section with the consolidation of estimated deadlines for outsourced trials
Figure 7 presents the spreadsheet section with the consolidation of total testing times analyzed, obtained from the integration of internal stages and supplier lead times, without considering the sample preparation time, which is treated specifically and incorporated later into the final spreadsheet for defining deadlines. It is observed that, in cases where the client requests more than one test, the schedule considers the test with the longest estimated duration as a reference, in order to adequately represent the total time for delivering the results. This approach avoids underestimating deadlines and contributes to more precise communication with the client.
Source: Original research results
Figure 8. Spreadsheet interface for selecting assays and defining preparation parameters
Subsequently, the characteristics related to sample preparation are informed, based on the developed risk matrix (Figure 4). This information includes the type of material, the type of sample, the type of operation required, and the finishing requirements, allowing the spreadsheet to automatically consider the impact of preparation on the total deadline. Figure 8 illustrates the sections of the spreadsheet referring to this stage of user selection and information filling, demonstrating the intuitive interface for data entry that feeds the deadline calculation.
From the definition of the start date and the completion of operational information, the spreadsheet automatically calculates the estimated deadlines for the completion of each stage of the process, including sample registration, initial technical evaluation, sample preparation, verification, shipment to the partner laboratory, assay execution, final technical evaluation, and report submission to the client. The calculations are performed in business days and follow the criteria defined in the activity duration estimation stages, considering both internal processes and deadlines provided by external suppliers. This functionality enables those responsible for each phase to monitor the progress of the work, identify any deviations, and act preventively, contributing to more effective schedule control throughout the execution.
In addition to calculating the most probable deadline, the spreadsheet also includes optimistic and pessimistic estimates for each test, allowing these scenarios to be evaluated according to the specific situation of each client, laboratory, and signed contract. This makes it possible to analyze the feasibility of shorter deadlines or the need for more conservative deadlines, considering factors such as work urgency, operational predictability, and logistical constraints. As an initial guideline, the deadline provided to the client corresponds to the most probable estimate, as it represents the expected scenario for work execution. The optimistic estimate can be adopted in specific situations, such as recurring tests with greater predictability, work contracted with an urgency rate, or cases where there is a prior agreement with the partner laboratory for early delivery of results. On the other hand, the pessimistic estimate is considered during critical periods of the calendar, such as proximity to holidays or year-end, as well as in situations involving logistical constraints or previously identified technical problems with suppliers.
Source: Original research results
Figure 9. Spreadsheet interface for viewing the optimistic, most likely, and pessimistic estimates of the trials
Figure 9 presents the spreadsheet section in which these estimates are visualized in a consolidated manner, offering managers a tool for decision-making based on different risk and opportunity scenarios. This flexibility in the presentation of deadlines is an important differentiator of the methodology, as it allows for more adaptive and strategic management of the schedule, aligned with the specific needs of each project and client.
As a way to exemplify the practical application of the developed tool, the complete spreadsheet was filled out for the Poisson coefficient test. This test was selected because it presents one of the longest lead times among those analyzed, requires internal sample preparation, and involves a partner laboratory located a significant distance from the company, which adds complexity to transportation. The analysis of this example showed how the information becomes clearer and more organized in this format, facilitating the insertion, verification, and eventual adjustment of data, in addition to allowing greater control over the progress of the work throughout its execution.
Source: Original research results
Figure 10. Complete spreadsheet for defining and consolidating deadlines
Figure 10 demonstrates the application of the methodology for a specific test, showing the estimated dates for each stage of the process in optimistic, probable, and pessimistic scenarios. This detailed visualization is fundamental for schedule control, allowing the project team to monitor progress and identify deviations in real time.
The schedule control stage aimed to track project performance throughout its execution, ensuring that planned deadlines were met or, when necessary, adjusted in a structured manner. This stage allowed for continuous comparison of the actual progress of activities with the established plan, enabling the identification of deviations and the adoption of corrective measures that contributed to greater predictability in the delivery of results. In the context of the subcontracted trials analyzed, schedule control was based on the comparison between the deadlines estimated in the schedule development stage and the actual completion dates of each process step. In this way, it became possible to verify whether the activities were being executed according to the plan or if they presented variations that could impact the final delivery deadline of the report to the client.
To enable this monitoring, the spreadsheet developed for the schedule was also used as a tool for monitoring activities. As each stage of the process was completed, the actual execution dates could be recorded, allowing for a direct comparison between planned deadlines and effectively realized deadlines. This procedure made it possible to identify potential delays, assess their magnitude, and understand in which stages of the process they occurred. Among the monitored stages, those that historically showed greater variability and impact on the total project deadline stood out, such as sample preparation, transportation to the partner laboratory, and external testing. These stages were considered critical in schedule control, as they depended on multiple technical and logistical factors that directly influenced execution time. Thus, closer monitoring allowed for the anticipation of possible problems and reduced the risk of delays in the final delivery of the work.
Source: Original research results
Figure 11. Evolution of estimated and actual deadlines throughout the process stages
Figure 11 presents the evolution of estimated and actual deadlines throughout the process stages, allowing for a clearer visualization of the schedule’s behavior and facilitating the identification of delays or advancements compared to the estimated scenarios. This type of integrated approach contributed to a more consistent analysis of schedule performance, supporting managerial decision-making and continuous process improvement. When deviations from the planned schedule were identified, an analysis of their possible causes and an evaluation of appropriate corrective actions were carried out. This analysis considered whether the delays were related to internal factors, such as technical difficulties in sample preparation or data processing, or external factors, such as transportation delays or variations in execution time by partner laboratories. Based on this evaluation, measures such as prioritizing certain internal activities, adjusting the schedule for subsequent stages, or early communication with the client about possible changes in the delivery deadline could be adopted.
Another relevant aspect of schedule control consisted of using optimistic, most likely, and pessimistic estimates as a reference for performance analysis. During the monitoring of activities, it was verified whether the actual execution remained within the previously estimated duration range or if it presented variations outside the foreseen scenario. When the execution occurred within this range, schedule performance was considered to be within expected behavior. On the other hand, deviations that exceeded the limits of the estimates indicated the need for revision of the assumptions used in planning or for the adoption of additional corrective actions. Schedule control allowed not only the monitoring of activities but also the continuous improvement of the deadline estimation process. The data obtained throughout the execution began to form a historical base, enabling the comparison between estimated values and the deadlines actually observed. The analysis of this data highlighted performance patterns, allowing the adjustment of parameters used in the risk matrix and the refinement of estimates. It was found that a relevant portion of the trials showed deviations from the plan, reinforcing the importance of systematic data-driven control.
Satisfaction surveys indicated that the failure to meet deadlines constituted one of the main sources of customer dissatisfaction. Thus, this aspect began to be treated as a key performance indicator, being continuously monitored. Additionally, periodic performance evaluations of trials were proposed, considering records of advances and delays. This approach allowed for the adjustment of established deadlines based on observed behavior, contributing to increased reliability of estimates.
In order to exemplify the expected effects of the proposed methodology, a simulation was developed comparing the previously practiced deadlines by the company with the estimated deadlines after applying the model developed in this work. For this purpose, the main trials analyzed were re-presented, considering the new estimation criteria established, such as the inclusion of internal stages, transport time, and sample preparation complexity. It is noteworthy that the values presented do not correspond to official indicators already obtained after the implementation of the methodology, but rather to a projection of improvement based on historical data from 2025 and the parameters defined throughout this study.
Table 2. Comparison between previously practiced deadlines and the estimated deadlines after applying the proposed methodology, in business days
|
Essay |
Marketable Term |
Elapsed Time |
Estimated Deadline |
|
Traction |
20 |
23 |
23 |
|
Traction |
20 |
19 |
23 |
|
Traction |
20 |
25 |
24 |
|
Traction |
20 |
21 |
24 |
|
Traction |
20 |
20 |
23 |
|
ICP-OES |
12 |
11 |
14 |
|
ICP-OES |
12 |
10 |
14 |
|
ICP-OES |
12 |
14 |
14 |
|
ICP-OES |
12 |
12 |
14 |
|
ICP-OES |
12 |
12 |
14 |
|
Flexion |
20 |
22 |
23 |
|
Flexion |
20 |
19 |
23 |
|
Flexion |
20 |
19 |
23 |
|
Flexion |
20 |
24 |
23 |
|
Moisture Content via Karl Fischer |
15 |
17 |
20 |
|
Moisture Content via Karl Fischer |
15 |
17 |
20 |
|
Moisture Content via Karl Fischer |
15 |
19 |
20 |
|
Moisture Content via Karl Fischer |
15 |
15 |
20 |
|
Poisson’s ratio |
15 |
23 |
22 |
|
Poisson’s ratio |
15 |
22 |
22 |
|
Poisson’s ratio |
15 |
20 |
20 |
|
Granulometric Distribution |
12 |
12 |
16 |
|
Granulometric Distribution |
12 |
11 |
16 |
|
Granulometric Distribution |
12 |
14 |
16 |
|
X-ray Diffraction |
10 |
11 |
12 |
|
X-ray Diffraction |
10 |
9 |
12 |
|
X-ray Diffraction |
10 |
8 |
12 |
|
Capillary Rheometry |
20 |
24 |
25 |
|
Capillary Rheometry |
20 |
25 |
25 |
|
Rockwell Hardness |
12 |
12 |
15 |
|
Rockwell Hardness |
12 |
11 |
15 |
|
UV-Vis |
15 |
14 |
17 |
|
UV-Vis |
15 |
16 |
17 |
Source: Original research results
According to Table 2, it is generally observed that the proposed methodology resulted in initially higher deadlines for some trials, especially those that previously did not adequately consider internal stages or logistical factors. However, this expansion represented a more realistic and coherent estimate of the time effectively needed for the execution of the work, reducing the probability of delays and rework. Thus, the presented comparison should be interpreted as an expected scenario of improved predictability and deadline control, rather than a result already proven by the company. The definitive validation of this projection will depend on the monitoring of official indicators after the full implementation of the methodology. The Brazilian Agricultural Research Corporation EMBRAPA (EMBRAPA, 2019) highlights that quality management in laboratories and experimental areas is intrinsically linked to the precision of time estimates, and the proposed methodology aligns with this premise by seeking a more faithful representation of operational reality.
4. Conclusion
It is concluded that the objective was achieved, as the present work successfully developed and applied a methodology for defining and controlling deadlines in subcontracted tests in a materials laboratory. Through the PERT technique and schedule management tools, it was possible to structure a previously informal process, incorporating crucial variables such as the complexity of sample preparation and logistical transport conditions, which were often neglected. The results indicated that the methodology contributed significantly to increasing deadline predictability and improving activity control, allowing for the identification of critical steps and the anticipation of possible deviations. The simulation carried out demonstrated the potential for reducing delays and setting more realistic and operationally coherent deadlines.
However, it is important to emphasize that a limitation of the study lies in the absence of official performance indicators after the full implementation of the methodology, with the observed effects being interpreted as projections based on historical data and proposed criteria. For future studies, it is recommended to integrate the developed methodology into the company’s computerized system, aiming at the automation of manual steps and the consolidation of the process on a single platform. Additionally, periodic monitoring of results and annual review of the deadlines practiced are suggested, in order to continuously improve the management model and empirically validate the projected improvements.
Bibliographic References
Empresa Brasileira de Pesquisa Agropecuária [EMBRAPA]. 2019. Gestão da Qualidade em Laboratórios e Áreas Experimentais: Orientações para a Embrapa. Embrapa, Brasília, DF, Brasil.
Fernandes, A.C. 2017. Gestão de Projetos: Teoria, prática e tendências. Atlas, São Paulo, SP, Brasil.
Kauark, F.; Manhães, F.C.; Medeiros, C.H. 2010. Metodologia da Pesquisa: Guia Prático. Via Litterarum, Itabuna, BA, Brasil.
Kerzner, H. 2013. Project Management: A systems approach to planning, scheduling, and controlling. 11ed. John Wiley & Sons, Hoboken, NJ, USA.
Neves, J.L. 1996. Pesquisa qualitativa: características, usos e possibilidades. Cadernos de Pesquisa em Administração 1(3):1-5.
Project Management Institute [PMI]. 2017. Um Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK®). 6ed. Project Management Institute, Newtown Square, PA, USA.
Rodrigues, J.A.; Leiva, D.R. 2014. Engenharia de Materiais para Todos. 2ed. EdUFSCar, São Carlos, SP, Brasil.
Rodrigues, T.V.; Jesus, R.G.; Oliveira, N.P. 2019. A importância do gerenciamento de projetos para pequenas e médias empresas. Gestão e Desenvolvimento em Revista 5(1): 4-12.
Thamhain, H.J.; Wilemon, D. 1975. Managing the risk of technological innovation. Research Management 18(4): 12-25.
Thiollent, M. 2025. Metodologia da Pesquisa-Ação. 19ed. Cortez Editora, São Paulo, SP, Brasil.
Vargas, R.V. 2009. Gerenciamento de Projetos: Estabelecendo diferenciais competitivos. 7ed. Brasport, Rio de Janeiro, RJ, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform