Communication management plan to integrate teams in large-scale event projects
Communication Management Plan to Integrate Teams in Large-Scale Event Projects
Rodolfo Schradi Yamada; Bruno de Lima
DOI: 10.22167/2675-6528-202601398
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Project management in large-scale events presents high operational complexity, requiring integration among multiple *stakeholders* and intense information flow. In this context, communication plays a central role, but in practice, it is often conducted informally, especially in projects with a strong dependence on outsourced teams, which can generate noise, rework, conflicts, and low traceability of decisions, compromising alignment and operational efficiency. The objective was to develop and apply a communication management plan to integrate teams and suppliers in a large-scale event project, based on the best practices of project management described by the PMBOK. To this end, a qualitative, descriptive action research was carried out, with participant observation and documentary analysis, comparing two projects: one without a formal communication structure (Event A) and another with the application of structured practices (Event B). The results showed that Event B presented significant improvements, such as greater clarity of responsibilities, reduction of rework, increased traceability, better coordination between teams, and greater agility in responding to unforeseen events. The transition to a structured and preventive communication model was associated with gains in decision-making clarity and a decrease in interorganizational conflicts. It was concluded that the adoption of structured communication practices contributed directly to team integration and the efficiency of project execution, highlighting communication as a strategic element of governance in event projects.
Keywords: Conflicts; Governance; Standardization; Traceability; Outsourced.
1. Introduction
Project management has consolidated itself as a strategic discipline for the success of complex initiatives, requiring the coordination of resources, people, and information under time and budget constraints (Kerzner, 2022). In dynamic environments, effective project management is a competitive differentiator. In this context, communication emerges as a fundamental pillar, integrating expectations and operations among multiple stakeholders. Clear, timely, and understandable information transmission is essential to mitigate risks, resolve conflicts, and ensure consistent decisions, impacting project performance (PMI, 2021).
Large-scale event projects represent a scenario of heightened operational complexity, demanding intensive coordination due to the volume of simultaneous activities, time pressure, and interdependence between teams and suppliers (Silvers, 2021). The ephemeral and high-visibility nature of these events amplifies the need for precision and agility, where communication failures can have immediate repercussions. The frequent reliance on outsourced teams, while bringing specialization and flexibility, introduces additional challenges. Integrating professionals from different companies, with distinct cultures and hierarchical levels, requires robust communication to align expectations, standardize processes, and ensure cohesion (Meredith et al., 2020). The absence of formal communication mechanisms in this context can fragment information, compromising synergy for successful execution.
The project management literature, notably the *Project Management Body of Knowledge* (PMBOK) from the Project Management Institute (PMI, 2021), elevates Communications Management to an essential knowledge area. This guide advocates for the structuring of processes to plan, manage, and monitor information flow, meeting the needs of *stakeholders*. Additionally, effective communication is a vector for Knowledge Management, allowing information to be captured and disseminated, promoting organizational learning (Alves and Finger, 2023). In organizational behavior, Robbins and Judge (2019) emphasize communication as a crucial integrating element, capable of reducing ambiguities and strengthening cooperation. In event projects, where interorganizational collaboration is intense, structured communication practices, such as defining channels and responsibilities, increase transparency and coordination (Vargas, 2021).
Despite the theoretical recognition of the centrality of communication, the practice in many projects, especially with third parties, is still characterized by informal and reactive approaches. This informality manifests in the absence of defined communication plans, lack of official channels, and undefined communication roles. This scenario results in informational noise, divergent interpretations, and misalignment between activities. The consequences directly impact operational efficiency: increased rework, higher incidence of interorganizational conflicts due to lack of decision-making clarity, and low traceability of decisions, hindering problem-solving and continuous learning. Reactive communication compromises the predictability and fluidity of project execution, generating delays and costs (Meredith et al., 2020).
Given the complexity inherent in large-scale event projects and the gap between theory and practice in communication management, it becomes imperative to investigate the relevance of applying structured approaches. This study is justified by the need to offer practical solutions for the integration and efficiency challenges faced by teams and outsourced suppliers, contributing to the reduction of operational failures and the strengthening of project governance. Academically, it seeks to deepen the understanding of how the formalization of communication processes can transform the dynamics of projects with multiple *stakeholders* in a high-pressure environment. Thus, the objective of this work was to develop and apply a communication management plan to integrate teams and suppliers in a large-scale event project, based on the best practices of project management described by the PMBOK (PMI, 2021).
2. Material and Methods
To achieve the proposed objectives, an action-research of a descriptive nature, with a qualitative approach, was carried out. It was conducted in the context of a real large-scale event project involving outsourced teams. The choice of action-research was justified by the need to investigate the phenomenon in its natural environment, observing communication practices and interactions throughout the project execution, without dissociating them from organizational and operational conditions (Thiollent, 2011; Tripp, 2005). This approach allowed for the simultaneous production of knowledge and practical improvement.
The descriptive nature of the study aimed to organize and detail how communication was structured and applied to integrate outsourced teams, identifying routines, roles, channels, informational flows, and critical points observed. According to Gil (2017), descriptive research is appropriate for recording, analyzing, and interpreting characteristics of a process or reality, without being limited to measuring isolated variables. Thus, the focus was on understanding “how” communication was configured and what operational effects were perceived in the event stages.
The qualitative approach was adopted due to the nature of the object of study, which required understanding relational, interpretive, and contextual aspects. Elements such as alignment, clarity of responsibilities, perception of integration, and quality of information flow between internal and outsourced parties would hardly be explained solely by numerical indicators. Minayo (2017) and Flick (2009) highlight that qualitative studies favor in-depth analysis of meanings, relationships, and social practices in complex organizational processes, interpreting dynamics and emerging patterns from the field.
The analyzed organization operates in the event planning and production sector, focusing on corporate events and large-scale fairs, characterized by high operational complexity and intense dependence on specialized suppliers. It is a medium-sized Brazilian company, located in a capital city in the Southeast region of Brazil, in an urban environment. Its internal structure is lean and project-oriented, maintaining a core group of professionals and expanding delivery capacity through outsourced hiring, according to the scale and profile of each event.
The research was conducted based on the comparative analysis of two large-scale event projects, named Event A and Event B, executed at different times by the same organization. Both events showed a strong dependence on outsourced teams. This choice was intentional, as it allowed for the comparison of communication dynamics in a previous scenario, without sufficient standardization (Event A), and in a later scenario, with structured communication strategies implemented (Event B), aiming to integrate suppliers and operational teams.
Data collection was carried out through the author’s direct participation in the project, in the role of Project Manager. This strategy enabled continuous monitoring of activities, decisions, and interactions between internal and outsourced teams throughout the lifecycle of the events. Participant observation, as recommended by Flick (2009) and Thiollent (2011), allowed the author to be immersed in the investigated context, acting in the project’s management and in the systematic recording of evidence relevant to the research.
Complementarily, data collection also occurred through documentary analysis. Records produced and used in project management were examined, including plans, schedules, operational “checklists”, alignments, internal communications, guidance materials for outsourced teams, and evidence of dealings with suppliers. This stage allowed for the identification of communication patterns, responsibilities, informational flows, and critical integration points, in addition to supporting the triangulation of information obtained in the field, strengthening the study’s consistency (Yin, 2015; Gil, 2017).
The study was structured in three main stages. Initially, the communication diagnosis of Event A was carried out, identifying integration failures between the teams involved. Then, the intervention was developed, which consisted of defining and applying a communication management plan in Event B. Finally, a comparative evaluation was carried out between the two projects, analyzing the effects of the implemented strategies on team integration and project activity coordination.
The Work Breakdown Structure (WBS) was developed as a methodological tool to decompose and organize the research scope, structuring the study’s stages and their respective deliverables in a logical and hierarchical manner. The construction of the WBS was based on the principles of the PMBOK guide (PMI, 2021), which advocates for the decomposition of work into progressive levels of detail for greater clarity in defining activities, and better organization and control of project components.
The WBS development process started with the definition of the research’s general objective, from which the macro-steps necessary for its achievement were identified. These macro-steps were organized into hierarchical levels, beginning with a more aggregated level, corresponding to the main phases of the study, and advancing to more detailed levels, where the subprocesses and deliverables associated with each step were defined. The WBS was used as the structuring basis for organizing the other methodological tools of the study.
In the first project, Event A, the execution was characterized by relevant failures in communication integration between the internal team and outsourced suppliers. The observed weaknesses included the absence of standardization of channels and messages, the ambiguity of roles and responsibilities, reactive information transfer, and low traceability of decisions and alignments. These conditions resulted in delays, rework, and operational misalignments, impacting project predictability (PMI, 2021; Kerzner, 2022).
In the second project, Event B, structured communication strategies were implemented with a focus on integrating outsourced teams into the project governance system. A communication plan defining audiences, messages, channels, and frequency was applied, along with a “Responsible”, “Accountable”, “Consulted”, “Informed” (RACI) matrix for clarifying responsibilities, standardized “checklists” and operational scripts, periodic “briefing” and alignment routines, and mechanisms for recording and tracing decisions and guidelines (Bourne, 2016; Alves and Finger, 2023).
The analysis of the results was structured from the macro-stages of the investigated real project, preserving the operational logic of the analyzed events. In each phase, the effects of the absence or presence of structured communication management practices were observed. The findings were organized according to the sequence of planning, contracting, assembly, execution, and post-event, comparing Event A, with informal and reactive communication, and Event B, with an applied communication management plan.
The comparative analysis between the two events allowed us to identify that the transition from an informal and reactive communication model to a structured and preventive model was associated with gains such as a reduction in operational rework, greater decision-making clarity, a decrease in interorganizational conflicts, increased traceability of decisions, and improved team integration. These elements were evaluated qualitatively, seeking to understand the meanings and social relationships that emerged from the application of communication practices (Minayo, 2017).
From a methodological point of view, the study presented some limitations. Access to detailed quantitative data was restricted, especially regarding consolidated historical metrics of the first event analyzed. Part of the evidence was based on qualitative records and participant observation, which may limit the generalization of the results. Furthermore, the research was conducted in a single organization, in a specific context of the events sector, which may influence the direct applicability of the findings to other scenarios.
3. Results and Discussion
The analysis of the results was meticulously structured from the macro-stages of the investigated real project, with the aim of preserving the operational logic of the analyzed events and, simultaneously, enabling the observation of the effects of the absence or presence of structured communication management practices in each phase. In line with the study’s methodological proposal, the findings were organized sequentially, covering the phases of planning, contracting, assembly, execution, and post-event. This comparative approach was crucial for contrasting Event A, characterized by predominantly informal and reactive communication practices, with Event B, in which a communication management plan was developed and applied with the explicit objective of integrating the teams involved in the project. The distinction between these two scenarios allowed for an in-depth evaluation of the impacts of communication formalization on operational efficiency and interorganizational integration.
Before delving into the comparative analysis of the project stages, it is essential to present the analytical structure that served as the basis for the intervention carried out in Event B. The Work Breakdown Structure (WBS) of the research, as detailed in Figure 1, was an essential methodological instrument for decomposing and organizing the study’s scope, structuring the stages and their respective deliverables in a logical and hierarchical manner. The construction of this WBS, based on the principles of the PMBOK guide (PMI, 2021), emphasized the decomposition of work into progressive levels of detail, which provided greater clarity in defining activities, better project organization, and more effective control over its components. Figure 1 illustrates this decomposition, starting from the general objective of the research and breaking it down into macro-stages and subprocesses, culminating in the specific deliverables of each phase.
Source: Original survey data
Figure 1. Research structure
The WBS (Work Breakdown Structure), as shown in Figure 1, was organized into three main levels. The first level corresponded to the major phases of the research: diagnosis, intervention planning, implementation at Event B, and evaluation. The second level detailed the main activity blocks within each phase, while the third level represented the specific deliverables associated with each action. This approach not only ensured traceability between research objectives and the results produced at each stage but also aligned the study’s structure with good project management practices, which prioritize value generation through clearly defined deliverables. Table 1, in turn, summarizes the WBS of the research and the communication intervention, consolidating the project’s macro-phases and the main communication management artifacts applied, providing a concise overview of the structure that guided the entire investigative process.
Table 1. Synthetic WBS of the research and communication intervention
|
Level 1 |
Level 2 |
Level 3 |
Main deliverable |
|
1. Diagnosis |
1.1 Survey of Event A |
1.1.1 Observation of communication failures |
Record of Event A’s weaknesses |
|
1.2 Document analysis |
1.2.1 Verification of flows, messages, and interfaces |
Comparative analytical base |
|
|
2. Intervention planning |
2.1 Communication Plan Structuring |
2.1.1 Definition of audiences, channels, and frequency |
Communication Management Plan |
|
2.2 Definition of responsibilities |
2.2.1 Elaboration of the RACI matrix |
Responsibility matrix |
|
|
2.3 Operational Standardization |
2.3.1 Development of “checklists” and scripts |
Standardized instruments |
|
|
3. Implementation in Event B |
3.1 Hiring and initial alignment |
3.1.1 Supplier positioning and communication flow |
Initial Team Integration |
|
3.2 Assembly |
3.2.1 Application of “briefings”, official channel and records |
Structured operational coordination |
|
|
3.3 Event execution |
3.3.1 Escalation and incident control |
More agile response to unforeseen events |
|
|
4. Evaluation |
4.1 Post-event |
4.1.1 Consolidation of records and A x B comparison |
Evaluation of the intervention’s effects |
Source: Original research results
The WBS (Work Breakdown Structure), synthesized in Table 1, showed that the intervention in Event B was not limited to specific or improvised actions, but was conceived as an articulated set of deliverables directly linked to project Communications Management. This aspect is of utmost importance from an academic point of view, as it demonstrates that communication was treated as a formal object of planning and control, rather than merely as a tacit practice of daily operations. This understanding finds strong support in the PMBOK (PMI, 2021), which recognizes communication as a fundamental knowledge area that must be planned and managed according to the informational needs of stakeholders and the inherent complexity of each project. The formalization of communication, therefore, transcends the mere organization of flows, positioning itself as a strategic pillar for the effective governance of complex projects, especially those that depend heavily on outsourced teams.
Communication Planning
The communication planning stage constituted the starting point for the integration of the teams involved in the analyzed projects, revealing significant structural differences between Event A and Event B, with direct impacts on the fluidity and efficiency of subsequent stages. In Event A, communication planning occurred in a predominantly informal and reactive manner. Although there was a constant flow of information between internal coordination and suppliers, the absence of a formal communication plan was notable. There was no clear definition of audiences, official channels, update frequency, or those responsible for each type of message. Operational guidelines were disseminated through multiple parallel channels, which often resulted in divergent interpretations and a considerable loss of information traceability. Operational changes were communicated reactively, often belatedly, increasing tension and stress among the teams, as detailed in Table 2.
Table 2. Characterization of the communication planning in Event A
|
Analyzed Element |
Observed situation |
Perceived Impact |
|
Formal communication plan |
Not elaborated |
Lack of standardization |
|
Definition of official channels |
Not defined |
Use of parallel channels |
|
Clarity of audiences and responsible parties |
Partial |
Questions about responsibilities |
|
Frequency of alignments |
Reactive |
Late information |
|
Decision log |
Nonexistent or dispersed |
Low traceability |
|
Interfaces between fronts |
Unconsolidated |
Priority conflicts |
Source: Original research results
Table 2 illustrates the weaknesses of communication planning in Event A, where the lack of standardization and informational dispersion were evident. The absence of prior consolidation of critical interfaces between operational fronts, such as reception, access control, assembly, and security, contributed to priority conflicts and doubts regarding decision-making authority. This scenario corroborates the observations of Kerzner (2022) and PMI (2021), who highlight how the lack of robust communication planning can lead to delays, rework, and operational misalignments, compromising project predictability. Reactive communication, without defined channels or decision records, prevents the construction of organizational memory and hinders learning, as pointed out by Alves and Finger (2023) when discussing knowledge management in events. The reliance on *ad hoc* interactions and the absence of a formal communication structure limited the project’s ability to anticipate and mitigate problems, resulting in a work environment more prone to failures and inefficiencies.
In contrast, in Event B, communication planning was fully incorporated into the overall project planning. Before the start of the operational phase, a comprehensive Communication Management Plan was developed and shared. This plan included the identification of internal and external audiences, the definition of objectives for information flow, the specification of official channels, the frequency of updates, and the designation of those responsible for issuing and validating messages. In parallel, a RACI (Responsible, Accountable, Consulted, Informed) matrix was structured to clearly define responsibilities between internal coordination and supplier leadership. This formalization, according to Table 3, contributed significantly to reducing ambiguities and establishing explicit rules for information circulation, strengthening communication governance from the project’s inception.
Table 3. Characterization of the communication planning in Event B
|
Analyzed Element |
Observed situation |
Perceived effect |
|
Formal communication plan |
Developed and shared |
Standardization of flows |
|
Definition of official channels |
Main channel set |
Reduction of parallel messages |
|
Clarity of audiences and responsible parties |
Defined by function |
Greater objectivity |
|
Frequency of alignments |
Previously established |
Adjustment anticipation |
|
Decision log |
Structured |
Increased traceability |
|
Interfaces between fronts |
Previously mapped |
Better initial coordination |
Source: Original research results
Table 3 shows the consistent advances of Event B in relation to the initial structuring of communication. The formalization of communication flows, the centralization of channels, and the clear definition of responsibilities and anticipation of changes contributed to greater predictability and control of interactions between the teams involved. While Event A was dominated by a dispersed and reactive communication logic, Event B showed a more structured organization, capable of reducing noise, minimizing ambiguities, and strengthening coordination between operational fronts. These findings indicate that planned communication favored more adequate conditions for team integration from the beginning of the project, aligning with Robbins and Judge’s (2019) perspective on effective communication as an integrating element. Proactivity in defining channels and responsibilities, as demonstrated, is crucial to avoid the conflicts and rework that characterized Event A, as also observed by Vargas (2021) in his work on project management. The ability to anticipate and manage stakeholder information needs from the initial planning is a differential that translates into greater efficiency and a lower incidence of problems during execution.
Table 4 presents a consolidated comparison between Event A and Event B regarding the main dimensions of communication planning, synthesizing the observed differences and highlighting the effects of adopting more structured practices in Event B.
Table 4. Comparison of initial communication structuring
|
Dimension |
Event A |
Event B |
Observed difference |
|
Formalization |
Casual |
Structured |
Introduction of standardization |
|
Channels |
Parallel |
Centralized |
Noise reduction |
|
Responsibility |
Ambiguous |
Clearly defined |
Greater decision clarity |
|
Anticipation of changes |
Reactive |
Preventive |
Increase in predictability |
|
Traceability |
Low |
High |
Better control |
|
Integration between fronts |
Fragmented |
Previously articulated |
Initial minor conflict |
Source: Original research results
The initial structuring of communication, according to Table 4, directly influenced the teams’ integration capacity and the stability of subsequent project phases. The transition from an informal, fragmented, and reactive model to a structured, centralized, and preventive model was associated with significant gains in clarity, control, and predictability. This comparison reinforces that communication planning is not merely a preparatory activity but a central element of project governance, with a concrete impact on operational coordination and the reduction of alignment failures among participants. This finding corroborates Kerzner’s (2022) understanding, which emphasizes the direct influence of structuring communication processes on interfunctional coordination in complex environments. Furthermore, it aligns with PMBOK (PMI, 2021) best practices, which advocate for the prior definition of audiences, channels, frequency, and responsibilities to align expectations and reduce conflicts among stakeholders. In this context, communication ceased to be an informal mechanism for problem response and became a structuring component of project governance, actively managed as part of the management system.
Hiring Phase
The hiring phase represented a critical moment for team integration, as it was at this stage that expectations, responsibilities, and interaction standards between project coordination and suppliers were defined. In Event A, hiring focused predominantly on technical and commercial aspects, such as scope of delivery, values, deadlines, and operational conditions. There was no specific formalization regarding communication flows, official interlocutors, escalation rules, or critical interfaces between the different suppliers. Each supplier received specific guidance, linked to their area of operation, without structured integration with other teams. Table 5 illustrates the communication elements observed during the hiring phase of Event A, highlighting the identified conditions and their operational consequences.
Table 5. Hiring phase in Event A
|
Analyzed Element |
Identified situation |
Observed consequence |
|
Formal communication alignment |
Not carried out |
Limited integration |
|
Definition of official interlocutors |
Partial |
Communication noise |
|
Presentation of critical interfaces |
Unstructured |
Operational Conflicts |
|
Escalation rules |
Not formalized |
Central coordination dependence |
|
Supplier integration |
Low |
Fragmented action |
Source: Original research results
Table 5 reveals that the absence of formal communication alignment during the contracting phase of Event A resulted in limited integration and communication noise. The ambiguity of official interlocutors and the lack of structured critical interfaces generated operational conflicts and an excessive dependence on central coordination to resolve problems. Unformalized escalation rules contributed to a fragmented performance by suppliers, hindering coordination and collaboration. This scenario reflects what Meredith et al. (2020) describe as a challenge in complex projects with multiple suppliers, where the absence of structured communication planning can limit the integration and alignment of activities. The lack of proactivity in communication management during contracting meant that many interface and responsibility issues would only emerge during the assembly and execution phases, requiring costly and reactive corrective interventions, rather than preventive ones.
In Event B, the contracting phase began to incorporate communication guidelines defined in the project planning. In addition to technical and commercial aspects, collective formal alignments were carried out, in which the official channels, the interfaces between operational fronts, the escalation rules, and the position of each supplier in the project responsibility matrix were presented. Table 6 presents the communication elements structured in the contracting phase of Event B, highlighting the positive effects of formalization on the initial integration of the teams.
Table 6. Hiring phase in Event B
|
Analyzed Element |
Identified situation |
Observed effect |
|
Formal communication alignment |
Previously performed |
Initial greater integration |
|
Definition of official interlocutors |
Established |
Noise reduction |
|
Presentation of critical interfaces |
Structured |
Better coordination between fronts |
|
Escalation rules |
Formalized |
Agility in problem solving |
|
Supplier integration |
Encouraged from the beginning |
Collaborative action |
Source: Original research results
Table 6 shows that the formalization of communication in the contracting phase of Event B resulted in greater initial team integration, reduced noise, and better coordination between fronts. The clear definition of interlocutors and the structuring of critical interfaces, along with formalized escalation rules, contributed to greater agility in problem-solving and encouraged collaborative action from the outset. This approach aligns with Bourne (2016), who highlights the importance of integrating external stakeholders into project governance from the initial phases to prevent them from acting in isolation. The PMBOK (PMI, 2021) also reinforces that stakeholder engagement and alignment should be considered from the beginning of the project lifecycle. In supplier-intensive projects, contracting, when conducted from the perspective of Communications Management, becomes a strategic step to prevent future noise and establish a more systemic perception of the project, expanding team integration right from the start of the operational cycle.
Assembly
The assembly phase constituted the moment of greatest operational interdependence between the teams, concentrating simultaneous activities of infrastructure, assembly, installation, accreditation, signage, security, and logistics. This stage allowed for a clearer observation of the practical effects of the absence or presence of structured communication tools. In Event A, the assembly occurred without the formal application of the tools described in the Materials and Methods. There was no structured use of a communication plan, consolidated RACI matrix, or standardized system for recording occurrences. Information flows were decentralized and heavily dependent on the direct mediation of project coordination, generating an environment of high uncertainty and reactivity.
The absence of an operational RACI matrix resulted in frequent doubts about who had the authority to approve *layout* adjustments, technical changes, or logistical shifts. In several situations, suppliers sought simultaneous validations from different contacts, leading to conflicting guidance and rework. The lack of standardized *checklists* per work front increased the probability of errors and inconsistencies, as evidenced in Table 7.
Table 7. Event A Assembly
|
Expected tool |
Practical application |
Observed consequence |
|
Communication plan |
Not formally applied |
Dispersed informational flow |
|
RACI Matrix |
Not operationalized |
Decision ambiguity |
|
“Standardized Checklists” |
Not used |
Rework and inconsistencies |
|
Centralized official channel |
Non-existent |
Parallel messages |
|
Occurrence log |
Non-systematic |
Low traceability |
Source: Original research results
Table 7 illustrates the consequences of unstructured communication in the assembly phase of Event A, where dispersed informational flow, decision-making ambiguity, and low traceability resulted in rework and inconsistencies. This scenario of dependence on direct mediation by central coordination to resolve conflicts and clarify doubts is a direct reflection of the lack of communication governance, as warned by Kerzner (2022). The absence of official channels and a systematic record of occurrences hindered the management of unforeseen events and organizational learning, perpetuating the same problems in different situations. The overload of central coordination, acting as an informational bottleneck, compromised the agility and efficiency of the operation, a critical point in large-scale events, as highlighted by Silvers (2021).
In Event B, communication tools were applied in an integrated manner during the assembly. The communication plan was operationalized with a clear definition of official channels and update schedules. The RACI matrix was used as a reference for operational decisions, reducing ambiguities about roles and responsibilities. Daily operational briefings, checklists per work front, and a central record of occurrences and decisions were implemented. Table 8 presents the application of these tools in the assembly phase of Event B, highlighting the form of use and the observed results.
Table 8. Event B Assembly
|
Applied tool |
Application method |
Observed result |
|
Communication plan |
Single official channel and defined rules |
Reduction of conflicting messages |
|
RACI Matrix |
Used for operational decisions |
Greater clarity of authority |
|
“Daily Briefings” |
Alignment of prior priorities |
Conflict anticipation |
|
“Standardized Checklists” |
Operational Front Control |
Reduction of rework |
|
Occurrence log |
Centralized document |
Increased traceability |
Source: Original research results
Table 8 demonstrates that the structured application of communication tools in Event B resulted in a significant reduction of conflicting messages, greater clarity of authority, and anticipation of conflicts. The use of a single official channel, daily briefings, and standardized checklists contributed to the reduction of rework and the increase of traceability. Table 9, in turn, presents the comparison between Events A and B in the assembly phase, highlighting differences related to coordination, clarity, and operational integration.
Table 9. Comparison of the assembly phase
|
Dimension |
Event A |
Event B |
Observed difference |
|
Decision clarity |
Low |
High |
Conflict Reduction |
|
Volume of rework |
Most frequent |
Reduced |
Operational improvement |
|
Response time to adjustments |
Variable |
More agile |
Greater predictability |
|
Coordination intervention |
High dependence |
Less dependence |
Self-oriented autonomy |
|
Supplier integration |
Fragmented |
Collaborative |
Better coordination |
Source: Original research results
The assembly phase, according to Table 9, presented the most concrete evidence of the effects of the adopted communication strategies. In analytical terms, the data suggest that the observed improvement in Event B did not stem solely from the isolated presence of tools, but from the systemic integration between them. The communication plan, the RACI matrix, the *briefings*, and the *checklists* functioned as complementary mechanisms for informational governance. This result aligns with Meredith et al. (2020), confirming that failures in interfunctional integration tend to generate rework, operational tension, and excessive dependence on central leadership. It also aligns with the contributions of Bourne (2016), who recognizes Communications Management and Stakeholder Management as interdependent dimensions in complex projects. From the perspective of practice transformed into academic analysis, the assembly revealed that the formalization of information flows contributed to reducing ambiguities, preventing interface conflicts, and increasing operational predictability. Therefore, it was concluded that structured communication operated as a preventive coordination mechanism, rather than just a corrective instrument, promoting oriented autonomy and better coordination among suppliers.
Event B RACI Matrix
The clarity of responsibilities constituted one of the central elements of the applied intervention in Event B. For this, a RACI matrix was built for the critical fronts of the event, synthesized in Table 10. This tool was fundamental to operationally define who should execute, approve, consult, or be informed in each project activity.
Table 10. Simplified RACI Matrix of Event B
|
Activity / Front |
Project Manager |
Operational Coordination |
Assembly Provider |
Security Provider |
Reception Provider / Registration |
Technical Support / Audiovisual |
|
Approval of the operational plan |
A |
R |
C |
C |
C |
C |
|
Definition of official channels |
A |
R |
I |
I |
I |
I |
|
Structure assembly |
C |
A |
R |
I |
I |
C |
|
Assembly access control |
C |
R |
C |
A/R |
I |
I |
|
Accreditation and reception |
C |
C |
I |
C |
A/R |
I |
|
Technical adjustments in equipment |
C |
C |
C |
I |
I |
A/R |
|
Occurrence log |
A |
R |
R |
R |
R |
R |
|
Escalation of critical issues |
A |
R |
C |
C |
C |
C |
|
“Daily Briefing” |
A |
R |
C |
C |
C |
C |
|
Closing and consolidation of lessons learned |
A |
R |
C |
C |
C |
C |
Source: Original research results
Table 10, which presents the simplified RACI Matrix for Event B, showed that the intervention was not limited to generically “improving communication” but delved into the operational definition of roles and responsibilities. In theoretical terms, this definition of roles reinforced the principle of accountability and decision-making clarity advocated by the PMBOK (PMI, 2021), in addition to reducing overlapping and conflicting areas typical of projects with multiple suppliers. The application of the RACI matrix allowed outsourced teams to clearly understand their duties and the limits of their autonomy, minimizing the need for constant validations and the occurrence of conflicting guidance. This resulted in greater agility in decision-making and problem-solving, as each stakeholder knew exactly whom to turn to or who should be involved in each stage of the process. The RACI matrix, therefore, was not just a document but a practical guide that institutionalized information and decision governance, transforming the work dynamic from reactive to proactive and collaborative.
Event Execution
The execution phase constituted the moment of greatest operational pressure, characterized by the simultaneity of activities, high public flow, need for immediate responses, and low tolerance for failures. In Event A, execution occurred under strong dependence on central coordination for conflict resolution and clarification of operational doubts. The absence of a single official channel generated situations where suppliers received distinct or incomplete guidance, resulting in misalignments and rework. Punctual changes were communicated in a decentralized manner, increasing the risk of inconsistencies. Furthermore, there was no structured system for real-time incident recording. Critical situations were resolved punctually, without formal consolidation of decisions, which hindered subsequent consultations and generated repetition of previously solved questions. Table 11 presents the communication elements observed in the execution phase of Event A, highlighting their limitations and operational consequences.
Table 11. Event A Execution
|
Analyzed Element |
Identified situation |
Observed consequence |
|
Official single channel |
Not established |
Divergent guidelines |
|
Occurrence log |
Unsystematized |
Low traceability |
|
Decision scaling |
Not formalized |
Coordination dependence |
|
Response to unforeseen events |
Reactive |
Adjustments under pressure |
|
Integration between fronts |
Fragmented |
Higher probability of conflict |
Source: Original research results
Table 11 illustrates the communication deficiencies in Event A during execution, where the lack of an official channel, incident reporting, and formal decision escalation resulted in divergent guidance, low traceability, and excessive reliance on coordination. The reactive response to unforeseen events and fragmented integration between fronts increased the probability of conflicts and pressure on the central team. This scenario is consistent with Silvers’ (2021) observations, which highlight the need for continuous informational coordination in large-scale events due to the simultaneity of operations and the low margin for error. The absence of formal communication and recording mechanisms not only hindered real-time problem-solving but also prevented the creation of a knowledge base for future improvements, perpetuating a cycle of inefficiency and operational stress.
In Event B, execution occurred with full application of the previously structured tools. The official channel defined in the communication plan was used as the main route for operational guidance, ensuring information uniformity. Emergency situations were recorded in a central occurrence document, allowing for monitoring and traceability of decisions and actions. Pre-operational briefings aligned priorities and anticipated risks, while the RACI matrix served as a reference for quick decisions, empowering teams with clarity on their responsibilities. Table 12 presents the communication practices applied in the execution phase of Event B, highlighting the effects of structuring on project management.
Table 12. Event B Execution
|
Applied tool |
How to use |
Observed result |
|
Centralized official channel |
Main use for guidance |
Reduction of divergences |
|
Structured log of occurrences |
Consolidation into a single document |
Greater traceability |
|
Formal scaling |
Clear definition of decision levels |
Agility in resolution |
|
“Pre-operational Briefings” |
Daily priority alignment |
Risk anticipation |
|
Application of RACI |
Basis for quick decisions |
Clarity of authority |
Source: Original research results
Table 12 shows that the application of a centralized official channel, structured recording of occurrences, formal escalation, and pre-operational briefings in Event B resulted in a reduction of divergences, greater traceability, agility in resolution and anticipation of risks, in addition to clarity of authority. Table 13 presents the comparison between Events A and B during execution, highlighting differences in response to unforeseen events, integration, and information control.
Table 13. Comparison of event execution
|
Dimension |
Event A |
Event B |
Observed difference |
|
Response time to unforeseen events |
Variable and dependent on coordination |
More agile and structured |
Greater decision-making efficiency |
|
Consistency of guidelines |
Non-standard |
Standardized |
Noise reduction |
|
Traceability of decisions |
Limited |
High |
Better control |
|
Supplier integration |
Reactive |
Preventive |
Increase in cooperation |
|
Pressure on central coordination |
High |
Reduced |
Balanced distribution of responsibility |
Source: Original research results
The execution, according to Table 13, revealed that the combined application of communication tools not only organized the informational flow but also reduced the project’s vulnerability to unforeseen events. Instead of relying exclusively on the continuous presence of the project manager as the center of all decisions, Event B began to operate with greater guided autonomy, supported by previously defined rules. This result aligned with the PMBOK (PMI, 2021), which emphasizes the importance of structured communications management to ensure alignment and efficiency in dynamic environments. It also approached Kerzner’s (2022) contributions, indicating that projects with multiple *stakeholders* require clear governance to preserve stability during execution. In analytical terms, the observed improvement was not only operational but managerial, with a more balanced redistribution of responsibilities, increased coherence of guidance, and reduced dependence on corrective mediations. Therefore, the execution of Event B demonstrated that structured communication acted as an instrument for coordination and support of project performance, promoting greater decision-making efficiency and increased cooperation among suppliers.
Post-event
The post-event stage represented the moment of consolidation of the evidence observed throughout the lifecycle of the analyzed projects. In Event A, the closure occurred without a structured process for formal recording of lessons learned related to communication. Although there was an informal perception of the difficulties faced, a consolidated analysis of the causes of the observed misalignments was not conducted. Specific indicators related to communication were also not consolidated, which limited the objective evaluation of the communication impact on project performance. The absence of a formal system for recording and analyzing feedback prevented the capitalization of the generated knowledge, resulting in the repetition of errors and the loss of opportunities for continuous improvement.
In contrast, in Event B, the post-event was conducted based on structured records generated during execution. The occurrence and decision logging system allowed for the identification of adjustment patterns made, as well as situations where the application of the RACI matrix and briefings contributed to a more agile resolution of conflicts. Table 14 presents a comparison of the results observed in the post-event, highlighting differences in the consolidation of learnings and in communication maturity.
Table 14. Post-event comparison
|
Dimension |
Event A |
Event B |
Observed result |
|
Lessons learned register |
Unstructured |
Based on formal records |
Greater organizational learning |
|
Communicational indicators |
Unconsolidated |
Recorded evidence |
Better analytical skills |
|
Rework associated with communication |
Most frequent |
Reduced |
Operational improvement |
|
Clarity of responsibilities |
Recurring questions |
Greater consistency |
Strengthened integration |
|
Informational governance |
Limited |
Structured |
Maturity increase |
Source: Original research results
Table 14 demonstrates that, in Event B, the lessons learned register was based on formal records, resulting in greater organizational learning and improved analytical capacity. The reduction in rework associated with communication and the increased consistency in the clarity of responsibilities indicated operational improvement and strengthened integration. Information governance, which was limited in Event A, became structured in Event B, contributing to an increase in the project’s communication maturity. These findings corroborate the guidelines of the PMBOK (PMI, 2021), which highlight Communications Management as a central element for the integration of stakeholders, and also align with the contributions of Kerzner (2022), by evidencing that projects with structured communication governance tend to present a lower incidence of operational conflicts and greater stability during execution. The ability to record, analyze, and apply lessons learned is fundamental for continuous improvement and for the development of a more resilient and efficient organizational culture, a crucial point for companies operating in highly complex environments such as the events sector.
Integrative Synthesis of Results
The comparative analysis between the two events allowed us to identify that the transition from an informal and reactive communication model to a structured and preventive model was associated with five main gains: reduction of operational rework, greater decision-making clarity, decrease in interorganizational conflicts, increased traceability of decisions, and improved team integration. Table 15 presented a synthesis of the gains observed in Event B in relation to Event A, based on the main aspects analyzed throughout the project.
Table 15. Synthesis of the gains observed in Event B
|
Analyzed aspect |
Predominant situation in Event A |
Predominant situation in Event B |
Observed trend |
|
Information flow |
Dispersed |
Organized |
Improvement |
|
Clarity of roles |
Ambiguous |
Defined |
Improvement |
|
Conflict Resolution |
Reactive |
Faster and oriented |
Improvement |
|
Decision log |
Dispersed |
Centered |
Improvement |
|
Team integration |
Fragmented |
More collaborative |
Improvement |
|
Pressure on the coordination |
High |
Reduced |
Improvement |
Source: Original research results
Table 15 consolidates the gains observed in Event B, highlighting the improvement in all analyzed aspects, from the organized flow of information to the reduction of pressure on coordination. This consolidation of results at the end of Event B indicated that the integrated application of the tools described in the Materials and Methods promoted not only specific improvements but also a noticeable increase in the project’s communication maturity. In academic terms, this allowed the intervention to be interpreted as a process of institutionalizing information governance practices in a supplier-intensive environment. The findings corroborated the guidelines of the PMBOK (PMI, 2021), which highlight Communications Management as a central element for stakeholder integration, and also aligned with Kerzner’s (2022) contributions by demonstrating that projects with structured communication governance tended to show a lower incidence of operational conflicts and greater stability during execution. Similarly, Silvers (2021) emphasized that large-scale events require continuous information coordination, given the simultaneity of operations and the low margin for error. Thus, it was concluded that the post-event stage systematically confirmed the positive effects of the intervention applied in Event B, reinforcing the relevance of structured communication as a project management practice for large-scale events.
Table 16 presented the general comparative synthesis between Events A and B, consolidating the main results related to communication throughout the project lifecycle.
Table 16. General comparative synthesis between Event A and Event B
|
Criterion |
Event A |
Event B |
Analytical interpretation |
|
Communication Planning |
Casual |
Formalized |
Initial greater governance |
|
Integration in hiring |
Limited |
Structured |
Better alignment between suppliers |
|
Coordination in assembly |
Reactive |
Preventive |
Reduction of interface conflicts |
|
Execution Management |
Dependent on central coordination |
More distributed and oriented |
Greater operational autonomy |
|
Post-event learning |
Casual |
Registered and analyzed |
Greater communication maturity |
Source: Original research results
Table 16, by synthesizing the general comparison, reinforces the analytical interpretation that the formalization of communication in Event B resulted in greater initial governance, better alignment between suppliers, reduction of interface conflicts, greater operational autonomy, and greater communicational maturity. From the perspective of academic contribution, the study demonstrated that current operational daily practices, when organized into artifacts such as a communication plan, RACI matrix, briefings, checklists, and occurrence records, could be interpreted as formal mechanisms for communication management. This movement proved important because it transformed practical experience into analytical evidence, bringing the project’s reality closer to the conceptual categories discussed in the literature.
The intervention applied in Event B was based on widely used communication management tools and artifacts in project management. Among the main instruments adopted were: the Communication Management Plan, which defined involved audiences, communication objectives, official channels, communication frequency, and those responsible for each informational flow, with the objective of organizing and standardizing information sharing in the project (PMI, 2021; Kerzner, 2022). The RACI Matrix was used to clarify responsibilities among the internal team, supplier leadership, and operational teams, reducing ambiguities about who should execute, approve, consult, or be informed about each project activity (PMI, 2021). Operational briefings and quick alignment meetings, periodic gatherings held during the event’s assembly and execution phases, focused on updating priorities, operational risks, and team integration (Silvers, 2021). Standardized operational checklists were instruments used to guide and monitor specific activities such as accreditation, security, reception, and access control, contributing to the standardization of instructions and the monitoring of task execution. The centralization of official communication channels defined formal channels for operational guidance and incident recording, reducing informational noise and facilitating decision monitoring. Finally, the recording of incidents and decisions was a mechanism used to document changes, problems, and referrals during the project, increasing information traceability and supporting decision-making in moments of operational pressure.
In general, the research results demonstrated that the transition from an informal and reactive communication model (Event A) to a structured and preventive model (Event B) was associated with: a reduction in operational rework; greater decision-making clarity; a decrease in interorganizational conflicts; an increase in decision traceability; and an improvement in the integration of outsourced teams. These elements met the objective proposed by the study, by evidencing that the structured application of communication strategies contributed measurably to the efficiency of project execution and to the strengthening of outsourced team integration. Finally, the findings reinforced that, in large-scale event projects, communication should not be understood as an accessory activity, but as a structuring dimension for team integration and operational project stability. The comparative experience between Event A and Event B indicated that planned, centralized, and traceable communication was associated with greater predictability, greater cooperation between fronts, and a better response capacity in critical situations, which confirmed its strategic relevance in the context of project management.
4. Conclusion
It is concluded that the objective was achieved, as the study demonstrated the effectiveness of developing and applying a communication management plan to integrate teams and suppliers in a large-scale event project, based on good project management practices. The comparison between Event A, with informal and reactive communication, and Event B, with structured practices, showed significant gains. In Event B, a reduction in operational rework, greater decision-making clarity, a decrease in inter-organizational conflicts, increased traceability of decisions, and substantial improvement in the integration of outsourced teams were observed. These results confirm communication as a strategic pillar for governance and operational stability in complex projects, transforming the work dynamic from reactive to proactive and collaborative.
However, the present study has limitations inherent to its methodological approach. Access to detailed quantitative data was restricted, and the evidence was predominantly based on qualitative records and participant observation, which may limit the generalization of results to other contexts. Furthermore, the research was conducted in a single organization and in a specific sector. For future studies, it is recommended to broaden the investigation to different types of events and organizational contexts, incorporating quantitative approaches to more objectively measure the impact of communication on performance indicators. It is also suggested to explore the integration of digital technologies in communication management and deepen the analysis of the relationship between communication, stakeholder engagement, and performance in projects with distributed teams and multicultural environments.
Bibliographic References
Alves, A. C. F.; Finger, A. B. 2023. Gestão do Conhecimento: Evento institucional como fonte de informação organizacional. In: Encontro Nacional De Pesquisa em Ciência da Informação, 21., 2021, Rio de Janeiro. Anais […]. Rio de Janeiro: IBICT: UFRJ, 2021. Disponível em: <https://enancib.ancib.org/index.php/enancib/xxienancib/paper/viewFile/32/198>. Acesso em: 9 abr. 2026.
Bourne, L. 2016. Stakeholder Relationship Management: A Maturity Model for Organisational Implementation. 2ed. Gower Publishing, Farnham, Surrey, Reino Unido.
Flick, U. 2009. Introdução à Pesquisa Qualitativa. 3ed. Artmed, Porto Alegre, RS, Brasil.
Gil, A.C. 2017. Como Elaborar Projetos de Pesquisa. 6ed. Atlas, São Paulo, SP, Brasil.
Kerzner, H. 2022. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 13ed. John Wiley & Sons, Hoboken, New Jersey, Estados Unidos.
Meredith, J.R.; Shafer, S.M.; Mantel, S.J. 2020. Project Management: A Strategic Managerial Approach. 10ed. John Wiley & Sons, Hoboken, New Jersey, Estados Unidos.
Minayo, M.C.S. 2014. O Desafio do Conhecimento: Pesquisa Qualitativa em Saúde. 14ed. Hucitec, São Paulo, SP, Brasil.
Project Management Institute [PMI]. 2021. A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 7ed. Project Management Institute, Newtown Square, Pennsylvania, Estados Unidos.
Robbins, S.P.; Judge, T.A. 2019. Organizational Behavior. 18ed. Pearson Education, Harlow, Essex, Reino Unido.
Silvers, J.R. 2021. Professional Event Coordination. 3ed. John Wiley & Sons, Hoboken, New Jersey, Estados Unidos.
Thiollent, M. 2011. Metodologia da Pesquisa-Ação. 18ed. Cortez, São Paulo, SP, Brasil.
Tripp, D. 2005. Pesquisa-ação: uma introdução metodológica. Educação e Pesquisa. 31(3): 443-466.
Vargas, R.V. 2021. Gerenciamento de Projetos: Estabelecendo Diferenciais Competitivos. 9ed. Brasport, Rio de Janeiro, RJ, Brasil.
Yin, R.K. 2015. Estudo de Caso: Planejamento e Métodos. 5ed. Bookman, Porto Alegre, RS, Brasil.