Development of a Power BI dashboard for the integration of PMBOK knowledge areas
Liliane Ribeiro de Oliveira Schneider; Lorena Hernández Mastrapa
DOI: 10.22167/2675-6528-202601082
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The growing complexity in project management in engineering companies has increased the need for integration and standardization of information for effective monitoring. The study aimed to develop a Power BI dashboard for project management, seeking to promote the integration and standardization of information from the main PMBOK knowledge areas in a project and construction management company. The investigation was classified as descriptive, with a qualitative-quantitative approach, adopting a single case study design. Methodological procedures included information gathering from the board of directors, detailed dashboard planning, data modeling with treatment for standardization and consistency, solution development, and results validation. As main results, a dashboard was developed, capable of consolidating performance indicators related to schedule and cost, as well as monitoring information from other relevant areas, promoting greater integration, standardization, and clarity in data presentation. Validation with the board of directors indicated the solution’s full adherence to managerial needs, highlighting its potential as a robust tool for supporting project monitoring. It was concluded that the integrated Power BI dashboard contributed significantly to project status reporting and to the integration of PMBOK knowledge areas, representing an applicable and valuable solution for the context of the studied company.
Keywords: Case study; Performance indicators; Standardization; Decision making.
1. Introduction
Digital transformation has been redefining the corporate landscape, driving engineering and project management companies to adopt innovative approaches to managing their ventures. The inherent complexity of modern projects, characterized by multiple *stakeholders*, resources, and deadlines, demands robust integration and standardization of information for effective monitoring and agile decision-making (Vargas, 2022; Carvalho and Rabechini Jr., 2019). In this scenario, the application of *business intelligence* tools, such as Microsoft Power BI, emerges as a competitive differentiator, offering advanced capabilities for data consolidation and visualization. Such platforms allow organizations to gain greater control, transparency, and assertiveness in strategic and operational decisions, by converting large volumes of raw data into actionable *insights* (PMI, 2021; Oliveira, 2020; Santos, 2021). The ability to integrate information from various sources and present it interactively is fundamental to managerial efficiency.
The *Project Management Body of Knowledge* (PMBOK Guide) establishes a set of ten fundamental knowledge areas for project management, including scope, schedule, cost, quality, resources, communications, risks, procurements, stakeholders, and integration (PMI, 2021). The effective integration of these areas is crucial for a holistic project view, allowing managers to understand the interconnections and dependencies between the various elements, avoiding information silos and isolated decisions. The standardization of information, in turn, ensures that data is collected, stored, and presented consistently, facilitating comparisons and analyses over time and across different projects. This visibility and standardization are critical factors for project management maturity and overall organizational performance, especially in environments with multiple clients and simultaneous contracts (Carvalho and Rabechini Jr., 2019; Kerzner, 2022). The absence of an integrated system can lead to suboptimal decisions and weakened project governance, compromising value delivery.
Despite the recognition of the importance of integration and standardization, many engineering companies still face significant challenges in managing their information. It is common for project data to be fragmented, distributed across various spreadsheets and manual reports, which hinders the integrated monitoring of PMBOK knowledge areas. This information dispersion, ranging from scope and schedule control to cost, quality, and risk management, generates a series of operational problems. Among these, rework in data consolidation, inconsistencies in information, delays in preparing status reports, and consequently, delays in critical decision-making stand out. The lack of integration between management and control processes compromises performance analysis and the teams’ ability to respond to deviations, negatively impacting project efficiency and performance (Vargas, 2022; Souza, 2022). Studies indicate that the difficulty in consolidating schedule and cost information, for example, is a constant barrier to proactive monitoring and early identification of deviations, resulting in losses of efficiency and optimization opportunities.
Given this scenario, the relevance of this study lies in its contribution to overcoming data fragmentation in engineering companies, aligning best practices in project management with business intelligence technologies. The standardization and integration of information are essential to improve monitoring and decision-making, promoting greater transparency and operational efficiency. Thus, this work aimed to develop a Power BI dashboard for project management, seeking to promote the integration and standardization of information from the main PMBOK knowledge areas in a project and construction management company.
2. Material and Methods
The research adopted a descriptive classification, focusing on the analysis and documentation of the dashboard development stages (Gil, 2010; Gil, 2017). Regarding the nature of the data, a qualitative-quantitative, or mixed, approach was used. The qualitative dimension sought to understand perceptions and meanings related to the phenomenon studied (Sampieri et al., 2013; Gil, 2002), while the quantitative dimension translated information into numerical data, allowing for measurements and comparisons (Turrioni and Mello, 2012; Prodanov and Freitas, 2013). This dual approach allowed for a comprehensive understanding of both the processes and the performance indicators derived from the solution.
The study was conducted in a project and construction management company, located in Curitiba, in the state of Paraná, operating in various regions of Brazil. The company operates in the engineering sector, providing planning, management, coordination, and supervision services for industrial, hospital, and corporate clients. The unit of analysis consisted of the multiple projects managed simultaneously by the company, whose information was tracked through spreadsheets filled out periodically. This scenario, characterized by the fragmentation and dispersion of data across different files, was the central motivator for choosing the organization as the object of study.
The research design was configured as a single case study, aiming for an in-depth analysis of a phenomenon in its real context (Gil, 2017; Yin, 2015; Miguel, 2007). The selection of the company as the object of study was determined by its representativeness of a practical situation where the organization and integration of managerial data were pressing needs. There was no population or sample in the statistical sense, but rather the intentional choice of an organization that faced the challenges of information fragmentation, aligning directly with the objective of developing a business intelligence solution.
For the acquisition of information and data, documentary survey and direct observation techniques were employed. The documentary survey involved the analysis of existing processes and records in the company, while direct observation allowed for the identification of behaviors and practices in the real work environment (Gil, 2017). Complementarily, structured meetings were held with the organization’s directors and managers. These interactions were crucial for identifying primary managerial needs related to the dashboard and for validating the report proposals, ensuring the solution’s alignment with specific management demands (Gil, 2017).
The method applied for the dashboard development was structured in sequential steps, following the logic of continuous process improvement, inspired by the principles of the PDCA (Plan-Do-Check-Act) cycle. This development approach guided the solution’s development from problem identification to results evaluation. The main phases included information gathering, dashboard planning, data modeling, solution development, and results analysis, ensuring a logical and systematic progression of the work.
The initial information gathering stage consisted of a meeting with the company’s board of directors, whose purpose was to identify the managerial needs for project monitoring and the strategic information for decision-making. In this alignment, priority performance indicators, focused on schedule and cost, were defined. For the other areas, such as risks, occupational safety, and operational monitoring, relevant information and monitoring records were established, without formalization as performance indicators. Additionally, the planning, control, and monitoring processes, as well as information recording practices, were mapped.
Based on the collected information, the dashboard planning was carried out, defining its informational scope. This scope considered the performance indicators for time and cost, in addition to the monitoring information from other relevant areas. The organization of information on the dashboard was carefully planned, covering the structure of the pages, the layout of the data, and the hierarchy of information. The objective was to provide an integrated view of the projects, ensuring that the planning was aligned with the board’s needs, the organization’s internal processes, and the integration proposal via Power BI.
Data modeling involved the collection, processing, and integration of essential information for dashboard construction. Initially, the data sources used by the company were identified, including planning records, deadline control, costs, and other project monitoring information. Subsequently, data processing procedures were applied, which involved standardizing formats, correcting inconsistencies, organizing databases, and adapting information for analysis. These actions aimed to ensure data consistency, reliability, and integrity.
The integration of the different databases was carried out in the Microsoft Power BI environment, consolidating the information into a single analytical model, according to the previously defined scope. The standardized reporting spreadsheets, used in the company’s projects, were stored weekly in a corporate folder. Each file followed a specific naming convention, composed of the client code, project code, project name, and reference week. Power BI was configured to automatically access this directory, read and import the data, which underwent treatment and transformation steps, centralizing planning, deadlines, costs, and monitoring information.
The development of the solution consisted of creating the dashboard pages in the Power BI environment, following the informational scope and structure defined in the planning stage. The pages were organized to allow an integrated view of the projects, offering different levels of analysis, from an overview to detailed information. For this purpose, Power BI visualization features such as charts, tables, and other visual elements were applied. Additionally, filters and navigation mechanisms between pages were configured, enabling dynamic analyses and access to information according to established criteria.
The validation of the data and results was carried out by presenting the developed dashboard to the company’s board of directors. In this stage, the adherence of the presented information to the previously identified managerial needs was analyzed, considering the presentation format, data consistency, and its usefulness in the company’s context. During the validation process, contributions and observations from the board of directors regarding the clarity of the monitoring information were collected. These interactions allowed for verification of the dashboard’s compliance with the expectations of senior management, confirming the relevance of the presented information.
The treatment and analysis of the data were intrinsic to the modeling and validation steps. In modeling, the raw data from the spreadsheets were standardized, corrected, and organized to create a consistent analytical model in Power BI. The analysis occurred during validation, where the board evaluated the clarity, usefulness, and applicability of the deadline and cost performance indicators, as well as the monitoring information from other areas. This qualitative assessment of adherence to managerial needs constituted the main form of analysis of the research results.
The study presented methodological limitations inherent to its design. As it was a single case study, the solution was developed and validated within the context of a single company, which restricts the generalization of results to other organizations without specific adaptations. It was observed that the dashboard’s effectiveness is directly linked to the quality and standardization of the information recorded in the monitoring spreadsheets, as well as to the project management maturity level of the collaborators. Furthermore, the volume of files used as a database influenced the information update time, representing a relevant operational aspect.
3. Results and Discussion
The Results and Discussion section details the research findings, interpreting them in light of the literature and exploring their practical implications in the context of project management. The results are presented in a structured manner, following the methodological steps of information gathering, dashboard planning, data modeling, solution development, and validation, culminating in a critical analysis and discussion of their contributions and limitations.
Regarding information gathering, it was found that the primary managerial needs of the company’s board focused on the integrated monitoring of projects, with special emphasis on schedule and cost indicators. This finding aligns with project management literature, which consistently points to schedule and cost as the fundamental pillars for evaluating the success of an undertaking (PMI, 2021; Kerzner, 2022). The pursuit of an integrated view of these aspects reflects the growing complexity of engineering projects, where the interdependence between variables demands a holistic approach to decision-making. The absence of a consolidated view of these indicators can lead to fragmented decisions, with negative impacts on the project’s overall performance and customer satisfaction.
The study revealed the formalization of two crucial performance indicators: the Project Schedule Indicator (IDP) and the Project Cost Indicator (IDC). The IDP, calculated by the ratio between estimated duration and planned duration, offers a clear metric for identifying trends of delay (values greater than 1) or anticipation (values less than 1). This approach is analogous to the Schedule Performance Index (SPI) from Earned Value Management (EVM), which measures schedule efficiency (PMI, 2021). The ability to predict schedule deviations is fundamental for proactive management, allowing project managers to implement corrective actions, such as resource reallocation or deadline renegotiation, before delays become critical. Without a clear and updated IDP, the company would be subject to reactive management, with a higher probability of schedule overruns and contractual penalties.
Similarly, the IDC, defined by the ratio between the final cost estimate and the planned budget, serves as a financial thermometer, indicating potential overruns (values greater than 1) or savings (values less than 1). This indicator mirrors the EVM’s Cost Performance Index (CPI), which assesses the efficiency of budgetary resource utilization (PMI, 2021). The relevance of the IDC transcends mere accounting, as it provides insights into the project’s financial health, influencing strategic decisions such as optimizing supplier contracts, revising scope, or seeking additional funding sources. The lack of a robust and transparent IDC can result in budgetary surprises, compromising the company’s profitability and its ability to invest in new projects.
A notable finding was the distinction between formal schedule and cost indicators and the monitoring of other areas, such as risks, occupational safety, and operational follow-up, which were tracked through operational information and managerial records, without formalization as performance indicators. This gap suggests a project management maturity still in development, where priority is given to the more tangible and financially impactful dimensions. However, project management literature, especially the PMBOK Guide, emphasizes the importance of integrated management that encompasses all knowledge areas, including risks, quality, resources, and communications (PMI, 2021). The absence of formal KPIs for these areas can create blind spots, leading to reactive rather than proactive management. For example, the lack of a safety indicator may mask an increase in incidents, resulting in serious accidents and reputational and financial impacts. The practical implication is the need to evolve management culture to incorporate formal metrics in all critical areas, promoting a truly 360-degree view of projects.
The fragmentation of information across different areas and projects was an evident result of the survey, reinforcing the pressing need for consolidation and standardization of data in a single environment. This scenario, characterized by the dispersion of data in multiple spreadsheets and manual reports, is a common challenge in organizations with low maturity in Business Intelligence (BI) and data management (Souza, 2022). Fragmentation not only hinders integrated monitoring but also generates rework, data inconsistencies, and delays in the preparation of status reports, compromising the agility and quality of decision-making (Vargas, 2022; Carvalho & Rabechini Jr., 2019). Consolidating data in a single environment, such as a BI dashboard, is crucial for transforming raw data into actionable information, allowing management to have a clear and standardized view of the performance of all projects simultaneously. This integration is not just a matter of operational efficiency, but a strategic imperative for the company’s competitiveness and growth.
In the dashboard planning stage, a detailed conceptual framework was established and presented to the board of directors through a PowerPoint file. This preliminary approach allowed for the definition of key indicators, page organization, and information hierarchy, ensuring an integrated view of the projects. Careful planning of the information architecture is a critical step in developing BI solutions, as it directly impacts the dashboard’s usability and effectiveness (Gil, 2017). Conceptual validation with the board ensured that the informational scope was aligned with managerial needs and the organization’s internal processes, minimizing the risk of rework in subsequent development phases.
The clarity of the defined scope allowed for a precise distinction between the performance indicators for schedule and cost and the monitoring information from other areas. This conceptual separation is fundamental to avoid information overload and ensure that each type of data is presented appropriately for its purpose. While schedule and cost KPIs require quantitative and comparative metrics, information for monitoring risks or safety can be more descriptive and contextual. This modular approach, as advocated by the PMBOK (PMI, 2021), facilitates understanding and analysis by different management levels, allowing each stakeholder to access the information relevant to their specific responsibilities.
The results of the planning were materialized in Figures 1 and 2, which supported the definition of the report’s structure. Figure 1, for example, illustrates the structure of the pages that make up the suggested dashboard, including the initial menu, the project overview, monitoring, and detailing.
Source: Original research results
Figure 1. Preliminary structure of the dashboard with the initial menu, overview, monitoring, and detailing pages
The first page, designed as a home menu, centralizes navigation and offers intuitive access to the other sections of the report, optimizing the user experience. The second page, an overview, consolidates essential synthetic information, such as project identification, phase, time and cost estimates, and tracking of key risks. This panoramic view is crucial for senior management, who need an executive summary for quick project status assessment. The third page, dedicated to performance monitoring, incorporates the project’s S-Curve, physical progress, completion forecast, latency tracking, non-conformity record, and a financial graph, allowing for an integrated analysis of project evolution. Finally, the fourth page presents descriptive execution information, including activities performed, next steps, points of attention, and actions assigned to the client, promoting systematic communication and follow-up. Figure 4 complements this structure, presenting pages focused on contractual monitoring, risk management, and occupational safety, detailing financial aspects, scopes to be contracted, risk matrix, and safety controls. Although not included as a visual tag due to the figure limit, discussing its content is relevant to understanding the scope of the planning. The inclusion of these preliminary views in the planning process is an example of how design thinking and low-fidelity prototyping can be used to align expectations and refine the information architecture before technical development.
The data modeling stage was fundamental for the dashboard’s construction, resulting in the structuring of a robust analytical model. This model was capable of consolidating information from standardized reporting spreadsheets, used weekly by project managers and stored in a corporate folder. The standardization of spreadsheets and the use of a specific naming convention (client code, project code, project name, and reference week) are essential practices for data governance and the automation of the extract, transform, and load (ETL) process. The absence of standardization would be an insurmountable obstacle for data integration, as highlighted by Souza (2022), who emphasizes the importance of data quality for the effectiveness of BI tools. The practical implication is that discipline in data entry and organization at the source is as critical as the BI tool itself; without clean and structured data, the dashboard cannot deliver value.
The dashboard was configured in Microsoft Power BI to automatically access this directory, read and import the data, which then underwent treatment and transformation steps. This automation is a significant differentiator, as it reduces dependence on manual processes, which are prone to errors and consume valuable time. Power BI’s ability to connect to diverse data sources and perform complex transformations is one of its main attributes, as described by Oliveira (2020) and Santos (2021). Centralizing planning, deadline, cost, and monitoring information in a single analytical model ensures greater reliability, traceability, and agility in updating dashboards. Figure 2 illustrates the Power BI modeling environment, where treated and structured data are displayed, demonstrating the consistent basis for report preparation.
Source: Original research results
Figure 2. Database processed in Power BI used as the foundation for the dashboard
The right column, the data panel, presents the available sets of information for analysis, with each item representing a project topic. These consolidated tables, originating from weekly spreadsheets, form the backbone for the construction of indicators and visualizations. The data model visualization is crucial for understanding the logic behind the reports and for ensuring that the relationships between the different tables are correctly established, which is a prerequisite for accurate and integrated analyses. Effective data modeling, as performed in this study, is a pillar for building a scalable and sustainable BI system, allowing the company to add new data sources and indicators in the future without compromising the system’s integrity.
The development of the solution resulted in a dashboard structured in multiple pages, providing an integrated and interactive visualization of the projects. The dashboard was designed as a dynamic management report, allowing users to navigate between pages and apply filters to analyze data by project or by period. This interactivity is one of the greatest benefits of BI tools, as it empowers users to explore data according to their specific needs, promoting a data-driven decision-making culture (Souza, 2022). The consolidation of schedule and cost performance indicators, along with monitoring information from other areas, directly addressed the problem of information fragmentation initially identified.
Figure 3 presents the overview of the integrated dashboard pages in Power BI, illustrating the final solution developed.
Source: Original research results
Figure 3. Overview of the integrated dashboard pages in Power BI
Page 1, the initial menu, serves as the starting point for navigation. Page 2, the project overview, displays the Schedule Variance (SV) and Cost Variance (CV) Indicators, allowing for a quick assessment of schedule and cost performance. This page also includes completion dates (baseline and trend), physical progress, S-Curve, non-conformity reports (NCRs), and financial charts, offering a comprehensive economic-financial view. The ability to apply filters by week and by project allows for detailed or consolidated analyses, as per management needs. Page 3 is dedicated to financial monitoring, with charts and tables of contracts, measurements, and associated values. Page 4 details the activities (executed, planned, points of attention, client actions, halted activities). Page 5 focuses on execution analysis, with S-Curves by service type and progress charts. Page 6 presents the photographic record of the works. Page 7 is for risk management, with identification, classification, and response actions. Finally, Page 8 gathers health, safety, and environmental information, including accident indicators, daily toolbox talks (DDS), project safety plans (PGR), and waste control. This multifaceted dashboard structure reflects the breadth of PMBOK’s knowledge areas (PMI, 2021), offering a complete tool for project monitoring and control. The ability to integrate all this information into a single interactive panel is a significant contribution to the company, transforming scattered data into actionable intelligence.
The validation and analysis of the results, carried out through the presentation of the dashboard to the board of directors, confirmed the adherence of the consolidated information to the managerial needs previously identified. The clarity, usefulness, and applicability of the panel were positively evaluated, with the collection of comments and suggestions for improvement. This validation step is crucial to ensure user acceptance and the relevance of the solution, as emphasized by Gil (2017). The deadline and cost performance indicators were considered adequate, and the monitoring information from other areas, even without formalization as KPIs, contributed to a broader view of the project situation. This shows that, although the company is still in a maturation process in some areas, the BI solution already delivers significant value by integrating and visualizing data that was previously scattered.
However, the validation process also revealed important challenges. Differences in project management maturity levels were observed among collaborators, resulting in inconsistencies in filling out the tracking spreadsheets. For example, the S-Curve data were recorded divergently between baseline, replanned, actual, and forecast. This inconsistency highlights the importance of training and standardization of data entry processes, as the quality of the dashboard is directly proportional to the quality of the source data (Turrioni & Mello, 2012). The lack of mastery of project management concepts by some collaborators is a bottleneck that needs to be addressed through training and clear guidelines, as suggested by Carvalho and Rabechini Jr. (2019) when discussing the development of project management competencies.
The board recognized the importance of data reliability and consistency for the effective use of the dashboard as a decision-making support tool. Furthermore, the need to adapt visualizations for different user profiles, including clients with varying levels of technical knowledge, was highlighted. This personalization is vital to ensure that the information is understood and used by all stakeholders, from the project manager to the end client. Usability and user experience are critical factors for the adoption of any BI tool.
Another relevant aspect was the impact of the volume of spreadsheets on the information update time. The need to store the spreadsheets in the same corporate folder (SharePoint) for Power BI to perform automated reading highlighted the importance of standardization in storage and the management of file dispersion. A large volume of spreadsheets and lack of organization can compromise the automatic update and report performance, requiring greater computational capacity. This points to the need for a more robust data architecture in the future, such as a data warehouse, to handle the growth in data volume and ensure system efficiency.
The results evidenced the dashboard’s potential as a tool to support managerial monitoring and decision-making, reinforcing the relevance of the proposed solution. Table 1 demonstrates how the dashboard encompasses multiple PMBOK knowledge areas, integrating them through information consolidation, performance indicators, financial controls, and risk analyses.
Table 1. Application of PMBOK knowledge areas in the dashboard
|
PMBOK Knowledge Area |
Dashboard Approach |
Evidence in the Dashboard |
|
Integration |
Consolidation of information in a single environment |
All tabs |
|
Scope |
Tracking of planned, executed, and halted activities |
Activities tab |
|
Schedule (Deadline) |
Schedule Performance Index (SPI), S-Curve and Trend |
Overview and execution tabs |
|
Costs |
Contractual control, addenda, financial exposure and projections |
Overview and financial tabs |
|
Quality |
Monitoring through management records and non-conformity report (NCR) |
Overview tab |
|
Risks |
Identification, analysis, magnitude, urgency, responses, DDS, training, accidents and residuals |
Tabs risks and health, safety and environment |
|
Procurement |
Tracking of contracts, addenda and items to be contracted |
Financial tab |
|
Communications |
Status reporting standardization |
General dashboard structure |
|
Interested parties |
Adequacy of visualizations by user profile |
Filters and views |
|
Resources |
Analysis of management capacity as a function of the volume of activities and the value of management |
All tabs |
Source: Original research results
Table 1 details the dashboard approach for each PMBOK knowledge area, such as Integration, Scope, Schedule (Deadline), Costs, Quality, Risks, Procurement, Communications, Stakeholders, and Resources. For Integration, the consolidation of information in a single analytical environment is evidenced in all tabs. For Scope, the monitoring of planned, executed, and stalled activities is visible in the activities tab. The Schedule is monitored by deadline indicators (IDP), S-curve, and trends, present in the overview and execution tabs. Costs are controlled through contracts, addendums, financial exposure, and projections, displayed in the overview and financial tabs. Quality is monitored by management records and non-conformity reports, in the overview tab. Risks are identified, analyzed, and managed, with responses, DDS, training, accidents, and residues, present in the risks and health, safety, and environment tabs. Procurement is monitored by contracts, addendums, and items to be contracted, in the financial tab. Communications are standardized in status reporting, reflected in the overall dashboard structure. Stakeholders have their needs met by adapting visualizations per user profile, with specific filters and views. Finally, Resources are analyzed by management capacity based on the volume of activities and value, present in all tabs. This structure demonstrates the solution’s alignment with project management best practices, strengthening its use as a management support tool.
The integration of information from different project areas into a single analytical environment aligns with the literature recommendations on project management and Business Intelligence. Souza (2022) highlights that BI tools allow consolidating data from multiple sources, favoring structured analyses and decision-making. Carvalho and Rabechini Jr. (2019) reinforce that visibility and standardization of information are essential for performance monitoring and deviation identification. The results obtained corroborate these discussions, demonstrating that the integrated dashboard enhances transparency, facilitates monitoring, and supports managerial decision-making. The integration between PMBOK knowledge areas (scope, schedule, costs, risks, and communications) is fundamental for a systemic view of the project (PMI, 2021). The developed dashboard highlights this integration, bringing together information from various areas into a single report, allowing for more comprehensive analyses of project performance and contributing to organizational maturity in project management.
4. Conclusion
It is concluded that the objective was achieved, as this work managed to develop an integrated dashboard in Power BI for project management. The proposed solution promoted the integration and standardization of information from the main knowledge areas of PMBOK in a project and construction management system, consolidating performance indicators for schedule and cost, in addition to monitoring information from other relevant areas. This resulted in greater clarity and organization of data, configuring itself as an effective tool for supporting managerial monitoring and decision-making, as validated by the company’s board of directors.
However, the study presented limitations inherent to its single-case design, which restricts the generalization of results without adaptations. It was observed that the dashboard’s effectiveness is intrinsically linked to the quality and standardization of the source data, as well as the project management maturity of the collaborators, which sometimes generated inconsistencies in filling it out. The volume of spreadsheets also impacted update time, suggesting the need for a more robust data architecture. For future studies, it is recommended to gradually expand the areas of knowledge in the dashboard, implement training programs for users, strengthen information standardization, and explore solutions to manage the growing volume of data and organizational complexity.
Bibliographic References
Carvalho, M. M.; Rabechini Jr., R. (2019). Construindo competências para gerenciar projetos. 3ª ed. São Paulo: Atlas.
Kerzner, H. (2022). Project management: a systems approach to planning, scheduling, and controlling. 13ª ed. Hoboken, NJ: John Wiley & Sons.
Oliveira, J. R. (2020). Power BI aplicado à gestão de projetos. 1ª ed. São Paulo: Érica.
PMI – Project Management Institute. (2021). A guide to the Project Management Body of Knowledge (PMBOK Guide). 7ª ed. Newtown Square, PA: Project Management Institute.
Santos, L. F. (2021). Aplicação do Power BI em gerenciamento de projetos. São Paulo: Ânima Educação. Disponível em: https://repositorio-api.animaeducacao.com.br/server/api/core/bitstreams/f699bb22-51fa-4b2a-979b-0ab46eb3937a/content. Acesso em: 29 out. 2025.
Souza, A. M. (2022). Implementação de Business Intelligence
Vargas, R. V. (2022). Gerenciamento de projetos: estabelecendo diferenciais competitivos. 9a ed. Rio de Janeiro: Brasport.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq