Lessons learned in project management in an energy distribution company
Lessons Learned in Project Management in an Energy Distribution Company
William Barbosa; Daniel Luis Garrido Monaro
DOI: 10.22167/2675-6528-202602442
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The lessons learned are crucial for organizational knowledge and improvement of future decisions. The present study aimed to identify and analyze the lessons learned in the management of an air conditioning systems automation project, focusing on the deviations between planning and execution and on the critical factors that impacted its performance. A qualitative case study was conducted, based on an air conditioning systems automation project in 21 units of a sports retail client, managed by a medium-sized company in the energy efficiency sector under a predictive approach. The methodology involved documentary analysis of project records and direct observation, comparing the planned with the executed in terms of scope, deadline, and cost, and identifying failures related to planning, communication, and supplier management. Significant weaknesses were identified in the initial planning, such as the absence of updated technical scope validation, resulting in approximately 50% of incompatible devices. The lack of contingency margins in the schedule generated accumulated delays of up to 177 days, and the underestimation of operational restrictions caused a 10.1% deviation in the budget, with additional unforeseen night labor costs. The lessons learned were systematized into standardized procedures for application in future projects. It was concluded that scope technical validation, risk management structuring, and the implementation of monitoring routines are crucial. The results reinforced the need for greater rigor in applying management practices in predictive projects with multiple units and high operational dependence, contributing to continuous improvement and project management maturity.
Keywords: Automation; Case study; Project management; Predictive methodology; Planning and control.
1. Introduction
Project management in contemporary organizations has become a fundamental pillar in the transition of business environments, which have evolved from low-demand scenarios to contexts of greater complexity and competitiveness. The application of structured project management practices allows for improved control over deadlines, costs, and scope, while also increasing the visibility of strategic initiatives for senior management and key stakeholders.
The adoption of structured project management practices contributes to greater predictability, strategic alignment, and organizational performance (Kerzner, 2017). In this sense, project management facilitates alignment between the various areas of the organization, promotes operational efficiency, and strengthens relationships with internal and external clients (Verzuh, 2016).
In the context of continuous organizational improvement, lessons learned emerge as an essential mechanism for incorporating knowledge generated during project execution. The Project Management Institute (PMI, 2021) defines lessons learned as the documentation, analysis, and dissemination of significant experiences that occurred throughout the project lifecycle. This process aims to inform future similar initiatives, transforming the rigorous identification of lessons learned into a strategic component for organizational excellence.
The structured systematization of lessons learned favors the reduction of costs and deadlines in subsequent projects, in addition to strengthening project management maturity in organizations (Kerzner, 2017). Studies show that organizations that implement formal processes for capturing lessons learned present a 23% lower rate of project delays and an 18% reduction in execution costs (Williams et al., 2012). The effective transfer of knowledge between projects also significantly reduces the learning time of teams, decreasing the adaptation curve to new methodologies and technologies (Disterer, 2002).
The importance of lessons learned transcends the merely operational aspect, acting as a central element in the construction of collective organizational knowledge. This allows the experiences of a specific project to be leveraged by the entire organization (Newell et al., 2006). This process of continuous organizational learning is fundamental for organizations to adapt to environmental changes and maintain their competitiveness in dynamic markets (Senge, 2006).
However, the effective capture of lessons learned does not occur automatically or intuitively. There are several challenges in implementing lessons learned processes, including the cultural resistance of teams to document failures, the lack of dedicated time for reflection and systematization, the absence of structured methodologies for collection and analysis, and the difficulty in transferring captured knowledge into concrete practices in new projects (Schindler & Eppler, 2003). Overcoming these obstacles requires intentionality, process structuring, and organizational commitment to continuous improvement.
Given the challenges in capturing and systematizing lessons learned, and considering the strategic importance of this process for continuous improvement, the need arises for empirical investigations that examine, in depth, how lessons learned manifest in real project execution contexts. It is relevant to understand which critical factors impact the performance of projects under a predictive approach and how the systemic analysis of these factors can generate lessons learned applicable to future similar initiatives. The present work aimed to analyze the application of project management in conducting an air conditioning system automation project, focusing on the evaluation of deviations between planning and execution, as well as on the identification of lessons learned throughout the project lifecycle.
2. Material and Methods
The present study was characterized as a qualitative research, adopting the case study strategy. According to Yin (2015), this approach is suitable for in-depth investigation of contemporary phenomena in their real context, especially when the boundaries between the phenomenon and the context are not clearly defined. The methodological focus was the analysis of an air-conditioning system automation project, considering its organizational and operational particularities.
The empirical object consisted of an air conditioning system automation project, conducted by a medium-sized company in the energy efficiency sector. This project involved the implementation of automation devices in approximately 21 units of a sports retail client, distributed across several Brazilian states, such as São Paulo, Rio de Janeiro, Rio Grande do Sul, Ceará, Paraná, Distrito Federal, and Bahia. The project management predominantly followed the predictive methodology.
After the contractual formalization, the scope, schedule, and costs were defined, elements that guided the planning, execution, monitoring, and control of activities. The project involved the participation of several stakeholders, including the project manager, the technical team, the procurement department, and the executing partners. Each of these actors played specific roles and responsibilities throughout the project lifecycle.
The study development was structured in sequential methodological steps. Initially, the object of study was delimited, characterizing the project, the organizational context, and the main stakeholders involved. Then, information was gathered and organized through the collection of internal project documents, such as the project charter, sales contract, follow-up emails, outsourced team contracts, and kickoff meeting minutes.
The sequence of the main activities developed throughout the project was outlined to understand the operational flow. In the planning stage, the project schedule was elaborated using a control spreadsheet. This spreadsheet detailed the activities by unit, execution deadlines, responsible parties, and task dependencies, serving as the primary tool for monitoring project performance.
The project execution occurred sequentially, with the mobilization of regional technical teams for the installation of automation devices in the units. Activities included validation of local conditions, equipment installation, and operational testing. Monitoring was carried out through a control spreadsheet, updated weekly with the status of activities, pending issues, and occurrences. Weekly follow-up meetings were conducted with the client and teams to discuss progress and corrective actions.
The data analysis was performed through a systematic comparison between the project’s planning and execution, focusing on scope, schedule, and cost. In terms of scope, changes and divergences in the planned deliverables were analyzed. Regarding the schedule, deviations between planned and actual dates were verified, identifying delays. For cost, the financial impacts of inconsistencies were assessed, including budget variations and additional costs. The data for this comparison were extracted from formal records, such as the tracking spreadsheet, meeting minutes, and electronic communications.
The identified deviations were compared with the best practices described in the Project Management Body of Knowledge (PMBOK) (PMI, 2021). The objective was to identify gaps between the practice adopted in the project and the recommendations from the literature. This analysis covered knowledge areas such as Integration Management, Scope, Schedule, Costs, Communications, and Risks, allowing for an in-depth understanding of the causes of deviations and their impacts on project performance.
The collection of lessons learned was conducted in a structured manner, employing the project retrospective analysis methodology. Multiple data sources were used, including documentary analysis of project records, direct observation by the researcher during the execution of activities, and mapping of critical events. The collected data were organized and synthesized to identify patterns, causal relationships, and insights into the management practices implemented.
The lessons learned were organized into a structured sheet, including the problem description, root cause analysis, impact generated, lesson learned, recommendation, and applicability in future projects. This organization occurred around the project lifecycle phases, covering initiation, planning, execution, and monitoring and control, aiming to transform operational experiences into reusable knowledge and standardized procedures.
3. Results and Discussion
The analysis of the management of the air conditioning systems automation project revealed significant deviations between the initial planning and the execution, directly impacting the scope, schedule, and cost. The study identified that weaknesses in the planning phase, especially in the technical validation of the scope and risk management, were the main factors contributing to the observed inconsistencies. These findings are crucial for understanding the challenges inherent in predictive projects with multiple units and high operational dependency, providing a solid basis for identifying and systematizing lessons learned.
The initial project planning was formalized with the definition of scope, deadline, and cost premises, covering execution in 21 units, an estimated deadline of 294 days, and a budget of R$ 300,000.00. However, the fundamental premise that the automation devices would be compatible with the unit layouts, based on technical surveys conducted in 2024, proved to be flawed. The absence of an updated technical validation before the start of execution was a critical factor that compromised the planning accuracy and generated substantial deviations.
Regarding the scope, approximately 50% of the planned automation devices were not compatible with the actual conditions of the units. This incompatibility resulted from structural changes in the environments that were not considered in the initial planning, highlighting the lack of a formal process for updated technical validation. According to the data, 32.7% of the devices required some type of scope adjustment, confirming the fragility of the initial premise and generating an additional total cost of R$ 13,030.00 for the necessary modifications.
The identification of these incompatibilities occurred only in the execution phase, and not during planning, which contradicts the best practices of scope management recommended by the Project Management Institute (PMI, 2021). The absence of an updated technical review before the start of activities not only compromised the scope but also limited the effectiveness of risk management. Projects based on imprecise assumptions tend to underestimate relevant risks, increasing the probability of cost and schedule deviations, as argued by Flyvbjerg (2023).
Regarding the schedule, the planning foresaw the sequential execution of the 21 units, with an average duration of 14 business days per unit, but did not include contingency margins. This omission resulted in the inability to absorb operational deviations, generating accumulated delays throughout the project. The detailed analysis revealed that 16 out of the 21 units registered delays exceeding 30 days, with an average deviation of 62 days and extreme cases reaching 126 calendar days in units such as Belo Horizonte/MG. The maximum accumulated delay in the project was 177 days, according to the study summary.
These delays were not isolated events, but a systemic pattern that reflected the inadequacy of deadline planning and the lack of flexibility to deal with unforeseen circumstances. The absence of contingency buffers, an essential practice in complex projects, made the schedule vulnerable to any change in field or operational conditions. The direct relationship between schedule performance and revenue generation was evidenced by the billing, which did not reach the initially projected amount of R$ 300,000.00 for the period.
In the financial aspect, the project presented a total deviation of R$ 30,400.00, representing an increase of 10.1% over the initial budget of R$ 300,000.00. The largest isolated impact was the additional cost of R$ 28,500.00 for night labor, which had not been foreseen in the original planning. This need arose due to unmapped operational restrictions, such as the requirement for complete de-energization of the environments for energy monitoring, which made execution during business hours unfeasible.
Other additional costs included R$ 7,300.00 for the replacement of incompatible equipment, R$ 4,400.00 for logistics and transportation due to access reprogramming, R$ 3,800.00 for on-site adjustments not foreseen in the contract with partners, and R$ 2,000.00 in penalties for failure to control access requests to the units. The combination of these underestimated variables in the planning phase demonstrates the importance of correctly identifying assumptions and constraints in financial planning, as highlighted by Kerzner (2022) and Shah et al. (2023).
Risk management was conducted in a limited way, without the adoption of a structured methodology or formal tools, such as a probability and impact matrix or a risk register. Risk identification occurred qualitatively, based on participants’ experience during the “kickoff” meeting, but without continuous monitoring or defined response plans. This weakened approach compromised the ability to anticipate problems, resulting in the materialization of critical risks that directly impacted the project’s scope, schedule, and cost.
The absence of a structured risk management process is particularly relevant in predictive projects, where the early definition of scope, deadlines, and costs requires greater rigor in planning. The PMBOK (PMI, 2021) emphasizes that risk identification must be directly based on a clear and validated scope, as risks emerge from project deliverables, activities, and constraints. Recent studies (Hussein & Moradinia, 2023) corroborate that deficiencies in initial planning, especially in defining scope and risks, are among the main causes of delays and cost overruns.
Communication with the client and the involved teams, although carried out through weekly follow-up meetings, proved insufficient due to the absence of a formal “follow-up” process. This gap hindered the timely identification of operational bottlenecks and misalignments, contributing to the spread of problems. The failure to control access requests to the units, which should have been made with a minimum advance notice of three business days, generated additional costs and impacted operational efficiency.
The importance of “follow-up” as a structuring practice in project management is fundamental for the quality of communication among stakeholders. Edmondson (2020) highlights that environments that favor open communication and constant “feedback” enable early problem identification. Complementarily, Karten (2020) emphasizes that clarity and frequency in communication are determinants for avoiding rework and coordination failures, especially in projects involving multiple agents and operational dependencies, such as the one analyzed.
Lessons Learned and Procedures Generated
Based on the analysis of deviations and critical factors identified, the study systematized the lessons learned in a structured format, which included the description of the situation, root cause analysis, generated impact, lesson learned, and recommendation on how to avoid or better leverage them in future projects. This process allowed for the transformation of operational experiences into reusable knowledge, contributing to the continuous improvement of project management within the organization.
The lessons learned were converted into standardized procedures for application in future projects. Among the main actions generated, the mandatory implementation of updated technical scope validation before execution, the structuring of formal “follow-up” routines with clear definition of responsibilities and deadlines, and the inclusion of operational restrictions in the pricing phase stand out. Additionally, the adoption of schedules with contingency margins and the creation of a continuous risk register with periodic monitoring were established, aiming to mitigate the recurrence of observed problems.
In summary, the results obtained demonstrate that the deviations identified in the automation project were not isolated events, but a reflection of structural weaknesses in planning and execution management. The comparative analysis between the planned and the executed, combined with the systematization of lessons learned, clearly highlighted the main critical factors that compromised the project’s performance. Technical scope validation, structuring of risk management, and implementation of monitoring routines are crucial for the success of predictive projects with similar characteristics, reinforcing the need for greater rigor in applying management practices for continuous improvement and organizational maturity.
4. Conclusion
The present study aimed to analyze the application of project management in conducting an air conditioning system automation project, focusing on the evaluation of deviations between planning and execution, as well as on the identification of lessons learned throughout the project lifecycle. It was found that the initial project planning presented significant weaknesses, especially in the absence of updated technical validation of the scope, which resulted in approximately 50% of devices being incompatible with the actual conditions of the units. The lack of contingency margins in the schedule was also observed, causing accumulated delays of up to 177 days, and the underestimation of operational constraints, such as the need for night labor, which generated a 10.1% budget deviation. Risk management was found to be conducted in a limited manner and communication with stakeholders proved insufficient, hindering the timely identification of obstacles. Based on these findings, lessons learned were systematized into standardized procedures, contributing to the continuous improvement of project management in the organization and reinforcing the need for greater rigor in applying management practices to predictive projects with multiple units and high operational dependency.
Despite the relevance of the results, the study was based on a single case, which limits the generalization of the findings. The researcher’s role as project manager may have introduced a bias in the analysis, even with the use of formal documentation. Additionally, data collection was restricted to documentary sources and direct observation, without the inclusion of stakeholder interviews, which reduced the scope of perspectives. The absence of formal risk management tools and a structured lessons learned register also limited the depth of the retrospective analysis. For future studies, it is suggested to conduct multi-case research, involving automation projects in different companies and segments, in order to broaden the validity of the results. It is recommended to investigate the effectiveness of formal risk management tools, such as the probability and impact matrix, and the exploration of hybrid management models (predictive and adaptive) in predictive projects, evaluating the contribution of iterative control cycles to the reduction of scope, schedule, and cost deviations.
Bibliographic References
Disterer, 2002 [Referência completa não encontrada no documento original]
Edmondson, Amy C. 2020. The fearless organization: Creating psychological safety in the workplace for learning, innovation, and growth. Wiley, Hoboken, USA.
Flyvbjerg, Bent; Gardner, Dan. 2023. How big things get done: the surprising factors that determine the fate of every project. Crown Currency, New York, USA.
Hussein, B.; Moradinia, S. 2023. Integration of Risk, Cost and Schedule in Project management. Journal of Systems Science and Engineering.
Karten, Naomi. 2020. Effective Communication for Technical Professionals. Dorset House Publishing, New York, USA.
Kerzner, Harold. 2017. Project Management: A systems approach to planning, scheduling, and controlling. 12. ed. John Wiley & Sons, Hoboken, USA.
Kerzner, Harold; SALADIS, Frank P. 2018. Value-driven project management. 2. ed. John Wiley & Sons, Hoboken, USA.
Newell et al., 2006 [Referência completa não encontrada no documento original]
Project Management Institute (PMI). 2021. A guide to the project management body of knowledge (PMBOK® Guide). 7. ed. PMI, Newtown Square, USA.
Schindler & Eppler, 2003 [Referência completa não encontrada no documento original]
Senge, 2006 [Referência completa não encontrada no documento original]
Shah, S. A. R.; Bhatti, A. A.; Ahmed, I. 2023. Impact of project management practices on project success. Engineering Proceedings, v. 44, n. 1.
Verzuh, Eric. 2016. The fast forward MBA in project management. 5. ed. John Wiley & Sons, Hoboken, USA.
Williams et al., 2012 [Referência completa não encontrada no documento original]
Yin, R. K. 2015. Estudo de caso: Planejamento e métodos. 5. ed. Bookman, Porto Alegre, RS, Brasil.