Negotiation and conflict management as instruments for stakeholder engagement in corporate works and retrofit

Allan Silveira Penha; Ranyery Segui de Souza Lima

DOI: 10.22167/2675-6528-202600510

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Corporate construction and retrofit interventions in occupied environments frequently involve multiple stakeholders, whose interdependencies increase the likelihood of conflicts related to access, schedules, and technical interfaces, impacting organizational routine. This study analyzed how negotiation and conflict management strategies can be used to engage stakeholders in corporate construction projects, aiming for greater decision-making predictability and operational stability. A qualitative, descriptive-interventional case study was conducted in a company in São Paulo, between October and December 2025, during the execution of a retrofit project in an occupied environment. The initial diagnosis was based on direct observation, document analysis, and mapping of communication flows. The intervention consisted of implementing a structured process for registering, classifying, and forwarding occurrences, operationalized through a database in Notion. Predominance of reactive negotiations, bilateral communication, and absence of formal records were observed, which was associated with the recurrence of conflicts and rescheduling. The formalization of the flow and the systematic recording of decisions favored traceability, pattern identification, and better direction of negotiation instances. The institutionalization of negotiation and conflict management processes, supported by simple recording systems, contributed to transforming one-off interactions into permanent engagement mechanisms, with positive effects on deadline predictability and inter-organizational coordination in corporate construction and retrofit projects.

Keywords: Interorganizational coordination; Project governance; Corporate works; Decision predictability; Retrofit.

1. Introduction

Civil construction is an intrinsically complex sector, characterized by the interaction of multiple actors who operate at all stages of a project, from initial planning to final delivery. This dynamic becomes even more challenging in the context of corporate construction and retrofit interventions, which frequently occur in already occupied and fully operational environments. The coexistence of work fronts with the routine activities of the user organization establishes a network of interdependencies that significantly increases the probability of divergences and conflicts. For the project manager, the ability to conduct interpersonal relationships is as fundamental as technical knowledge to ensure work continuity (Góis et al., 2023).

In this scenario, the diversity of expectations among the parties involved and the need to integrate multidisciplinary teams make the occurrence of conflicts practically inevitable. Such divergences can arise from issues related to access to specific areas, intervention schedules, complex technical interfaces, and direct impacts on organizational routine. Conflicts, by their nature, can assume both productive and destructive dimensions, depending fundamentally on how they are managed. Approaches that prioritize cooperation tend to generate broader and more acceptable results for all parties. In contrast, overly competitive strategies may only be effective in less intense situations. In contexts of high novelty, criticality, or potential for disruption, collaboration proves to be more effective in rebuilding trust and satisfying those involved (Zhang et al., 2024).

The relevance of stakeholder alignment is a central theme in international project management standards. ISO 21502:2020, for example, emphasizes that the identification of stakeholders, the understanding of their expectations, and the implementation of structured communication mechanisms are essential practices for project performance. In this regard, conflict management and negotiation are recognized as intrinsic tools to the engagement process and organizational governance (ISO, 2020). The role of the construction coordinator assumes particular relevance in this process, acting as a mediator of divergences and a facilitator of dialogue between the different parties of the undertaking. In corporate construction projects, where deadlines and costs are frequently under pressure, the adequate management of relationships between clients, suppliers, designers, and execution teams is a determining factor in avoiding rework and delays.

Despite the recognized importance of negotiation and conflict management for project success, the practice in many corporate construction and retrofit ventures is still characterized by reactive approaches, predominantly bilateral communication, and a notable absence of formal records. This gap, often associated with the recurrence of conflicts and the constant need for rescheduling, indicates a fragility in interorganizational coordination and decision-making predictability. Divergences are often treated in a punctual and emergency manner, without a structure that allows for organizational learning and the prevention of future occurrences, which compromises operational stability and project efficiency.

Given this scenario, the choice of theme is justified by the pressing need to deepen the understanding of practices applicable to the daily lives of construction managers. The corporate sector, in particular, demands a high capacity for articulation among multiple agents, making it essential to develop more effective strategies for managing interdependencies. By relating empirical evidence with normative references, this study seeks to offer practical and theoretical subsidies to improve the performance of professionals who face recurring situations of conflict and divergence, contributing to greater operational stability and deadline predictability.

The relevance of addressing conflict management and negotiation as proactive stakeholder engagement tools lies in their ability to transform one-off interactions into permanent interorganizational coordination mechanisms, with direct effects on deadline predictability and operational stability. Thus, this study aims to analyze the use of conflict management strategies as instruments for engaging stakeholders in corporate construction projects, at a private institution in São Paulo.

2. Material and Methods

The present study was characterized as applied, qualitative, and descriptive-interventional research, using a case study (Gil, 2017; Prodanov; Freitas, 2013). The methodological design approached action-research and intervention, as the researcher acted as the company’s operations coordinator and agent responsible for the diagnosis, proposition, and implementation of changes in negotiation processes and Conflict Management.

The study was conducted in a company in the corporate construction and retrofit sector in São Paulo, between October and December 2025. The setting was a construction site in an occupied environment, where administrative and operational activities of the user organization coexisted with the work fronts, generating continuous interdependencies.

The project involved multiple stakeholders, including the venture management team, main contractor, subcontractors, building managers, security, IT, facilities departments, and end-users. The unit of analysis corresponded to the observed flows of communication, negotiation, and operational conflict resolution, focusing on area release, intervention schedules, interferences in critical systems, and activity rescheduling.

The organizational diagnosis was carried out in October 2025, employing direct observation of site routines, monitoring of planning meetings, and emergency field negotiations. Additionally, existing operational documents were analyzed, such as schedules, meeting minutes, scope change requests, and informal occurrence records.

Based on this diagnosis and on theoretical references on conflict management, negotiation, and stakeholder engagement (Tsao et al., 2021; Yang; Wei; Zhang, 2023; Sabri, 2025; Van Oerle, 2022), a managerial intervention was structured. This aimed at formalizing the process of recording, classifying, and forwarding occurrences, as well as defining negotiation instances compatible with the type of impact identified.

To operationalize the intervention, the Notion platform was adopted. This tool allowed the creation of personalized databases, filtered views, decision-making history logging, and remote access, with low cost, flexibility, and rapid implementation in the organizational environment.

Between the end of October and the beginning of November 2025, a database of occurrences was structured in Notion. Standardized fields were defined for recording the date, location/sector, type of impact (technical, operational, or contractual), stakeholders involved, problem description, negotiation instance triggered (operational, tactical, or strategic), decision made, decision-maker, occurrence status, and observations regarding recurrence.

The implementation phase occurred between November and December 2025. All relevant occurrences were registered in the system, and the decisions arising from the negotiations were formalized in the database. The researcher acted as a mediator in the discussions, guiding the handling of demands according to the identified impact level. Low-complexity operational conflicts were addressed at the operational level; situations with an impact on the schedule, activity sequencing, or multiple sectors were forwarded to the tactical level; and conflicts with potential contractual or institutional repercussions were discussed at the strategic level, with the participation of project management and building management. The history of the discussions was documented to track the evolution of conflicts and those responsible for their resolution.

The data analysis was performed through a qualitative examination of the records in the database, considering the frequency, typology, recurrence of conflicts, and negotiation levels triggered. The treatment of occurrences was compared before and after the implementation of the structured process, in light of the reviewed literature on project governance and stakeholder management (Couanau, 2019; Zheng, Sun, and Liu, 2024; Omondi and Kimutai, 2018). For monitoring, the records were updated with implementation results and observations on recurrence, building a historical database useful for identifying patterns, recurring causes, and critical themes by area or sector (Van Oerle, 2022; Yang; Wei; Zhang, 2023). Notion was also used as a “library” of lessons learned, with dedicated visualizations for recurrences and recommendations.

3. Results and Discussion

The analysis of empirical results revealed that conflict management and negotiation in corporate construction and retrofit projects, in the studied environment, occurred predominantly in a reactive and unstructured manner. It was observed that stakeholder engagement was concentrated at managerial levels and was frequently triggered only when project execution was already compromised by immediate impediments, such as lack of area release, access restrictions, or scheduling conflicts. This scenario aligns with the literature that describes weaknesses in interorganizational coordination when there are no regular mechanisms for participation and communication that precede the materialization of problems (Yang; Wei; Zhang, 2023; Li, 2024).

In operational terms, the low inclusion of users and operational managers in short-term planning resulted in significant resistance to interventions in sensitive time windows and the need for repeated rescheduling. This dynamic reinforces the association between participation gaps and negative impacts on project performance, as pointed out by Omondi and Kimutai (2018). Communication was predominantly bilateral, punctual, and with scattered records, which led to fragmented and, in some cases, contradictory decisions. The absence of a formal instance of interorganizational dialogue, especially when the conflict involved more than two actors, increased the risk of incompatible referrals, resulting in rework and renegotiations on issues already addressed.

This finding is consistent with the literature relating process and interdependence conflicts to the lack of standardization of procedures and the need for coordination between organizations with partially divergent objectives (Omondi; Kimutai, 2018). Furthermore, stakeholder attributes, such as power, legitimacy, and urgency, influenced behavior in interactions, often shifting the decision from the technical level to institutional disputes. This was particularly evident in environments where the building user had the capacity to restrict the progress of the work for operational reasons, as highlighted by Yang; Wei; Zhang (2023) and Couanau (2019).

The analysis of the decision-making process revealed a reactive negotiation, triggered only when the activity was already blocked, without stable criteria for prioritizing competing demands. The literature on negotiation in projects indicates that, under time pressure and without preparation of alternatives, negotiations tend to produce circumstantial concessions and unstable agreements, especially in scenarios of power asymmetry (Couanau, 2019; Sabri, 2025). In the empirical context, this manifested in the variability of the referrals, which depended on the manager involved, and in the recurrence of conflicts in repetitive activities per floor or sector, due to the absence of formal records of what was agreed upon and the lack of organizational memory of the decision-making process.

The engagement problems identified in the empirical study can be categorized into four main dimensions. The first dimension refers to user participation, which was low in planning decisions, resulting in resistance to interventions and delays. The second dimension, intersectoral coordination, was characterized by bilateral and non-integrated communication, leading to partial solutions and rework. The predictability of impacts, the third dimension, was hampered by late communication of interferences, which generated frequent rescheduling. Finally, the formalization of agreements, the fourth dimension, was marked by the predominance of verbal agreements, resulting in instability of commitments.

The types of conflict observed and their treatment methods were also analyzed. Technical conflicts, such as interferences between systems, were treated with specific activity adjustments, resulting in temporary solutions. Operational conflicts, such as disputes over intervention schedules, were resolved by emergency reprogrammings, impacting deadlines. Relational conflicts, manifested as tensions between teams, were addressed by informal mediation by managers, which frequently resulted in the persistence of the conflict. Institutional conflicts, related to disagreements over responsibilities, were treated by hierarchical escalation, culminating in imposed decisions.

These findings reveal that conflicts were often treated as isolated occurrences, rather than an integral part of the production process in corporate and retrofit projects. Problem resolution depended heavily on the individual actions of managers and the momentary willingness of stakeholders to cooperate, which reduced schedule predictability and project control capability. This management dynamic, which neglected the systemic nature of conflicts, generated negative impacts on schedule, cost, and operation, such as delays, additional costs, and operational restrictions.

In summary, the project’s central problems manifested in four interdependent axes: limited engagement of operational stakeholders, resulting in decisions with low adherence to organizational routines; reactive and personalized negotiation, without formal protocols, which increased decision variability and conflict recurrence; conflict management focused solely on technical adjustments, without considering relational and institutional dimensions; and the absence of systematic conflict monitoring, which prevented organizational learning and continuous process improvement. These axes configured a governance pattern in which conflicts were seen as isolated events, rather than a structural part of the process.

Faced with this diagnosis, the proposed future state for the work was based on the institutionalization of a structured process for negotiation and conflict management, integrating it into project governance, rather than being an occasional response to critical events. This proposition aligns with the guidelines of ISO 21502:2020, which recommends the integration of stakeholder management, communication, decision-making, and problem-solving throughout the entire project lifecycle (ISO, 2020). It is also in line with the findings of Yang, Wei, and Zhang (2023), who indicate that the quality of stakeholder relationships directly influences operational performance and project stability.

The proposed process began with the formalization of stakeholder mapping and classification, considering their degree of influence, level of interest, and direct impact of interventions on their operational routines, as suggested by Couanau (2019) and Zheng, Sun, and Liu (2024). Unlike previous practice, where operational actors were only involved in crisis situations, the new model provided for their regular participation in monitoring instances, allowing for the identification of demands and risks before conflicts materialized. This strategy responds to the findings of Omondi and Kimutai (2018), who associate recurring conflicts with the exclusion of actors directly affected by project decisions.

Subsequently, the process incorporated formal communication and negotiation protocols at three levels: operational, tactical, and strategic. At the operational level, discussions focused on daily alignment between work fronts and company operations, with quick meetings and standardized recording of incidents. At the tactical level, schedule adjustments, resource reallocation, and activity replanning were discussed. At the strategic level, decisions involving contractual impact, relevant scope changes, or institutional risk were handled, ensuring that decisions were made at the appropriate level.

Negotiation, in the future state, ceased to be merely reactive and personalized, starting to follow principles of integrative negotiation, focusing on the parties’ interests and not just on positions, as discussed by Tsao et al. (2021) and Sabri (2025). For this, the process involved the use of minimal negotiation scripts, which included problem identification, surveying the parties’ interests, analyzing technical and operational alternatives, evaluating impacts, and jointly defining next steps, promoting more lasting and acceptable solutions.

The incorporation of leadership practices focused on mediation and facilitation, associated with the leader coach model, as proposed by Claro (2013) and Zimmermann (2019), was highlighted. Contract managers and production coordinators began to act not only as technical decision-makers but also as facilitators of dialogue between areas, promoting active listening, alignment of expectations, and construction of operational commitments. Studies by Donato, Gonçalves, and Sanches (2011) and Alvarez and Carvalho (2019) indicate that this type of leadership contributes to reducing resistance, increasing adherence to decisions, and improving the organizational climate, factors directly related to conflict prevention.

The proposed process also included the creation of a simple system for registering and monitoring conflicts, allowing occurrences to be classified by type, affected area, main cause, and adopted solution. This practice meets the methodological recommendations of Gil (2017) and Prodanov and Freitas (2013) regarding the importance of systematic records for the analysis of organizational processes, transforming isolated episodes into inputs for organizational learning. Periodic analysis of these records supports adjustments in planning, communication, and negotiation protocols, promoting continuous improvement.

The operationalization of the intervention was enabled through the use of Notion as a digital environment for recording, organizing, and monitoring project occurrences and decisions. The platform was configured as a database with standardized fields for each occurrence, including date, location/sector, description, stakeholders involved, person responsible for recording, attached evidence, impact classification (technical, operational, or contractual), negotiation level triggered, alternatives considered, defined referral, agreed deadline, person responsible for implementation, and status.

This structure allowed for the replacement of scattered records, such as instant messages, emails, and verbal reports, with a documented and traceable flow, reinforcing decision-making predictability and reducing subsequent disagreements about what was agreed upon. Notion was also used as a mechanism to support escalation, as the impact classification guided the summoning of the appropriate negotiation instance, bringing the observed practice closer to the guidelines for governance and structured communication indicated by ISO 21502:2020 (ISO, 2020) and the literature on project negotiation (Couanau, 2019; Tsao et al., 2021; Sabri, 2025).

For monitoring purposes, the records began to be updated with the implementation results and observations on recidivism, allowing for the production of a historical database of occurrences. This database is useful for identifying patterns, recurring causes, and critical themes by area or sector, in line with the understanding of conflicts as phenomena associated with decision-making routines and coordination practices, and not just as isolated episodes (Van Oerle, 2022; Yang; Wei; Zhang, 2023). In the empirical context, the use of Notion served as an instrument for stabilizing the negotiation process by recording discussed interests and alternatives and by formalizing follow-ups, an aspect related to satisfaction with the resolution in scenarios of higher conflict intensity, when informal decisions tend to generate unstable agreements (Zhang et al., 2024).

The distribution of functions among the contracting party/users, project management, construction teams, suppliers, and internal support areas showed that risk identification, impact analysis, negotiation, and monitoring ceased to be responsibilities concentrated in a single actor and became a cooperative and institutionalized flow. This structure favored the early communication of interferences, the technical mediation of negotiations, and the organizational validation of decisions, in line with literature recommendations that indicate the need for alignment between stakeholder management, structured negotiation, and mediating leadership in construction projects in occupied environments (ISO, 2020; Tsao et al., 2021; Yang; Wei; Zhang, 2023; Sabri, 2025).

This organization dialogues with the study by Li (2024), which highlights the need for formal mechanisms of participation and continuous communication, and with the systemic approach defended by Van Oerle (2022), according to which technical, relational, and institutional decisions produce cumulative effects throughout the project. Thus, negotiation and conflict management ceased to be mere corrective instruments and began to act as permanent mechanisms for engagement, coordination, and performance stabilization in corporate works, contributing to greater predictability and efficiency.

The project coordination concentrated the function of recording, mediating, and consolidating decisions, in alignment with ISO 21502:2020, which assigns the project manager the integration between technical and organizational areas (ISO, 2020). The occupant company’s management acted as the institutional representative of the production routines, validating impacts and negotiating adjustments that went beyond the local level, as recommended by Couanau (2019) when discussing the formal representation of interests in project negotiations. The operational team began to structure the communication of practical impacts, preventing conflicts from being detected only after failures in the space’s functioning occurred, an aspect also identified by Zheng, Sun, and Liu (2024) in urban requalification contexts.

The contractors stopped negotiating directly with end-users, focusing on technical negotiation mediated by the coordination, which helped reduce interpersonal conflicts and operational misalignments, as discussed by Van Oerle (2022). Senior management participated only in decisions with contractual, overall deadline, or cost implications, avoiding the excessive centralization of operational decisions, pointed out by Omondi and Kimutai (2018) as a factor in decision-making slowness in complex projects. The operationalization of the proposed intervention, through Notion, structured a single repository for negotiation and conflict management, replacing scattered records with a documented and traceable flow.

The problem investigated was not restricted to the lack of a tool, but to the way the organization defined who participated, when they participated, and how decisions were recorded and validated. The tool made the distribution of responsibilities visible and allowed decisions to be tracked, but its effectiveness depended on adherence to the record-keeping and clear criteria for escalation and validation, especially when the impact was contractual or involved operational restrictions of the building user (ISO, 2020; Sabri, 2025). The set of empirical evidence and the alignment with the reviewed studies support the interpretation that negotiation and conflict management operate as engagement instruments when treated as a formalizable process, with record-keeping, decision-making instances, and memory of occurrences, reducing the variation in referrals and the recurrence of problems throughout the retrofit.

In summary, the results indicate that the institutionalization of negotiation and conflict management processes, supported by simple registration systems like Notion, transformed punctual interactions into permanent engagement mechanisms. This approach contributed to greater predictability of deadlines and operational stability by formalizing the handling of occurrences, classifying impacts, directing negotiations to the appropriate instances, and promoting continuous organizational learning. The research demonstrated that the formalization of communication and decision flows is crucial for interorganizational coordination in corporate and retrofit works in occupied environments, directly responding to the study’s objective.

The analysis of empirical results revealed that conflict management and negotiation in corporate construction and retrofit projects, in the studied environment, occurred predominantly in a reactive and unstructured manner. It was observed that stakeholder engagement was concentrated at managerial levels and was frequently triggered only when project execution was already compromised by immediate impediments, such as lack of area release, access restrictions, or scheduling conflicts. This scenario aligns with the literature that describes weaknesses in interorganizational coordination when there are no regular mechanisms for participation and communication that precede the materialization of problems (Yang; Wei; Zhang, 2023; Li, 2024).

In operational terms, the low inclusion of users and operational managers in short-term planning resulted in significant resistance to interventions in sensitive time windows and the need for repeated rescheduling. This dynamic reinforces the association between participation gaps and negative impacts on project performance, as pointed out by Omondi and Kimutai (2018). Communication was predominantly bilateral, punctual, and with scattered records, which led to fragmented and, in some cases, contradictory decisions. The absence of a formal instance of interorganizational dialogue, especially when the conflict involved more than two actors, increased the risk of incompatible referrals, resulting in rework and renegotiations on issues already addressed.

This finding is consistent with the literature relating process and interdependence conflicts to the lack of standardization of procedures and the need for coordination between organizations with partially divergent objectives (Omondi; Kimutai, 2018). Furthermore, stakeholder attributes, such as power, legitimacy, and urgency, influenced behavior in interactions, often shifting the decision from the technical level to institutional disputes. This was particularly evident in environments where the building user had the capacity to restrict the progress of the work for operational reasons, as highlighted by Yang; Wei; Zhang (2023) and Couanau (2019).

The analysis of the decision-making process revealed a reactive negotiation, triggered only when the activity was already blocked, without stable criteria for prioritizing competing demands. The literature on negotiation in projects indicates that, under time pressure and without preparation of alternatives, negotiations tend to produce circumstantial concessions and unstable agreements, especially in scenarios of power asymmetry (Couanau, 2019; Sabri, 2025). In the empirical case, this manifested in the variability of the referrals, which depended on the manager involved, and in the recurrence of conflicts in repetitive activities per floor or sector, due to the absence of formal records of what was agreed upon and the lack of organizational memory of the decision-making process.

The engagement problems identified in the empirical study can be categorized into four main dimensions. The first dimension refers to user participation, which was low in planning decisions, resulting in resistance to interventions and delays. The second dimension, intersectoral coordination, was characterized by bilateral and non-integrated communication, leading to partial solutions and rework. The predictability of impacts, the third dimension, was hampered by late communication of interferences, which generated frequent rescheduling. Finally, the formalization of agreements, the fourth dimension, was marked by the predominance of verbal agreements, resulting in instability of commitments.

The types of conflict observed and their treatment methods were also analyzed. Technical conflicts, such as interferences between systems, were treated with specific activity adjustments, resulting in temporary solutions. Operational conflicts, such as disputes over intervention schedules, were resolved by emergency reprogrammings, impacting deadlines. Relational conflicts, manifested as tensions between teams, were addressed by informal mediation by managers, which frequently resulted in the persistence of the conflict. Institutional conflicts, related to disagreements over responsibilities, were treated by hierarchical escalation, culminating in imposed decisions.

These findings reveal that conflicts were often treated as isolated occurrences, rather than an integral part of the production process in corporate and retrofit projects. Problem resolution depended heavily on the individual actions of managers and the momentary willingness of stakeholders to cooperate, which reduced schedule predictability and project control capability. This management dynamic, which neglected the systemic nature of conflicts, generated negative impacts on schedule, cost, and operation, such as delays, additional costs, and operational restrictions.

In summary, the project’s central problems manifested in four interdependent axes: limited engagement of operational stakeholders, resulting in decisions with low adherence to organizational routines; reactive and personalized negotiation, without formal protocols, which increased decision variability and conflict recurrence; conflict management focused solely on technical adjustments, without considering relational and institutional dimensions; and the absence of systematic conflict monitoring, which prevented organizational learning and continuous process improvement. These axes configured a governance pattern in which conflicts were seen as isolated events, rather than a structural part of the process.

Faced with this diagnosis, the proposed future state for the work was based on the institutionalization of a structured process for negotiation and conflict management, integrating it into project governance, rather than being an occasional response to critical events. This proposition aligns with the guidelines of ISO 21502:2020, which recommends the integration of stakeholder management, communication, decision-making, and problem-solving throughout the entire project lifecycle (ISO, 2020). It is also in line with the findings of Yang, Wei, and Zhang (2023), who indicate that the quality of stakeholder relationships directly influences operational performance and project stability.

The proposed process began with the formalization of stakeholder mapping and classification, considering their degree of influence, level of interest, and direct impact of interventions on their operational routines, as suggested by Couanau (2019) and Zheng, Sun, and Liu (2024). Unlike previous practice, where operational actors were only involved in crisis situations, the new model provided for their regular participation in monitoring instances, allowing for the identification of demands and risks before conflicts materialized. This strategy responds to the findings of Omondi and Kimutai (2018), who associate recurring conflicts with the exclusion of actors directly affected by project decisions.

Subsequently, the process incorporated formal communication and negotiation protocols at three levels: operational, tactical, and strategic. At the operational level, discussions focused on daily alignment between work fronts and company operations, with quick meetings and standardized recording of incidents. At the tactical level, schedule adjustments, resource reallocation, and activity replanning were discussed. At the strategic level, decisions involving contractual impact, relevant scope changes, or institutional risk were handled, ensuring that decisions were made at the appropriate level.

Negotiation, in the future state, ceased to be merely reactive and personalized, starting to follow principles of integrative negotiation, focusing on the parties’ interests and not just on positions, as discussed by Tsao et al. (2021) and Sabri (2025). For this, the process involved the use of minimal negotiation scripts, which included problem identification, surveying the parties’ interests, analyzing technical and operational alternatives, evaluating impacts, and jointly defining next steps, promoting more lasting and acceptable solutions.

The incorporation of leadership practices focused on mediation and facilitation, associated with the leader coach model, as proposed by Claro (2013) and Zimmermann (2019), was highlighted. Contract managers and production coordinators began to act not only as technical decision-makers but also as facilitators of dialogue between areas, promoting active listening, alignment of expectations, and construction of operational commitments. Studies by Donato, Gonçalves, and Sanches (2011) and Alvarez and Carvalho (2019) indicate that this type of leadership contributes to reducing resistance, increasing adherence to decisions, and improving the organizational climate, factors directly related to conflict prevention.

The proposed process also included the creation of a simple system for registering and monitoring conflicts, allowing occurrences to be classified by type, affected area, main cause, and adopted solution. This practice meets the methodological recommendations of Gil (2017) and Prodanov and Freitas (2013) regarding the importance of systematic records for the analysis of organizational processes, transforming isolated episodes into inputs for organizational learning. Periodic analysis of these records supports adjustments in planning, communication, and negotiation protocols, promoting continuous improvement.

The operationalization of the intervention was enabled through the use of Notion as a digital environment for recording, organizing, and monitoring project occurrences and decisions. The platform was configured as a database with standardized fields for each occurrence, including date, location/sector, description, stakeholders involved, person responsible for recording, attached evidence, impact classification (technical, operational, or contractual), negotiation level triggered, alternatives considered, defined referral, agreed deadline, person responsible for implementation, and status.

This structure allowed for the replacement of scattered records, such as instant messages, emails, and verbal reports, with a documented and traceable flow, reinforcing decision-making predictability and reducing subsequent disagreements about what was agreed upon. Notion was also used as a mechanism to support escalation, as the impact classification guided the summoning of the appropriate negotiation instance, bringing the observed practice closer to the guidelines for governance and structured communication indicated by ISO 21502:2020 (ISO, 2020) and the literature on project negotiation (Couanau, 2019; Tsao et al., 2021; Sabri, 2025).

For monitoring purposes, the records began to be updated with the implementation results and observations on recidivism, allowing for the production of a historical database of occurrences. This database is useful for identifying patterns, recurring causes, and critical themes by area or sector, in line with the understanding of conflicts as phenomena associated with decision-making routines and coordination practices, and not just as isolated episodes (Van Oerle, 2022; Yang; Wei; Zhang, 2023). In the empirical context, the use of Notion served as an instrument for stabilizing the negotiation process by recording discussed interests and alternatives and by formalizing follow-ups, an aspect related to satisfaction with the resolution in scenarios of higher conflict intensity, when informal decisions tend to generate unstable agreements (Zhang et al., 2024).

The distribution of functions among the contracting party/users, project management, construction teams, suppliers, and internal support areas showed that risk identification, impact analysis, negotiation, and monitoring ceased to be responsibilities concentrated in a single actor and became a cooperative and institutionalized flow. This structure favored the early communication of interferences, the technical mediation of negotiations, and the organizational validation of decisions, in line with literature recommendations that indicate the need for alignment between stakeholder management, structured negotiation, and mediating leadership in construction projects in occupied environments (ISO, 2020; Tsao et al., 2021; Yang; Wei; Zhang, 2023; Sabri, 2025).

This organization dialogues with the study by Li (2024), which highlights the need for formal mechanisms of participation and continuous communication, and with the systemic approach defended by Van Oerle (2022), according to which technical, relational, and institutional decisions produce cumulative effects throughout the project. Thus, negotiation and conflict management ceased to be mere corrective instruments and began to act as permanent mechanisms for engagement, coordination, and performance stabilization in corporate works, contributing to greater predictability and efficiency.

The project coordination concentrated the function of recording, mediating, and consolidating decisions, in alignment with ISO 21502:2020, which assigns the project manager the integration between technical and organizational areas (ISO, 2020). The occupant company’s management acted as the institutional representative of the production routines, validating impacts and negotiating adjustments that went beyond the local level, as recommended by Couanau (2019) when discussing the formal representation of interests in project negotiations. The operational team began to structure the communication of practical impacts, preventing conflicts from being detected only after failures in the space’s functioning occurred, an aspect also identified by Zheng, Sun, and Liu (2024) in urban requalification contexts.

The contractors stopped negotiating directly with end-users, focusing on technical negotiation mediated by the coordination, which helped reduce interpersonal conflicts and operational misalignments, as discussed by Van Oerle (2022). Senior management participated only in decisions with contractual, overall deadline, or cost implications, avoiding the excessive centralization of operational decisions, pointed out by Omondi and Kimutai (2018) as a factor in decision-making slowness in complex projects. The operationalization of the proposed intervention, through Notion, structured a single repository for negotiation and conflict management, replacing scattered records with a documented and traceable flow.

The problem investigated was not restricted to the lack of a tool, but to the way the organization defined who participated, when they participated, and how decisions were recorded and validated. The tool made the distribution of responsibilities visible and allowed decisions to be tracked, but its effectiveness depended on adherence to the record-keeping and clear criteria for escalation and validation, especially when the impact was contractual or involved operational restrictions of the building user (ISO, 2020; Sabri, 2025). The set of empirical evidence and the alignment with the reviewed studies support the interpretation that negotiation and conflict management operate as engagement instruments when treated as a formalizable process, with record-keeping, decision-making instances, and memory of occurrences, reducing the variation in referrals and the recurrence of problems throughout the retrofit.

In summary, the results indicate that the institutionalization of negotiation and conflict management processes, supported by simple registration systems like Notion, transformed punctual interactions into permanent engagement mechanisms. This approach contributed to greater predictability of deadlines and operational stability by formalizing the handling of occurrences, classifying impacts, directing negotiations to the appropriate instances, and promoting continuous organizational learning. The research demonstrated that the formalization of communication and decision flows is crucial for interorganizational coordination in corporate and retrofit works in occupied environments, directly responding to the study’s objective.

4. Conclusion

This study analyzed the use of conflict management strategies as instruments for stakeholder engagement in corporate construction projects, within a private institution in São Paulo. It was initially verified that conflict management and negotiation occurred in a predominantly reactive and unstructured manner, with engagement concentrated at managerial levels and triggered only when impediments arose. It was observed that the low inclusion of users and operational managers in short-term planning resulted in resistance and reprogramming, while bilateral communication and dispersed records generated fragmented decisions and the recurrence of conflicts. The institutionalization of a structured process for registering, classifying, and forwarding occurrences, operationalized through a database in Notion, transformed these punctual interactions into permanent engagement mechanisms. This approach contributed to greater predictability of deadlines and operational stability, by formalizing the treatment of occurrences, classifying impacts, and directing negotiations to the appropriate instances.

The study’s main contribution lies in proposing an organizational model for conflict management, which replaces reactive responses with predictable steps, incorporating process memory and a consultation base for the company. This model promotes early detection of interferences, technical mediation of negotiations, and organizational validation of decisions, aligning with literature recommendations on project governance. As a limitation, the study was configured as a single case, with observation concentrated in a specific period, implying that the generalization of findings should be analytical, by correspondence with mechanisms described in the literature, rather than statistical. It is suggested that future studies evaluate the model’s effect on indicators such as response time, recurrence by impact type, number of rescheduling, and agreement stability across different projects and teams, enhancing comparability between contexts and retrofit phases.

Bibliographic References

Gil, A. C. 2017. Métodos e técnicas de pesquisa social. 7. ed. Atlas.

Góis, L. de J.; Freitas Junior, S. L. T.; Nascimento, K. R. F.; Cotrim, R. A. Gestão de conflitos na construção civil: canteiro de obras, um estudo de caso. Apoena Revista Eletrônica, Salvador, v. 6, p. 99-114, 2023. Disponível em: https://transformauj.com.br/apoena-revista-eletronica/.

International Organization for Standardization (ISO). ISO 21502:2020 – Project, programme and portfolio management – Guidance on project management. Geneva: ISO, 2020.

Prodanov, C. C.; Freitas, E. C. 2013. Metodologia do trabalho científico: métodos e técnicas da pesquisa e do trabalho acadêmico. 2. ed. Feevale.

Ts

Zhang, L.; Lou, J.; Fu, Y.; Ding, T. Impacts of management approaches on conflict resolution satisfaction: conflict strength matters. KSCE Journal of Civil Engineering, v. 28, n. 6, p. 2091-2104, 2024. DOI: https://doi.org/10.1007/s12205-024-0724-1.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.