Corporate construction planning under operational constraints and change control
Marcelo Righetti Frugoli Marcolino; Aline Gisele Zanão Benatto
DOI: 10.22167/2675-6528-202601188
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Corporate works with restricted hours and specific operational conditions presented high complexity in planning and control, especially due to access limitations, noise restrictions, area segregation, and recurring changes. In this context, the mere existence of a detailed schedule proved insufficient to ensure predictability. This study aimed to develop a planning model based on execution windows and integrated change control, grounded in schedule management and constraint-based planning, applicable to corporate works with restricted hours, aiming to increase reliability and mitigate operational impacts. A predominantly qualitative approach was adopted, supported by descriptive quantitative data, through a single case study in a corporate office renovation in São Paulo (SP). Data collection involved document analysis and retrospective information. The results showed that the low schedule reliability was associated with the interaction between restricted work windows, readiness failures, scope omissions, recurring changes, and the frequent need for replanning. As a result, a model was developed structured by defining work windows, decomposing the scope into executable packages, medium-term planning, checking activity readiness, and integrated change control. It was concluded that planning reliability depended less on its formalization and more on the ability to integrate constraints, readiness, and governance into the project decision-making process.
Keywords: Reliability; Change control; Last Planner System; Constraint-based planning; Re-planning.
1. Introduction
Corporate works, which include renovations, “retrofits” (modernization and technical adaptation of existing buildings) and “fit-outs” (functional and aesthetic configuration of internal spaces for specific use) in offices, hospitals, bank branches, and operational centers, present a remarkable complexity in planning and control. These interventions are distinguished from ventures in unoccupied areas by requiring management focused on minimizing impacts on occupants and ensuring operational continuity during execution (Ward et al., 2017).
Such projects are often executed within restricted work windows and conditioned by additional controls, such as noise and vibration limits, access management, area segregation, and protection of critical systems. Guidelines for works in operating facilities, including those from the “American Society for Health Care Engineering” (2022) and recommendations for “occupied site construction” (HB Construction, 2019), emphasize the need for detailed logistical planning, circulation control, and effective communication with users. This scenario tends to intensify pressure on deadlines, interfaces with multiple stakeholders, and the frequency of replanning, leading to the adoption of overtime and extended shifts, which can compromise the predictability and productivity of teams (Hanna et al., 2005).
In this challenging context, the mere existence of a detailed schedule is not sufficient to guarantee predictability and adherence between planning and execution. Low schedule reliability is a recurring problem, associated with the interaction of restricted work windows, readiness failures, scope omissions, frequent changes, and the constant need for replanning. Although the case analyzed in this study did not involve simultaneous occupation of the building, the project was subject to typical constraints of restricted corporate works, such as rigid windows, noise control, and access restrictions, which maintains the relevance of the planning and control problem under operational conditions.
Project management literature recognizes that delivering value in complex environments depends on rigorous planning discipline, integration across diverse areas, and governance capable of sustaining decisions under uncertainty. The guidelines of the “Project Management Institute” (PMI, 2021) highlight the importance of alignment between strategy, scope, schedule, resources, risks, and stakeholders, as well as the need for formal mechanisms to handle changes and preserve coherence between planning and execution. In corporate works with time and access constraints, this challenge is intensified, as execution requires breaking down the scope into achievable units, sequencing compatible with authorizations, and clear readiness criteria to avoid stoppages due to lack of releases, materials, or access.
In the field of production planning and control in construction, the “Lean Construction” approaches explain why long-term schedules, when disconnected from site constraints, tend to lose reliability in scenarios of high variability. Koskela’s (1992) perspective, by treating production as transformation, flow, and value generation, reinforces the importance of reducing waste and removing constraints to sustain performance in terms of time and cost. Complementarily, the “Last Planner System” (Ballard, 2000) emphasizes the connection between medium and short-term planning and execution, with monitoring of plan reliability and learning from the causes of non-compliance. In corporate projects with frequent interruptions, the logic of planning by executable packages and managing constraints becomes particularly relevant.
Furthermore, scope changes are frequent in corporate works, driven by internal client demands, regulatory requirements, information technology needs, and typical “retrofit” discoveries. Evidence indicates that changes without adequate governance tend to provoke successive replannings, conflicts between teams, and increased rework, affecting cost and schedule (Love et al., 2002; Ibbs et al., 2001). Thus, in restricted environments, integrated change control must be part of the project control system, with clear decision trails, impact analysis, and disciplined baseline updates, mitigating the predominance of reactive decisions.
Given this complex scenario, which demands the integration of diverse approaches to ensure predictability and governance, the development of an applicable model is justified. This model integrates the consolidated contributions of project management and “Lean Construction” to enhance predictability and governance in corporate construction projects subjected to operational constraints and restricted schedules (PMI, 2021; Koskela, 1992; Ballard, 2000). Thus, the objective of this work was to develop a model for window-based scheduling and integrated change control, based on schedule management and constraint-based planning, applicable to corporate projects with restricted schedules, aiming to increase reliability and mitigate operational impacts.
2. Material and Methods
This research was characterized as applied, aimed at understanding a concrete problem in the planning and control of corporate works under operational restrictions, with the objective of supporting the elaboration of a practical solution. According to Gil (2019), applied research is oriented towards the production of knowledge with practical utility, especially in solving organizational problems. Regarding the objectives, the study assumed a descriptive and explanatory character, seeking not only to describe the observed conditions but also to understand how certain factors influenced schedule performance (Vergara, 2016; Creswell, 2014).
A predominantly qualitative approach was adopted, supported by quantitative information of a descriptive nature. This choice proved adequate for examining complex phenomena in a real context, allowing for the analysis of relationships between events, causes, and effects (Creswell, 2014). Quantitative data, such as estimates of team mobilization, frequency of replanings, and overtime hours, were used as descriptive support, without any claim of statistical generalization (Hair et al., 2019).
As a methodological strategy, a single case study was conducted, a relevant approach for investigations of contemporary phenomena in real organizational contexts (Yin, 2017). The analyzed case referred to a corporate office renovation project, located in the Itaim Bibi neighborhood, in the city of São Paulo (SP), executed between October 2024 and January 2025. The unit of analysis corresponded to the project schedule management process, with an emphasis on reliability in an environment subject to operational constraints and changes (PMI, 2021).
Although the work was not carried out with simultaneous occupation of the building, its execution occurred under typical conditions of corporate works with strong operational restrictions. Among these conditions, rigid work windows, access limitations imposed by the condominium, noise restrictions, and the need to create specific circulation routes, protection of common areas, and the use of temporary enclosures stood out. The activities could be executed, in general, from Monday to Thursday during the night, from 9:00 PM to 5:00 AM, and on Saturdays, Sundays, and holidays during the day, from 8:00 AM to 6:00 PM. Specific noise restrictions were also verified at determined times.
The theoretical-methodological foundation of the research was based on two main fronts. The first corresponded to good Project Management practices, with emphasis on schedule management and integrated change control, as systematized by the “PMBOK® Guide” (PMI, 2021). The second referred to the field of “Lean Construction”, whose contribution proved relevant in contexts of high variability and operational constraints, highlighting Koskela’s (1992) approach and Ballard’s (2000) “Last Planner System”.
The selection of evidence occurred intentionally and by accessibility, prioritizing documents, records, and information directly related to the schedule’s behavior and replanning decisions. Detailed activity-based schedules, Work Breakdown Structure (WBS), descriptive memorials, attack plans, meeting minutes, medium-term planning records (“lookahead plans”), constraint records, change orders, and operational information related to physical progress, rework, and overtime usage were analyzed (Yin, 2017; Bowen, 2009).
In addition to the technical documentation, the case characterization was complemented by retrospective information provided by a professional directly involved in the project management of the work. This material allowed for the recovery of operational and decision-making aspects not always fully recorded in formal documents, contributing to the identification of the causes for replanning, the main deviations that occurred during execution, the approved scope changes, and their perceived impacts on the schedule.
Data collection was carried out in stages. Initially, available documents and records were organized and analyzed with the objective of reconstructing the original project plan and identifying the main milestones and execution constraints. Subsequently, information related to operational restrictions, replanning occurrences, change events, and factors that directly impacted the progress of the work was systematized. Following this, these evidences were consolidated into an analytical database.
The data analysis was conducted through descriptive and categorical analysis, with the occurrences grouped into categories such as operational constraints, scope failures, resource limitations, supplier delays, compatibility failures, and scope changes. The interpretation of the findings was carried out in light of the adopted theoretical framework, seeking to understand how these factors compromised the reliability of the schedule and contributed to the need for frequent replanning, use of additional effort, and alterations to the originally planned sequence.
After organizing the evidence, the data were analyzed through thematic categorization guided by the research problem and the adopted theoretical framework, allowing the grouping of occurrences related to operational constraints, readiness failures, scope changes, additional effort, and replanning. This procedure enabled an integrated interpretation of the factors that influenced schedule reliability in the analyzed case and, from this, supported the development of the model proposed in this study.
The principles of confidentiality and anonymity were respected. Thus, no information that would allow the identification of the organization, the venture, or the professionals involved was included, in accordance with the methodological recommendations applicable to case studies in an organizational context (Yin, 2017). The methodological path involved the collection and organization of project documents, the analytical reconstruction of planning and execution conditions, the identification of main deviations, constraints, replanings, and changes, the categorization of observed critical factors, the interpretation of findings in light of the theoretical framework, and the elaboration of the proposed model.
3. Results and Discussion
The results obtained in this study showed that the main challenge faced in the analyzed case did not lie in the absence of formal planning, but rather in the low adherence between the initially elaborated schedule and the real conditions of the work execution. It was found that, even with the existence of a detailed schedule and the prior definition of activities, the execution was strongly conditioned by a series of factors, including operational restrictions, scope changes, readiness failures, and the recurrence of replanning. These elements, together, compromised the stability of the plan and significantly reduced the predictability of the project schedule.
This finding proved particularly relevant from a Project Management perspective, as it reinforced the understanding that the temporal performance of a corporate construction project did not depend exclusively on the existence of a schedule. Instead, the schedule’s ability to realistically reflect the inherent constraints and variabilities of the execution environment was the determining factor. The findings directly aligned with the best practices of the Project Management Institute (PMI, 2021), which advocate that schedule management requires not only initial technical planning but also the implementation of continuous monitoring, adaptation, and control mechanisms throughout the entire project lifecycle.
Characterization of the case and execution conditions
The case investigated corresponded to a renovation in a corporate office, located in the city of São Paulo, in the Itaim Bibi neighborhood, with execution planned between October 2024 and January 2025. Although the work did not occur with simultaneous occupancy of the building, it was subjected to a significant set of operational restrictions, typical of corporate environments that demand high requirements. These conditions included strict limitations on activity execution schedules, specific noise restrictions, limited service access to the docks at times defined by the condominium, and the need to establish specific circulation routes, protect common areas, and install temporary enclosures for area segregation.
The permitted execution windows were predominantly concentrated from Monday to Thursday during the night, from 9:00 PM to 5:00 AM, totaling eight permitted working hours per day. On Saturdays, Sundays, and holidays, activities could be carried out during the day, from 8:00 AM to 5:00 PM, totaling nine working hours per day. In contrast, noise restrictions imposed additional limitations, covering fourteen hours on weekdays and eleven hours on weekends and holidays. These noise restrictions coincided with part of the potentially most productive windows, reducing the operational flexibility of the work.
From the perspective of schedule management, these operational conditions assumed a central role, as they significantly reduced flexibility for sequencing activities. They also increased the need for rigorous coordination between different work fronts, access, material logistics, and execution discipline. This finding was consistent with the literature on works in environments with operational restrictions, which points out that limitations on access, circulation, and noise tend to increase execution complexity and require greater rigor in planning structure (Ward et al., 2017; HB Construction, 2019).
The logic of “Lean Construction” also aligned with these results, emphasizing that production reliability depends on the prior removal of constraints and the adequacy of the plan to real execution conditions (Koskela, 1992; Ballard, 2000). Thus, the studied environment presented sufficient characteristics to compromise the predictability of execution, reinforcing the need for planning that was adherent to available work windows and real field constraints. From the perspective of project management, this context indicated that schedule reliability depended less on the isolated technical logic of activities and more on their compatibility with the real execution conditions imposed on the project.
Mobilization of teams and use of additional effort
Regarding human resources mobilization, a more intense concentration of teams was observed during the night shifts of weekdays, with an average estimate of twenty-five to thirty professionals. In contrast, during the daytime shifts of weekends and holidays, mobilization was estimated between fifteen and twenty professionals, considering the periods of greatest construction activity. This distribution suggested an operational intensification during weekday night periods, which demanded greater simultaneous coordination among the different work fronts.
In addition to team mobilization, the recurrent use of overtime was identified, concentrated mainly on weekends, with an estimated volume of approximately one hundred and fifty hours throughout the entire project. This use of additional effort as a recurrent resource suggested low stability in the execution plan, as overtime was employed as a response to the difficulty of maintaining the execution pace within the available work windows. This finding was supported by studies that demonstrated that the continuous use of extended working hours and work at unconventional times can compromise productivity, safety, and operational consistency, especially in environments already marked by restrictions and high time pressure (Hanna et al., 2005; Folkard and Lombardi, 2006; Meister, 1999).
In managerial terms, the observed mobilization and the use of additional effort indicated that the schedule operated with a low margin for deviation absorption. This made the work excessively dependent on operational compensations to maintain the planned pace. This result suggested that the schedule had little managerial slack and a limited capacity to absorb deviations, which implied that the execution was excessively dependent on operational adjustments and compensations to meet the established deadline.
Recurring planning and low schedule reliability
One of the most relevant findings of the research was the high recurrence of replanning throughout the project execution. Although the project had a detailed schedule, with scope activities, planned durations, and interdisciplinary dependency relationships clearly defined, revisions of the plan were reported practically every two days. This replanning frequency highlighted a scenario of high operational variability and low stability of the execution plan, compromising predictability.
The formally structured schedule, with activities distributed by disciplines and precedence relationships, proved to be limited in the face of real execution conditions. This reinforced the interpretation that the main observed weakness was not in the absence of planning, but in the low reliability of the plan throughout the work. The main causes reported for replanning included the lack of specialized labor and the unavailability of teams in the market, failures in monitoring and supervision of execution, errors in field planning, relevant omissions in the originally contracted scope, absence of complete executive projects at the beginning of the work, and delays from suppliers and approvals.
Specific replannings due to delays in painting, in carpentry (due to the delay in approving technical drawings), and in carpet contracting after changes demanded by the client were also mentioned. These factors approached the discussions present in the literature on planning reliability in construction, especially within the scope of “Lean Construction” and the “Last Planner System”. These approaches highlight that plan stability depends on the prior removal of constraints, the readiness of activities, and the compatibility between medium and short-term planning (Ballard, 2000; Koskela, 1992). When these conditions are not ensured, the consequence tends to be exactly what was observed in this study: frequent replanning, loss of predictability, and reactive use of the schedule as a management tool.
The findings of this section reinforced that the schedule, although it existed as a formal planning instrument, operated in a predominantly reactive manner. This required successive reprogrammings to accommodate restrictions, changes, and readiness failures that were not fully absorbed by the initial plan. From a managerial point of view, the recurrence of replannings did not represent just a natural adaptation of the work, but rather evidence of fragility in the executability of the originally established planning, indicating that the plan was not robust enough for the real field conditions.
Scope changes and fragilities in the commercial phase
Another relevant result was the identification of five approved scope changes, known as “change orders”, which had a direct impact on the schedule and execution stability. The observed changes were strongly associated with definition failures in the project’s commercial phase, technical gaps, and scope omissions that were only perceived during the execution of the work. These initial weaknesses compromised predictability and required significant adjustments throughout the project.
Among the main items identified as omitted or inadequately defined in the initial phase of the project, the following stood out: the inclusion of an industrial glass partition in the meeting room, the multimedia infrastructure and cabling, raised floor cutouts for the partition wall in glass divisions, VAV (Variable Air Volume) units for the air conditioning system, a pivoting door for bathroom access, and a metal ceiling in the auditorium. These changes, which arose after the execution began, generated significant impacts on the schedule.
The change in the studio’s metallic structure, for example, originated from a compatibility failure between the architecture and information technology projects, resulting in an estimated delay of seven days. The inclusion of VAV units in the air-conditioning system was an omission in the commercial phase and a lack of prior inspection, causing an estimated delay of ten days. The industrial acoustic partition, in turn, resulted from a divergence between the architectural concept and the client’s decision, leading to an estimated delay of thirty days. Additional IT demands, arising from technical scope gaps, and complementary finishing and infrastructure items, which were initial scope omissions, required reprogramming, interferences, rework, and sequence adjustments during execution.
These scope changes were mostly associated with definition and compatibility failures in stages prior to execution, reinforcing their direct influence on schedule stability. This result indicated that a significant part of the replanning observed in the field originated from scope weaknesses and decisions made even before the start of the construction. According to PMI (2021), scope changes not handled in a structured manner tend to compromise project baselines and generate chain effects on schedule, cost, resources, and coordination between teams. Classic studies in the field also indicated that alterations introduced late or without adequate impact analysis contribute to increased rework, conflicts between disciplines, and loss of temporal performance (Ibbs et al., 2001; Love et al., 2002).
From the perspective of Project Management, the findings of this section reinforced the importance of integrated change control as an essential governance mechanism to preserve the coherence between scope, planning, and execution. This result showed that the reliability of the schedule in corporate works depended not only on the quality of the executive planning but also on the technical and commercial robustness of the scope before the start of execution, underscoring the need for a more rigorous and complete planning phase.
Relationship between constraints, replanning, and schedule performance
The integrated analysis of the results showed that the schedule behavior was not impacted by a single isolated factor, but rather by the complex interaction between different operational and managerial conditions. Restricted work windows, logistical limitations, supplier delays, scope definition failures, and the occurrence of changes combined to produce an execution environment with low predictability and a high need for continuous rescheduling. This interdependence of factors was crucial for the observed instability.
The restricted execution windows, characterized by night work on weekdays and weekends, resulted in a reduction of activity sequencing flexibility, implying the need for more detailed planning by windows. Frequent replanning, evidenced by revisions practically every two days, generated significant plan instability, indicating low schedule reliability. The five approved scope changes, in turn, caused alterations in the sequence and deadline of activities, reinforcing the need for a more robust integrated change control.
Omissions in the commercial phase, which manifested as initially unforeseen items, resulted in rework and rescheduling, exposing a fragility in scope definition. The use of approximately one hundred and fifty overtime hours indicated a compensation for deviations, revealing an excessive reliance on additional effort to maintain the pace of the work. Finally, access and noise restrictions, with controlled docks and hours, caused interferences in execution, increasing the need for operational readiness to avoid stoppages and delays.
These observed factors in the case did not act in isolation, but interdependently, compromising the schedule’s stability and reinforcing the need for a planning arrangement more aligned with real execution conditions. This reading showed that the work’s temporal performance was strongly associated with the ability to anticipate constraints, organize activity readiness, and handle changes in a structured manner. This interpretation proved to be aligned with the concept of plan reliability present in the “Last Planner System”, according to which planning performance should not be evaluated solely by what was originally foreseen, but by the ability to consistently fulfill what was effectively assumed to be executable (Ballard, 2000).
When activities are planned without all readiness conditions being assured, the tendency is for the schedule to become reactive, with progressive loss of predictability, exactly as observed in the analyzed case. The integrated analysis of the results therefore indicated that the main difficulty observed in the project was not just in the completion of specific activities, but in the low reliability of the planning system as a whole. Together, these elements showed that the loss of schedule reliability stemmed less from isolated factors and more from the cumulative interaction between operational constraints, readiness failures, changes, and reactive decisions throughout execution, culminating in the need for a more integrated model.
Development and discussion of the proposed model
From the integrated analysis of the obtained results, it was possible to develop an applied model of planning by execution windows and integrated change control. The objective of this model is to increase adherence between planning and execution in corporate projects with restricted schedules, mitigating operational impacts and increasing schedule reliability. The model was based on the integration between the best practices of schedule management and integrated change control, as systematized by PMI (2021), and the principles of “Lean Construction”, with emphasis on the contributions of the “Last Planner System” (Koskela, 1992; Ballard, 2000).
The model brings together five central components that act in an integrated way. The first component corresponds to the explicit definition of execution windows, considering available schedules, noise restrictions, access, and operational limitations. This element proved to be fundamental because, in the analyzed case, part of the schedule’s reliability loss was associated with planning activities without sufficient adherence to real execution conditions, which the model seeks to correct by establishing clear rules for operation.
The second component refers to the decomposition of the scope into executable packages, compatible with the duration and constraints of each work window. Instead of treating the schedule merely as a technical chaining of activities, the model begins to consider what could actually be executed in each available interval. This reduces the probability of replanings arising from operational incompatibilities, promoting a more realistic view of execution capacity.
The third component corresponds to medium-term planning aimed at removing constraints, in a logic close to “lookahead planning”. At this level, the model seeks to anticipate impediments, organize interfaces between different disciplines, and previously verify the availability of materials, releases, approvals, and resources. This anticipation is crucial to ensure that the planned activities have all the conditions to be executed, minimizing interruptions.
The fourth component consists of checking the readiness of activities, understood as the verification of the minimum necessary conditions for the release of execution. This aspect proved especially relevant given the findings related to delays caused by the absence of complete executive projects, scope omissions, pending approvals, and compatibility failures. Readiness verification ensures that activities are only initiated when all prerequisites are met, avoiding stoppages and rework.
The fifth component corresponds to integrated change control, structured to record, analyze, and incorporate scope changes with managerial discipline and coherent planning updates. This element proved central, as the results indicated that a significant part of the observed schedule instability was precisely associated with the introduction of changes and additions during execution without a formal process. Change control aims to mitigate the impact of these alterations, maintaining project coherence.
Thus, the elaborated model did not present itself as a substitute for the traditional schedule, but as a complementary structure aimed at making it more executable, more reliable, and more aligned with the real conditions of corporate projects subjected to operational constraints. From a managerial point of view, the proposed model offered a practical framework to increase schedule executability, reduce reactive rescheduling, and enhance project predictability in contexts marked by relevant operational restrictions, contributing to a more proactive management less dependent on reactive compensations.
In summary, the results and discussion developed demonstrated that the reliability of the schedule in corporate projects with restricted hours depended less on the simple existence of a formally detailed schedule and more on the ability to integrate, in a structured way, operational restrictions, activity readiness, and change governance into the project planning system, transforming planning into an effectively executable and adaptable system to real production conditions.
4. Conclusion
This study aimed to develop a planning model based on execution windows and integrated change control, applicable to corporate construction projects with restricted schedules, in order to increase reliability and mitigate operational impacts. It was found that the main weakness observed was not the absence of formal planning, but the low adherence between the developed schedule and the actual execution conditions. It was identified that execution was strongly conditioned by operational restrictions, such as limited work windows and noise controls, in addition to scope changes, readiness failures, and recurring replanning. These factors, collectively, compromised the plan’s stability and significantly reduced predictability. The recurrent use of additional effort, such as overtime, was also observed, indicating a low margin for absorbing deviations and an excessive reliance on operational compensations. It was concluded that schedule reliability depended less on its formalization and more on the ability to integrate restrictions, readiness, and governance into the project decision-making process.
The study’s main contribution was the development of a model structured into five central components: explicit definition of execution windows, decomposition of the scope into executable packages, medium-term planning aimed at constraint removal, activity readiness verification, and integrated change control. This model, based on schedule management and constraint-based planning, offers a practical framework to increase schedule executability, reduce reactive rescheduling, and enhance project predictability in contexts marked by significant operational constraints. As a limitation, it was acknowledged that the study focused on a single case, which restricts statistical generalizations, and part of the operational information was reconstructed retrospectively. For future studies, it is suggested to apply and refine the model in other types of corporate works or projects with different degrees of operational restriction, as well as to develop research exploring planning reliability indicators and more systematic monitoring mechanisms in work environments with high variability.
Bibliographic References
American Society for Health Care Engineering. 2022. ICRA 2.0® toolkit: Matrix of Precautions for Construction, Renovation and Operations. Disponível em: https://www.ashe.org/system/files/media/file/2023/01/ASHE_ICRA_2_TM_form_0.pdf. Acesso em: 04 fev. 2026.
Ballard, G. 2000. The Last Planner System of Production Control. Tese de Doutorado, University of Birmingham, Birmingham, UK.
Bowen, G. A. 2009. Document analysis as a qualitative research method. Qualitative Research Journal, 9(2), 27–40.
Creswell, 2014 [Referência completa não encontrada no documento original]
Folkard, S.; Lombardi, D. A. 2006. Modeling the impact of the components of long work hours on injuries and “accidents”. American Journal of Industrial Medicine, 49(11), 953–963.
Gil, A. C. 2019. Métodos e técnicas de pesquisa social. 7ª ed. Atlas, São Paulo, SP, Brasil.
Hair et al., 2019 [Referência completa não encontrada no documento original]
Hanna, A. S.; Taylor, C.S.; Sullivan, K.T. 2005. Impact of extended overtime on construction labor productivity. Journal of Construction Engineering and Management, 131(6), 734–740.
HB Construction. 2019. 5 Keys to Occupied Site Construction. Disponível em: https://www.hbconstruction.com/wp-content/uploads/2019/07/5-Keys-to-Occupied-Site-Construction-Web.pdf. Acesso em: 04 fev. 2026.
Ibbs, C. W.; Wong, C. K.; Kwak, Y. H. 2001. Project change management system. Journal of Management in Engineering, 17(3), 159–165.
Koskela, L. 1992. Application of the new production philosophy to construction. VTT Technical Research Centre of Finland, Espoo, Finland.
Love, P. E. D. 2002. Influence of project type and procurement method on rework costs in building construction projects. Journal of Construction Engineering and Management, 128(1), 18-29.
Meister, D. 1999. The history of human factors and ergonomics. Lawrence Erlbaum Associates, Mahwah, NJ, USA.
PMI- Project Management Institute. 2021. A guide to the Project Management Body of Knowledge (PMBOK Guide). Project Management Institute, Newtown Square, PA, USA.
Vergara, S. C. 2016. Projetos e relatórios de pesquisa em administração. Atlas, São Paulo, SP, Brasil.
Ward, A.E.; Azhar, S.; Khalfan, M. 2017. Construction in Occupied Spaces. Slovak Journal of Civil Engineering, 25(2), 15-23.
Yin, R.K. 2017. Case study research and applications: Design and methods. SAGE Publications, Thousand Oaks, CA, USA.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq