Stakeholder Planning and Engagement: Efficiency and Cost Reduction in Corporate Projects
Stakeholder Planning and Engagement: Efficiency and Cost Reduction in Corporate Projects
Renan Bussi Machado; Aline Gisele Zanão Benatto
DOI: 10.22167/2675-6528-202601349
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Stakeholder management holds fundamental relevance in the performance of corporate architecture projects, especially in challenging contexts with short deadlines, multiple interfaces, and a high need for alignment among those involved. The study aimed to analyze how stakeholder planning and engagement contributed to the reduction of rework and costs in these projects, and proposed a structured model to support the management of these interested parties throughout the lifecycle. The research was conducted through a qualitative, descriptive, and exploratory approach, using a structured questionnaire applied to 53 professionals in the corporate architecture segment in the city of São Paulo, with data collection between April 2025 and March 2026. The results revealed that, although most professionals recognized the importance of planning stakeholder engagement, the application of structured tools proved to be limited and little widespread. This scenario contributed to the recurrence of problems such as late inclusion of stakeholders, communication failures, rework, and increased costs, evidencing a gap between perception and practice. Based on the data obtained, a structured stakeholder management model was proposed, organized into six stages, to systematize identification, analysis, planning, engagement, and monitoring. It was concluded that the adoption of structured stakeholder management practices can significantly improve efficiency, reduce risks, and optimize costs in corporate architecture projects.
Keywords: Communication; Project management; Power and interest matrix; Process optimization; Rework.
1. Introduction
Project management, as a discipline, has gained prominence in recent decades as a fundamental pillar for organizational success in an increasingly competitive and dynamic global scenario (Kerzner, 2015). Within this scope, corporate architecture presents intrinsic particularities, characterized by frequently tight deadlines, multiple technical interfaces, and a constant demand for alignment among the various parties involved. The inherent complexity of these projects requires a strategic approach to mitigate risks and optimize resources, making stakeholder management a critical component for value delivery.
The concept of stakeholder, popularized by Freeman (1984), refers to any individual or group that can affect or be affected by the objectives of a project. Effective management of these stakeholders transcends mere communication, encompassing identification, analysis, engagement planning, and continuous monitoring throughout the entire project lifecycle (PMI, 2021). This proactive approach is essential for building collaborative relationships, managing expectations, and anticipating potential conflicts, which, if not addressed, can severely compromise project performance (Bourne, 2015).
In the corporate architecture sector, inefficiency in stakeholder management manifests in recurring problems, such as the late inclusion of critical stakeholders, communication failures leading to misalignments, and consequently, a significant increase in rework and additional costs (Gray & Larson, 2020). Data from the construction and project industry, although not specific to corporate architecture, frequently indicate that poor communication and inadequate management of stakeholder expectations are primary causes of project failures, contributing to budget overruns and schedule delays (Dultra-de-Lima et al., 2020). The absence of structured planning for engaging these parties, from the initial phases, amplifies these challenges, transforming potentially successful projects into high-risk ventures.
Despite the theoretical recognition of the importance of stakeholder management, the practical application of structured methodologies and tools is still limited in many professional contexts, including the corporate architecture segment. A gap is observed between the perception of the topic’s relevance and the effective adoption of formalized practices to identify, analyze, and engage stakeholders (Lopes et al., 2020). This inconsistency results in informal processes, dependent on individual managers’ experience, and the underutilization of resources that could optimize decision-making and coordination of efforts. The lack of systematization contributes to the persistence of problems such as information centralization and difficulty in reconciling diverse interests, directly impacting the efficiency and predictability of projects (Noro, 2012).
Given the growing complexity of corporate architecture projects and the observed gap between theory and practice in stakeholder management, it becomes imperative to investigate how more effective planning and engagement can mitigate the challenges inherent in this sector. The justification for this study lies in the need to improve operational efficiency, reduce costs associated with rework, and optimize value delivery in corporate architecture projects, contributing to project management maturity in the segment. Thus, this work aims to analyze how stakeholder planning and engagement contribute to the reduction of rework and costs in these projects, and to propose a structured model to support the management of these interested parties throughout the lifecycle.
2. Material and Methods
This work was conducted based on a qualitative, descriptive, and survey approach, characterizing itself as applied research. The main intention was to generate material for practical application, aiming at solving specific problems in the context of corporate architecture. Descriptive research, according to Gil (2017), sought to describe the characteristics of a phenomenon and the relationships between variables, without direct intervention from the researcher. Thus, it was sought to understand how corporate architecture professionals perceive, apply, and face the challenges of stakeholder management in their projects.
The qualitative approach was selected to allow for an in-depth understanding of the dynamics studied, considering the subjectivity of the relationships between stakeholders and the particularities of each architectural project. This choice proved adequate for analyzing processes, perceptions, and practices in a specific context, marked by multiple interactions and variables not measurable in isolation, such as communication, alignment, and the relationship between interested parties in corporate architectural projects. The descriptive design emphasized obtaining data to map practices, challenges, and professionals’ perceptions of stakeholder planning and engagement.
The study’s unit of analysis was the processes and practices observed in a multinational architecture company, headquartered in São Paulo, Brazil. This organization has over twenty-five years of experience in the national corporate architecture market, competing with other major players in the sector. Its team is composed mainly of architects and urban planners, totaling more than eighty professionals. The company’s portfolio covers various segments, with a primary focus on corporate interior projects, ranging from small interventions of 200 m² to large corporations with over 10,000 m².
Data collection was carried out in a period between April 2025 and March 2026, with the highest concentration of responses recorded in the first quarter of 2026. The participants were professionals working in the corporate architecture segment, specifically in the city of São Paulo. The choice of this location allowed us to focus on a relevant market for the sector, where the studied company has a strong presence and a significant volume of projects, offering a conducive scenario for the investigation of stakeholder management practices.
The target population of the research consisted of professionals with experience in corporate architecture projects in the city of São Paulo. The sampling adopted was non-probabilistic, by convenience, justified by the ease of access to participants and the specific scope of the study. The final sample was composed of fifty-three respondents, predominantly professionals with experience or background in corporate architecture projects. Participant selection occurred through the researcher’s professional network and social networks, such as LinkedIn and WhatsApp.
The data collection instrument was a structured questionnaire, developed based on consolidated theoretical references in the area of project and stakeholder management. The PMBOK® Guide (PMI, 2021), as well as the works of Gil (2017) and Kerzner (2015), were used as pillars. The comprehensive literature review, which included current publications, technical books, and scientific articles, addressed concepts of stakeholder management, project planning, communication, and engagement strategies. This theoretical foundation was crucial for structuring the questionnaire questions and for the subsequent analysis of the collected data.
The questionnaire was developed based on the theoretical references mentioned, also including Freeman (1984) and Bourne (2015), and was divided into two main blocks. The first block focused on surveying the professional profile of the respondents, collecting information on education, position, experience, and company type. The second block focused on the participants’ practices, perceptions, and familiarity with the theme of stakeholder management. The instrument totaled twenty-nine questions, presented in various formats, such as multiple choice, Likert scale, and open-ended questions, allowing for a mixed data collection, both quantitative and qualitative.
Data collection was operationalized through a digital form, using the Google Forms platform, which facilitated distribution and completion by participants. The questionnaire link was disseminated to professionals working in the corporate architecture segment in the city of São Paulo. The dissemination occurred through a strategic combination of channels, including the researcher’s professional network and social media platforms, such as LinkedIn and WhatsApp, aiming to reach a relevant audience engaged with the research topic.
The analysis of the collected data was carried out on two fronts, according to the format of the questions. The answers to the closed questions were tabulated by relative frequency, allowing the identification of patterns and the performance of exploratory cross-tabulations between different variables. For the open-ended answers, a simple content analysis was employed, organizing them based on the most recurrent themes. This method enabled the observation of common practices, perceived challenges, and points of divergence among professionals, contributing to an in-depth understanding of perceptions regarding stakeholder management.
Although the sample does not have a statistically representative character of the entire corporate architecture sector, the number of participants was considered adequate for the exploratory and descriptive objectives of the study, which aimed to identify patterns of perception and professional practices, as recommended by Gil (2017). The punctual inclusion of respondents from other areas of training or practice was observed, which, although it represents a methodological limitation in terms of homogeneity, was considered relevant to broaden the understanding of stakeholder management in related contexts, enriching the analyzed perspectives.
The study’s limitations include the sample size, composed of fifty-three professionals, and the concentration of respondents in the city of São Paulo. This geographical delimitation may not fully reflect the reality of other markets or regions in Brazil. Additionally, the analysis was conducted with an exclusive focus on the corporate architecture segment, not encompassing other architecture sectors, such as residential, hospital, or educational projects. These aspects limit the generalization of the findings, but do not compromise the validity of the perceptions within the specific scope investigated.
3. Results and Discussion
In this stage of the work, the main results obtained by applying a structured questionnaire to professionals working in corporate architecture projects are presented. The central objective was to map current practices, prevailing perceptions, and intrinsic challenges related to stakeholder planning and engagement. Additionally, we sought to identify opportunities and patterns that could support the structuring of a more efficient model for managing and monitoring stakeholders throughout the entire project lifecycle. 53 valid responses were collected, a number that, although it does not confer statistical representativeness to the entire sector, allows for a consistent and comprehensive analysis for the exploratory and descriptive objectives of the study, as recommended by Gil (2017).
For clearer data organization and analysis, the results were structured into five main thematic blocks: Respondent Profile, Stakeholder Management Experience, Tools Used, Engagement Level, and finally, Key Challenges and Best Practices. This segmentation facilitates the understanding of the interconnections between the different dimensions of stakeholder management within the context of corporate architecture.
Respondent profile
The research sample consisted of 53 professionals, with a notable predominance of architects and urban planners active in the corporate architecture segment. This profile is crucial for the internal validity of the study, as the perceptions and practices analyzed emanate directly from those who experience the day-to-day of projects. A particularly relevant piece of data is that 67.9% of respondents have more than seven years of professional experience in the sector. This high level of experience, as illustrated in Figure 1, indicates a qualified profile with substantial practical experience, which lends greater robustness and reliability to the analyzed perceptions. Professionals with long careers in the market tend to have a more holistic and critical view of project processes, challenges, and successes, enriching the quality of the collected data.
Source: Original research results
Figure 1. Respondents’ experience in the sector
The predominant training in Architecture and Urbanism, complemented by the participation of professionals from related areas such as Engineering and Design, reinforces the consistency of the results. This multidisciplinary composition of the sample, even with the main focus on architects, allows the analyzed perceptions to reflect consolidated and diversified experiences in real projects. The presence of different perspectives, although occasional, enriches the understanding of stakeholder management in related contexts, broadening the scope of the analysis and the adherence of the research findings to the complex reality of corporate architecture projects. The consolidated experience of the participants is a fundamental pillar for the interpretation of the results, as their responses are based on in-depth practical knowledge, allowing for a more accurate analysis of the nuances of stakeholder management.
Stakeholder Management
The results obtained indicate that stakeholder management is widely recognized as a critical factor for the success of corporate architecture projects. The vast majority of respondents attributed a high degree of importance to the planning of stakeholder engagement, which is in line with the literature that emphasizes the centrality of stakeholders for the success of any undertaking (PMI, 2021; Freeman, 1984). This theoretical recognition, however, contrasts with a significant gap in practical application.
There is a notable difference between the perception of the importance of stakeholder management and its effective application in the day-to-day of projects. The majority of professionals, specifically 62.3%, indicated that they do not participate in the definition of stakeholders in the initial phases of projects, as evidenced in Figure 2. This absence of early involvement is a critical finding, because, as pointed out by Freeman (1984), the identification and analysis of stakeholders from the beginning are fundamental to anticipating expectations, mitigating risks, and establishing solid bases for engagement. The late inclusion of relevant agents, or their initial non-identification, can lead to failures in mapping interests and influences, resulting in misalignment of expectations and rework, as widely discussed by the PMI (2021).
Source: Original research results
Figure 2. Participation of professionals in defining stakeholders in the initial phases
The practical implication of this gap is profound. Non-participation in the initial definition of stakeholders means that many projects may be conceived and developed without a complete understanding of all parties who will be affected or who can influence the project. This can lead to suboptimal decisions, incomplete requirements, and consequently, scope and design revisions in advanced stages, generating additional costs and delays. Project management literature, such as Kerzner (2015), consistently emphasizes that stakeholder identification and engagement planning are continuous processes that should begin as early as possible to ensure alignment and collaboration. The observed discrepancy suggests that, although professionals understand the theory, organizational barriers or the lack of structured processes prevent its effective application.
Additionally, 56.6% of respondents indicated they had already participated in projects where stakeholder turnover compromised the project’s development or completion. This data is alarming and reinforces the perception of a negative impact on project progress, with 73.6% of participants indicating that stakeholder replacement generates adverse effects. This sensitivity of projects to the stability and continuity of the agents involved underscores the importance of robust planning that includes Change Management and the transition of responsibilities among stakeholders. The turnover or late entry of new actors with unforeseen demands can destabilize the project’s schedule, budget, and even final quality, as highlighted by Dultra-de-Lima et al. (2020) when discussing success and failure factors in projects. The lack of a formal process to manage these changes further exacerbates the situation, turning a potentially manageable event into a project crisis.
This discrepancy between the perceived importance and the practical application of stakeholder management highlights a recurring gap between theory and practice, widely discussed in project management literature. The PMI (2021) reiterates that early identification and engagement of stakeholders are critical factors for project success. Lopes et al. (2020) also reinforce that the adoption of structured management practices, aligned with the PMBOK, is directly associated with increased project success rates. The data that contrasts with this perception is the low adoption of structured tools, evidencing an inconsistency between the importance attributed to the topic and its practical application in the professional context. This suggests that, although professionals recognize the value of stakeholder management, the implementation of formal methodologies and tools is still a significant challenge, which may be attributed to a lack of training, resources, or an organizational culture that prioritizes more informal approaches.
Tools used
Regarding the tools used for stakeholder management, the research revealed a clear preference for simple and accessible solutions, over more structured methodologies. There is a predominance of the use of Excel spreadsheets, cited by 67.9% of respondents, followed by project management tools such as Microsoft Project (37.7%) and basic collaborative platforms, such as Trello (26.4%), as detailed in Figure 3. Although these tools are useful for general organization and tracking, their capacity for in-depth and strategic stakeholder analysis is limited.
Source: Original research results
Figure 3. Tools used in stakeholder monitoring
The use of more structured tools, such as power and interest matrices, which are pillars in strategic stakeholder management (Bourne, 2015; PMI, 2021), is still quite limited among professionals. Only a small portion of respondents reported knowing or applying this type of tool, which highlights a low level of formalization of stakeholder management processes in the corporate architecture sector. This informality can lead to reactive, rather than proactive, management of the interests and influences of the parties involved, increasing the probability of conflicts and misalignments.
According to Bourne (2015), the use of structured tools, such as the power and interest matrix, contributes significantly to the proper prioritization of stakeholders and to the definition of more effective engagement strategies. By mapping the power and interest of each stakeholder, project managers can allocate communication and engagement resources more intelligently, focusing on the actors who can have the greatest impact on the project. Thus, the low adoption of these tools may be directly associated with the difficulties reported by professionals in managing expectations and resolving conflicts, as they do not have a solid analytical basis for their engagement decisions.
This scenario highlights a low level of maturity in applying structured stakeholder management practices within the context of enterprise architecture. Although consolidated tools and methodologies exist in the literature, their adoption remains limited. This can be attributed to several factors, such as a lack of specific training, the perception that these tools are complex or time-consuming, or the absence of an organizational culture that values the formalization of these processes. Such a result reinforces the pressing need to develop and implement more accessible and adaptable models to the reality of industry professionals, which can be organically integrated into existing workflows without adding an excessive administrative burden. The transition from informal practices to more structured approaches is fundamental to increasing predictability, reducing risks, and optimizing costs in enterprise architecture projects.
Engagement level
Regarding the perceived stakeholder engagement level in projects, the survey results revealed a distribution that, although showing a predominance of medium and high levels, still points to a significant portion of projects with insufficient engagement. Specifically, 37.7% of respondents classified engagement as “Medium”, and 39.6% as “High”. However, 9.4% described it as “Low” and 5.7% as “Very low”, while 7.5% considered it “Very high”. The sum of the “Low” and “Very low” categories totals 15.1%, which represents a considerable slice of projects where stakeholder engagement occurs inadequately.
This result indicates that, despite a generally positive perception, there is still a relevant portion of projects where stakeholder engagement does not reach the desired level, evidencing clear opportunities for improvement in conducting this process. Insufficient engagement can manifest in various ways, such as a lack of active participation in meetings, absence of constructive feedback, or difficulty in obtaining timely approvals, all factors that can delay the project and increase its costs.
This scenario reinforces what Gray and Larson (2020) point out as one of the main risks in projects: excessive centralization of information. When communication and decisions are centralized in a few individuals, communication efficiency is compromised, and decision-making becomes slower and less informed. The lack of a transparent and distributed information flow prevents stakeholders from feeling truly engaged and informed, which can lead to resistance and conflicts in later stages of the project. Centralization can also create bottlenecks and dependencies, making the project more vulnerable to disruptions.
The collected data, therefore, indicate that although there is a positive perception regarding the importance of engagement, there is still an inconsistency in its practical application. This inconsistency can directly impact the efficiency of processes and the quality of decisions throughout the project. Superficial or intermittent engagement is not sufficient to ensure alignment of expectations and the collaboration necessary for the success of complex enterprise architecture projects. The absence of continuous and strategic engagement can result in surprises, rework, and additional costs, contrary to best project management practices (PMI, 2021). The practical implication is the need to develop more proactive and systematic engagement strategies, which ensure the effective participation of all relevant stakeholders in all project phases, promoting transparency and collaboration.
Main challenges and best practices
The data analysis revealed a set of recurring challenges in stakeholder management in corporate architecture projects, which align with the difficulties widely discussed in project management literature. Among the main difficulties reported by professionals, the late inclusion of stakeholders, the lack of clarity in defining roles and responsibilities, and the challenge of reconciling divergent interests among those involved stand out. The late inclusion of stakeholders, already mentioned as a significant problem, often results in scope and design revisions in advanced phases, generating rework and increased costs. This finding corroborates the view of Noro (2012), who emphasizes how inadequate involvement of interested parties can create communication gaps and substantial delays.
Problems related to information management, data centralization, and inefficient communication are pointed out as recurring obstacles in project development. Excessive centralization of information, evidenced by 90.6% of respondents, indicates a critical fragility in communication flows. This fragility can compromise the agility and quality of decisions, as vital information may not reach stakeholders at the right time or in its entirety. Such a scenario is a significant risk, as Gray and Larson (2020) warn about the importance of effective communication for project success.
The occurrence of conflicts between stakeholders also proved relevant, having been reported by 49.1% of respondents. This data reinforces the need for structured alignment and communication mechanisms throughout the project to proactively mediate and resolve disputes. Unmanaged conflicts can escalate, leading to impasses, delays, and even project paralysis. The ability to reconcile divergent interests is an essential competence for the project manager, and the absence of tools and processes for this makes this task even more challenging.
Furthermore, 56.6% of the participants reported having already gone through projects where the exchange of stakeholders harmed the results. This result is reinforced by the perception of impact on project progress: 73.6% of respondents indicated that the replacement of stakeholders generates negative effects, which highlights the sensitivity of projects to the stability and continuity of the agents involved. The loss of institutional knowledge, the need to re-educate new stakeholders, and the renegotiation of expectations are just some of the challenges imposed by this dynamic, which can severely compromise the project schedule and budget.
The main impacts associated with the lack of stakeholder engagement were rework, schedule delays, cost increases, and compromised quality, as evidenced by the survey data, as shown in Figure 4. Rework, cited by 47% of respondents, is a direct consequence of late stakeholder inclusion and lack of clarity in expectations, resulting in design and documentation revisions. Schedule delays (38%) and cost increases (25%) are cascading effects of rework and poor communication, while compromised quality (22%) reflects the inability to fully meet the needs and expectations of all stakeholders. Only 1% of respondents were unsure, which reinforces the clarity and recurrence of these issues.
Source: Original research results
Figure 4. Impacts of stakeholder disengagement
This recurrence of problems suggests that stakeholder management still occurs in a predominantly informal way, without clearly defined processes, which increases the vulnerability of projects to operational and strategic risks. The absence of a standardized methodology prevents the replication of good practices and organizational learning, keeping projects in a cycle of predictable but unmitigated challenges. This result reinforces the direct relationship between failures in stakeholder management and negative impacts on project performance, as discussed by Kerzner (2015) and Bourne (2015). Both authors highlight that the lack of proactive stakeholder management is one of the main causes of project failures. This result is also aligned with Dultra-de-Lima et al. (2020), who emphasize the relationship between project management failures and increased risks, rework, and operational inefficiency.
On the other hand, the research also identified best practices that, when applied, contribute to mitigating these challenges. Among them, the holding of alignment meetings right at the beginning of the project, which are crucial for establishing expectations and defining the scope, stand out. Defining a focal point responsible for stakeholder management is another valuable practice, as it centralizes communication and coordination, avoiding noise and ensuring that information is disseminated consistently. The use of schedules with specific milestones for each stakeholder increases transparency and accountability. Furthermore, the adoption of document and information management tools, such as BIM 360 or similar platforms, ensures that everyone has access to the same project data and updates, combating excessive information centralization and promoting collaboration.
In general, the results reinforce the pressing need to evolve from informal practices to a structured and standardized stakeholder management process in the corporate architecture sector. Based on the perceptions collected, there is a lack of formalized methodologies, which directly impacts the predictability, cost control, and efficiency of projects. The transition to a more systematic and proactive approach is fundamental for corporate architecture projects to achieve their objectives more efficiently and with less risk, aligning with international best practices in project management, as Shao, Müller, and Turner (2012) point out regarding the relationship between governance and project success.
Proposed structured model
In this context of challenges and opportunities, the proposed structured model aims to organize, sequentially and practically, the necessary steps to ensure that all stakeholders are duly identified, communicated with, aligned, and monitored throughout the entire project lifecycle, from conception to delivery. This approach is intrinsically aligned with the recommendations of the PMI (2021), which emphasize the importance of structured communication planning and continuous stakeholder engagement throughout the project. Given the identified challenges and the analysis of current practices, it becomes fundamental to structure a more formal and systematized stakeholder management process, applicable to the reality of corporate architecture projects, which often operate under tight deadlines and multiple interfaces.
The proposed model was developed from the main *gaps* identified in the research, seeking to organize sequentially and practically the necessary steps for efficient stakeholder management. Table 1 presents a synthesis of this structured model, detailing each step, its main objective, and the suggested tools for its execution.
Table 1. Summary structured model
|
Stage |
Main Objective |
Suggested Tools |
|
Identification |
Map all stakeholders |
Trello, Planner, Excel |
|
Individualized analysis |
Understand the power and interest of each stakeholder |
Power x Interest Matrix |
|
Engagement Planning |
Define how and when to involve each stakeholder |
Schedule, communication channels |
|
Execution |
Hold meetings, distribute responsibilities |
Meetings |
|
Monitoring |
Monitor changes, review engagement |
Dashboards, meetings, checklists |
|
Conclude |
Collect feedback, document lessons learned |
Final reports and sharing with the team |
Source: Original research results
The presented structure allows for practical and adaptable application, being usable in both smaller-scale projects and more complex ventures, respecting the particularities of each context. This flexibility is crucial for the corporate architecture sector, which deals with a wide range of projects, from small interventions to large corporations. The proposed model was conceived considering the particularities of corporate architecture projects, especially their relatively short deadlines and the multiplicity of disciplines involved, which require intensive coordination and communication.
Your application aims to mitigate the main problems identified in the research, such as the late inclusion of stakeholders, lack of clarity on responsibilities, and communication failures. By formalizing each step, the model seeks to transform informal practices into standardized processes, reducing subjectivity and increasing predictability.
1. Identification of stakeholders: This initial stage is fundamental and directly addresses the issue of late stakeholder inclusion, one of the main challenges identified. The model proposes a comprehensive initial survey of all interested parties who will be part of the architectural project development and subsequent implementation. This includes not only direct stakeholders, such as the client, project teams, and suppliers, but also indirect ones, such as the condominium, technical consultants, *facilities*, security, and IT teams. Failure to identify these actors from the outset, as revealed by the research (62.3% of professionals do not participate in the initial definition), can lead to unforeseen demands and rework. The suggestion to define a tool for collaborative and centralized management (Trello, Planner, Excel) from this phase aims to ensure that the stakeholder list is accessible and updated by everyone, promoting initial transparency and collaboration.
2. Individualized stakeholder analysis: After identification, the model proposes classifying each stakeholder according to their influence and level of interest in the project. This step is crucial for building the Power x Interest Matrix, a widely recognized tool in the literature (Bourne, 2015; PMI, 2021) for prioritizing and segmenting engagement efforts. The matrix allows defining the type of individualized approach for each group: monitor (low power, low interest), keep satisfied (high power, low interest), keep informed (low power, high interest), or actively engage (high power, high interest). The low utilization of formal tools like this, observed in the survey (only 20.8% of respondents), is a *gap* that the model seeks to fill, providing an analytical basis for more effective and targeted engagement strategies.
3. Engagement Planning: This stage focuses on defining a communication and participation strategy for each stakeholder, based on the previous analysis. It involves establishing formal channels (meetings, schedules, collaborative platforms) and, crucially, the appropriate frequency of contact. The research highlighted inefficient communication and data centralization as problems, and this stage aims to combat them by formalizing information flows. Clear recording of responsibilities and milestones for each stakeholder is essential to avoid a lack of clarity in roles, another recurring challenge.
4. Execution and management of communication: Execution involves holding periodic or project-stage meetings, promoting frequent updates of shared schedules, and assigning a focal point or manager responsible for interlocution with each stakeholder group. The focal point is vital to ensure communication consistency and efficient resolution of doubts and conflicts, mitigating excessive information centralization (90.6% of respondents) and inefficient communication.
5. Continuous monitoring: Stakeholder management is not static. The model proposes to periodically evaluate the level of engagement, verify changes in the stakeholder landscape (inclusions, departures, or changes in influence), and adapt plans and redefine communication strategies when necessary. This proactive monitoring is essential to deal with the sensitivity of projects to stakeholder changes (73.6% indicated negative effects), ensuring stability and continuity.
6. Close out (project closure): The final stage emphasizes the importance of conducting a final meeting with stakeholders for feedback, lessons learned, and areas for improvement for future projects. Documenting insights and learnings about the stakeholder management process and disseminating information with the team are crucial for continuous improvement and organizational maturity, transforming challenges into learning opportunities.
An important aspect revealed by the research is the need for greater formalization of stakeholder management processes. As observed, only 20.8% of respondents use or are aware of formal tools such as the power/interest matrix, despite 88.7% considering engagement planning as important or very important for project success. This discrepancy between the perceived importance and the practical application of structured methodologies represents a significant opportunity for improvement in the sector. The research also revealed that 62.3% of professionals do not participate in the definition of stakeholders in the initial phases of the project, which can contribute to the late inclusion of relevant stakeholders. In this regard, the proposed model emphasizes the importance of systematic and comprehensive identification from the project’s conception, involving different perspectives and experiences, aligning with best practices in project management (Mandlate and Benatto, 2024).
The presented structure allows for practical and adaptable application, being usable in both smaller-scale projects and more complex ventures, respecting the particularities of each context. The proposed model was developed considering the particularities of corporate architecture projects, especially their relatively short deadlines and the multiplicity of disciplines involved. Its application aims to mitigate the main problems identified in the research, such as the late inclusion of stakeholders, lack of clarity on responsibilities, and communication failures. By formalizing each stage, the model seeks to transform informal practices into standardized processes, reducing subjectivity and increasing predictability.
Regarding the tools used, a preference was observed for simpler and more accessible solutions, with emphasis on Excel (67.9%), Microsoft Project (37.7%), and Trello (26.4%). This suggests that the proposed model should be flexible enough to be implemented with different levels of technological sophistication, adapting to the reality and resources available in each office or company. The model’s adaptability is, therefore, one of its strengths, allowing organizations of different sizes and with distinct levels of project management maturity to adopt and customize it according to their needs.
In general, the results obtained point to the pressing need to formalize and structure stakeholder management practices in the corporate architecture sector. The data collected reinforce the hypothesis that more robust strategies for mapping, communication planning, and continuous engagement of stakeholders are fundamental to mitigating risks, reducing costs, and improving project outcomes. As pointed out by Shao, Müller, and Turner (2012), project success is directly related to the ability to align stakeholders and the adopted governance processes. The absence of formalized processes, as evidenced by the low adoption of structured tools and the predominant informality, creates an environment conducive to the occurrence of problems that could be avoided with a more systematic approach.
These results highlight a significant gap between the perceived importance of stakeholder management and its practical application, indicating a relevant potential for improvement in the sector. The adoption of structured models, such as the one proposed in this work, can directly contribute to risk mitigation, rework reduction, and cost optimization, as pointed out by the literature and validated by the empirical data obtained. The implementation of a model like this not only improves operational efficiency but also strengthens the company’s reputation, increases customer satisfaction, and promotes a more collaborative work environment less prone to conflicts. The formalization of stakeholder management is, therefore, a strategic investment that translates into tangible benefits for corporate architecture projects.
4. Conclusion
It is concluded that the objective was achieved, as this work analyzed how planning and stakeholder engagement contribute to the reduction of rework and costs in corporate architecture projects, and proposed a structured model to support the management of these stakeholders throughout the lifecycle. The research confirmed the widespread perception of the importance of stakeholder management for project success, but also revealed a significant gap between this perception and the practical application of formalized methodologies. Problems such as late inclusion of stakeholders, inefficient communication, and low adoption of structured tools were identified as direct causes of rework, delays, and cost increases. Therefore, the proposed six-step model offers a systematic and adaptable approach to organize the identification, analysis, planning, execution, monitoring, and closing of stakeholder management, aiming to mitigate these challenges and promote greater predictability and efficiency.
However, it is important to acknowledge the limitations of this study, which include the sample size of 53 professionals and their geographical concentration in the city of São Paulo, which may restrict the generalization of the results to other markets or regions. Furthermore, the exclusive focus on corporate architecture prevents broad coverage of other industry segments. For future research, it is suggested to expand the sample to include professionals from diverse regions and profiles, as well as to conduct case studies to validate the practical application of the proposed model. It is also recommended to investigate the impact of adopting collaborative software and platforms on stakeholder management and to explore the adaptability of the model to other types of architectural projects. The formalization of stakeholder management is, therefore, a promising path to enhance the maturity and success of projects in the sector.
Bibliographic References
Bourne, L. (2015). Stakeholder Relationship Management: A Maturity Model for Organisational Implementation. Routledge, New York, EUA.
Dultra-de-Lima, R. et al. (2020). Fatores que contribuem ao sucesso ou fracasso em projetos. Revista de Gestão e Projetos, 11(1): 21–44.
Freeman, R. E. (1984). Strategic Management: A Stakeholder Approach. Pitman, Boston, MA, EUA.
Gray, C. F.; Larson, E. W. (2020). Project Management: The Managerial Process. 7. ed. McGraw-Hill Education, New York, NY, EUA.
Kerzner, H. (2015). Gestão de Projetos: As melhores práticas. 3. ed. Bookman, Porto Alegre, RS, Brasil.
Lopes, J. C. F. F. et al. (2020). Fatores que contribuem para o sucesso de projetos e o alinhamento com PMBOK: mapeamento sistemático. Revista de Gestão de Projetos, 11(1): 45-59.
Noro, G. B. (20
Project Management Institute [PMI]. (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide). 7th ed. Project Management Institute, Newtown Square, PA, USA.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq