Schedule management as a factor of satisfaction and motivation of the team in social projects

Ana Carolina Chaves Fonseca; Carina Campese

DOI: 10.22167/2675-6528-202600514

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

The management of schedules in social projects was investigated as a factor of team satisfaction and motivation, focusing on the experience of a community center that serves children and adolescents in social vulnerability. The study analyzed the schedule as an instrument for organizing work and guiding socio-educational practices, exploring its construction, application, and the meanings attributed by the professionals involved. A qualitative approach was adopted, using semi-structured interviews with six collaborators and participant observation in planning and execution meetings. The results revealed that the schedule, structured in macro and micro levels, acted as a central element for organizing activities, clarifying processes, and ensuring professional safety. The team’s participation in the elaboration and evaluation of the schedule reinforced the sense of belonging and recognition, contributing to predictability, safety, and stability in work. It was concluded that schedule management, when flexible and collaborative, transcends its technical function, promoting engagement and improvement of socio-educational practices, and that the principles of project management are adaptable to this context.

Keywords: Institutional Schedule; Team Engagement; Motivation; Third Sector; Socio-educational Work.

1. Introduction

Project management constitutes a fundamental pillar for achieving organizational goals in various sectors. In the specific context of third-sector institutions, efficiency in the use of human and material resources assumes even greater importance. These organizations, often dedicated to social causes, operate with limited budgets and rely heavily on the engagement and motivation of their teams to realize their missions.

Within the scope of social projects, such as those aimed at assisting children and adolescents in social vulnerability, action planning and schedule management play an essential role. The schedule is not just a technical tool, but an instrument for work organization that guides socio-educational practices. It details the sequence of tasks, deadlines, and resources needed for activity execution, as highlighted by Maia and Oliveira (2018). Furthermore, the schedule represents meticulous planning that indicates the periods and methods for delivering the products, services, and results foreseen in the project scope (Picinni and Dias, 2022).

The third sector, by its nature, comprises the action of non-profit legal entities that aim to carry out activities with significant social impact (MPPR, 2023). The correlation between the social activities carried out by these philanthropic entities and the principles of project management, with an emphasis on schedule management, is direct. The effective application of these fundamentals directly influences the quality of services provided to the community and the sustainability of social initiatives, making planning a strategic element for the success and longevity of projects.

Despite the recognized technical importance of the schedule, there is a gap in understanding how its management relates to the human aspects of teams. The planning and control of activities not only optimize internal processes but also exert influence on behavioral factors, such as the perception of autonomy, the level of engagement, and the motivation of the professionals involved. The absence of a deep understanding of these dynamics can compromise the effectiveness of projects and the well-being of socio-educational teams.

Understanding these interactions is crucial for improving the management of social projects, integrating the perspective of project management with social sciences. The research thus seeks to contribute to the debate on the relevance of planning in social projects and its implications in the daily lives of teams. By analyzing how the schedule is constructed, applied, and perceived by professionals, it is possible to identify ways to optimize practices and strengthen the performance and satisfaction of collaborators.

In this context, the present study aims to generally analyze the relationship between schedule management and team behavior in social projects of an organization, seeking to map how schedules are planned and executed, identify the impacts of this management on the motivation, engagement, and satisfaction of collaborators, and suggest improvements in planning practices to promote increased performance and well-being of the team involved in the activities.

2. Material and Methods

For the development of this study, a qualitative methodological approach was adopted, with the purpose of deepening the understanding of the relationship between schedule management and the satisfaction and motivation of teams in social projects. The choice of this approach was justified by its capacity to analyze perceptions, feelings, and experiences of the participants, providing a detailed and subjective view of the investigated phenomenon, according to the general objective of analyzing the relationship between schedule management and team behavior.

The research was designed as a case study, with a non-profit philanthropic institution located in Belo Horizonte as the field of investigation. This organization works with social projects focused on strengthening family and community bonds, serving children and adolescents in situations of social vulnerability. The selection of the institution was based on the relevance of its projects and the availability of access to data and teams, facilitated by the author’s previous work as a Social Educator at the company.

The unit of analysis was composed of six collaborators from the institution, who directly participate in the execution of the projects. The participants included a pedagogue and five social educators. The selection of these individuals occurred through intentional sampling, considering their involvement and experience with project schedule management and the application of activities with service users.

Data collection was carried out through two main strategies: semi-structured interviews and participant observation. The interviews were applied to team members directly involved in the project execution, using the Google Forms platform to record responses. The interview protocol was developed based on the theories of the PMBOK Guide (PMI, 2017).

The interview questions were based on the main processes in the schedule knowledge area, according to the PMBOK Guide (PMI, 2017). They covered activity definition, activity sequencing, duration estimating, schedule development, which includes methods such as the critical path method (Critical Path Method), and schedule control, which involves continuous progress monitoring. The complete interview protocol is in the appendix.

Complementary to the interviews, participant observation was carried out in project planning and execution meetings. The objective of this technique was to record team practices, behaviors, and interactions related to time management and schedule adherence. The observation sought to identify patterns that revealed the influence of deadline planning and control on the organizational climate, team motivation, and satisfaction.

The collected data were organized and analyzed using a thematic analysis technique. The process sought to identify recurring patterns and perceptions among participants regarding aspects such as motivation, engagement, satisfaction, and performance. This analysis allowed for an understanding of how deadline management influences the team’s daily routine, without anticipating empirical findings or specific results.

Thematic analysis focused on aspects such as the clarity of deadlines, adherence to temporal goals, leadership communication, and the perception of autonomy in task planning. The objective was to structure the information to later discuss in the results section how schedule management impacts the well-being of those involved and the performance of socio-educational activities.

3. Results and Discussion

The analysis of the collected data revealed a detailed panorama of schedule management in a community center that serves children and adolescents in social vulnerability. The research universe comprised six professionals, including one pedagogue and five social educators, which represented the entirety of the team directly involved with the institutional schedule. The diversity of participants’ tenure, with educators who had more than ten years of experience and others with only one year, provided a rich range of perceptions on the topic, enriching the understanding of the findings.

The results indicated that the institution operated with a scheduling system on two distinct levels. The first, on a macro scale, was applied nationally and provided general guidelines for the activities developed in all units of the organization in Brazil. This macro level established an annual thematic structure, organized into guiding axes such as “me with myself”, “me with the other”, “me with the city”, and “Protagonize”, which directed the pedagogical work and the execution of actions throughout the annual cycles.

The second level, on a micro scale, was elaborated locally by social educators in conjunction with the pedagogue. This micro schedule considered the specificities of the territory, the target audience, and the daily routine of the community center. It was observed that, based on the common thematic axes defined at the macro level, each educator developed their own activity schedule, adapting the pedagogical path to the reality of the group served. This individual planning included information such as start and end dates, duration of activities, necessary resources, and time estimates, previously established by the headquarters’ supervision.

Regarding the participants’ perception of the schedule’s development, the entirety of respondents, 100%, stated that the schedule considered the necessary time for planning, execution, and evaluation of activities. This finding is significant, as it demonstrates that the instrument was not limited to mere execution but encompassed all stages of a project’s lifecycle, from its conception to its closure, as advocated by Vargas (2005). The inclusion of these phases in the schedule is crucial for the organization and structuring of the project, as pointed out by Bonfim et al. (2012), contributing to the prevention of unforeseen events and rework.

The incorporation of prior planning and evaluation into the schedule proved to be an important factor for organizing activities, allowing for the anticipation of difficulties and optimization of task distribution among the team. Execution, in turn, corresponded to the accomplishment of proposed activities, while evaluation enabled the analysis of results, identification of improvements, and correction of flaws for future actions. The absence of dedicated time for these stages can lead to overload, disorganization, and demotivation, negatively impacting the team.

The data evidenced that the schedule adopted by the institution directly aligned with the “Schedule Performance Domain”, as proposed in project management literature (PMI, 2025). This domain encompasses the processes and practices related to the definition, organization, execution, monitoring, and evaluation of time, ensuring that activities were carried out in a structured manner. The macro-scale planning, with its annual thematic axes, functioned as a mechanism for institutional alignment, ensuring coherence among units and guiding the development of activities throughout the year, establishing clear temporal guidelines and favoring predictability.

In line with the macro planning, the micro scale of the schedule, developed by the educators and the pedagogue, operationalized the “Schedule Performance Domain” in daily practice. Each educator detailed the daily schedule, considering duration, resources, and objectives, which reinforced the procedural and controlled nature of temporal planning. The institutional MAPREI methodology, organized in quarterly cycles, demonstrated adherence to the assumptions of the schedule domain by structuring the work into defined periods, allowing for continuous monitoring of activity performance.

The possibility of conducting surveys with users at the beginning of each stage contributed to adjustments in the schedule without compromising its central structure, evidencing a balance between planning and flexibility, a fundamental aspect in time management in social projects. This approach allowed certain activities to be incorporated into the schedule, provided they were aligned with the proposed axes, and that the planning was validated by the pedagogue and supervision, ensuring an institutional monitoring process.

Participants’ accounts indicated that the schedule functioned as a guiding instrument for practice, even in the face of unforeseen events inherent in working with children and adolescents. This characteristic reinforced the understanding of the schedule not just as a formal document, but as a dynamic guide, capable of supporting the execution of activities throughout the entire project structure. The cyclical process of planning, execution, and evaluation contributed to the organization of actions and to the construction of a schedule with a defined beginning, middle, and end, reinforcing its role as a guiding instrument for socio-educational work.

The final evaluation of the schedule, conducted by the educator and users at the end of each activity cycle, demonstrated the presence of monitoring and control mechanisms, central elements of the “Schedule Performance Domain”. This stage allowed for verification of the adequacy of time, the relevance of activities, and the achievement of objectives, enabling adjustments for subsequent cycles. One of the interviewees highlighted that the schedule helped to structure, record, and organize ideas, serving as a fundamental guide for the development of activities, even with daily setbacks.

Another participant highlighted that, after a restructuring of the model, the micro-scale schedule became lighter and more flexible, granting greater freedom for the creation of activities and routine organization, although some aspects of the planning remained previously established. This flexibility, combined with the structure, demonstrates the schedule’s adaptability to the needs of the socio-educational context, without losing its guiding function.

Regarding the presentation of the schedule in advance for work planning, the collected data revealed varied perceptions among participants. Half of the respondents, 50%, stated that the schedule was presented beforehand. However, 33.3% indicated that this occurred only at certain times, and 16.7% stated that the schedule was not presented in advance. This distribution of responses suggests communication and standardization failures in the schedule presentation process.

The preliminary presentation of the schedule is a crucial factor for the organization of activities, as it allows team members to plan, organize their tasks, and have greater predictability of project actions. The absence of advance notice can lead to difficulties in executing activities, a feeling of disorganization, and team demotivation, as pointed out by Carvalho (2007). Thus, schedule management is not limited to deadline control, but encompasses communication and activity planning, and the lack of information alignment can impact team satisfaction and engagement.

Despite the inconsistencies in the preliminary presentation, there was consensus among the interviewees that when the schedule was followed as planned, the work flowed more organized. This promoted a sense of predictability, security, and stability in professional practice, positively impacting daily work. The structuring incorporated into the schedule, aligned with institutional axes, evidenced the practical application of PMBOK guidelines in a socio-educational context, demonstrating that schedule management acted as a strategic element for improving project performance, organizing professional routines, and qualifying the actions developed.

Participant observation reinforced that the schedule was a structuring element of the work routine, contributing to the organization of activities, clarity of processes, and professional security, even in the face of the flexibility required by the social projects’ context. The author’s daily experience confirmed the existence of the schedule model on a macro and micro scale, with structured periods for collective elaboration, especially at the beginning and middle of the year, although in other months planning occurred in a more fragmented way.

During the construction process of the micro-schedule, the pedagogue played a central and guiding role, mediating the dialogue with educators about the themes to be worked on within the axes of the MAPREI methodology. Based on these guidelines, educators collectively built their proposals, adapting them to the reality of the group served and the age range. A significant example was the development of a thematic schedule based on the symbolic construction of a “garden” for a group of children, organized weekly for three months, culminating in a final presentation event.

This example demonstrates how the micro-schedule allowed for the materialization of continuous pedagogical proposals, with a beginning, middle, and end, as also pointed out by the interviewees. Furthermore, the institution monthly provided a financial resource of one thousand reais for the purchase of materials, divided among the six educators. This amount contributed to the viability of the schedule and expanded the team’s autonomy in choosing pedagogical resources, strengthening the commitment to the elaborated plan.

Regarding team engagement, participant observation corroborated the survey data, indicating that the schedule was an important motivational factor. Its development intensely mobilized educators, generating involvement, exchange of ideas, and the desire to develop increasingly qualified proposals. In addition to formal planning meetings, the team held periodic gatherings to discuss cases and evaluate the impact of activities, strengthening teamwork and allowing for constant adjustments in practices.

Both the interviewees’ accounts and participant observation indicated that the schedule acted as an important mobilizing element for socio-educational work. The construction of the planning aroused a sense of belonging in the educators, as the activities were not just executed, but collectively thought out, organized, and monitored. This process strengthened the commitment to the project and contributed to educators becoming more actively and creatively involved in the institutional routine.

However, this engagement was not without tensions. One of the interviewees pointed out that, at certain times, the bureaucracy related to the schedule became excessive. Although she recognized the importance of a guiding instrument, she assessed that the volume of records, forms, and formal steps could hinder daily practice, especially given the unpredictable demands of working with children and adolescents. This account highlights an ambiguity in the use of the schedule: while it organizes and guides, it can also generate overload when it does not fully dialogue with the rhythm of institutional daily life.

Nevertheless, the existence of structured planning contributed to the feeling of job security, positively impacting team motivation. Educators demonstrated greater confidence in conducting activities when they knew there was a pre-defined path, with clear objectives and delimited steps. This aspect reinforced the perception that the schedule had a beginning, middle, and end, allowing for the monitoring of action development and the evaluation of their results over time.

Another relevant element for engagement was the evaluation stage at the end of each cycle of the schedule by the project’s beneficiaries. At the end of each thematic axis, users were listened to about how they experienced the activities, what they liked, what didn’t work, and what could be different. This feedback moment was incorporated into the planning process, allowing for course adjustments and reformulations in future proposals.

The inclusion of user assessment strengthened not only the quality of the activities but also the team’s motivation, as educators concretely perceived the impacts of their work. The feedback from children and adolescents served as symbolic reinforcement, legitimizing the effort invested in planning and executing the actions. Thus, engagement was not limited to meeting the schedule but expanded to a reflective stance, in which the team analyzed, revised, and reframed its practices based on listening and shared experience.

The results obtained in the research allowed the identification of some improvement proposals related to the elaboration and execution of institutional schedules, aiming to contribute to team satisfaction and to enhance activity planning. One of the main proposals refers to schedule flexibility. Considering that working with children and adolescents is subject to unforeseen events, such as absences, emergency demands, and behavioral changes, overly rigid schedules can lead to frustration, unproductivity, and overload.

In this sense, it is suggested that schedules be developed with greater flexibility, foreseeing possibilities for adaptation, reallocation of activities, and moments for planning reorganization. Another important proposal is the expansion of educators’ participation in the schedule construction process, especially from a macro-scale planning perspective. Team participation can increase the sense of belonging, professional appreciation, and commitment to the proposed activities, in addition to enabling the construction of more realistic schedules aligned with the daily dynamics of work.

It is therefore suggested that the development of schedules not be centralized, but collective, involving educators from the annual and semi-annual planning stage of activities. Additionally, it is proposed to institutionalize specific periods dedicated exclusively to the development of plans and schedules, especially in the middle of the year. Ensuring at least one week for the team to dedicate to these tasks can contribute to work organization, reduction of rework, improvement in communication, and higher quality of activities developed, favoring team satisfaction and the development of institutional actions.

In summary, schedule management in the studied institution transcended the function of a mere technical instrument, acting as a structuring axis for socio-educational work. The findings demonstrated that, when flexible and collaborative, the schedule promoted engagement, predictability, security, and a collective sense to the developed actions, positively impacting the team’s motivation and satisfaction, while aligning practices with project management principles.

4. Conclusion

The present study sought to analyze the relationship between schedule management and team behavior in social projects of an organization, with the aim of mapping schedule planning and execution, identifying their impacts on employee motivation, engagement, and satisfaction, and proposing improvements in practices. It was found that the institution operated with a system of schedules at macro and micro levels, with the macro being national in scope and the micro elaborated locally by educators and the pedagogue. It was observed that all participants affirmed that the schedule considered the necessary time for planning, execution, and evaluation of activities, which contributed to the organization and structuring of the work. The schedule acted as a guiding instrument for socio-educational practice, even in the face of unforeseen events, and demonstrated alignment with the “Schedule Performance Domain” of project management, favoring predictability and overall organization.

Despite some inconsistencies in the preliminary presentation of the schedule, it was found that its adherence promoted a sense of predictability, security, and stability in the work, positively impacting professional daily life. The team’s participation in the micro-schedule elaboration, mediated by the pedagogue, and the inclusion of user evaluation at the end of each cycle, reinforced the feeling of belonging and recognition, mobilizing educators for active and creative engagement. Thus, schedule management transcended its merely technical function, configuring itself as a structuring axis that promoted engagement, predictability, and a collective sense to the developed actions, positively impacting team motivation and satisfaction, while aligning practices with project management principles. However, the study identified limitations, such as the author’s change of workplace during the research, which hindered daily follow-up and direct observation of dynamics. Additionally, the reduced number of six participants restricts the generalization of findings to other institutions or contexts. As a practical contribution, it was suggested to flexibilize schedules to deal with unforeseen events inherent in working with children and adolescents, expand educators’ participation in macro-level planning construction, and institutionalize specific periods for schedule elaboration and evaluation. For future studies, it is recommended to conduct research on a larger scale, involving a broader number of educators and different units of the institution, which would allow for comparative analyses and the production of more comprehensive knowledge about time management and team satisfaction in social projects. The research reinforces that project management principles are adaptable and valuable for improving the management of social projects, integrating the technical perspective with social sciences to optimize team performance and well-being.

Bibliographic References

Bomfin, D. F.; Nunes, P. C. A.; Hastenreiter, F. 2012. Gerenciamento de Projetos Segundo o Guia PMBOK: Desafios para os Gestores. Revista De Gestão E Projetos, 3(3), 58–87.

Carvalho, Gisele S. B. 2007. Passo a passo do gerenciamento de projetos. Gestão & Tecnologia de Projetos, v. 2, n. 1.

Maia, D; Oliveira, R. 2018. Revista Iberoamericana de Gestão de Projetos. Abordagens e perspectivas para gestão do cronograma em projetos: Análise dos métodos tradicionais e ágeis. 9. 48-70.

Ministério Público do Paraná [MPPR]. 2023. Terceiro Setor: perguntas frequentes. Patrimônio Público. Disponível em: <https://site.mppr.mp.br/patrimoniopublico/Pagina/Terceiro-Setor-Perguntas-frequentes>. Acesso em: 05 out. 2025.

Picinini, E. F.; Dias, T. F. 2022. Gerenciamento do Cronograma de Projetos Como Fator De Sucesso Para Sua Execução: Estudo de caso em uma empresa de calçados no Vale Do Paranhana/RS. Faculdades Integradas de Taquara. Disponível em: <https://seer.faccat.br/index.php/administracao/article/view/2453/1539>. Acesso em: 03 de out. 2025.

Project Management Institute [PMI]. 2017. Um guia do conhecimento em gerenciamento de projetos. Guia PMBOK® 6. ed. Pennsylvania. EUA: Project Management Institute, Inc, 2017.

Project Management Institute [PMI]. 2025. Guia do conjunto de conhecimentos em gerenciamento de projetos (Guia PMBOK®). 8. ed. EUA: Project Management Institute, Inc, PMI.

Vargas, R. V. (2005). Gerenciamento de projetos: estabelecendo diferenciais competitivos. Rio de Janeiro: Brasport.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 23, 2026

Improvements in the efficiency of a secondary biological sludge drying plant

The management of industrial solid waste, especially secondary biological sludge, represented an operational and strategic challenge for a company in the pulp and paper sector. A secondary biological sludge drying plant, installed to meet environmental requirements and reduce costs, operated with low efficiency and high unavailability. The objective of this study was to evaluate and propose a set of actions to increase the operational availability of the plant, ensure the integral processing of the generated sludge, and reduce treatment and transportation costs, in addition to mitigating environmental risks. To this end, an analysis of the root causes of low efficiency was carried out, using tools such as the cause-and-effect diagram (Ishikawa) and the “5 whys” analysis, and hypotheses were tested to identify the most impactful factors. Three main root causes were identified: addition of low-load effluent to the process, absence of a dedicated maintenance team, and lower consistency of dewatered sludge. The proposed countermeasures, which included stopping the addition of effluent, hiring a maintenance team, and testing polymers, had a monthly implementation cost of R$ 35,000.00. An annual reduction in operating expenses of up to R$ 1,800,000.00 and maintenance costs of R$ 600,000.00 was estimated, in addition to a 25% reduction in operational unavailability. It was concluded that the proposed measures are viable, quick to implement, and capable of ensuring the integral processing of secondary biological sludge, strengthening the company’s ESG strategy and ensuring environmental compliance.

Keywords: Operational costs; Operational efficiency; ESG; Biological sludge; Sludge drying.

Data Science And Analytics For Operations

November 19, 2026

Polyp-YOLO: an efficient, low-latency detector for polyps in colonoscopies

The early detection of colorectal polyps is crucial for the prevention of colorectal cancer, and real-time computer-aided detection (CADe) systems have shown gains in endoscopic practice. The objective was to develop and validate a lightweight colorectal polyp detector, based on the YOLO architecture, capable of operating on restricted hardware with high precision and low latency. The methodology used public datasets of endoscopic images, partitioning the Kvasir-SEG dataset for training and internal validation, and CVC-ClinicDB and ETIS-Larib Polyp DB for cross-dataset evaluation. Lightweight variants of the YOLOv8, YOLO11, and YOLO26 families with 640×640 pixel input were evaluated. A grid search tested 70 combinations of optimizers and activation functions, and identified AdaBelief and LeakyReLU as the configuration with the best generalization. The optimization pipeline applied unstructured pruning, knowledge distillation, and fine-tuning. The optimized YOLO11n-seg model outperformed the higher-capacity architecture (YOLO26m-seg) in mAP50 and showed similar performance in F1-Score, operating with approximately seven times fewer parameters. It achieved an mAP50 of 0.7929 and an F1-Score of 0.7514 on the ETIS-Larib dataset, and fast inference was demonstrated in different formats, with real-time latencies. The explainability of predictions was validated by Grad-CAM activation maps. The proposed solution demonstrated itself to be a promising experimental tool for diagnostic support, with technical feasibility for integration into environments with reduced computational power, although it requires future clinical validation.

Keywords: Computer-aided detection; Edge computing; Hyperparameter optimization; Endoscopic image segmentation; Medical computer vision.

Data Science And Analytics For Operations

November 19, 2026

Multi-touch Attribution in E-commerce: A Comparison between Markov Chains and Last-Click

The research investigated Multi-touch Attribution (MTA) Models in e-commerce, seeking to overcome the limitations of the Last-Click model, widely used in the market. The objective was to compare the performance of first-order Markov Chains with Last-Click and Position-Based approaches, identifying the value of assistance channels frequently ignored. To this end, Markov Chain algorithms were applied to a large volume of purchase journey data from the Google Merchandise Store, extracted via BigQuery. The study probabilistically mapped the purchase journey and calculated the Removal Effect to quantify channel relevance. The results demonstrated that data-driven models identified the strategic role of discovery (awareness) and assistance channels, which Last-Click neglected in 65% of complex journeys. Simulated financial analysis indicated an approximate 28% hidden efficiency in Cost Per Acquisition (CPA) for Paid Search, compared to the Last-Click model. It was concluded that Markov Chains allowed for a more accurate mapping of purchase journeys, validating the technical feasibility of the modeling and providing evidence for more efficient budget allocation in digital media, mitigating the risk of early divestment in crucial channels.

Keywords: Assistance channels; Data science; E-commerce; Digital marketing; Media optimization.

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Data Science And Analytics For Operations

November 19, 2026

Predictive Analysis Methodology for Performance Optimization in E-commerce: Correlation between Public Data and Paid Media

A predictive analysis methodology was developed for e-commerce, integrating transactional data and public search trends. The objective was to develop and validate a predictive model, based on machine learning algorithms, capable of correlating organic search trends with sales performance and paid media costs in the Beauty and Health category of Brazilian e-commerce. The Brazilian E-Commerce Public Dataset by Olist and data from Google Trends were used, processed in Python with the Random Forest Regressor algorithm. A moderate inverse correlation (r = -0.43) with a seven-day lag was identified between organic search volume and purchase. Initial models, based solely on behavioral variables, presented insufficient metrics (R² = -0.47; MAE of R$ 2,120.54). The incorporation of microeconomic (average ticket and shipping) and macroeconomic (exchange rate and Ibovespa index) variables raised the R² of the final model to 0.29, with an MAE of R$ 1,489.63, representing a 24.7% reduction in error compared to the baseline. Temporal cross-validation showed that, in periods of mature operation (2018), the model achieved an R² of 0.42. It was concluded that isolated search volume explains the moment of consumer interest, but not the financial magnitude of sales, making the fusion with transactional and economic data mandatory for predictive viability.

Keywords: Beauty and Health; Consumer Behavior; Google Trends; Machine Learning; Time Series.