Development of a proposal for improvements through project management methodologies for a non-profit engineering organization

Luís Felipe Melo Barros; Ailton José do Amaral

DOI: 10.22167/2675-6528-202601128

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

Project management in non-profit organizations faces unique challenges, demanding efficient approaches to optimize resources and deliverables. The study aimed to analyze the project management practices of a non-profit engineering organization, identifying gaps and proposing improvements through the integrated implementation of the agile methodologies Scrum and Kanban to enhance operational efficiency, flexibility, and alignment with the institutional mission. A qualitative, exploratory, case study approach was adopted, using SWOT analysis and the Cause-and-Effect Diagram to diagnose problems such as lack of planning, volunteer turnover, and resource constraints. Data collection included literature review, document analysis, and unstructured interviews with leaders and volunteers, and content analysis was employed to interpret the findings. An action plan was proposed with staggered training, definition of OKRs, configuration of digital boards in Notion, and establishment of work-in-progress limits. Initial implementation steps, including training leaders and volunteers, resulted in greater transparency, agility in task prioritization, and engagement. A transition to more objective daily meetings and a noticeable reduction in rework were observed. It was concluded that the combination of Scrum and Kanban proved to be viable for the organization’s context, standardizing roles, creating a responsibility matrix, and establishing work-in-progress limits. Expansion of the model and continuous monitoring with flow metrics to validate future quantitative gains are recommended.

Keywords: Social engineering; Process optimization; Non-governmental organizations; Transparency; Volunteering.

1. Introduction

Non-profit organizations play a crucial role in social and technical development, filling gaps that the public and private sectors often fail to reach. Entities like Engineers Without Borders (EWB) operate with the mission of promoting well-being and advancement in vulnerable communities, facing unique challenges in project management. In Brazil, EWB has expanded significantly, establishing dozens of chapters and mobilizing thousands of volunteers in projects aimed at improving quality of life (EWB, 2022). The Viçosa chapter, the subject of this study, in partnership with the Federal University of Viçosa, has faced recurring problems such as delays, resource waste, rework, and cost overruns. These difficulties are attributed to deficiencies in scope planning and control, directly impacting deadlines and quality. Effective project management is imperative to optimize resources and ensure sustainability.

Project management, according to the PMBOK Guide (2013), involves applying knowledge to control deadlines, costs, and resources, mitigating risks. Traditionally, the predictive approach emphasizes detailed planning and rigorous control of scope, time, and budget, seeking predictability in stable environments (Keeling & Branco, 2014; Rodrigues & Rabetti, 2021). However, this rigidity proves limited in dynamic contexts with changing requirements, such as those of non-profit organizations, where the difficulty in incorporating changes quickly compromises adaptability and efficiency (Lima & Santos, 2021). In this scenario, agile methodologies emerge as a robust alternative, standing out for their ability to respond to changes and promote collaboration (Branco, 2023).

Among the agile methodologies, Scrum and Kanban stand out. Scrum, based on empirical control, prioritizes transparency, inspection, and rapid adaptation, organizing work in short, iterative cycles (*sprints*) to deliver usable increments and obtain *feedback* (Schwaber & Sutherland, 2020; Larman & Vodde, 2016). Kanban, a visual flow management method, adopts a *pull* model, promoting transparency about task *status* and identifying bottlenecks, with principles of visualization, limiting work in progress (*WIP*), flow management with metrics (*lead time*, *throughput*), and continuous *feedback* (Soler, 2022; Galhardo et al., 2017). The combination of these methodologies offers a balance between predictable cadence and flow flexibility, suitable for contexts that demand structure and adaptability.

The fragilities observed in the Engineers Without Borders chapter in Viçosa, such as the lack of integrated planning, high volunteer turnover, and resource constraints, align with challenges faced by other non-profit organizations. A study by Oyekunle and Anibaloye (2025) revealed that sixty-four percent of projects in NGOs exceeded the initial deadline and fifty-one percent suffered rework, attributed to the absence of standardization and volunteer turnover, factors that the PMBOK Guide (2013) also points to as causes of variance. In other sectors, such as civil construction, Kashikar et al. (2016) identified average delays of twenty-two percent and cost increases in projects with fragile scope control. However, the introduction of agile rituals in this context resulted in a thirty percent reduction in the *lead time* of construction fronts, mainly by increasing bottleneck visibility. This empirical data reinforces the universality of management problems and the potential effectiveness of agile methodologies in mitigating these issues.

In this scenario, the need to optimize project management in organizations like Engineers Without Borders – Viçosa Chapter is evident, given the complexity of the challenges and the criticality of their resources. The implementation of approaches that promote operational efficiency, flexibility, and alignment with the institutional mission is fundamental for the sustainability and social impact of the projects. Thus, the present research is justified by the urgency to propose innovative solutions for the gaps identified in the organization’s project management practices, aiming to improve value delivery to the community. The study aims to analyze the project management practices of a non-profit engineering organization, identifying gaps and proposing improvements through the integrated implementation of the agile methodologies Scrum and Kanban to enhance operational efficiency, flexibility, and alignment with the institutional mission.

2. Material and Methods

This research was classified as applied, seeking to solve real problems identified in the project management of a non-profit organization, as advocated by Gil (2002). A qualitative approach was adopted, which prioritizes the in-depth understanding of observed phenomena and the interpretation of the meanings of human relationships, essential elements for the accumulation of scientific knowledge (Carvalho, 2021; Marconi and Lakatos, 2010). Regarding the objectives, the study is exploratory in nature, aiming to elaborate and clarify concepts, as well as to formulate more precise problems for future investigations (Gil, 2002).

The study was developed in the context of Engineers Without Borders – Viçosa Chapter, a non-profit organization that partners with the Federal University of Viçosa, located in the southeastern region of Minas Gerais. The unit of analysis consisted of the project management practices adopted by this organization. The data collection period for the initial diagnosis covered reports and documents from the year 2025, while the implementation and monitoring phase of improvements occurred between January and July 2026, a period of mentoring and application of agile methodologies.

The study population was composed of active members of Engineers Without Borders – Viçosa Chapter. The sample included fourteen subjects, consisting of three veteran leaders from the organization’s permanent staff and eleven volunteers working part-time. The selection criteria for interview participants were acting as a leader of the entity, ensuring the coverage of all leadership positions, and active participation as a volunteer in projects, aiming to capture perceptions of current processes and proposed improvements. Participatory research, according to Gil (2002), actively involved researchers and the researched.

Data collection was carried out through a multifaceted approach, combining bibliographic research, document analysis, and unstructured interviews. The bibliographic research involved reviewing books, scientific articles, and other relevant sources to support the topics of project management and agile methodologies. Document analysis included reviewing screenshots of internal systems, PDF reports of projects completed in 2025, and the project control spreadsheet used by the organization, providing an overview of existing practices. These documents were provided by the entity’s leaders.

Unstructured interviews were conducted with all leaders of the entity, both in person and via video call, and records were kept in field notes. The objective was to capture the leaders’ perceptions of the current project management processes and their expectations regarding the proposed improvements. This approach allowed for a deeper understanding of the operational challenges and internal dynamics of the organization, complementing the data obtained through documentary and bibliographic analysis.

During the implementation phase of the improvements, instruments were used that also served as data sources for the process evaluation. A digital Scrum Board was configured on the Notion platform, allowing for table and Kanban views, recording the status, priority, responsible person, deadline, and last edit date of projects and tasks. Additionally, a physical Kanban board was implemented for pedagogical purposes, enabling the visualization and movement of project cards. The Scrum artifacts, such as Product Backlog, Sprint Backlog, and Increment, were defined and used, generating records on planning and deliveries.

The research execution followed two main stages. The first stage, diagnostic, focused on identifying and analyzing the organization’s current project management practices. For this, gaps and restrictive factors were identified through the application of the SWOT Matrix (Strengths, Weaknesses, Opportunities, Threats) and the Cause-and-Effect Diagram (Ishikawa). This phase aimed to map how existing deficiencies impacted project schedule, cost, and quality, providing a solid basis for proposing improvements. Interviews and document analysis were crucial for this phase.

The second stage consisted of the construction and implementation of an action plan based on the agile methodologies Scrum and Kanban, defining roles, rituals, artifacts, and work in progress (WIP) limits. The implementation and monitoring of these adjustments were carried out during a two-month cycle, aiming to increase operational efficiency, make the workflow more flexible, optimize resources, and align deliveries with the institutional mission. To guide this transition, a six-month mentorship schedule was developed, from January to July 2026, with structured sessions.

The mentoring schedule detailed the activities to ensure a gradual and supported introduction to agile methodologies. It included the presentation of improvement proposals, specific training for leaders, goal alignment meetings to define OKRs and WIP limits, and awareness training for all volunteers. Subsequently, small group training sessions were conducted, focusing on the practical application of tools, such as filling out the Product Backlog and moving cards. The final phase involved assisted application of the methods and feedback and adjustment sessions, aiming to consolidate practices and achieve continuous improvement.

The collected data were submitted to a qualitative analysis and treatment, using the Content Analysis technique proposed by Bardin (2006). This technique comprises three distinct moments: pre-analysis, material exploration, and results treatment/interpretation. The choice of this approach allowed for an in-depth investigation of the meanings and patterns emerging from textual and documentary data, aligning with the exploratory and qualitative nature of the study. The focus was on understanding the organization’s perceptions and work dynamics.

In the pre-analysis phase, data sources were selected, including 2025 reports, tracking spreadsheets, system screenshots, relevant literature, and transcripts of unstructured interviews with leaders and volunteers. The analysis objectives were defined, and thematic axes were established for material organization. These axes included planning, execution, and control, each articulated with subcategories such as scope, schedule, resources, communication, and people, allowing for an initial structuring to identify patterns of fragility and opportunities for improvement.

The material exploration stage involved an exhaustive reading of all collected content, followed by the organization of records into predefined thematic categories. We sought to identify regularities, recurrences, and divergences in the data, which could highlight the challenges and opportunities in project management. Finally, in the treatment and interpretation of results, the findings were related to the theoretical frameworks of project management and Agile methodologies, allowing for the production of coherent inferences and the support of the improvement proposals presented in the study.

The study presented some important methodological limitations. The improvement implementation cycle, lasting five months, did not allow the completion of a full sprint of planning, execution, and delivery, which made it impossible to generate robust data for a “before and after” comparison. Additionally, the organization did not have standardized metrics for *lead time* or rework, which hindered the establishment of a reliable baseline for quantitative evaluation. The absence of standardized historical comparative data was also a limiting factor for performance analysis.

Another relevant limitation was the reduced number of participants in the sample, which may impact the generalization of the findings to other contexts. The high turnover of volunteers, a characteristic of academic organizations such as Engineers Without Borders, also represented a challenge, potentially affecting the consistency in the adoption of the proposed methodologies and the continuity of practices. These factors indicate that the initial results obtained are predominantly qualitative and serve more as a proof of concept of the viability of agile methodologies in the studied context.

3. Results and Discussion

The project management practices observed in the organization Engineers Without Borders – Viçosa Chapter, before the intervention, revealed a complex scenario, characterized by challenges inherent both to the non-profit sector and to the particularities of an academic environment with high volunteer turnover. The initial analysis of the 2025 reports and spreadsheets, as detailed in Table 1 of the original document, indicated that the organization managed seven active projects, with an average duration of six months and an average budget between R$ 1,000.00 and R$ 1,500.00. The total number of volunteers was 35, with project teams composed of four to six people. This data, although not presented here in table format to avoid duplication and adhere to the established limit, served as a starting point for understanding the scale and nature of the organization’s endeavors. The relevance of these projects, focused on architectural, electrical, and fire prevention solutions for vulnerable communities, as well as technical training and mentoring, underscores the importance of efficient management to maximize social impact.

The depth of the challenges was better understood through the development of the SWOT Matrix and the Cause-and-Effect Diagram, crucial tools for diagnosis. The SWOT Matrix, presented in Table 1, outlined the strengths, weaknesses, opportunities, and threats that permeated the organization’s project management.

Table 1. SWOT Matrix

Dimension

Main findings

Strengths (Strengths)

– Majority of projects are structured to be completed within 12 months, with partial deliveries in 4-6 months;
– Pool of 40 to 50 engineering undergraduate volunteers per year, with qualified labor;
– Access to academic infrastructure (laboratories, professors, partner network), facilitating mentorship and low-cost solutions;
– Production of technical manuals and checklists.

Weaknesses

– Delays, waste, changeable scope, planning and time management failures;
– Volunteer turnover;
– Difficulty in attracting sponsorships;
– Dependence on external technical advisors, which limits project completion;
– Irregular internal communication and low initial adherence in some training sessions;

Opportunities (Opportunities)

– Limited monitoring of construction execution after project delivery.
– Alignment with SDGs.
– Cooperation with 60 national ESF hubs;
– Trend of funders preferring projects with agile metrics;
– Recognition in conferences (CBESF) and awards;
– Proficiency in CAD/BIM software by members.

Threats

– Intense competition for resources: donors have restricted transfers and demand proven efficiency;
– Economic instability that can cancel activities and increase material costs;
– Dependence on volunteerism: academic terms, internships, or graduations can deplete critical teams;
– Scarcity of available advisors or tutor professors;
– Variation in material prices impacts social project budgets.

Source: Authorial (2026)

Among the strengths, the project structure with partial deliveries in 4-6 months, a pool of 40 to 50 qualified engineering volunteers annually, access to the academic infrastructure of the Federal University of Viçosa, and the production of technical manuals and *check-lists* stand out. These strengths represent significant assets, such as the availability of qualified human capital and institutional support, which, if well managed, could mitigate many of the weaknesses. The existence of partial deliveries, for example, already demonstrates an inclination towards shorter work cycles, which aligns with agile principles of continuous feedback and incremental deliveries (Schwaber & Sutherland, 2020). However, the lack of a formal structure to fully capitalize on these strengths was evident.

The weaknesses, in turn, were numerous and impactful: delays, waste, mutable scope, planning and time management failures, high volunteer turnover, difficulty in attracting sponsorships, dependence on external technical advisors, and irregular internal communication. These findings corroborate the literature that points to common challenges in non-profit organizations, where project management often lacks formalization and dedicated resources (Oyekunle & Anibaloye, 2025). Volunteer turnover, in particular, is a critical weakness, as it fragments knowledge and requires constant training cycles, increasing the risk of errors and delays, a problem widely recognized in volunteer work environments (PMI, 2013). Irregular internal communication, in turn, is a classic obstacle to team coordination and alignment, as discussed by Keeling and Branco (2014), who emphasize communication as one of the pillars of effective project management.

The opportunities included alignment with the Sustainable Development Goals (SDGs), cooperation with other 60 national ESF hubs, the trend of funders preferring projects with agile metrics, recognition in congresses and awards, and the mastery of CAD/BIM software by members. These opportunities indicate fertile ground for the adoption of more efficient practices and for strengthening the organization. Funders’ preference for agile metrics, for example, is a strong incentive for the transition, as it demonstrates that the market and partners value the transparency and adaptability that agile methodologies offer (Branco, 2023).

Threats, such as intense competition for resources, economic instability, reliance on volunteers (with academic terms and graduations emptying teams), scarcity of mentors, and variation in material prices, added a layer of complexity and uncertainty. Reliance on volunteers, while being the essence of the organization, also constitutes a threat due to its intermittent nature and the difficulty in maintaining work continuity, a challenge that Agile methodologies, with their emphasis on processes and documentation, can help mitigate (Soler, 2022).

The lack of integrated planning and scope control, evidenced by the SWOT Matrix, directly compromised the time-cost-quality tripod. Unformalized changes resulted in rework, extended schedules, and strained already tight budgets. This finding aligns with what Oyekunle and Anibaloye (2025) observed in other NGOs, where 64% of projects exceeded the initial deadline and 51% suffered rework due to a lack of standardization and high volunteer turnover. These phenomena are described by the PMBOK Guide (PMI, 2013) as classic causes of project variance, highlighting the universality of these challenges. Procedural fragility, with the dispersed use of spreadsheets and scope changes without replanning, amplified rework and inefficiency.

To deepen the understanding of the root causes, the Cause-and-Effect (Ishikawa) Diagram was developed, presented in Figure 1.

Source: Authorial (2026)

Figure 1. Cause-and-Effect Diagram

The diagram revealed that the causes were concentrated on three main fronts: materials, methods, and people, with a common denominator of lack of systemic visibility and short feedback cycles. In the Materials category, the limited budget for acquiring inputs and the lack of reliable suppliers directly impacted late delivery and quality. In Methods, poor definition of requirements, scope changes without deadline/cost review, and lack of standardization were critical factors. The absence of unified software and excessive reliance on manual tools (isolated spreadsheets) were identified in the Machines category (which in this context refers to tools and technology). Finally, in the People category, volunteer turnover, insufficient training, and informal communication and meetings were significant causes. The environment, with price inflation, weather conditions, and economic instability, also contributed to the problems. The lack of key performance indicators (KPIs) and insufficient estimation of duration and budget were categorized under Measurement.

This multifaceted analysis of the Ishikawa Diagram reinforces the need for an integrated approach to improving project management. The interconnection of causes demonstrates that solving a problem in isolation would not be sufficient; a systemic intervention was needed to address the roots of the lack of visibility and feedback. Kashikar et al. (2016) observed similar patterns in the construction sector, where average delays of 22% and cost increases were common in projects with fragile scope control. The introduction of agile rituals, in this context, reduced the *lead-time* of construction fronts by 30%, mainly by making material and communication bottlenecks visible, which validates the premise that transparency and rapid feedback are essential for efficiency.

Given this diagnosis, the proposal for improvements was based on the combined application of the agile methodologies Scrum and Kanban, aiming to mitigate rework, stabilize teams, and optimize resource utilization. Scrum, as an agile framework, is based on empirical process control, prioritizing transparency, inspection, and rapid adaptation (Schwaber & Sutherland, 2020). It organizes work into short, fixed cycles, called *sprints*, generally lasting two to four weeks, with the goal of delivering a usable increment at the end of each cycle, allowing for rapid feedback and real-time risk mitigation (Larman & Vodde, 2016).

The flow of the Scrum Framework, as illustrated in Figure 2, details the roles, artifacts, and events that comprise it.

Source: Oliveira (2025)

Figure 2. Scrum Framework Flow

Figure 2 demonstrates that the process begins with the *Product Backlog*, a prioritized list of requirements maintained by the *Product Owner*. At the start of each *sprint*, the team holds the *Sprint Planning* to select high-value items and detail the *Sprint Backlog*. During execution, the *Daily Scrum* is a 15-minute daily meeting to inspect progress and adjust the plan. At the end of the cycle, the *Increment* is presented at the *Sprint Review*, generating immediate feedback, and the team conducts the *Sprint Retrospective* to reflect on the process and define improvements (Oliveira, 2025). This structure, with its formal events and artifacts such as *Product Backlog*, *Sprint Backlog*, and *Increment*, ensures daily alignment, continuous inspection, and incremental improvement, directly addressing the planning and communication weaknesses identified in the SWOT. The clarity of roles (Product Owner, Scrum Master, Development Team) also contributes to reducing dependence on external advisors and irregular communication.

Complementarily, Kanban, originating from the Toyota production system, is a visual flow management method that adopts the *pull* model, where activities advance only when there is free capacity in the next stage (Soler, 2022). Its principles include visualizing work, limiting work in progress (WIP), measuring and managing flow through metrics such as *lead time* and *throughput*, and implementing continuous feedback. Unlike Scrum, Kanban does not impose fixed roles or *time-boxes*, allowing for a gradual and less disruptive evolution of the existing process (Galhardo et al., 2017). The combination of Scrum and Kanban, known as Scrumban, offers a balance between Scrum’s predictable cadence and Kanban’s flow flexibility, being ideal for the organization’s context that required gradual adaptation rather than a complete revolution.

The implementation of the improvements began in January 2026 with an alignment meeting with the six functional leaders of the organization. In this meeting, the synthetic diagnosis of the SWOT Matrix and the Cause-and-Effect Diagram was presented, highlighting how delays, rework, and resource volatility compromised the deadlines, costs, and quality of the projects. The vision of Scrum and Kanban was introduced, emphasizing their ability to generate short feedback cycles, reduce waste, and maximize value for the community.

For operationalization, a digital Scrum Board was configured on the Notion platform, which combines a relational database with multiple views, facilitating the transition between the tabular view and the Kanban board by status. In the table view, volunteers record, for each project, the Status (planned, in progress, completed), Priority, DRI (*Directly Responsible Individual*), Deadline, and date of the Last edit. These fields function as dynamic filters and sorting options, allowing for the generation of instant reports on workload or priorities. Figure 3 illustrates this table view.

Source: Authorial (2026)

Figure 3. Digital Scrum board using Notion

The table view, as demonstrated in Figure 3, allows for granular and transparent project management. The ability to filter and sort by status, priority, or responsible person is fundamental for the quick identification of bottlenecks and for agile decision-making, a significant advancement compared to the scattered use of spreadsheets and the lack of standardization observed in the diagnosis. This digital tool, by centralizing information and making it accessible, directly addresses the weakness of irregular internal communication and the lack of systemic visibility, allowing all team members to have a clear understanding of the current status of projects and their responsibilities. Assigning a DRI to each task or project, for example, promotes individual and collective accountability, a central principle of effective project management (PMI, 2013).

Besides the table view, the Notion platform also allows a Kanban view, which automatically groups projects by the Status column, reproducing the “Planned → In progress → Completed” flow. This view, although not presented here as a separate figure to adhere to the figure limit, is equally important as it offers quick visual feedback on progress and bottleneck identification. The color-coded priority (high, medium, low) and deadline are displayed, providing immediate visual feedback on delays. The initial guideline was that as soon as each team finished its *Product Backlog*, they would add new cards or update existing ones, defining responsible parties, realistic deadlines, and acceptance criteria. Notion also allows creating a specific Task database (Figure 5 in the original document), linked to the respective project, where the volunteer inserts the task Status, Priority, Responsible, Deadline, and Last edited date. This structure automatically integrates with the main board, offering fine-grained traceability between the strategic (project) and operational (tasks) levels.

Real-time transparency is the foundation of Scrum, and the daily update of the board in Notion was emphasized as crucial. Without accurate data on status, responsible parties, and deadlines, the *Daily Scrum* loses its effectiveness, hindering the early identification of impediments and the agile redistribution of tasks (Oliveira, 2025). The daily update also ensures that *lead time* and rework indicators reflect reality, enabling immediate adjustments before delays turn into additional costs.

In parallel with the digital Scrum board, a physical Kanban board was implemented for pedagogical purposes, with physical cards affixed to a wall. This option, although Figure 6 of the original document illustrates a more general “Visual Management” and “Our Projects” board, aimed to allow volunteers to visualize the volume of projects at each stage, move cards, and internalize WIP limits before migrating to the *online* solution. The assembly of the pilot board with information from previous completed projects (2024-2025) served as illustrative material to demonstrate the ideal format for filling out and applying the Kanban method. This pedagogical approach is fundamental in volunteer organizations, where adherence to and understanding of new practices can be a challenge (Moe et al., 2021).

To ensure a gradual and guided introduction to agile methodologies, a six-month mentorship schedule was developed, from January to July 2026, detailing the macro-activities. Although Table 3 and Table 4 of the original document detail this schedule and activities, they will not be included here as separate tables to adhere to the established limit. However, the schedule included the presentation of improvement proposals, specific training for leaders, goal alignment meetings to define OKRs and WIP limits, awareness training for all volunteers, small group training focused on the practical application of tools, and finally, assisted application of methods and feedback and adjustment sessions. This structured approach is vital for the successful adoption of new methodologies, especially in contexts with high staff turnover, such as Engineers Without Borders (Lima & Santos, 2021).

The initial results, although partial due to the study’s temporal limitation (five months of implementation did not allow the completion of a full planning-execution-delivery *sprint*), already indicate significant progress. Table 2 presents a preliminary comparison between the practices of 2025 and the advances obtained from January to April 2026.

Table 2. Preliminary comparison between the 2025 practices and the advances obtained from January to April 2026

Operational indicator

2025 (reference)

Jan. 26

Feb/26

March 26

Apr/26

Formal project kick-off meetings

1 general meeting for initiation and another for closing

1

1

1

Daily meetings held

0

7

7

8

12

Volunteers trained in the tools

0

3 leaders

+10 vol.

+17 vol.

All volunteers.

Cards inserted/updated on the digital board

7

12

18

+ than 25

Formalized and published OKRs

3 macro-OKRs

% of tasks with a defined deadline

35%

50%

68%

75%

82%

Perception of transparency (1-5)

2,1

3,0

3,6

4,1

4,3

Source: Authorial (2026)

The analysis of Table 2 reveals notable improvements in several operational indicators. The number of *Daily Meetings* held went from zero in 2025 to 7 in January and February 2026, 8 in March, and 12 in April. This exponential increase in daily meetings is a direct indication of the adoption of Scrum, which advocates for the *Daily Scrum* as a fundamental event for daily alignment and progress inspection (Schwaber & Sutherland, 2020). The higher frequency of these meetings, as reported by leaders, resulted in more objective discussions and faster prioritization decisions, reducing the risk of rework and delays. This demonstrates that the transparency provided by the digital board and the cadence of daily meetings are beginning to generate a more efficient and proactive workflow.

The training of volunteers in the tools also showed progress. From zero trained volunteers in 2025, the number rose to 3 leaders in January, +10 volunteers in February, +17 in March, and all volunteers in April. This gradual training, according to the mentoring schedule, is essential for the internalization of new practices. The high adherence to training and volunteer engagement, evidenced by the presence of 85% of active members in the general presentation session (Figure 7 in the original document), suggest a positive receptivity to agile methodologies. Continuous training is crucial to sustain change in organizations with high turnover, ensuring that knowledge is transferred and practices are maintained (Rodrigues & Rabetti, 2021).

The use of the digital board also grew consistently, with 7 cards inserted/updated in January, 12 in February, 18 in March, and over 25 in April. This increase in card registration and updating in Notion indicates greater formalization and visibility of tasks and projects. The transition from isolated spreadsheets to a unified and dynamic system, such as Notion, is a fundamental step towards overcoming the procedural fragility and lack of standardization identified in the diagnosis. The ability to generate instant reports on workload and priorities, previously non-existent, now allows for more strategic management of resources and time.

The formalization and publication of OKRs (Objectives and Key Results) is another important advancement. Three macro-OKRs were defined, representing a gain in operational clarity compared to the pre-intervention scenario, where there were no standardized metrics. The definition of OKRs aligns the organization’s activities with its institutional mission and strategic objectives, providing clear direction for all involved (Branco, 2023).

The percentage of tasks with defined deadlines increased significantly, from 35% in 2025 to 50% in January, 68% in February, 75% in March, and 82% in April 2026. This indicator, calculated according to Figure 8 of the original document, demonstrates greater rigor in planning and time management. The clear definition of deadlines is a critical component for effective project management, as it allows for progress monitoring and early identification of deviations (PMI, 2013). The increase in this percentage reflects greater discipline in the team and better use of agile tools to manage the schedule.

The perception of transparency, measured on a Likert scale from 1 to 5, also improved from 2.1 in 2025 to 3.0 in January, 3.6 in February, 4.1 in March, and 4.3 in April 2026. This constant increase in the perception of transparency is one of the most impactful results of the implementation of agile methodologies. Transparency, one of the pillars of Scrum, is fundamental for building trust, promoting collaboration, and facilitating the identification and resolution of impediments (Schwaber & Sutherland, 2020). The improvement in the clarity of project tracking, as reported by volunteers, indicates that digital tools and daily meetings are fulfilling their role in making work more visible and understandable to everyone.

Despite these promising results, it is crucial to acknowledge the study’s limitations. The five-month implementation cycle did not allow for the completion of a full planning-execution-delivery *sprint*, which made it impossible to generate robust data for a “before and after” quantitative comparison of metrics such as *lead time* or rework. The organization also lacked standardized historical metrics, which hindered the establishment of a reliable baseline for quantitative evaluation. This absence of standardized comparative data is a common limitation in case studies of organizations that are beginning to formalize their processes (Yin, 2001). Therefore, the initial results are predominantly qualitative and serve more as a proof of concept for the feasibility of Agile methodologies in the studied context, rather than a statistical performance evaluation.

The high turnover of volunteers, a characteristic of academic organizations, also represents a continuous challenge for consistency in the adoption of methodologies. However, continuous training and process documentation, such as existing technical manuals and checklists, and the formalization of Scrum roles and artifacts, can mitigate this impact, ensuring that knowledge is institutionalized and does not depend exclusively on the individual memory of volunteers (Carvalho, 2021).

In summary, the combined application of Scrum and Kanban has proven to be a viable approach to address the main gaps diagnosed in the project management of the Engineers Without Borders – Viçosa Chapter organization. The initial steps of presentation, leader training, and OKR definition standardized roles, created a framework of responsibilities, and established work-in-progress limits, increasing transparency and predictability. The initial results, although qualitative, point to more objective daily meetings, greater engagement on the digital board, and faster priority decisions, indicating a lower risk of rework and delays. The completion of the training batches and the next phase of assisted application will allow for the collection of *lead time*, *throughput*, and stakeholder satisfaction metrics, consolidating the quantitative gains.

The practical implications of these findings are significant. For the organization, the adoption of agile methodologies represents a path to optimize the use of scarce resources, make the workflow more flexible, and align deliveries with the institutional mission more efficiently. Greater transparency and continuous feedback promote a more collaborative and engaging work environment, which can, in the long run, contribute to volunteer retention and the building of more robust intellectual capital. For other non-profit organizations, this study offers a model of how agile methodologies can be adapted to overcome common project management challenges, even in contexts with limited resources and high turnover. The emphasis on continuous training and the creation of a measurement infrastructure (digital boards, WIP limits, OKRs) is a valuable lesson for any entity seeking to improve its operational efficiency.

Future studies should follow several complete cycles of *sprints*, consolidate quantitative indicators, and compare annual series to validate the real impact of the proposed improvements. Expanding the model to other cores of the Engineers Without Borders network, after confirming the time and cost gains in the pilot cycle, is also an important recommendation. The research demonstrated that agile methodologies are viable in volunteer organizations when accompanied by continuous training and simple metrics, paving the way for more effective and sustainable project management in the social sector.

4. Conclusion

It is concluded that the objective was achieved by analyzing the project management practices of Engineers Without Borders – Viçosa Chapter, identifying its gaps, and proposing improvements through the integrated implementation of the agile methodologies Scrum and Kanban. The application of these approaches proved to be viable for enhancing operational efficiency, flexibility, and alignment with the organization’s institutional mission. Initial results, although predominantly qualitative, indicated significant progress in process formalization, management transparency, and volunteer engagement. The standardization of roles, the creation of a responsibility matrix, and the establishment of work-in-progress limits contributed to more objective daily meetings, faster priority decisions, and a general perception of greater clarity in project tracking, signaling a lower risk of rework and delays.

However, it is crucial to acknowledge the limitations of this study. The five-month implementation cycle did not allow for the completion of a full plan-execute-deliver cycle, making it impossible to collect robust data for a “before and after” quantitative comparison of metrics such as *lead time* or rework. Furthermore, the absence of standardized historical metrics within the organization hindered the establishment of a reliable baseline. The high volunteer turnover, inherent in academic organizations, also presents an ongoing challenge to consistency in methodology adoption. For future studies, it is recommended to follow several complete *sprint* cycles, consolidate quantitative indicators, and compare annual series to validate the real impact of the proposed improvements. It is also suggested to expand the model to other nuclei of the Engineers Without Borders network, after confirming the time and cost gains in the pilot cycle, reinforcing the applicability and scalability of Agile methodologies in volunteer contexts.

Bibliographic References

BARDIN, Laurence et al. Análise de conteúdo (I. De a. Rego & a. Pinheiro, trads.). Lisboa: edições, v. 70, n. 3, 2006.

BRANCO, Pedro. Estratégia em projetos: geração de valor para o negócio. Editora Senac São Paulo, 2023.

CARVALHO, Maria Cecilia M. Construindo o saber: metodologia científica-fundamentos e técnicas. Papirus Editora, 2021.

ESF. Quem somos. Engenheiros Sem Fronteiras – Núcleo Viçosa, 2022. Disponível em: vicosa.esf.org.br. Acesso em: 21 mar. 2025.

GALHARDO, Larissa Cristina et al. Implementação do quadro kanban na linha de produção. In: VI JORNACITEC-Jornada Científica e Tecnológica. 2017.

GIL, Antônio Carlos et al. Como elaborar projetos de pesquisa. São Paulo: Atlas, 2002.

KASHIKAR, Ajendra et al. A case study on agile and lean project management in construction industry. IOSR Journal of Mechanical and Civil Engineering, v. 13, n. 4, p. 31-39, 2016.

KEELING, Ralph; BRANCO, Renato Henrique Ferreira. Gestão de projetos. Saraiva Educação SA, 2017.

LARMAN, Craig; VODDE, Bas. Large-scale scrum: More with LeSS. Addison-Wesley Professional, 2016.

LIMA, Ana Luiza Ferreira; SANTOS, Alex Silva. Gestão Híbrida de Projetos: o Modelo FLEKS. Boletim do Gerenciamento, v. 31, n. 31, p. 46-55, 2022.

MARCONI, Marina de Andrade; LAKATOS, Eva Maria. Metodologia. 5ª edição. São Paulo, SP. Editora Atlas, 2010.

MOE, Nils Brede et al. Finding the sweet spot for organizational control and team autonomy in large-scale agile software development. Empirical Software Engineering, v. 26, n. 5, p. 101, 2021.

OLIVEIRA, Elias Miguel. Implementando Scrum na sua Empresa. Elias Miguel De Oliveira, 2025.

OYEKUNLE, David Oyewumi Taiwo; ANIBALOYE, Ifeoluwa. Beyond Profit for Social Good: Project Management Practices in the Operations of Not-for-Profit Organizations: A Case Study of Performance for All Northwest. Open Journal of Business and Management, special, n. 123, 2024.

PMBOK, G. Um guia do conhecimento em gerenciamento de projetos. Quarta Edição, v. 123, 2013.

RODRIGUES, Ivete; RABETTI, Danilo. Gestão adaptativa de projetos: um levantamento dos artefatos mais utilizados para gerenciar o escopo do projeto. Gestão e Projetos: GeP, v. 12, n. 1, p. 95-122, 2021.

SCHWABER, Ken; SUTHERLAND, Jeff. The scrum guide. Scrum Alliance, v. 21, n. 19, p. 1, 2020.

SOLER, Alonso Mazini. Abordagens ágeis para projetos e processos. Editora Senac São Paulo, 2022.

YIN, Robert K. Estudo de caso: Planejamento e métodos (2nd ed.). Bookman, 2001.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.