Agile methodology applied to civil engineering project development: Scope equalization and pricing with suppliers

Agile Methodology Applied to Civil Engineering Project Development: Scope Equalization and Pricing with Suppliers

Washingnton Silva Souza; Gleison De Souza

DOI: 10.22167/2675-6528-202602441

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

The complexity of construction ventures, the need for integration between areas, and the pursuit of greater cost and deadline predictability have made the application of project management fundamental. The application of the agile Scrum methodology in the third-party contracting process was analyzed, focusing on the elaboration of scopes, equalization of proposals, and communication between stakeholders in a logistic shed renovation project. The research was developed through a qualitative and descriptive case study, applied to a venture of approximately 7,500 m² in Guarulhos (SP). The methodology adapted the Scrum framework to the processes of defining scopes and equalizing proposals, structuring activities into cycles (sprints) with progressive validations between internal teams and suppliers. The results showed significant improvements in the clarity of technical specifications, greater alignment among those involved, reduction of discrepancies between proposals, and decreased time needed for budget equalization. Increased transparency in the contracting process and better technical and financial analysis capabilities were also observed. It was concluded that the application of Scrum contributed positively to scope management and assertiveness in contracting, proving to be a viable approach for civil engineering projects, especially in logistic contexts with frequent changes and service to diverse market segments.

Keywords: Project management; Scrum; Stakeholders.

1. Introduction

The application of project management has established itself as a strategic role in organizations, especially with the increasing complexity of ventures, pressure for results, and the need for integration between different areas and stakeholders. Modern projects require not only technical mastery but also methods capable of organizing processes, aligning expectations, and supporting decision-making throughout their entire lifecycle, in order to reduce uncertainties and increase the predictability of results (Sawada and Bertoletto, 2019).

According to the Project Management Institute (PMI, 2021), project management is the implementation and development of a project with tools and methodologies to meet stakeholder expectations. In civil construction, operational efficiency has been presented as a competitive differentiator. However, one of the main challenges encountered in civil construction projects lies in the definition of scope and project conception, as well as in communication and alignment with the client (Brandstetter and Ribeiro, 2019).

The traditional hiring process often reveals irregularities in scopes, projects, and budget spreadsheets only during execution, generating extra costs for the contractor (Porto et al., 2023). Challenges in developing effective scopes include a lack of clarity in proposals, inconsistency in internal definition among those involved, and inefficiency in the equalization process, stemming from the absence of detailed technical specifications. This lack of management during scope definition compromises the final added value, the competitiveness of the hiring process, project financial management, deadline compliance, and quality (Kaiser, 2024). The previous hiring scenario was marked by generalist scopes, low technical detail, and proposals with diverse interpretations, hindering analysis and equalization.

In this context, the use of agile methodologies emerges as a promising alternative to mitigate these problems. They promote greater interaction between parties, continuous scope reviews, and incremental deliveries, allowing for rapid adjustments as project needs evolve. This approach favors transparency, collaboration, and constant alignment of expectations, reducing contractual risks and contributing to more efficient and adaptable management in the civil construction environment. Miranda and Alves (2023) highlight that agile methodology allows for faster identification of changes and implementation of coherent actions with less impact.

The Scrum methodology, according to PMI (2021), is an agile method that provides integration and frequent reviews for project development. Ramos (2023) emphasizes that the main characteristic of Scrum is its flexible approach to management, adaptability to changes, validation in value deliveries, closeness between client and process improvement. In civil engineering, the adoption of Scrum has proven advantageous, enabling greater control over execution stages, reduction of rework, and better management of deadlines and resources. Scrum management is based on three pillars for its development: transparency, inspection, and adaptation (Gomes, 2022).

Considering the complexities and recurring challenges in defining scope and contracting service providers in civil engineering projects, especially in dynamic environments such as logistics warehouses, this study is justified by the need to explore more effective management approaches. In this context, this study seeks to evaluate the practical development with Scrum as a tool to support scope management in renovation projects in a logistics warehouse, analyzing its impacts on the definition of activities, the equalization of service provider proposals, cost predictability during the contracting phase, and total alignment among internal “stakeholders”.

2. Material and Methods

The present study was characterized as a qualitative and descriptive research, developed through a case study. The empirical object was a civil engineering project for renovation and adaptation in a logistics warehouse with air-conditioned operation, located in Guarulhos, São Paulo. The undertaking aimed to meet the client’s contractual specifications, regulatory requirements, and internal guidelines of the logistics operator.

The project involved several work fronts, such as civil services, electrical installations, air conditioning, roof regularization, energy entrance adaptation, metalwork, pallet gate installation, elevator, AVCB (Fire Department inspection certificate), and cleaning. For each front, at least three suppliers were sought for proposal composition. The study focused on the service provider contracting stage, with an approximate duration of 50 days.

The adopted methodology was based on the adapted application of the Scrum framework to the process of scope definition, pricing, and proposal equalization. The structure was organized into sequential stages to allow for understanding and eventual replication of the process. The methodological procedures were outlined to evaluate the practice of Scrum as a tool for supporting scope management.

Initially, a diagnosis of the traditional hiring process was carried out. In this model, the project was presented in a “kick-off” meeting between the engineering and facilities teams, who developed generalist scopes. The proposals received presented varied formats and a lack of standardization, making technical analysis and financial comparison difficult. Divergences in interpretation, lack of technical detail, and difficulty in equalizing proposals were identified, with the occurrence of addendums during the execution of the work.

Next, the scope was structured through a Work Breakdown Structure (WBS), organizing it into work packages for greater clarity of activities. Based on this WBS, material with essential information for each service was developed. The WBS items were then organized into a backlog format, representing the expected deliverables of the process.

Subsequently, a standard budget spreadsheet was developed, based on market models and initial Engineering premises, according to the guidelines of the PMBOK Guide (PMI, 2021). This spreadsheet contained a detailed description of activities, units of measure, unit and total values, standardizing the receipt of pricing. For this stage, three base files were sent: architectural project, statement of work, and the standardized budget spreadsheet.

The application of Scrum was structured in four iterative cycles, called sprints, with an average duration of two weeks. The first sprint consisted of an internal meeting between the Facilities and Engineering teams to align the technical scope and premises. The second sprint was an in-person external meeting at the logistics warehouse, involving Facilities, Procurement, and service providers, focused on the initial understanding of the scope and technical guidelines.

The third sprint occurred online, focusing on the discussion of submitted budgets and proposed solutions by suppliers, analyzing methods and adjustments in scope. The fourth and final sprint was held internally, with Facilities, Engineering, Occupational Safety, and Procurement, proceeding to the comparative analysis of proposals, considering technical and financial criteria to define the most aligned supplier.

The monitoring of activities throughout the sprints was carried out through periodic meetings, minutes records, updating of progress control spreadsheets, and the use of the digital tool Microsoft Planner. This approach allowed for continuous monitoring of progress and interaction between teams, ensuring process transparency.

After the completion of the sprints, a quotation map was elaborated. This map consolidated the three budget proposals received and was shared for cost approval. It presented comparative characteristics such as final value, guarantees, timeline, and responsibility matrix, to support the hiring decision. The evaluation of the methodological procedures was carried out qualitatively, considering aspects such as clarity of specifications and ease of proposal equalization.

3. Results and Discussion

The application of the agile Scrum methodology in the third-party contracting process for a logistics shed renovation project revealed significant transformations compared to the traditional model. The results obtained demonstrate a substantial improvement in the clarity of technical specifications, alignment among stakeholders, and efficiency in proposal equalization, directly impacting cost predictability and contracting assertiveness. The research highlighted how structuring activities into iterative cycles, with progressive validations, contributed to mitigating recurring challenges in civil engineering, in line with the central objective of this study.

Initially, the hiring scenario was characterized by a traditional process based on generalist scopes, elaborated in standard text format and with a low level of technical detail. This material was then forwarded to service providers, who frequently returned with proposals based on their own interpretations, presenting distinct technical solutions and global values. The absence of a standardized on-site meeting and structured material for contractors resulted in a lack of a common basis for comparison, hindering technical analysis and effective alignment between the proposals received.

The lack of technical detail compromised the reading of unit values and the assessment of coherence between proposals, making it difficult to identify possible distortions, especially in more sensitive cost items. This lack of clarity also impacted internal discussions, with areas such as Occupational Safety, Operations, and Quality facing difficulties in validating the scope due to insufficient visibility on executive methods, risks, and operational impacts. Historically, in the last five projects carried out, the company registered significant contractual addendums, resulting from the misalignment of the proposed activities, which corroborates the observation by Porto et al. (2023) regarding irregularities perceived only during execution.

This previous model, therefore, compromised the precise definition of project deliverables, economic viability, and the technical capacity of the area, generating extra costs and harming the competitiveness of the contracting process, the project’s financial management, deadline compliance, and quality, as pointed out by Kaiser (2024). The absence of adequate management in the scope definition phase resulted in a complex and less reliable contracting process, with divergent proposals both technically and financially, evidencing the fragility of scope management and the need for methods that promote greater clarity and alignment in the initial phases of the project.

Structuring the agile process with Scrum

The application of the agile methodology based on the Scrum framework was implemented with the purpose of reorganizing the scope definition and contracting process, structuring the interactions between those involved through sequential validation cycles. Unlike the previous model, which operated in an isolated and fragmented manner, the new process began to be conducted in a more structured way, following a logical sequence of sprints. Each sprint had a specific objective within the scope evolution, which provided greater predictability to internal processes and deadlines, according to the adaptability and process improvement highlighted by Ramos (2023).

The first sprint consisted of an internal meeting between the Facilities and Engineering teams, focused on aligning the technical scope, project assumptions, priorities, and cycle objectives. This stage was crucial for consolidating internal understanding before contacting suppliers, presenting the project, criticality points, and stakeholder interests, as well as the client’s final objectives with the structuring of the environments. The previously prepared documentation and the alignment with stakeholders allowed the work to be presented simply and clearly, unlike the previous informality.

In the second sprint, which involved Facilities, Procurement, and service providers, the meeting was held in person at the logistics warehouse. The main focus was to seek initial scope understanding, indicate technical guidelines, and open space for contributions from the providers. This interaction was of great value, allowing for important adaptations, such as the alteration of the HVAC piping path, which, after discussion with the providers, had its location modified, resulting in reduced length and increased system performance. This moment was fundamental to level the understanding between the parties and review the items for the final delivery of the proposals.

The third sprint, held online, focused on discussing the submitted budgets and the solutions proposed by the suppliers. Alternative methods to the initial executive standard were analyzed, seeking greater alignment between the proposals and possible scope adjustments. With the adjusted budgets and scopes, the fourth sprint was held internally, involving Facilities, Engineering, Occupational Safety, and Procurement. At this stage, the comparative analysis of the proposals considered technical and financial criteria to define the supplier most aligned with the project, with comments and observations from each area, as illustrated in the lifecycle of the applied sprints.

As support for the process, the Work Breakdown Structure (WBS) was developed to organize the scope into work packages, bringing clarity about the activities involved and serving as a basis for a standardized scope model. The items defined in the WBS were organized into a backlog, representing the expected deliverables. Furthermore, visual tools such as Kanban assisted in tracking activities and organizing the stages. The standard scope spreadsheet, based on market models, was developed to standardize the receipt of pricing, containing a description of activities, units of measure, unit and total values, facilitating the final equalization of proposals.

The preparation of the quotation map, in the ninth stage, was the result of the analysis of the three budgetary proposals received by the Procurement team. This map was shared for cost approval, with the aim of presenting characteristics that compare and justify the hiring, demonstrating total transparency in the process. Points such as final value, guarantees, schedule, and responsibility matrix were evaluated. In general, the adopted structure brought more organization to the process and facilitated communication between the involved areas, evidencing the engagement of the teams and a better assessment before hiring the provider.

Results in defining and detailing the scope

The application of the Scrum methodology promoted a clear change in how the scope was built, transforming it from a static and poorly detailed document into a progressive development process, following the discussions held in the sprints. This collaborative format allowed for greater participation from all stakeholders, both internal and external. Areas such as Engineering, Occupational Safety, and Operations contributed more actively, and the service providers themselves brought relevant technical suggestions, enriching the scope throughout the process. This approach aligns with the premise of transparency, inspection, and adaptation of management with Scrum, according to Gomes (2022).

As a direct result of this approach, the final scope presented a significantly higher level of clarity. There was a better definition of activities, responsibilities, and execution criteria, which reduced the ambiguities that were common in the traditional model. This gain in clarity and detail is crucial, as, according to Brandstetter and Ribeiro (2019), failures in project definition are directly associated with increased costs and addendums. In the present case study, these failures were addressed and mitigated in advance, demonstrating the effectiveness of the methodology.

Another important benefit was the early alignment of critical project points. Aspects such as the execution sequence, interdisciplinary interferences, and operational impacts were discussed during the planning phase, which helped to avoid rework during execution. This anticipation of problems is a significant differentiator, as, according to Porto et al. (2023), scope problems are often perceived only during execution, generating extra costs. The applied methodology allowed these discussions to be anticipated and the scope adjusted before contracting, reducing inconsistencies.

Throughout the progressive validations in the sprints, it was possible to identify gaps that were not evident at the beginning of the project. Doubts, different interpretations, and even services that had not been initially considered arose, which were promptly adjusted and incorporated into the final scope. This capacity for continuous inspection and adaptation, pillars of Scrum, allowed the scope to evolve in a more complete and robust way. Although the process required greater team involvement and an initial time dedication in the planning phase, the gains obtained in terms of clarity and alignment indicate that the approach is viable and beneficial compared to the traditional model.

Results in proposal equalization and pricing

The improvement in scope definition had a direct and positive impact on the proposal equalization stage. By using common material, with standardized units of measure, clear execution criteria, and detailed and validated activities, providers began to present budgets more aligned with real activities and similar to each other. This standardization facilitated comparison between suppliers and reduced the subjectivity of the analysis, a common problem in the previous model, where very different proposals for the same service made the decision-making process complex and less reliable, compromising pricing accuracy.

A crucial point for improvement was the reduction in the time required for budget equalization. With the data already organized in a similar and standardized way, the Procurement team’s work became more agile, eliminating the need to extract information from long files to build the hiring map. Previously, equalization and map construction required seven business days, but with the application of the method, it was possible to develop this work in just four business days, representing a time optimization of approximately 43%.

Furthermore, the use of the method enabled the removal of frequent meetings that were previously requested from the Facilities team to explain the services, freeing up time and resources. The clarity of the scope, according to PMI (2021), is fundamental for the accuracy of cost estimates, and this premise was confirmed in the case study. The agile methodology also improved communication between parties, which was evidenced in practice, especially in the interaction with contractors and suppliers, as highlighted by Miranda and Alves (2023), contributing to an environment of greater collaboration and mutual understanding.

Another important perception obtained was the equality judgment by the providers. By using a standard spreadsheet, contractors were sure that all submitted budgets had the same activities and standards, which promoted a fairer and more transparent process. This standardization and scope detailing, combined with the agile methodology, contributed to more assertive pricing and greater cost control, resulting in a more transparent and justified quotation map, which evaluated the final value, guarantees, schedule, and responsibility matrix for the approval of the hiring.

In summary, the application of the agile Scrum methodology in the logistics shed renovation project proved to be an effective tool for scope management and contractor hiring. The transition from a traditional process, characterized by generalist scopes and misalignment, to an iterative and collaborative model resulted in greater clarity in technical definitions, reduced ambiguity, and optimized proposal equalization time. Although the methodology demands greater initial team involvement, the benefits in terms of cost predictability, reduction of contractual addendums, and assertiveness in decision-making confirm its viability and potential for civil engineering projects in dynamic and complex environments.

4. Conclusion

This study sought to evaluate the application of the agile methodology Scrum as a tool to support scope management in the renovation projects of a logistics warehouse, analyzing its impacts on the definition of activities, the equalization of service provider proposals, the predictability of costs during the contracting phase, and the alignment among internal stakeholders. It was verified that the adoption of the Scrum framework transformed the third-party contracting process, which was previously characterized by generalist scopes and divergent proposals, into a more structured and collaborative model. A significant improvement was observed in the clarity of technical specifications and greater alignment between internal teams and suppliers, which contributed to the reduction of ambiguities and the anticipation of critical project points. The structuring of activities into iterative cycles, with progressive validations, allowed the scope to evolve in a more complete and robust manner, incorporating technical suggestions and adjusting gaps identified throughout the process.

The study’s main practical contribution lies in demonstrating the feasibility of Scrum for scope management and assertiveness in contracting for civil engineering projects, especially in dynamic logistics environments. The standardization of proposals and the detailing of the scope resulted in a more agile and objective equalization, with an optimization of approximately 43% in the time required for this stage, in addition to promoting greater transparency and cost control. However, the application of the methodology presented limitations, such as the demand for greater involvement and availability of teams for meetings and the need for adaptation to the new work model, which sometimes required rescheduling. Additionally, changes requested by the client and the late hiring of the quality team generated contractual addendums and impacted the initial deadline. Despite these challenges, the gains in cost predictability, reduction of addendums, and assertiveness in decision-making confirm the effectiveness of the approach in complex contexts.

Bibliographic References

Brandstetter, M.C.G.O.; Ribeiro, H.R.O. 2019. Causas de custos adicionais e impacto financeiro em obras públicas sob a perspectiva da gestão de risco. Revista Ambiente Construído 20(1): 41-63.

Gomes, C.J.V. 2022. Metodologias ágeis aplicadas no processo de gerenciamento de um portfólio de projetos de infraestrutura. Trabalho de Conclusão de Curso. Pós-Graduação em Gestão de Projetos, Universidade de São Paulo, Piracicaba, SP, Brasil.

Kaiser, A.F. 2024. A. F. Planejamento de um projeto de construção civil, a partir do PMBOK 12(22): 21-36.

Miranda, R.G.; Alves, L.A. 2023. Gestão ágil aplicada à construção civil. Revista Boletim do Gerenciamento 36(1): 1-84.

Porto, A.L.G.; Maués, L.M.F.; Leite, E.L.; Diocesano, S.L. 2023. As consequências das falhas de gerenciamento do escopo em uma obra de um estádio de futebol. Simpósio Brasileiro de Gestão e Economia da Construção 13: Anais. ANTAC, Porto Alegre, RS, Brasil.

Project Management Institute [PMI]. 2021. Guia do conhecimento em Gerenciamento de Projetos (Guia PMBOK). 7ed. PMI, Newtown Square, PA, USA.

Ramos, R.Q. 2023. Estudo da viabilidade de implementação do método de gerenciamento Scrum na construção civil. Trabalho de Conclusão de Curso Bacharelado. Engenharia Civil Instituto Federal de Educação, Ciência e Tecnologia de Goiás, Goiânia, GO, Brasil.

Sawada, V.S.; Bertoletto, W. 2018 A integração do Guia PMBOK e do Scrum para o gerenciamento de projetos editoriais inovadores. Trabalho de Conclusão de Curso. Tecnologia em Gestão de Projetos, Universidade de São Paulo, Piracicaba, SP, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.