FEL-AWP-BIM Integration in Industrial Project Sequencing

Integration of Fel-awp-bim in the Sequencing of Industrial Projects

Ramon Barreto Amora; Carolina Rossi de Oliveira

DOI: 10.22167/2675-6528-202601359

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

The study addressed the challenges of productivity, costs, and deadlines in infrastructure projects, often caused by process fragmentation. It proposed and preliminarily validated an integration model between Front-End Loading (FEL), Advanced Work Packaging (AWP), and Building Information Modeling (BIM) to optimize sequencing. A simulated case study of the Morro do Moreno Tourist-Commercial Cable Car was conducted, using a comparative quasi-experimental design. In Scenario A (baseline), planning remained segmented, while in Scenario B (integration), the Path of Construction (PoC), hierarchical work package breakdown, and validation via 4D BIM simulation were established. Schedule Performance Index (SPI), Cost Performance Index (CPI), Information Quality (RFI), and constructability indicators were analyzed. The results showed a significant increase in predictability (SPI from 0.85 to 0.98) and cost efficiency (CPI from 0.90 to 1.00) in Scenario B. The 4D simulation allowed for the early detection and resolution of 12 space-time conflicts, reducing rework and improving adherence to sequencing. It was concluded that the FEL-AWP-BIM integration transformed planning into a production assurance process, offering a viable path to elevate execution maturity in capital projects.

Keywords: Virtual construction; Capital project management; Constraint management; Governance; Advanced planning.

1. Introduction

Large-scale capital projects, especially in the infrastructure sector, face recurring challenges of productivity, cost overruns, and schedule delays. Such failures are not solely attributed to technical complexity but to organizations’ inability to integrate processes, information, and agents throughout the project lifecycle. The literature shows that structural fragmentation between strategic planning, engineering, procurement, and execution is one of the main causes of performance loss in infrastructure projects (CONSTRUCTION INDUSTRY INSTITUTE, 2015). This disarticulation prevents a holistic and coordinated view, resulting in rework and reduced predictability. Although Integration Management is essential to ensure coherence and alignment of objectives, its practical application is often superficial, limited to status reports, without a robust model that articulates methods, technologies, and decisions systemically (KPMG, 2020). This integration gap generates substantial value losses and increases the risks inherent in large-scale projects.

In this scenario, several methodologies and technologies seek greater discipline and predictability. Front-End Loading (FEL) is crucial for the progressive definition of scope and feasibility assessment in the initial phases, aiming to mitigate risks (MERROW, 2011). However, its effectiveness is limited when the transition to execution is not adequately structured. Advanced Work Packaging (AWP) proposes a construction-driven planning logic, structuring work into execution packages starting from the Path of Construction (PoC) to ensure input availability. Although it presents proven gains, late adoption or misalignment with the initial phases reduces its impact, and its implementation faces cultural and contractual barriers (CONSTRUCTION INDUSTRY INSTITUTE; COAA, 2013; SINGH; WILLCOX, 2021). In parallel, Building Information Modeling (BIM) emerges as an integrating technology, offering a common data environment and enabling four-dimensional (4D) constructive simulations, which link the 3D model to the schedule to validate sequencing and detect conflicts (EASTMAN et al., 2018). Despite its potential to improve constructability, BIM’s effectiveness depends on factors such as interoperability and digital maturity, and its isolated use, without governance and integration with planning methodologies, limits its strategic value (MCGRAW HILL, 2020). Thus, the individual relevance of FEL, AWP, and BIM does not resolve fragmentation, requiring an approach that aligns methodologies, technologies, and organizational structures in a coherent governance model.

Given the persistence of fragmentation and the isolated application of promising methodologies and technologies, it becomes imperative to develop and validate models that promote systemic and continuous integration throughout the lifecycle of capital projects. This work is inserted in this context, addressing the need to overcome the limitations of traditional approaches to elevate execution maturity and predictability in complex ventures. The general objective of this study is to propose and validate an integration model between Front-End Loading (FEL), Advanced Work Packaging (AWP), and Building Information Modeling (BIM) to optimize the sequencing of infrastructure projects. To this end, a simulated case of the Morro do Moreno Tourist-Commercial Cable Car is used as the object of study, aiming to verify how the early and coordinated articulation of these three approaches contributes to the effective structuring of work packages and to the validation of executive sequencing through 4D simulation, increasing the predictability of costs and deadlines and transforming planning into a proactive production assurance process.

2. Material and Methods

This research was classified as applied, seeking to generate knowledge for practical application in the integration of processes in capital projects. Regarding its objectives, it was characterized as exploratory, by seeking initial evidence on the benefits of integration between Front-End Loading (FEL), Advanced Work Packaging (AWP), and Building Information Modeling (BIM). Additionally, it was explanatory, testing the causal relationship between integration and project indicator performance. The central technical procedure adopted was a simulated case study, with a comparative quasi-experimental design between distinct scenarios.

The object of study consisted of a simulated project for a tourist-commercial cable car, connecting Morro do Moreno to Morro da Marinha, located in the state of Espírito Santo. This undertaking included boarding and alighting stations, towers, cables, cabins, civil-electromechanical interfaces, access, and support services. The technical-managerial context was reconstructed from the researcher’s own artifacts, such as the Project Charter, Feasibility Study, and Project Execution Plan, which provided the factual basis for the simulation of the FEL-1, FEL-2, and FEL-3 phases, as well as the integrated application of AWP and BIM (3D and 4D).

The study’s scope was focused on planning and coordination, specifically on the planning and validation of sequencing, without encompassing the actual physical execution of the project. There was no population or sample in the statistical sense, as it was a simulated case study. The unit of analysis was the two comparative scenarios developed: Scenario A (baseline) and Scenario B (integrated model). The data selection criteria were based on the researcher’s authorial documentation, which provided the inputs for the construction and simulation of these scenarios, ensuring fidelity to the project’s technical-managerial context.

The sources and instruments used for data collection included various artifacts from the simulated case. Among them, the Project Charter, the Feasibility Study, the Project Execution Plan (PEP), the preliminary Project Breakdown Structure (WBS), the Cost Database, and the Risk Matrix stood out. Additionally, Gate checklists for the FEL-2 and FEL-3 phases were used, containing objective rubrics, a CWA-CWP-IWP decomposition matrix, a Constraint Log for recording restrictions, a Path of Construction (PoC) protocol, and evidence from the 4D BIM simulation, such as spatio-temporal conflict reports.

To validate the proposed model, the simulation was structured in two comparative scenarios. Scenario A, named Baseline, represented the traditional planning practice, characterized by segmentation by disciplines, without the structuring of work packages (AWP) or the use of 4D simulation for validation. In contrast, Scenario B, named Integrated Model, applied the integration between FEL, AWP, and BIM, establishing the Path of Construction (PoC), performing the hierarchical decomposition of Construction Work Areas (CWA) into Construction Work Packages (CWP) and Installation Work Packages (IWP), and carrying out the validation of the sequencing through 4D simulation.

The research operationalization occurred in four main stages. The FEL-1 and FEL-2 phases involved consolidating the justification, objectives, initial scope, stakeholders, assumptions, and constraints, based on the Project Charter and the Feasibility Study, culminating in the issuance of Gate FEL-2. Subsequently, in the FEL-3 phase, integrated with the WBS, the Path of Construction (PoC) was conducted to restructure the project into Construction Work Areas (CWAs). Examples of CWAs included the Morro do Moreno Station, the Marine Station, the Towers & Cables, and the Accesses/Infrastructure, organizing the scope constructively.

The hierarchical breakdown of CWAs into Engineering Work Packages (EWP), Procurement Work Packages (PWP), and Installation Work Packages (IWP) was performed, defining the predecessors, interfaces, and release rules for the IWPs. In Scenario B, operationalization considered an ongoing project, with packages in different states and active constraints classified by categories such as material, method, environment, labor, and machine. The Constraint Log was used as a governance mechanism to release work fronts, ensuring that readiness was met according to objective criteria before physical execution.

The 4D BIM simulation stage consisted of linking the schedule activities to the three-dimensional model, allowing for the verification of space-time conflicts, the analysis of logistical windows, and the identification of access and storage restrictions. This simulation was crucial for validating the logical sequencing and anticipating potential interferences. For consistency and traceability purposes, the analysis was conducted as a “snapshot” of the project on a specific cut-off date, April 8, 2026. This date corresponded to the last completed IWP and the IWP in progress at the study’s operational base, providing a temporal scope for the evaluation.

For the integrated model performance analysis, four main propositions were tested: P1 (Schedule), which evaluated the simulated Schedule Performance Index (SPI) elevation; P2 (Cost), which verified the simulated Cost Performance Index (CPI) improvement; P3 (Quality), which analyzed the reduction of requests for information (RFI) and the effectiveness in logging constraints (Constraint Log); and P4 (Constructability), which investigated the reduction of space-time conflicts detected in the 4D simulation. These indicators were fundamental to quantifying the benefits of the proposed integration.

The analytical treatment of the data involved synthesis into a comparative matrix between Scenario A and Scenario B, complemented by simple graphs and discussion. Quantitatively, the means of the performance indicators were compared, and where applicable, the effect size was indicated. Qualitatively, a thematic analysis of the barriers and enablers of integration was performed, in addition to *pattern matching* between the findings and propositions P1-P4. The validity and reliability of the results were reinforced by triangulation of artifacts and the 4D model, by the chain of evidence, and by the explicit statement of the study’s methodological assumptions and limitations.

The research ethical procedures were rigorously observed. The data used in the study were classified as non-sensitive, as they derived exclusively from the researcher’s authorial documentation, without involving personal information of individuals or confidential company data. All records generated during the research, including protocols, minutes of simulated meetings, evidence of the 4D simulation, and restriction logs, were kept in an organized and accessible manner. This practice ensured the traceability and integrity of the information used, allowing for academic auditing of procedures and results, in accordance with the ethical guidelines applicable to final course projects.

The research presented some methodological limitations inherent to its design. The simulation performed, although robust, did not replace the actual physical execution of the project, which restricted direct causal inference from the results. Performance indicators, such as SPI, CPI, and PPC, were used as *proxies* based on controlled estimates and hypotheses, rather than as Actual Values from a real project. The 4D model used was representative, with a level of detail compatible with planning decisions, which limited the granularity in detecting minor conflicts. However, the approach was considered adequate for the preliminary validation of the proposed conceptual model.

3. Results and Discussion

The results and discussion of this study provide significant evidence on the impact of the integration between Front-End Loading (FEL), Advanced Work Packaging (AWP), and Building Information Modeling (BIM) on the sequencing and performance of capital projects. The comparative analysis between Scenario A (traditional planning) and Scenario B (integrated model) revealed substantial improvements in key indicators of schedule, cost, information quality, and constructability, corroborating the initial research propositions.

The FEL governance and constraint management, central elements of Scenario B, were operationalized to connect project definition maturity to execution readiness. The FEL-2 and FEL-3 Gates, rather than being mere binary approval points, functioned as objective maturity filters, conditioning the advancement of definitions and preventing the transition of incomplete information to the execution phases. In the analyzed scope, the flexibility of Gate FEL-3 to remain partial/pending while engineering, procurement, and risk requirements are stabilized is a differentiator. This proactive approach strongly contrasts with the traditional model, where a lack of maturity in the initial phases frequently results in rework and delays in later stages, as pointed out by Merrow (2011), who emphasizes the critical importance of FEL for the success of megaprojects. Structured constraint management, consolidated in a Constraint Log with standardized classification by categories (material, method, environment, labor, and machine), allowed for visibility, traceability, and early treatment of impediments. This transformed Scenario B into a “constraint-managed” regime, where the absence of constraints is not presumed but actively managed to protect performance and enhance planning reliability. Project management literature, such as that from KPMG (2020), often highlights the superficiality with which integration is treated, reducing it to status reports. The present study, however, demonstrates that a robust model that articulates methodologies and technologies systemically, like the one proposed, can overcome this limitation, ensuring that work package release decisions are based on objective readiness criteria.

The structuring and decomposition of the scope through AWP and Path of Construction (PoC) represented a fundamental reconfiguration of planning in Scenario B. Instead of a discipline-driven (“push”) flow, planning became “construction-driven”, where the sequence of assembly and field execution defines the needs and deadlines for engineering and procurement. This inversion of the traditional logic broke down disciplinary fragmentation, adopting Construction Work Areas (CWAs) as primary management units. The hierarchical decomposition of CWAs into Construction Work Packages (CWP), Engineering Work Packages (EWP), Procurement Work Packages (PWP), and Installation Work Packages (IWP) ensured traceability between planning, readiness, and execution. Figure 1 of the original document, which represents the traditional schedule, illustrates the discipline-based chaining, where interdependencies with engineering and procurement are less visible, resulting in a “push” flow. In contrast, Figure 2 of the original document, showing the integrated schedule with work packages, highlights the reconfiguration of sequencing to be construction-driven, organized by packages and oriented towards the PoC. This change is crucial for constructability from the initial FEL-2 phases, as advocated by the Construction Industry Institute (CII) and Construction Owners Association of Alberta (COAA, 2013) in their AWP guidelines. Late adoption or misalignment of AWP with the initial phases, as observed in many projects, reduces its impact, but the integration proposed in this study mitigates this problem by incorporating AWP from FEL-3.

The decomposition of the project into CWAs, as illustrated in Figure 3 of the original document, acts as the “backbone” of AWP, concentrating construction packages and their respective engineering and procurement packages. This allows for readiness release to be applied systematically and audibly, ensuring that each work front is truly “ready-to-work”.

Source: Original research results

Figure 4. 4D planning by work packages

The operationalization of 4D planning by work packages, as presented in Figure 1 (originally Figure 4), demonstrates how executive sequencing transcends a mere list of isolated activities, coming to reflect deliverable fronts of execution, coherent with the PoC and conditioned by the AWP readiness criteria. This integrated visualization, often consolidated in analytical dashboards like Power BI, acts as a “control tower”, integrating planning information, work packages, and constraints in a single layer of analysis. This approach is fundamental for proactive decision-making, allowing project managers to identify bottlenecks and constraints before they impact physical execution. The ability to visualize the progress and readiness status of work packages in real-time, as demonstrated, is a significant advancement over traditional static schedules, which often fail to capture the complexity of interdependencies in capital projects (EASTMAN et al., 2018).

Source: Original research results

Figure 5. Supplier delivery tracking (PWP)

Complementarily, Figure 2 (originally Figure 5) illustrates the monitoring of supplier deliveries associated with work packages, reinforcing the integration between procurement and execution. This visualization is crucial to demonstrate that the release of work fronts depends not only on logical sequencing but also on the synchronization between engineering, supply, and field. The lack of synchronization between these areas is a common cause of delays and cost overruns in capital projects, according to the Construction Industry Institute (2015). By integrating the PWP (Procurement Work Package) directly into the AWP flow, the proposed model reduces the risk of premature release of activities without the necessary inputs, ensuring that materials and equipment are available at the right place and time. This minimizes waiting time, optimizes site logistics, and improves overall supply chain efficiency, a critical aspect for productivity in large-scale projects. Procurement management, when disconnected from construction planning, can generate significant additional costs due to inadequate storage, losses, or delivery delays, problems that the FEL-AWP-BIM integration seeks to proactively mitigate.

The comparative analysis of performance indicators between scenarios A and B, summarized in Table 1, quantifies the benefits of the proposed integration.

Table 1. Comparison of indicators

Indicator

Scenario A (Traditional)

Scenario B (Integrated)

Observed Impact

P1: Simulated SPI

0.85 (latent delay)

0.98 (adherence)

Relative gain in predictability of approximately 15.3% (SPI: 0.85 → 0.98)

P2: Simulated CPI

0.90 (rework)

1.00 (budgeted)

Relative improvement in cost efficiency of approximately 11.1% (CPI: 0.90 ← 1.00), associated with the reduction of rework and waiting

P3: RFI/Restrictions

Higher incidence of RFI and restrictions treated reactively (baseline)

Reduction and anticipation of constraint treatment (Constraint Log)

Higher information quality and greater plan reliability, with removal/mitigation of restrictions before the release of IWPs (“constraint-managed”)

P4: 4D Conflicts

Not detected (high risk)

12 detected/resolved

Buildability gain

Source: Original research results

The P1 proposition (Schedule) was validated with a relative gain in predictability of approximately 15.3% in the Schedule Performance Index (SPI), which rose from 0.85 in Scenario A (latent delay) to 0.98 in Scenario B (adherence). This result is particularly relevant, as an SPI below 1.00, as in Scenario A, indicates that the project is behind schedule, suggesting inefficiencies and potential unplanned shutdowns. The “latent delay” in Scenario A, although the schedule might have seemed logical in project management software, operated “blind” to the site’s geometric constraints and interdependencies not visible in traditional disciplinary planning. The improvement to 0.98 in Scenario B demonstrates that the FEL-AWP-BIM integration, by establishing the PoC, decomposing the scope into work packages, and validating sequencing via BIM 4D, allowed for more precise and proactive time management. This corroborates literature emphasizing the importance of robust and advanced planning for capital project performance (MERROW, 2011; CONSTRUCTION INDUSTRY INSTITUTE, 2015). Merrow (2011) argues that the FEL phase, when well executed, is a significant predictor of success, and integration with AWP and BIM enhances this capability by extending planning maturity to execution. In practice, an SPI close to 1.00 means the project team can rely significantly more on the schedule, optimizing resource allocation, minimizing idle time for teams and equipment, and reducing the need for costly acceleration. The ability to anticipate and resolve space-time conflicts, such as those identified in the 4D simulation, translates into less rework in the field, greater operational safety, and a more predictable supply chain, directly impacting the organization’s ability to deliver projects on time to stakeholders.

The P2 (Cost) proposition was also validated, with a relative cost efficiency improvement of approximately 11.1% in the Cost Performance Index (CPI), which evolved from 0.90 (rework) in Scenario A to 1.00 (budgeted) in Scenario B. A CPI of 0.90 in Scenario A indicates that the project was spending more than planned for the work performed, a common symptom of rework, delays, and inefficiencies. Achieving a CPI of 1.00 in Scenario B demonstrates that the integrated model allowed the work to be executed within the planned budget, mainly due to the reduction of rework and waiting times. This improvement is directly linked to the greater predictability and constructability achieved in Scenario B. Literature, such as the McGraw Hill report (2020) on the value of BIM for infrastructure, highlights that the adoption of integrated technologies can lead to significant cost savings through process optimization and error reduction. The fragmentation of planning in Scenario A, without the structuring of work packages or 4D validation, resulted in additional costs arising from reactive decisions and the late discovery of problems. In contrast, the “constraint-managed” approach of Scenario B, by ensuring that work packages were released only when “ready to work,” avoided the premature mobilization of resources and the execution of activities with incomplete information, which are primary sources of waste and cost overruns. The practical implications of a CPI of 1.00 are vast: better budget control, lower risk of cost overruns, optimization of material and service procurement, and reduction of contractual claims and disputes. This allows organizations to allocate their financial resources more efficiently, freeing up capital for other investments and increasing project profitability.

Proposition P3 (Information Quality) was confirmed by the transition from a “higher incidence of RFIs and reactively handled constraints” in Scenario A to a “reduction and anticipation of treatment” in Scenario B. The effectiveness in registering constraints via the Constraint Log was a determining factor. In Scenario A, the lack of a structured mechanism to manage constraints resulted in a constant flow of RFIs, indicating information gaps and interface problems discovered only during execution. This generated interruptions, delays, and the need for reactive engineering. In Scenario B, the FEL-AWP-BIM integration, with its maturity Gates and the Constraint Log, ensured that information was matured and constraints were identified and mitigated proactively. This aligns with KPMG’s (2020) vision on the need for governance and objective alignment to overcome the superficiality of integration. The reduction of RFIs and proactive constraint management have direct implications for information quality and planning reliability. Fewer RFIs mean fewer interruptions in the field, less engineering time spent on emergency responses, and greater clarity for execution teams. The Constraint Log, by acting as a governance mechanism, ensures that work fronts are only released when they are “ready-to-work”, avoiding rework, unexpected stoppages, and consequently improving team productivity and morale. This translates into a safer and more efficient work environment, with less waste of resources and greater adherence to quality standards.

The P4 proposition (Constructability) was validated by the “reduction of spatio-temporal conflicts detected in the 4D simulation”, moving from “undetected (high risk)” in Scenario A to “12 detected/resolved” in Scenario B, resulting in a “constructability gain”. In Scenario A, the absence of 4D simulation meant that interface conflicts and site geometric constraints would only be discovered during physical execution, generating costly rework and delays. The 4D BIM simulation in Scenario B acted as proof of the PoC, allowing for the early detection and resolution of conflicts invisible in traditional Gantt charts.

Source: Original research results

Figure 10. 4D validation of the powertrain lifting sequence

As evidenced in Figure 3 (originally Figure 10), the 4D validation of the powertrain lifting sequence allowed for the adjustment of the fronts’ positioning before physical mobilization. This is a clear example of how 4D BIM technology, as described by Eastman et al. (2018), transforms planning from a static exercise into a dynamic, spatio-temporal validation. The ability to simulate complex operations, such as lifting heavy components, months before execution, allows for optimization of logistics, ensuring safety, and avoiding costly disruptions. The 4D simulation also revealed critical impact points, such as access and logistics conflicts, and interferences in lifting and crane reach. The optimization of the overlap between the structural assembly of the stations and the transport routes for heavy components, for example, avoided logistical blockages that would have forced work fronts to a standstill. Similarly, the simulation of the cable car tower installation, as per Figure 11 of the original document, demonstrated control over the reach of simultaneously operating cranes, ensuring the technical feasibility of the attack strategy. These virtual validations are crucial for constructability, as they allow value engineering to be applied proactively, significantly reducing the risk of rework and accidents in the field. The practical implications are immense: increased operational safety, optimized site layout, reduction of schedule delays due to physical collisions, and better coordination between engineering, procurement, and construction teams. The ability to “see” the project unfold in time and space before the first shovel of earth is moved is a competitive advantage that elevates execution maturity and project predictability.

The detailed analysis of financial and schedule performance, using Earned Value Management (EVM), reinforces the findings. Table 2 presents an example of a calculation sheet per package/activity, illustrating the logic of SPI and CPI in the comparison between scenarios.

Table 2. Example of EVM calculation (comparison between scenarios)

Scenario

Package/Activity (example)

Planned Value

Earned Value

AC Real

schedule performance index (SPI)

cost performance index

The Traditional

Civil works (example)

BRL 200,000.00

BRL 180,000.00

BRL 210,000

0,90

0,86

Electrical installations (example)

BRL 300,000.00

BRL 240,000

BRL 280,000

0,80

0,86

Mechanical assembly (example)

BRL 500,000.00

BRL 430,000

BRL 454,444

0,86

0,95

Total for A

BRL 1,000,000

BRL 850,000

BRL 944,444

0,85

0,90

B Integrated

Civil works (example)

BRL 200,000.00

BRL 200,000.00

BRL 200,000.00

1,00

1,00

Electrical installations (example)

BRL 300,000.00

BRL 290,000

BRL 290,000

0,97

1,00

Mechanical assembly (example)

BRL 500,000.00

BRL 490,000.00

BRL 490,000.00

0,98

1,00

TOTAL B

BRL 1,000,000

BRL 980,000.00

BRL 980,000.00

0,98

1,00

Source: Original research results

In Scenario A (Traditional), civil works presented an SPI of 0.90 and CPI of 0.86, electrical installations SPI of 0.80 and CPI of 0.86, and mechanical assembly SPI of 0.86 and CPI of 0.95. The consolidated total for Scenario A was SPI=0.85 and CPI=0.90, reflecting latent delay and inefficiencies associated with the reactive discovery of constraints. The electromechanical package, with an SPI of 0.80, was the most affected, indicating that the lack of cleared fronts by civil works tends to paralyze assembly, a classic problem of disciplinary fragmentation. In contrast, in Scenario B (Integrated FEL-AWP-BIM), civil works achieved SPI=1.00 and CPI=1.00, electrical installations SPI=0.97 and CPI=1.00, and mechanical assembly SPI=0.98 and CPI=1.00. The consolidated total for Scenario B was SPI=0.98 and CPI=1.00, consistent with the logic of readiness-based release and active constraint management. These values, although simulated and based on controlled premises, demonstrate the causal mechanism of integration: each work package (IWP) is virtually validated and governed by readiness before being released to the field, reducing rework and waiting. The improvement in performance indicators is not just a reflection of the individual efficiency of each package, but of the synergy generated by integration, which allows for coordination between disciplines and anticipation of problems.

The FEL-AWP-BIM integration, therefore, transforms planning from an estimation exercise into a production assurance process. FEL governance, by acting as a risk mitigator, prevents the advancement of immature engineering into the field, making constraints visible, categorized, and traceable. AWP, in turn, restructures the schedule based on the assembly logic, ensuring workflow continuity and reducing the probability of rework. BIM 4D, as a validation tool, allows for the adjustment of logistical and lifting strategies months before physical mobilization, enhancing constructability and safety.

In summary, the FEL-AWP-BIM model has consolidated itself as a strategy capable of transforming the management of infrastructure projects, offering the transparency and predictability required by the contemporary market. The analysis, although based on a simulated case study, offers a practical and preliminarily validated roadmap for the application of integration in future ventures, mitigating sequencing failures and increasing the predictability of costs and deadlines. Methodological limitations, such as the simulated nature of the study and the use of performance indicators as proxies, have been explicitly stated and considered adequate for the preliminary validation of the conceptual model. It is recommended that future works apply this model in real execution environments to measure the impacts of unforeseen external variables, such as climatic variations and market fluctuations, in order to further strengthen the causal inference of the results.

4. Conclusion

It is concluded that the objective was achieved, as this study proposed and validated an integration model between Front-End Loading (FEL), Advanced Work Packaging (AWP), and Building Information Modeling (BIM) to optimize the sequencing of infrastructure projects. The model’s application in a simulated case of the Morro do Moreno Tourist-Commercial Cable Car demonstrated significant gains in schedule and cost predictability, with improvements in SPI and CPI indices, in addition to a notable increase in information quality and constructability. FEL governance, scope structuring via AWP, and BIM’s 4D validation acted synergistically to transform traditional planning into a proactive production assurance process, overcoming fragmentation and reactivity.

However, it is essential to acknowledge the inherent limitations of this work. The simulated nature of the study, while controlled to highlight the causal mechanism, does not replicate the complexity of real-world execution. Performance indicators, such as SPI and CPI, were used as proxies based on controlled estimates and hypotheses, and the 4D model, although representative, had a level of detail that limited the detection of minor conflicts. To strengthen causal inference and fully validate the model, it is recommended that future studies apply this integrated approach in real execution environments, measuring the impacts of unforeseen external variables, such as weather conditions and market fluctuations.

Bibliographic References

Construction Industry Institute (CII). 2015. Benchmarking & Metrics Report. CII, Austin.

Construction Industry Institute (CII); Construction Owners Association of Alberta (COAA). 2013. Advanced Work Packaging: From Project Definition through Site Execution. CII, Austin.

Eastman, C.; Teicholz, P.; Sacks, R.; Liston, K. 2018. BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers, and Contractors. 3 ed. Wiley, New Jersey.

KPMG. 2020. Global Construction Survey 2020: Value of Resilience. KPMG, Londres.

McGraw Hill. 2020. The Business Value of BIM for Infrastructure (SmartMarket Report). McGraw Hill Construction, Bedford.

Merrow, E. 2011. Industrial Megaprojects: Concepts, Strategies, and Practices for Success. Wiley, New Jersey.

Singh, V.; Willcox, D. 2021. Barriers to Advanced Work Packaging implementation in construction projects. Journal of Construction Engineering and Management 147(6).

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.