Negotiation and conflict management as instruments for stakeholder engagement in corporate works and retrofit
Allan Silveira Penha; Ranyery Segui de Souza Lima
DOI: 10.22167/2675-6528-202600510
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Corporate construction and retrofit interventions in occupied environments frequently involve multiple stakeholders, whose interdependencies increase the likelihood of conflicts related to access, schedules, and technical interfaces, impacting organizational routine. This study analyzed how negotiation and conflict management strategies can be used to engage stakeholders in corporate construction projects, aiming for greater decision-making predictability and operational stability. A qualitative, descriptive-interventional case study was conducted in a company in São Paulo, between October and December 2025, during the execution of a retrofit project in an occupied environment. The initial diagnosis was based on direct observation, document analysis, and mapping of communication flows. The intervention consisted of implementing a structured process for registering, classifying, and forwarding occurrences, operationalized through a database in Notion. Predominance of reactive negotiations, bilateral communication, and absence of formal records were observed, which was associated with the recurrence of conflicts and rescheduling. The formalization of the flow and the systematic recording of decisions favored traceability, pattern identification, and better direction of negotiation instances. The institutionalization of negotiation and conflict management processes, supported by simple recording systems, contributed to transforming one-off interactions into permanent engagement mechanisms, with positive effects on deadline predictability and inter-organizational coordination in corporate construction and retrofit projects.
Keywords: Interorganizational coordination; Project governance; Corporate works; Decision predictability; Retrofit.
1. Introduction
Civil construction is an intrinsically complex sector, characterized by the interaction of multiple actors who operate at all stages of a project, from initial planning to final delivery. This dynamic becomes even more challenging in the context of corporate construction and retrofit interventions, which frequently occur in already occupied and fully operational environments. The coexistence of work fronts with the routine activities of the user organization establishes a network of interdependencies that significantly increases the probability of divergences and conflicts. For the project manager, the ability to conduct interpersonal relationships is as fundamental as technical knowledge to ensure work continuity (Góis et al., 2023).
In this scenario, the diversity of expectations among the parties involved and the need to integrate multidisciplinary teams make the occurrence of conflicts practically inevitable. Such divergences can arise from issues related to access to specific areas, intervention schedules, complex technical interfaces, and direct impacts on organizational routine. Conflicts, by their nature, can assume both productive and destructive dimensions, depending fundamentally on how they are managed. Approaches that prioritize cooperation tend to generate broader and more acceptable results for all parties. In contrast, overly competitive strategies may only be effective in less intense situations. In contexts of high novelty, criticality, or potential for disruption, collaboration proves to be more effective in rebuilding trust and satisfying those involved (Zhang et al., 2024).
The relevance of stakeholder alignment is a central theme in international project management standards. ISO 21502:2020, for example, emphasizes that the identification of stakeholders, the understanding of their expectations, and the implementation of structured communication mechanisms are essential practices for project performance. In this regard, conflict management and negotiation are recognized as intrinsic tools to the engagement process and organizational governance (ISO, 2020). The role of the construction coordinator assumes particular relevance in this process, acting as a mediator of divergences and a facilitator of dialogue between the different parties of the undertaking. In corporate construction projects, where deadlines and costs are frequently under pressure, the adequate management of relationships between clients, suppliers, designers, and execution teams is a determining factor in avoiding rework and delays.
Despite the recognized importance of negotiation and conflict management for project success, the practice in many corporate construction and retrofit ventures is still characterized by reactive approaches, predominantly bilateral communication, and a notable absence of formal records. This gap, often associated with the recurrence of conflicts and the constant need for rescheduling, indicates a fragility in interorganizational coordination and decision-making predictability. Divergences are often treated in a punctual and emergency manner, without a structure that allows for organizational learning and the prevention of future occurrences, which compromises operational stability and project efficiency.
Given this scenario, the choice of theme is justified by the pressing need to deepen the understanding of practices applicable to the daily lives of construction managers. The corporate sector, in particular, demands a high capacity for articulation among multiple agents, making it essential to develop more effective strategies for managing interdependencies. By relating empirical evidence with normative references, this study seeks to offer practical and theoretical subsidies to improve the performance of professionals who face recurring situations of conflict and divergence, contributing to greater operational stability and deadline predictability.
The relevance of addressing conflict management and negotiation as proactive stakeholder engagement tools lies in their ability to transform one-off interactions into permanent interorganizational coordination mechanisms, with direct effects on deadline predictability and operational stability. Thus, this study aims to analyze the use of conflict management strategies as instruments for engaging stakeholders in corporate construction projects, at a private institution in São Paulo.
2. Material and Methods
The present study was characterized as applied, qualitative, and descriptive-interventional research, using a case study (Gil, 2017; Prodanov; Freitas, 2013). The methodological design approached action-research and intervention, as the researcher acted as the company’s operations coordinator and agent responsible for the diagnosis, proposition, and implementation of changes in negotiation processes and Conflict Management.
The study was conducted in a company in the corporate construction and retrofit sector in São Paulo, between October and December 2025. The setting was a construction site in an occupied environment, where administrative and operational activities of the user organization coexisted with the work fronts, generating continuous interdependencies.
The project involved multiple stakeholders, including the venture management team, main contractor, subcontractors, building managers, security, IT, facilities departments, and end-users. The unit of analysis corresponded to the observed flows of communication, negotiation, and operational conflict resolution, focusing on area release, intervention schedules, interferences in critical systems, and activity rescheduling.
The organizational diagnosis was carried out in October 2025, employing direct observation of site routines, monitoring of planning meetings, and emergency field negotiations. Additionally, existing operational documents were analyzed, such as schedules, meeting minutes, scope change requests, and informal occurrence records.
Based on this diagnosis and on theoretical references on conflict management, negotiation, and stakeholder engagement (Tsao et al., 2021; Yang; Wei; Zhang, 2023; Sabri, 2025; Van Oerle, 2022), a managerial intervention was structured. This aimed at formalizing the process of recording, classifying, and forwarding occurrences, as well as defining negotiation instances compatible with the type of impact identified.
To operationalize the intervention, the Notion platform was adopted. This tool allowed the creation of personalized databases, filtered views, decision-making history logging, and remote access, with low cost, flexibility, and rapid implementation in the organizational environment.
Between the end of October and the beginning of November 2025, a database of occurrences was structured in Notion. Standardized fields were defined for recording the date, location/sector, type of impact (technical, operational, or contractual), stakeholders involved, problem description, negotiation instance triggered (operational, tactical, or strategic), decision made, decision-maker, occurrence status, and observations regarding recurrence.
The implementation phase occurred between November and December 2025. All relevant occurrences were registered in the system, and the decisions arising from the negotiations were formalized in the database. The researcher acted as a mediator in the discussions, guiding the handling of demands according to the identified impact level. Low-complexity operational conflicts were addressed at the operational level; situations with an impact on the schedule, activity sequencing, or multiple sectors were forwarded to the tactical level; and conflicts with potential contractual or institutional repercussions were discussed at the strategic level, with the participation of project management and building management. The history of the discussions was documented to track the evolution of conflicts and those responsible for their resolution.
The data analysis was performed through a qualitative examination of the records in the database, considering the frequency, typology, recurrence of conflicts, and negotiation levels triggered. The treatment of occurrences was compared before and after the implementation of the structured process, in light of the reviewed literature on project governance and stakeholder management (Couanau, 2019; Zheng, Sun, and Liu, 2024; Omondi and Kimutai, 2018). For monitoring, the records were updated with implementation results and observations on recurrence, building a historical database useful for identifying patterns, recurring causes, and critical themes by area or sector (Van Oerle, 2022; Yang; Wei; Zhang, 2023). Notion was also used as a “library” of lessons learned, with dedicated visualizations for recurrences and recommendations.
3. Results and Discussion
The analysis of empirical results revealed that conflict management and negotiation in corporate construction and retrofit projects, in the studied environment, occurred predominantly in a reactive and unstructured manner. It was observed that stakeholder engagement was concentrated at managerial levels and was frequently triggered only when project execution was already compromised by immediate impediments, such as lack of area release, access restrictions, or scheduling conflicts. This scenario aligns with the literature that describes weaknesses in interorganizational coordination when there are no regular mechanisms for participation and communication that precede the materialization of problems (Yang; Wei; Zhang, 2023; Li, 2024).
In operational terms, the low inclusion of users and operational managers in short-term planning resulted in significant resistance to interventions in sensitive time windows and the need for repeated rescheduling. This dynamic reinforces the association between participation gaps and negative impacts on project performance, as pointed out by Omondi and Kimutai (2018). Communication was predominantly bilateral, punctual, and with scattered records, which led to fragmented and, in some cases, contradictory decisions. The absence of a formal instance of interorganizational dialogue, especially when the conflict involved more than two actors, increased the risk of incompatible referrals, resulting in rework and renegotiations on issues already addressed.
This finding is consistent with the literature relating process and interdependence conflicts to the lack of standardization of procedures and the need for coordination between organizations with partially divergent objectives (Omondi; Kimutai, 2018). Furthermore, stakeholder attributes, such as power, legitimacy, and urgency, influenced behavior in interactions, often shifting the decision from the technical level to institutional disputes. This was particularly evident in environments where the building user had the capacity to restrict the progress of the work for operational reasons, as highlighted by Yang; Wei; Zhang (2023) and Couanau (2019).
The analysis of the decision-making process revealed a reactive negotiation, triggered only when the activity was already blocked, without stable criteria for prioritizing competing demands. The literature on negotiation in projects indicates that, under time pressure and without preparation of alternatives, negotiations tend to produce circumstantial concessions and unstable agreements, especially in scenarios of power asymmetry (Couanau, 2019; Sabri, 2025). In the empirical context, this manifested in the variability of the referrals, which depended on the manager involved, and in the recurrence of conflicts in repetitive activities per floor or sector, due to the absence of formal records of what was agreed upon and the lack of organizational memory of the decision-making process.
The engagement problems identified in the empirical study can be categorized into four main dimensions. The first dimension refers to user participation, which was low in planning decisions, resulting in resistance to interventions and delays. The second dimension, intersectoral coordination, was characterized by bilateral and non-integrated communication, leading to partial solutions and rework. The predictability of impacts, the third dimension, was hampered by late communication of interferences, which generated frequent rescheduling. Finally, the formalization of agreements, the fourth dimension, was marked by the predominance of verbal agreements, resulting in instability of commitments.
The types of conflict observed and their treatment methods were also analyzed. Technical conflicts, such as interferences between systems, were treated with specific activity adjustments, resulting in temporary solutions. Operational conflicts, such as disputes over intervention schedules, were resolved by emergency reprogrammings, impacting deadlines. Relational conflicts, manifested as tensions between teams, were addressed by informal mediation by managers, which frequently resulted in the persistence of the conflict. Institutional conflicts, related to disagreements over responsibilities, were treated by hierarchical escalation, culminating in imposed decisions.
These findings reveal that conflicts were often treated as isolated occurrences, rather than an integral part of the production process in corporate and retrofit projects. Problem resolution depended heavily on the individual actions of managers and the momentary willingness of stakeholders to cooperate, which reduced schedule predictability and project control capability. This management dynamic, which neglected the systemic nature of conflicts, generated negative impacts on schedule, cost, and operation, such as delays, additional costs, and operational restrictions.
In summary, the project’s central problems manifested in four interdependent axes: limited engagement of operational stakeholders, resulting in decisions with low adherence to organizational routines; reactive and personalized negotiation, without formal protocols, which increased decision variability and conflict recurrence; conflict management focused solely on technical adjustments, without considering relational and institutional dimensions; and the absence of systematic conflict monitoring, which prevented organizational learning and continuous process improvement. These axes configured a governance pattern in which conflicts were seen as isolated events, rather than a structural part of the process.
Faced with this diagnosis, the proposed future state for the work was based on the institutionalization of a structured process for negotiation and conflict management, integrating it into project governance, rather than being an occasional response to critical events. This proposition aligns with the guidelines of ISO 21502:2020, which recommends the integration of stakeholder management, communication, decision-making, and problem-solving throughout the entire project lifecycle (ISO, 2020). It is also in line with the findings of Yang, Wei, and Zhang (2023), who indicate that the quality of stakeholder relationships directly influences operational performance and project stability.
The proposed process began with the formalization of stakeholder mapping and classification, considering their degree of influence, level of interest, and direct impact of interventions on their operational routines, as suggested by Couanau (2019) and Zheng, Sun, and Liu (2024). Unlike previous practice, where operational actors were only involved in crisis situations, the new model provided for their regular participation in monitoring instances, allowing for the identification of demands and risks before conflicts materialized. This strategy responds to the findings of Omondi and Kimutai (2018), who associate recurring conflicts with the exclusion of actors directly affected by project decisions.
Subsequently, the process incorporated formal communication and negotiation protocols at three levels: operational, tactical, and strategic. At the operational level, discussions focused on daily alignment between work fronts and company operations, with quick meetings and standardized recording of incidents. At the tactical level, schedule adjustments, resource reallocation, and activity replanning were discussed. At the strategic level, decisions involving contractual impact, relevant scope changes, or institutional risk were handled, ensuring that decisions were made at the appropriate level.
Negotiation, in the future state, ceased to be merely reactive and personalized, starting to follow principles of integrative negotiation, focusing on the parties’ interests and not just on positions, as discussed by Tsao et al. (2021) and Sabri (2025). For this, the process involved the use of minimal negotiation scripts, which included problem identification, surveying the parties’ interests, analyzing technical and operational alternatives, evaluating impacts, and jointly defining next steps, promoting more lasting and acceptable solutions.
The incorporation of leadership practices focused on mediation and facilitation, associated with the leader coach model, as proposed by Claro (2013) and Zimmermann (2019), was highlighted. Contract managers and production coordinators began to act not only as technical decision-makers but also as facilitators of dialogue between areas, promoting active listening, alignment of expectations, and construction of operational commitments. Studies by Donato, Gonçalves, and Sanches (2011) and Alvarez and Carvalho (2019) indicate that this type of leadership contributes to reducing resistance, increasing adherence to decisions, and improving the organizational climate, factors directly related to conflict prevention.
The proposed process also included the creation of a simple system for registering and monitoring conflicts, allowing occurrences to be classified by type, affected area, main cause, and adopted solution. This practice meets the methodological recommendations of Gil (2017) and Prodanov and Freitas (2013) regarding the importance of systematic records for the analysis of organizational processes, transforming isolated episodes into inputs for organizational learning. Periodic analysis of these records supports adjustments in planning, communication, and negotiation protocols, promoting continuous improvement.
The operationalization of the intervention was enabled through the use of Notion as a digital environment for recording, organizing, and monitoring project occurrences and decisions. The platform was configured as a database with standardized fields for each occurrence, including date, location/sector, description, stakeholders involved, person responsible for recording, attached evidence, impact classification (technical, operational, or contractual), negotiation level triggered, alternatives considered, defined referral, agreed deadline, person responsible for implementation, and status.
This structure allowed for the replacement of scattered records, such as instant messages, emails, and verbal reports, with a documented and traceable flow, reinforcing decision-making predictability and reducing subsequent disagreements about what was agreed upon. Notion was also used as a mechanism to support escalation, as the impact classification guided the summoning of the appropriate negotiation instance, bringing the observed practice closer to the guidelines for governance and structured communication indicated by ISO 21502:2020 (ISO, 2020) and the literature on project negotiation (Couanau, 2019; Tsao et al., 2021; Sabri, 2025).
For monitoring purposes, the records began to be updated with the implementation results and observations on recidivism, allowing for the production of a historical database of occurrences. This database is useful for identifying patterns, recurring causes, and critical themes by area or sector, in line with the understanding of conflicts as phenomena associated with decision-making routines and coordination practices, and not just as isolated episodes (Van Oerle, 2022; Yang; Wei; Zhang, 2023). In the empirical context, the use of Notion served as an instrument for stabilizing the negotiation process by recording discussed interests and alternatives and by formalizing follow-ups, an aspect related to satisfaction with the resolution in scenarios of higher conflict intensity, when informal decisions tend to generate unstable agreements (Zhang et al., 2024).
The distribution of functions among the contracting party/users, project management, construction teams, suppliers, and internal support areas showed that risk identification, impact analysis, negotiation, and monitoring ceased to be responsibilities concentrated in a single actor and became a cooperative and institutionalized flow. This structure favored the early communication of interferences, the technical mediation of negotiations, and the organizational validation of decisions, in line with literature recommendations that indicate the need for alignment between stakeholder management, structured negotiation, and mediating leadership in construction projects in occupied environments (ISO, 2020; Tsao et al., 2021; Yang; Wei; Zhang, 2023; Sabri, 2025).
This organization dialogues with the study by Li (2024), which highlights the need for formal mechanisms of participation and continuous communication, and with the systemic approach defended by Van Oerle (2022), according to which technical, relational, and institutional decisions produce cumulative effects throughout the project. Thus, negotiation and conflict management ceased to be mere corrective instruments and began to act as permanent mechanisms for engagement, coordination, and performance stabilization in corporate works, contributing to greater predictability and efficiency.
The project coordination concentrated the function of recording, mediating, and consolidating decisions, in alignment with ISO 21502:2020, which assigns the project manager the integration between technical and organizational areas (ISO, 2020). The occupant company’s management acted as the institutional representative of the production routines, validating impacts and negotiating adjustments that went beyond the local level, as recommended by Couanau (2019) when discussing the formal representation of interests in project negotiations. The operational team began to structure the communication of practical impacts, preventing conflicts from being detected only after failures in the space’s functioning occurred, an aspect also identified by Zheng, Sun, and Liu (2024) in urban requalification contexts.
The contractors stopped negotiating directly with end-users, focusing on technical negotiation mediated by the coordination, which helped reduce interpersonal conflicts and operational misalignments, as discussed by Van Oerle (2022). Senior management participated only in decisions with contractual, overall deadline, or cost implications, avoiding the excessive centralization of operational decisions, pointed out by Omondi and Kimutai (2018) as a factor in decision-making slowness in complex projects. The operationalization of the proposed intervention, through Notion, structured a single repository for negotiation and conflict management, replacing scattered records with a documented and traceable flow.
The problem investigated was not restricted to the lack of a tool, but to the way the organization defined who participated, when they participated, and how decisions were recorded and validated. The tool made the distribution of responsibilities visible and allowed decisions to be tracked, but its effectiveness depended on adherence to the record-keeping and clear criteria for escalation and validation, especially when the impact was contractual or involved operational restrictions of the building user (ISO, 2020; Sabri, 2025). The set of empirical evidence and the alignment with the reviewed studies support the interpretation that negotiation and conflict management operate as engagement instruments when treated as a formalizable process, with record-keeping, decision-making instances, and memory of occurrences, reducing the variation in referrals and the recurrence of problems throughout the retrofit.
In summary, the results indicate that the institutionalization of negotiation and conflict management processes, supported by simple registration systems like Notion, transformed punctual interactions into permanent engagement mechanisms. This approach contributed to greater predictability of deadlines and operational stability by formalizing the handling of occurrences, classifying impacts, directing negotiations to the appropriate instances, and promoting continuous organizational learning. The research demonstrated that the formalization of communication and decision flows is crucial for interorganizational coordination in corporate and retrofit works in occupied environments, directly responding to the study’s objective.
The analysis of empirical results revealed that conflict management and negotiation in corporate construction and retrofit projects, in the studied environment, occurred predominantly in a reactive and unstructured manner. It was observed that stakeholder engagement was concentrated at managerial levels and was frequently triggered only when project execution was already compromised by immediate impediments, such as lack of area release, access restrictions, or scheduling conflicts. This scenario aligns with the literature that describes weaknesses in interorganizational coordination when there are no regular mechanisms for participation and communication that precede the materialization of problems (Yang; Wei; Zhang, 2023; Li, 2024).
In operational terms, the low inclusion of users and operational managers in short-term planning resulted in significant resistance to interventions in sensitive time windows and the need for repeated rescheduling. This dynamic reinforces the association between participation gaps and negative impacts on project performance, as pointed out by Omondi and Kimutai (2018). Communication was predominantly bilateral, punctual, and with scattered records, which led to fragmented and, in some cases, contradictory decisions. The absence of a formal instance of interorganizational dialogue, especially when the conflict involved more than two actors, increased the risk of incompatible referrals, resulting in rework and renegotiations on issues already addressed.
This finding is consistent with the literature relating process and interdependence conflicts to the lack of standardization of procedures and the need for coordination between organizations with partially divergent objectives (Omondi; Kimutai, 2018). Furthermore, stakeholder attributes, such as power, legitimacy, and urgency, influenced behavior in interactions, often shifting the decision from the technical level to institutional disputes. This was particularly evident in environments where the building user had the capacity to restrict the progress of the work for operational reasons, as highlighted by Yang; Wei; Zhang (2023) and Couanau (2019).
The analysis of the decision-making process revealed a reactive negotiation, triggered only when the activity was already blocked, without stable criteria for prioritizing competing demands. The literature on negotiation in projects indicates that, under time pressure and without preparation of alternatives, negotiations tend to produce circumstantial concessions and unstable agreements, especially in scenarios of power asymmetry (Couanau, 2019; Sabri, 2025). In the empirical case, this manifested in the variability of the referrals, which depended on the manager involved, and in the recurrence of conflicts in repetitive activities per floor or sector, due to the absence of formal records of what was agreed upon and the lack of organizational memory of the decision-making process.
The engagement problems identified in the empirical study can be categorized into four main dimensions. The first dimension refers to user participation, which was low in planning decisions, resulting in resistance to interventions and delays. The second dimension, intersectoral coordination, was characterized by bilateral and non-integrated communication, leading to partial solutions and rework. The predictability of impacts, the third dimension, was hampered by late communication of interferences, which generated frequent rescheduling. Finally, the formalization of agreements, the fourth dimension, was marked by the predominance of verbal agreements, resulting in instability of commitments.
The types of conflict observed and their treatment methods were also analyzed. Technical conflicts, such as interferences between systems, were treated with specific activity adjustments, resulting in temporary solutions. Operational conflicts, such as disputes over intervention schedules, were resolved by emergency reprogrammings, impacting deadlines. Relational conflicts, manifested as tensions between teams, were addressed by informal mediation by managers, which frequently resulted in the persistence of the conflict. Institutional conflicts, related to disagreements over responsibilities, were treated by hierarchical escalation, culminating in imposed decisions.
These findings reveal that conflicts were often treated as isolated occurrences, rather than an integral part of the production process in corporate and retrofit projects. Problem resolution depended heavily on the individual actions of managers and the momentary willingness of stakeholders to cooperate, which reduced schedule predictability and project control capability. This management dynamic, which neglected the systemic nature of conflicts, generated negative impacts on schedule, cost, and operation, such as delays, additional costs, and operational restrictions.
In summary, the project’s central problems manifested in four interdependent axes: limited engagement of operational stakeholders, resulting in decisions with low adherence to organizational routines; reactive and personalized negotiation, without formal protocols, which increased decision variability and conflict recurrence; conflict management focused solely on technical adjustments, without considering relational and institutional dimensions; and the absence of systematic conflict monitoring, which prevented organizational learning and continuous process improvement. These axes configured a governance pattern in which conflicts were seen as isolated events, rather than a structural part of the process.
Faced with this diagnosis, the proposed future state for the work was based on the institutionalization of a structured process for negotiation and conflict management, integrating it into project governance, rather than being an occasional response to critical events. This proposition aligns with the guidelines of ISO 21502:2020, which recommends the integration of stakeholder management, communication, decision-making, and problem-solving throughout the entire project lifecycle (ISO, 2020). It is also in line with the findings of Yang, Wei, and Zhang (2023), who indicate that the quality of stakeholder relationships directly influences operational performance and project stability.
The proposed process began with the formalization of stakeholder mapping and classification, considering their degree of influence, level of interest, and direct impact of interventions on their operational routines, as suggested by Couanau (2019) and Zheng, Sun, and Liu (2024). Unlike previous practice, where operational actors were only involved in crisis situations, the new model provided for their regular participation in monitoring instances, allowing for the identification of demands and risks before conflicts materialized. This strategy responds to the findings of Omondi and Kimutai (2018), who associate recurring conflicts with the exclusion of actors directly affected by project decisions.
Subsequently, the process incorporated formal communication and negotiation protocols at three levels: operational, tactical, and strategic. At the operational level, discussions focused on daily alignment between work fronts and company operations, with quick meetings and standardized recording of incidents. At the tactical level, schedule adjustments, resource reallocation, and activity replanning were discussed. At the strategic level, decisions involving contractual impact, relevant scope changes, or institutional risk were handled, ensuring that decisions were made at the appropriate level.
Negotiation, in the future state, ceased to be merely reactive and personalized, starting to follow principles of integrative negotiation, focusing on the parties’ interests and not just on positions, as discussed by Tsao et al. (2021) and Sabri (2025). For this, the process involved the use of minimal negotiation scripts, which included problem identification, surveying the parties’ interests, analyzing technical and operational alternatives, evaluating impacts, and jointly defining next steps, promoting more lasting and acceptable solutions.
The incorporation of leadership practices focused on mediation and facilitation, associated with the leader coach model, as proposed by Claro (2013) and Zimmermann (2019), was highlighted. Contract managers and production coordinators began to act not only as technical decision-makers but also as facilitators of dialogue between areas, promoting active listening, alignment of expectations, and construction of operational commitments. Studies by Donato, Gonçalves, and Sanches (2011) and Alvarez and Carvalho (2019) indicate that this type of leadership contributes to reducing resistance, increasing adherence to decisions, and improving the organizational climate, factors directly related to conflict prevention.
The proposed process also included the creation of a simple system for registering and monitoring conflicts, allowing occurrences to be classified by type, affected area, main cause, and adopted solution. This practice meets the methodological recommendations of Gil (2017) and Prodanov and Freitas (2013) regarding the importance of systematic records for the analysis of organizational processes, transforming isolated episodes into inputs for organizational learning. Periodic analysis of these records supports adjustments in planning, communication, and negotiation protocols, promoting continuous improvement.
The operationalization of the intervention was enabled through the use of Notion as a digital environment for recording, organizing, and monitoring project occurrences and decisions. The platform was configured as a database with standardized fields for each occurrence, including date, location/sector, description, stakeholders involved, person responsible for recording, attached evidence, impact classification (technical, operational, or contractual), negotiation level triggered, alternatives considered, defined referral, agreed deadline, person responsible for implementation, and status.
This structure allowed for the replacement of scattered records, such as instant messages, emails, and verbal reports, with a documented and traceable flow, reinforcing decision-making predictability and reducing subsequent disagreements about what was agreed upon. Notion was also used as a mechanism to support escalation, as the impact classification guided the summoning of the appropriate negotiation instance, bringing the observed practice closer to the guidelines for governance and structured communication indicated by ISO 21502:2020 (ISO, 2020) and the literature on project negotiation (Couanau, 2019; Tsao et al., 2021; Sabri, 2025).
For monitoring purposes, the records began to be updated with the implementation results and observations on recidivism, allowing for the production of a historical database of occurrences. This database is useful for identifying patterns, recurring causes, and critical themes by area or sector, in line with the understanding of conflicts as phenomena associated with decision-making routines and coordination practices, and not just as isolated episodes (Van Oerle, 2022; Yang; Wei; Zhang, 2023). In the empirical context, the use of Notion served as an instrument for stabilizing the negotiation process by recording discussed interests and alternatives and by formalizing follow-ups, an aspect related to satisfaction with the resolution in scenarios of higher conflict intensity, when informal decisions tend to generate unstable agreements (Zhang et al., 2024).
The distribution of functions among the contracting party/users, project management, construction teams, suppliers, and internal support areas showed that risk identification, impact analysis, negotiation, and monitoring ceased to be responsibilities concentrated in a single actor and became a cooperative and institutionalized flow. This structure favored the early communication of interferences, the technical mediation of negotiations, and the organizational validation of decisions, in line with literature recommendations that indicate the need for alignment between stakeholder management, structured negotiation, and mediating leadership in construction projects in occupied environments (ISO, 2020; Tsao et al., 2021; Yang; Wei; Zhang, 2023; Sabri, 2025).
This organization dialogues with the study by Li (2024), which highlights the need for formal mechanisms of participation and continuous communication, and with the systemic approach defended by Van Oerle (2022), according to which technical, relational, and institutional decisions produce cumulative effects throughout the project. Thus, negotiation and conflict management ceased to be mere corrective instruments and began to act as permanent mechanisms for engagement, coordination, and performance stabilization in corporate works, contributing to greater predictability and efficiency.
The project coordination concentrated the function of recording, mediating, and consolidating decisions, in alignment with ISO 21502:2020, which assigns the project manager the integration between technical and organizational areas (ISO, 2020). The occupant company’s management acted as the institutional representative of the production routines, validating impacts and negotiating adjustments that went beyond the local level, as recommended by Couanau (2019) when discussing the formal representation of interests in project negotiations. The operational team began to structure the communication of practical impacts, preventing conflicts from being detected only after failures in the space’s functioning occurred, an aspect also identified by Zheng, Sun, and Liu (2024) in urban requalification contexts.
The contractors stopped negotiating directly with end-users, focusing on technical negotiation mediated by the coordination, which helped reduce interpersonal conflicts and operational misalignments, as discussed by Van Oerle (2022). Senior management participated only in decisions with contractual, overall deadline, or cost implications, avoiding the excessive centralization of operational decisions, pointed out by Omondi and Kimutai (2018) as a factor in decision-making slowness in complex projects. The operationalization of the proposed intervention, through Notion, structured a single repository for negotiation and conflict management, replacing scattered records with a documented and traceable flow.
The problem investigated was not restricted to the lack of a tool, but to the way the organization defined who participated, when they participated, and how decisions were recorded and validated. The tool made the distribution of responsibilities visible and allowed decisions to be tracked, but its effectiveness depended on adherence to the record-keeping and clear criteria for escalation and validation, especially when the impact was contractual or involved operational restrictions of the building user (ISO, 2020; Sabri, 2025). The set of empirical evidence and the alignment with the reviewed studies support the interpretation that negotiation and conflict management operate as engagement instruments when treated as a formalizable process, with record-keeping, decision-making instances, and memory of occurrences, reducing the variation in referrals and the recurrence of problems throughout the retrofit.
In summary, the results indicate that the institutionalization of negotiation and conflict management processes, supported by simple registration systems like Notion, transformed punctual interactions into permanent engagement mechanisms. This approach contributed to greater predictability of deadlines and operational stability by formalizing the handling of occurrences, classifying impacts, directing negotiations to the appropriate instances, and promoting continuous organizational learning. The research demonstrated that the formalization of communication and decision flows is crucial for interorganizational coordination in corporate and retrofit works in occupied environments, directly responding to the study’s objective.
4. Conclusion
This study analyzed the use of conflict management strategies as instruments for stakeholder engagement in corporate construction projects, within a private institution in São Paulo. It was initially verified that conflict management and negotiation occurred in a predominantly reactive and unstructured manner, with engagement concentrated at managerial levels and triggered only when impediments arose. It was observed that the low inclusion of users and operational managers in short-term planning resulted in resistance and reprogramming, while bilateral communication and dispersed records generated fragmented decisions and the recurrence of conflicts. The institutionalization of a structured process for registering, classifying, and forwarding occurrences, operationalized through a database in Notion, transformed these punctual interactions into permanent engagement mechanisms. This approach contributed to greater predictability of deadlines and operational stability, by formalizing the treatment of occurrences, classifying impacts, and directing negotiations to the appropriate instances.
The study’s main contribution lies in proposing an organizational model for conflict management, which replaces reactive responses with predictable steps, incorporating process memory and a consultation base for the company. This model promotes early detection of interferences, technical mediation of negotiations, and organizational validation of decisions, aligning with literature recommendations on project governance. As a limitation, the study was configured as a single case, with observation concentrated in a specific period, implying that the generalization of findings should be analytical, by correspondence with mechanisms described in the literature, rather than statistical. It is suggested that future studies evaluate the model’s effect on indicators such as response time, recurrence by impact type, number of rescheduling, and agreement stability across different projects and teams, enhancing comparability between contexts and retrofit phases.
Bibliographic References
Gil, A. C. 2017. Métodos e técnicas de pesquisa social. 7. ed. Atlas.
Góis, L. de J.; Freitas Junior, S. L. T.; Nascimento, K. R. F.; Cotrim, R. A. Gestão de conflitos na construção civil: canteiro de obras, um estudo de caso. Apoena Revista Eletrônica, Salvador, v. 6, p. 99-114, 2023. Disponível em: https://transformauj.com.br/apoena-revista-eletronica/.
International Organization for Standardization (ISO). ISO 21502:2020 – Project, programme and portfolio management – Guidance on project management. Geneva: ISO, 2020.
Prodanov, C. C.; Freitas, E. C. 2013. Metodologia do trabalho científico: métodos e técnicas da pesquisa e do trabalho acadêmico. 2. ed. Feevale.
Ts
Zhang, L.; Lou, J.; Fu, Y.; Ding, T. Impacts of management approaches on conflict resolution satisfaction: conflict strength matters. KSCE Journal of Civil Engineering, v. 28, n. 6, p. 2091-2104, 2024. DOI: https://doi.org/10.1007/s12205-024-0724-1.