Executive Summary

April 22, 2026

Value Management in Sugarcane Ethanol Projects

Estevão Henrique Rodrigues De Souza; Gleison De Souza

Summary prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

The sugarcane-ethanol sector holds a strategic position in both the Brazilian and global scenarios, playing a fundamental role in the production of sugar, ethanol, and bioelectricity. Brazil consolidates itself as the largest global producer of sugarcane, responsible for over 20% of the world’s sugar production and approximately 50% of global exports of this product, which reinforces the importance of operational efficiency for food security and the agricultural trade balance (UNICA, 2023). Beyond its economic relevance, the national sugarcane-ethanol industry is a pioneer in the large-scale use of ethanol as a biofuel, representing one of the main sustainable alternatives for the transportation matrix, with a direct impact on reducing greenhouse gas emissions, in full alignment with global decarbonization goals (IEA, 2021). Bioelectricity generated from sugarcane bagasse complements the country’s renewable electricity matrix, highlighting Brazilian experience as a model for integration between agribusiness and clean energy. In this environment of high competitiveness and technical demands, project management emerges as a critical discipline to ensure that industrial interventions occur without compromising crop productivity.

Schedule management constitutes one of the central pillars of project administration and is essential for the success of predominantly predictive endeavors (PMI, 2017). This knowledge area aims to organize and structure all activities and work packages necessary to ensure that goals are met within determined deadlines. According to the guidelines established in the best practices guide for management, schedule control comprises fundamental processes such as defining activities, logical sequencing, estimating durations, and developing a solid basis for performance monitoring (PMI, 2021). The rigorous application of these practices improves predictability and mitigates uncertainties, especially in industrial environments characterized by severe time constraints and high technical complexity. Effective time management, supported by consolidated techniques such as the critical path method and earned value analysis, is decisive for delivering projects with quality and meeting stakeholder expectations (Kerzner, 2017).

In sugarcane-ethanol mills, schedule management faces significant challenges due to the intrinsic complexity of the production process, which combines continuous operations of milling, distillation, energy cogeneration, and storage. Such processes require precise coordination between mechanical, electrical, and automation specialties (Ferreira and Pires, 2019). The execution of maintenance and renovations is strongly limited to the off-season period, which defines fixed time windows for carrying out critical interventions. This temporal limitation increases pressure on meeting deadlines and on the efficient allocation of resources (Kerzner, 2017). Integration between planning, supervision, and execution is vital, as any schedule deviation can generate direct impacts on equipment availability and overall plant reliability for the subsequent harvest. Given this scenario, the application of Earned Value indicators, such as the Schedule Performance Index and the Cost Performance Index, allows for monitoring actual progress against the plan, identifying deviations early, and adopting timely corrective actions (PMI, 2021).

The concept of earned value management systematically integrates project scope, schedule, and cost, offering a quantitative approach that overcomes the limitations of traditional monitoring based solely on completion percentages (PMI, 2021). While the conventional method can be subjective, performance indicators provide reliable metrics for communication with managers and reinforce institutional governance. The Schedule Performance Index is an efficiency ratio that measures the degree of adherence to the original schedule; a result greater than 1.0 indicates that physical progress is ahead of schedule, while a value less than 1.0 signals delays. In parallel, the Cost Performance Index measures financial efficiency, comparing the value of work actually performed with the actual cost incurred (PMI, 2017). Trend analysis based on these indicators allows for predicting future performance and correcting anomalies during execution, ensuring that maintenance and renovations are completed with maximum operational efficiency. The objective of this study is to evaluate the application of these indicators in a heat exchanger implementation project, verifying whether the methodology adds greater predictability and agility to decision-making compared to the traditional method.

The methodology applied for the analysis was based on a case study conducted during the implementation of two shell-and-tube heat exchangers in a medium-sized industrial unit located in the interior of the state of São Paulo. The plant in question has an installed capacity for processing 2.6 million tons of sugarcane per harvest, with an average production of 3.8 million bags of VHP sugar and 145 million liters of ethanol (hydrated, anhydrous, and Grade B). The project was identified as a priority opportunity within the unit’s operational improvement program. The monitoring of activities occurred during the 2024/2025 off-season, initially using the unit’s conventional methodology, based on weekly updates of completion percentages, and subsequently applying the concepts of earned value management for evaluation and comparison of effectiveness.

For data collection, routine weekly progress meetings were held every Monday morning. In these meetings, the main bottlenecks observed in the previous week, points of attention, and critical activities for the subsequent week were discussed. This process was essential for obtaining complementary information that is not always included in formal documents. Additionally, a record of lessons learned throughout the project’s entire lifecycle was used, covering the conception, procurement, and planning stages, as per the recommendations of the project management guide (PMI, 2021). Planning and control data were processed with the aid of MS Project and Excel software, ensuring precision and accuracy in indicator calculations.

The survey of applied costs was carried out through the SAP integrated management system, where all material transactions, stock allocations, and labor contracts are recorded. This data was compiled in accordance with the schedule task references, allowing for the establishment of a baseline for planned value and its cross-referencing with actual cost and earned value. The unit adopts a strict change management policy, which requires documentary formalization of all physical, operational, and safety impacts arising from the project. This evaluation is conducted by a multidisciplinary team composed of professionals from the production, maintenance, conceptual engineering, and occupational safety areas. The synergy between these teams is fundamental for mitigating financial and temporal risks, especially in highly complex industrial environments (Silva, 2021).

The detailed schedule for the execution of activities covered a total period of 25 weeks, from the premise survey and conceptual design development to final testing and commissioning. The baseline was formalized through an S-curve, which is the corporate standard used for discussing physical progress in weekly meetings. However, it was observed that the unit’s common practice did not include the detailed specification of resources required for each stage, which can compromise the robustness of management in complex activities involving multiple professionals and equipment (PMI, 2017). To address this gap, schedule and cost performance indicators were experimentally applied throughout the execution, allowing for a deeper analysis of the variations between planned and actual performance.

The results obtained revealed that the project was delayed for most of its lifecycle. Detailed analysis of physical progress showed that between weeks 04 and 06, there was a slight deviation due to delays in the delivery of conceptual and isometric drawings required for assembly. This initial delay impacted the logical sequence of subsequent activities. Between weeks 07 and 09, the delay was extended by difficulties faced by the supply sector in negotiating the hiring of services and in acquiring steel materials, valves, and accessories. Only in week 10 was there a temporary alignment with the planned schedule, driven by the speed of the contracted supplier for manufacturing and by the progress in disassembly and interference removal activities in the field.

From week 11 onwards, the project again showed a sustained delay, mainly due to the existence of overlapping work in some service fronts. The group adopts a safety policy that requires complementary analyses when two or more teams operate on different floor levels in the same area, aiming to mitigate the risk of falling materials and tools (Silva, 2021). Although this practice is essential for accident prevention, it imposes restrictions on the execution pace. In week 15, an aggravation of the delay was observed due to a failure in the assembly planning, which did not foresee the need to rent a mobile elevating work platform for certain interventions at height. Furthermore, the need for partial replacement of the existing metal structure to support the new piping sections was identified, which was not included in the original scope.

Given the persistence of deviations, the unit management decided, in week 22, to increase the assembly team’s workforce. This decision was made late, as the schedule’s flexibility margin was only one week in relation to the final deadline for the off-season completion. In the final weeks, specifically between weeks 23 and 25, leak tests and commissioning were carried out. During this process, leaks were evident in some valve connections, requiring immediate rework. After the non-conformities were resolved, the new tests were approved and the technical delivery was formalized. Despite the setbacks, safety management was considered effective, as there were no registered accidents involving people or material damage, proving the efficiency of the established preventive measures (Silva, 2021).

The application of the Schedule Performance Index confirmed the perceptions gathered in the weekly meetings, but with superior quantitative precision. The indicator started the project at 1.00, but dropped to 0.75 in week 04, reflecting the delay in conceptual projects. There was a gradual recovery until it reached 1.00 again in week 10, followed by a new drop that stabilized around 0.92 and 0.95 during the most critical phase of assembly. In week 22, the index was 0.93, and only in week 25, with the completion of all pending issues, did the value return to 1.00. This oscillation shows that traditional monitoring by completion percentages often masks the severity of delays, while the Schedule Performance Index immediately highlights the loss of temporal efficiency.

Regarding costs, the Cost Performance Index showed initially favorable results, remaining above 1.00 until week 16. This indicated that the actual cost incurred was below the value added for the work performed. However, from week 17 onwards, the indicator began to decline, reaching 0.92 in week 22. This drop was the direct result of unforeseen additional costs, such as the emergency rental of the elevating platform and the increase in labor to accelerate assembly in the final stretch. The final project cost exceeded the initial budget by approximately 10%, a variation considered acceptable for medium-complexity interventions in an industrial environment, but which could have been mitigated if the indicators had been used for earlier proactive decisions.

The discussion of the results indicates that the detailing of field assembly activities was insufficient. Items such as disassembly of interferences, piping assembly, and system interconnection were treated as macro packages, which hindered the individualized management of critical subtasks. The guidance from the corporate engineering team suggests that work packages should have durations between 0.5 and 10 business days to allow for more assertive control. The lack of foresight regarding the lifting platform and the need for structural reinforcement highlight flaws in the conceptual development of the demand, which could have been identified through more rigorous technical inspections during the planning phase. The decision to increase the team only in week 22 demonstrates a reactive approach, confirming that the vision provided by the traditional monitoring method is limited (Kerzner, 2017).

The integration of the scope, schedule, and cost pillars through the earned value methodology contributes to greater visibility of project governance, providing robust information for managers and assisting in facing the challenges of the sugar-alcohol sector. The fixed off-season window does not allow for significant schedule extensions, making early trend detection a crucial competitive advantage. Experience has shown that, although the final cost was higher than expected and the schedule was extended by two weeks, the use of indicators allowed for a clear understanding of where the failures occurred, generating valuable lessons learned for future projects of a similar nature (Kerzner, 2018). It is recommended that the application of this methodology be expanded to all capital investment projects of the group, consolidating it as a strategic tool to increase operational reliability and efficiency.

It is concluded that the objective was achieved, as the application of Earned Value Analysis (EVA) indicators proved superior to the traditional schedule monitoring method, providing a quantitative and early view of schedule and cost deviations. The use of the Schedule Performance Index and the Cost Performance Index allowed for the identification that the main causes of delays and cost overruns were related to flaws in conceptual planning and resource estimation, such as the absence of lifting equipment and the need for unforeseen structural reinforcements. The study showed that reactive management, based solely on completion percentages, delays critical decision-making, while the earned value methodology offers the necessary predictability for interventions within restricted windows such as the sugar-alcohol off-season. The effectiveness of safety management and the absence of accidents reinforced the project’s operational feasibility, despite the technical challenges faced. Therefore, the systematic adoption of these indicators is recommended to elevate the level of governance and efficiency in the execution of complex industrial projects.

Bibliographic References:

Ferreira, T.S.; Pires, S.R.I. 2019. Gestão de manutenção em indústrias de processo: desafios e práticas em ambientes de alta complexidade. Gestão & Produção 26(3): 1-14.

International Energy Agency [IEA]. 2021. Renewables 2021: Analysis and forecast to 2026. IEA. Paris, França.

Kerzner, H. 2017. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 12ed. Wiley, Hoboken.

Kerzner, H. 2018. Melhores práticas de gerenciamento de projetos: Alcançando excelência global. John Wiley & Sons.

Project Management Institute [PMI]. 2017. Um guia do conhecimento em gerenciamento de projetos. 6ed. Project Management Institute, Newtown Square, PA, EUA.

Project Management Institute [PMI]. 2021. Um guia do conhecimento em gerenciamento de projetos. 7ed. Project Management Institute, Pennsylvania, EUA.

Silva, R.A.L. 2021. Gerenciamento da Manutenção correlacionada à Eficiência da Segurança. Revista Científica e-Locução 1(20): 21-21.

Brazilian Sugarcane Industry Association [ÚNICA]. 2023. Annual Report 2023. UNICA. São Paulo, SP, Brazil.


Executive summary from the Final Course Work of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

Who edited this article

Most recent

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.