Budget structuring and schedule management in the execution of a single-family residential construction
Michele Mayumi Murakami; Felipe Miranda de Souza Almeida
DOI: 10.22167/2675-6528-202601230
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Residential civil construction faces significant challenges in cost and time control, especially in small-scale developments, which have resource limitations and high interdependence between activities. With the objective of elaborating the budget and managing the schedule of a single-family residential construction, the study promoted the integration between financial planning and project temporal control. The research was characterized as descriptive, with a qualitative approach, and was developed through documentary analysis of a residential work located in the interior of São Paulo. The methodology included the structuring of the Project Breakdown Structure, the elaboration of the budget by the Bottom-Up method, the definition of the schedule based on the best practices of the Project Management Body of Knowledge, using the Precedence Diagram Method and the Critical Path Method, in addition to the application of the Plan, Do, Check, Act cycle as support for integrated control. The results showed that the adequate decomposition of the scope, combined with the integration between budget and schedule, made it possible to identify critical activities, organize the parallelism between phases, and increase the predictability of the work’s schedule and costs. It was concluded that the adoption of structured project management practices contributed to greater operational efficiency and project control, demonstrating the applicability of the proposed model to single-family residential works of similar characteristics.
Keywords: CPM; Civil construction; MDP; PDCA; Integrated planning.
1. Introduction
The civil construction industry represents one of the most relevant sectors for the Brazilian economy, generating jobs, stimulating production chains, and driving the Gross Domestic Product. The residential segment has growing prominence, accounting for the largest share of buildings in the country and being directly linked to the improvement of housing conditions and the valorization of urban space. Studies indicate that investments in this sector exert a multiplier effect on the economy, contributing to income generation and increased consumption in various industrial segments (Taioka et al., 2023).
Despite its socioeconomic importance, the residential segment faces recurring challenges related to cost control, adherence to deadlines, and lack of standardization in project management. In small-scale developments, such as single-family homes, resource limitations and the high interdependence between activities increase the risks of deviations, compromising efficiency and predictability.
In this scenario, budgetary planning assumes a decisive role, guiding the efficient allocation of financial resources and sustaining the economic feasibility of the undertaking. The budget is a strategic management tool that, when detailed meticulously, allows for cost forecasting, uncertainty reduction, and decision-making direction during project execution (Maués et al., 2022). For small and medium-sized constructions, budgetary accuracy is critical, as financial deviations can directly compromise the project’s completion and quality.
Complementarily, budgeting should be treated as a continuous process, integrated into the project lifecycle and articulated with the physical and financial planning stages. This integration favors the predictability and sustainability of the undertaking, especially when associated with recognized methodologies, such as the National System of Costs and Indices for Civil Construction (SINAPI) and building information modeling (BIM) (Felisberto et al., 2021).
Beyond budgetary control, schedule management is equally essential in the execution of residential works, ensuring that activities are carried out within the planned deadlines and maintaining coherence between construction stages. Time management, the central axis of project management, is decisive for meeting goals and operational efficiency (Julião et al., 2019). However, many family construction projects are still conducted without structured management practices, which leads to delays, rework, and cost increases.
The absence of integration between budgetary planning and the schedule is one of the main causes of inefficiency in the sector (Marcos and Lúcio, 2022). This fragmentation compromises financial and temporal predictability, resulting in deviations. Thus, synchronizing budget and schedule is essential to ensure orderly execution, reduce waste, and optimize resources.
In the context of single-family residential constructions, the absence of systematized planning and control practices highlights the need for more structured and integrated management models. The use of techniques and tools such as the Program Evaluation and Review Technique/Critical Path Method (PERT/CPM) favors the joint analysis of time and cost, allowing for risk anticipation and the adoption of corrective measures (Vergara et al., 2017). Thus, cost and schedule management should be treated in a coordinated manner, with indicators to monitor progress and adjust deviations in a timely manner, according to the best practices of the Project Management Institute (PMI, 2021).
The relevance of integrated planning and rigorous cost and deadline control in single-family residential construction justifies the search for models that promote greater operational efficiency and predictability. In this context, the general objective of this work is to develop the budget and manage the schedule of a single-family residential construction, applying the best project management practices described in the Project Management Body of Knowledge (PMBOK). The aim is to integrally develop the budgetary planning and the control of execution deadlines, in order to ensure greater efficiency, predictability, and sustainability in the management of small-scale housing developments.
2. Material and Methods
The present study was characterized as a descriptive research, with a qualitative approach, seeking to systematically understand and detail the process of budget elaboration and schedule management applied to a single-family residential construction. Descriptive research aims to observe, record, and analyze phenomena without directly interfering in their development (Gil, 2017), enabling the precise description of a specific reality (Prodanov and Freitas, 2013).
The methodological design adopted allowed for the analysis of budget planning and schedule control practices, considering the technical and operational particularities of the residential construction sector. The object of study corresponded to a single-family residential work located in the municipality of Jacareí, state of São Paulo. The project consisted of a residence with approximately 480 square meters of built area.
The studied residence represented a medium-standard housing model, characterized by the use of reinforced concrete structure, masonry walls, conventional construction systems, intermediate to superior standard finishes, and integration between social areas, in addition to a leisure area. These characteristics reflected recurring typologies of contemporary residential developments in the interior of São Paulo.
The execution of this study was organized in two main and complementary stages. The first stage focused on the elaboration and control of the work budget, while the second was dedicated to the planning and management of the schedule. For the development of the analyses, document analysis was adopted as the main data collection technique.
Three technical documents produced in the context of the project were used: the detailed cost budget, the final consolidated budget, and the physical schedule of the work. The documentary analysis consisted of the systematic examination of formal records prepared in the very environment in which the phenomenon occurred (Gil, 2017), which contributed to the reliability and consistency of the analyzed information.
In the first stage, for the elaboration and control of the budget for the single-family residential construction, the Bottom-Up approach was adopted. This approach was applied through the decomposition of the work into services, sub-services, and individualized cost items, allowing each component to be quantified and estimated separately before consolidating the overall project value.
The use of the Bottom-Up approach began with the reading, organization, and classification of available technical documents. The services were identified and grouped according to their constructive nature, including initial expenses, foundations, superstructure, masonry and sealing, roofing, coatings, finishes, paving, frames, installations, and final services.
The physical quantities associated with each budgetary item were surveyed, expressed in cubic meters, square meters, or linear meters, depending on the nature of the service. These quantities were extracted from the budget documents and used as the basis for the composition of unit costs, considering inputs, productivity, and regional average prices.
As the main reference, compositions from the National System of Costs and Indices of Civil Construction (SINAPI) were used, complemented, when necessary, by market data and parameters compatible with the construction standard of the analyzed residence. Complementary projects, such as sanitary, electrical, and interior design, were not included in the detailed budget due to the unavailability of the documents at the time of the research.
The Work Breakdown Structure (WBS) was conceived from the hierarchical decomposition of the project scope, with the construction of the single-family residence as the highest level. In subsequent levels, the major executive phases identified in the budgeting process were detailed into work packages and operational activities.
This hierarchical organization, which unfolded into four levels – Global Vision, Major Phases, Work Packages, and Operational Detailing – allowed for the alignment of work packages with construction stages and ensured coherence between technical scope, costs, and time planning. The WBS (Work Breakdown Structure) was used as the budget organization structure, distributing costs according to hierarchical levels compatible with the scope of the work.
The second methodological stage focused on the development of the project schedule, based on the best practices of the Project Management Body of Knowledge (PMBOK) 7th edition (PMI, 2021). The development of the schedule involved defining activities, identifying logical dependencies between them, and estimating their durations.
For the sequencing of activities, the Precedence Diagramming Method (PDM) was adopted, with the application of the Critical Path Method (CPM), using Microsoft Project software as a support tool. The CPM was used to identify critical activities and evaluate the impact of any delays on the overall project deadline (PMI, 2021).
The Plan-Do-Check-Act (PDCA) cycle was applied as a continuous schedule control mechanism. In the Plan stage, the schedule baseline, the estimated durations for each activity, their dependency relationships, and the control milestones derived from the WBS were defined.
In the Execute stage, the sequential and parallel execution of activities was considered according to the structured schedule. In the Check stage, the planned durations were compared with the actual chaining of phases, identifying points of greatest temporal sensitivity. Finally, in the Act stage, adjustment alternatives were analyzed in sequencing, parallelism between work fronts, and prioritization of critical activities.
3. Results and Discussion
The results presented derive from the integrated application of project management tools, as described in the methodology, based on the documentary analysis of the budget and schedule of a single-family residential construction. The analysis sought to interpret how the structuring of the budget and schedule contributed to the achievement of the study’s objective, focusing on the integration between cost and time. The findings are discussed in light of good project management practices, emphasizing the gains from the joint use of the adopted tools, which allowed for a more strategic view of the undertaking and greater predictability in its execution.
Budget preparation
The systematization of the physical quantities of the budget allowed for a detailed understanding of the scope structure of the work, distributed among the different construction systems. More than a simple technical survey, this data revealed the operational complexity of the undertaking and the need for meticulous planning to ensure coherence between the various work fronts. Adequate scope decomposition is crucial to reduce ambiguities, strengthen control, and increase project performance predictability, especially in residential projects with limited resources, where deviations directly impact financial flow.
From a managerial perspective, the organization of physical quantities into structured categories enabled the linking of each construction system to work packages defined in the Project Work Breakdown Structure (WBS), promoting integration between scope, cost, and schedule. This structuring represented a fundamental step for the integrated control of the undertaking, transforming technical data into managerial information that supports decisions on resource allocation, activity prioritization, and identification of stages with higher risk exposure. The synthesis of physical quantities determined in the final budget for the residential construction included services such as manual trench excavation (58.26 m³), reinforced concrete for foundations (33.33 m³), superstructure (814.6 m²), walls and panels (713.17 m), roofing and protections (444.74 m²), and various finishes, such as plaster ceiling (189.72 m²) and rustic cement flooring (660.34 m²).
The consolidated analysis of these physical quantities not only evidenced the complexity and diversity of the services involved in the execution of the work, but also allowed us to understand how the scope was structured from the perspective of project management. The predominance of structural, sealing, and surface preparation stages indicated a concentration of productive effort in the initial and intermediate phases of the undertaking. From a managerial point of view, this concentration represents a greater exposure to financial and temporal risks, requiring more rigorous monitoring. Kerzner (2022) highlights that the clear definition of scope and its decomposition are essential to reduce uncertainties and increase project predictability, especially in environments with multiple technical interdependencies, which reinforces the importance of systematizing physical quantities as a reliable planning basis (PMI, 2021).
The organization of quantities by type of service favored the direct link between scope, cost, and deadline, allowing each construction system to be associated with work packages defined in the WBS (Work Breakdown Structure). This practice aligns with the principle of integrating knowledge areas, widely defended in the literature, according to which project performance depends on the coherence between its technical and managerial dimensions (PMI, 2021). Studies in the civil construction field indicate that the fragmentation between budget and schedule is among the main causes of delays and cost overruns, with the integration between these dimensions being an effective strategy to mitigate deviations and strengthen project control (Maués et al., 2022).
Regarding monetary costs, the consolidation of the final budget allowed for an analysis of the distribution of financial resources among the main stages of the work, highlighting how the investment was allocated throughout the construction cycle. The cost engineering literature supports that visibility into the composition and concentration of expenses enables greater capacity for prioritization and strategic resource allocation, in addition to contributing to project governance and to the mitigation of risks associated with performance variations (Felisberto et al., 2021). The financial analysis was not restricted to the presentation of absolute values, but allowed for the interpretation of which phases concentrate greater economic impact and, consequently, demand greater managerial monitoring.
The distribution of costs showed that financial resources were concentrated in the stages that have the greatest structural and temporal impact on the undertaking. The superstructure, for example, concentrated the largest financial volume, totaling R$ 439,016.00, representing not only a relevant technical component but the core risk of the project, as delays or variations in this phase tend to generate cascading effects on the schedule and subsequent costs. Project management literature highlights that structural phases concentrate high criticality, as they combine high financial outlay and strong technical dependence between activities, requiring priority monitoring (PMI, 2021).
It was also observed that significant portions of the investment are associated with the covering (R$ 157,490.00), cladding (R$ 150,100.00), and paving (R$ 164,055.00) phases, demonstrating that costs are not restricted to structural elements but are significantly distributed throughout the intermediate and final stages of the work. Studies in the civil construction area indicate that finishes and complementary systems often present high cost variability, mainly due to choices in standards and technical specifications, becoming potential sources of budgetary deviations (Felisberto et al., 2021; Maués et al., 2022). Visibility into the financial representativeness of these stages allows for prioritizing managerial control and aligning technical decisions with the previously defined budgetary limit.
Additionally, the analysis of resource allocation among building facilities (R$ 83,047.00), frames (R$ 74,175.00 for aluminum and R$ 9,976.00 for wood), complementary systems, and initial expenses (R$ 77,866.00) highlighted the importance of considering the project as an integrated system. Decisions made in the initial phases have financial repercussions in subsequent stages, and the project’s financial governance depends on the ability to anticipate cross-impacts between scope, cost, and schedule (Felisberto et al., 2021; PMI, 2021). The presence of relevant investments in technical projects (R$ 45,000.00) and preliminary expenses reinforces the understanding that planning is a structuring element of the venture’s performance, as projects with greater maturity in initial planning tend to show a lower incidence of rework and financial variations during execution (Kerzner, 2022).
The consolidation of these values resulted in an estimated total work cost of R$ 1,427,075.00, evidencing the distribution of financial resources among the different stages of the work. Given this distribution and the organization of the budget according to the executive sequence, the Work Breakdown Structure (WBS) became an integrating instrument between planning, budget, and schedule. The WBS was conceived from the hierarchical decomposition of the scope, with the construction of the single-family residence at the highest level and, in subsequent levels, the major executive phases identified in the budgeting process, such as Mobilization and Projects, Foundations, Superstructure, Walls, Roofing and Systems, Finishes, and Delivery.
This approach allowed for the alignment of work packages with the construction stages effectively executed in the field, ensuring coherence between the technical scope, estimated costs, and temporal planning. The application of the WBS (Work Breakdown Structure) proved to be decisive for the organization and integrated control of the project, as it enabled the transformation of the project scope into manageable and measurable units. By structuring the project into hierarchical levels, it was possible to establish a direct relationship between the construction systems, estimated costs, and activities planned in the schedule, reducing ambiguities and strengthening the coherence between financial and temporal planning. This alignment contributed to greater predictability in execution and to the mitigation of risks associated with fragmentation between budget and deadline, a problem frequently pointed out in the literature as a cause of deviations in small-scale projects.
From a managerial perspective, the WBS (Work Breakdown Structure) favored the consolidation of costs by major executive phases, allowing the identification of which stages concentrated greater financial volume and greater temporal criticality. This visibility enabled the direction of monitoring efforts to the most sensitive phases of the project, especially those with a direct impact on the critical path. Furthermore, the association between work packages and schedule activities facilitated the monitoring of physical-financial performance, making the relationship between construction progress and resource disbursement clearer. The definition of work packages as planning and control units also allowed for greater traceability between physical quantities, unit costs, and estimated durations, operationalizing the study’s central objective of connecting budget and schedule.
Project schedule
The structuring of the schedule from the Project Breakdown Structure allowed the previously organized scope to be converted into a temporal logic coherent with the execution of the work, making visible the dependency relationships between activities and the points of greatest project sensitivity. More than a programming tool, the schedule began to act as support for schedule management, by highlighting which stages demanded greater managerial attention and which could compromise the overall performance of the undertaking in case of delay. This finding is consistent with the literature, which points out that control failures in the initial phases of residential construction tend to produce cumulative impacts on subsequent stages, increasing indirect costs and reducing project efficiency (Julião et al., 2019; Marcos and Lúcio, 2022).
The consolidation of activity durations allowed us to observe that the project’s temporal effort was concentrated in the design (180 days), foundations (30 days), structure (30 days), and masonry (30 days) stages. From a managerial perspective, this behavior indicates that the initial phases played a decisive role in the schedule’s stability, as they conditioned the release of the other work fronts. This result reinforces the argument by Santos and Garcia (2012), according to whom detailed planning in the initial phases favors greater control over deadlines and costs. The identification of the critical path, in turn, allowed for the definition of monitoring and resource allocation priorities, demonstrating that the application of the Critical Path Method (CPM) contributed not only to the technical sequencing of activities but also to the direction of management decisions throughout the construction.
From the detailed schedule, the application of CPM allowed the identification of activities that had no float and that, therefore, directly influenced the total project completion time. These activities were concentrated, above all, in the initial stages of design, foundations, structure, and masonry, reinforcing the need for continuous monitoring of these phases throughout execution. The consolidation of activities by major phases, such as Planning and design (up to 180 days), Initial structures (up to 150 days), and Enclosures and roofing (up to 30 days), expanded the managerial analysis capacity by allowing observation of the effort distribution throughout the project cycle. This synthetic view favored decision-making, as it highlighted which phases concentrated longer durations and higher risk of delay propagation.
The literature indicates that the fragmentation between planning and execution is one of the recurring challenges in Brazilian civil construction, even impacting sustainability and efficiency goals (Silva, 2018). The organization of the schedule by phases contributed to mitigating this problem by making explicit the transition logic between structural stages, installations, and finishes. The analysis of Phase 1, which covered from planning to structure, showed that the initial months concentrated activities with high temporal criticality, especially those related to the development of executive projects, site preparation, foundations, and structure. This behavior highlights that the schedule’s performance, from the beginning of the work, depended heavily on the maturity of the planning and the correct release of the preceding stages, as these activities structured the entire chaining of subsequent phases.
In managerial terms, any delay occurring at this initial moment would have the potential to compromise not only the physical execution of the work, but also the allocation of resources, the scheduling of teams, and the balance between deadline and cost. This result converges with the literature that points out that decisions made in the initial phases have a greater capacity to influence the overall performance of the undertaking, precisely because they condition the executive sequence and the start of other work fronts (Julião et al., 2019). In the analyzed case, it was observed that the long duration of the project phase, combined with the direct dependency between foundation, structure, and masonry, configured a temporal core of high sensitivity, in which the absence of significant slack increased the need for rigorous monitoring.
From a project management perspective, the early identification of this behavior allowed for greater attention to be directed towards activities with a higher capacity for deviation propagation. This aspect was particularly relevant to achieving the study’s objective, as it highlighted how the integration between scope, schedule, and budget favored a more strategic reading of the project. By recognizing that the initial stages had a greater influence on the overall deadline, it became possible to reinforce the monitoring of these activities and prioritize control decisions before any delays affected the subsequent phases of installations, coverings, and finishes.
The Phase 1 results demonstrated that the schedule acted not only as a temporal record instrument but as a decision-making support tool. Visualizing critical activities and their position in the initial months allowed us to understand that the success of subsequent stages depended directly on the stability of this phase. Thus, rigorous control of the construction start was decisive in reducing the risk of delay propagation and in sustaining the predictability of the total timeframe for the single-family residential development, with activities such as design, soil testing, topography, earthmoving, site office/fencing, foundation, structure, and masonry concentrated in the first months.
In Phase 2, which included installations and closures, greater parallelism between activities was observed, especially in the stages of sanitary and electrical installations, aluminum frames, and concealed roofing. Although this strategy contributes to schedule compression, it also increases managerial complexity, requiring finer control of interfaces between teams. The literature highlights that increased parallelism, when not accompanied by adequate control mechanisms, can lead to rework and cost overruns (Marcos and Lúcio, 2022). In this study, the combined application of the Precedence Diagramming Method (PDM) and continuous monitoring allowed for the identification of activities that could be performed simultaneously without compromising the critical path, maintaining the balance between schedule optimization and risk control.
The analysis of Phase 2 showed that, although not all activities directly integrated the critical path, delays in building installations or closures could compromise the start of Phase 3, which is predominantly dedicated to final finishes and external areas. Thus, the performance of Phase 2, with activities such as concealed roof, house wall, sanitary and electrical installations, aluminum frames, plaster ceiling, and air conditioning, assumed a strategic role in maintaining the total deadline for the single-family residential development, especially since the execution of the house wall occurred in parallel with internal installations, optimizing the total deadline.
Phase 3, which focused on finishing activities and external areas, such as the pool, tiling, porcelain flooring, stonework/metals, interior/exterior painting, and gardens, was characterized by high interdependence and sensitivity to punctual delays. In this stage, it was observed that systematic control of sequencing was crucial to prevent delays in internal finishes from compromising the final delivery. Studies on project management in small companies indicate that applying the Plan-Do-Check-Act (PDCA) cycle favors continuous adjustments and greater integration between planning and execution (Pinotti and Guth, 2014). The results observed in this phase corroborate this evidence, as successive adjustments in sequencing allowed for alignment between physical progress and the planned deadline.
In Phase 3, the critical path analysis remained essential to ensure that final activities, such as painting and finishing, did not suffer delays that would compromise the delivery of the undertaking. The use of PDCA in this stage allowed for fine-tuning the planning, especially given the high interdependence between internal finishes and external areas. The results observed in Phases 1, 2, and 3 also align with the contributions of the literature that deals with the optimization of the critical path in the face of uncertainties in activity durations. Studies indicate that the early identification of critical activities, combined with continuous monitoring of their durations, allows for reducing the impacts of variability inherent in civil construction projects, especially when associated with structured schedule control techniques (Cao et al., 2025).
The application of CPM in this work showed similar behavior, demonstrating that delays concentrated in the initial stages tend to compromise the overall performance of the schedule, reinforcing the need for rigorous control of these phases. Additionally, research focused on the application of the PDCA cycle in small and medium-sized projects indicates that this approach contributes to greater integration between planning and execution, promoting more assertive decisions and reduction of deadline deviations (Pinotti and Guth, 2014). The results of this study corroborate these conclusions, by showing that the use of PDCA allowed for continuous adjustments in the sequencing of activities and greater control of interdependencies between phases, strengthening schedule management in the context of a single-family residential construction.
In an integrated manner, the analysis of the three phases of the schedule demonstrated that progressive temporal planning, associated with continuous monitoring, contributed to greater project predictability. This finding aligns with research indicating that workflow reliability increases when planning is structured in successive cycles of control and feedback (Javanmardi et al., 2023). Furthermore, recent studies suggest that systematic identification of the critical path and monitoring of activities without float reduce the impacts of variability in estimated durations (Cao et al., 2025), a result also observed in this study.
Thus, the practical effects of the combined application of structured sequencing, critical path identification, and continuous monitoring cycle were reflected in greater coherence between planning and execution. This integration contributed directly to achieving the work’s objective by ensuring alignment between deadline and cost, reducing exposure to significant deviations, and strengthening decision-making throughout the single-family residential development cycle. The application of structured budgeting practices, associated with the use of time planning and control tools, made it possible to ensure coherence between the predicted cost and the execution deadline of activities. This integration contributed to greater operational efficiency, predictability of results, and better support for decision-making throughout the project cycle, demonstrating the relevance of joint cost and schedule management for the management of small-scale residential developments.
4. Conclusion
The study aimed to develop the budget and manage the schedule of a single-family residential construction, promoting the integration between financial planning and the project’s temporal control. It was verified that the decomposition of the scope through the Work Breakdown Structure (WBS) and the Bottom-Up budgeting method allowed for a detailed understanding of operational complexity, linking physical quantities and monetary costs to work packages. It was observed that resource allocation was concentrated in the structural phases, such as the superstructure, and in intermediate and final stages, such as roofing and finishes, highlighting the need for priority monitoring. The WBS acted as an integrating instrument, transforming the scope into manageable and measurable units, which strengthened the coherence between financial and temporal planning.
In schedule management, the WBS (Work Breakdown Structure) based structuring made dependency relationships and the most sensitive points visible. It was identified that the temporal effort was concentrated in the initial phases of design, foundations, structure, and masonry, which conditioned the release of subsequent stages. The application of the Critical Path Method (CPM) allowed for the identification of critical activities, directing monitoring and resource allocation. The use of the Plan-Do-Check-Act (PDCA) cycle enabled continuous adjustments in sequencing and greater control of interdependencies, especially in phases with parallel activities. This integrated approach ensured greater predictability of the construction timeline and costs, reducing exposure to significant deviations. The study’s main contribution lies in demonstrating the applicability of an integrated cost and schedule management model for single-family residential construction, promoting greater operational efficiency, predictability of results, and better support for decision-making. However, a methodological limitation observed was the non-inclusion of complementary projects, such as plumbing, electrical, and interior design, in the detailed budget, due to the unavailability of these documents at the time of the research. This implied the exclusion of more detailed items associated with these disciplines. For future studies, it is recommended to expand the analysis by comparing the planning with the actual execution of the work, as well as incorporating physical-financial performance indicators, in order to deepen the evaluation of the effectiveness of the adopted management tools.
Bibliographic References
Felisberto, A. D.; Marchiori, F. F.; Love, P.; Signor, R.; Lima, C. R. (2021). Diretrizes para orçamentação de obras públicas brasileiras: aprimorando precisão e transpar
Maués, F. C. A.; Melo, K. P.; Leão, C. B. O.; Serra, Sheyla Mara Baptista. (2022). Estimativa de custos paramétricos de construção de edifícios usando modelo de regressão linear. São Carlos: Universidade de São Paulo. Disponível em: https://doi.org/10.11606/gtp.v17i2.168355. Acesso em: 06 out. 2025.
Taioka, T.; Sanches, M.; Brenck, C.; Oliveira, R. (2023). O Novo Programa de Aceleração do Crescimento (PAC): comparação com os PACs anteriores e estimativa de seu efeito no PIB. Nota de Política Econômica MADE/USP. Disponível em: https://madeusp.com.br/publicacoes/artigos/npe-45-o-novo-programa-de-aceleracao-do-crescimento-pac-comparacao-com-os-pacs-anteriores-e-estimacao-de-seu-efeito-no-pib/. Acesso em: 06 out. 2025.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq