Implementation of the OEE indicator in a furniture factory
Andressa Pereira de Castro Massardi; Karina Tonelli Silveira Dias
DOI: 10.22167/2675-6528-202600564
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Operational efficiency is crucial for industrial performance, directly influencing market competitiveness. This study aimed to structure and implement the Overall Equipment Effectiveness (OEE) indicator in a furniture factory, using the project lifecycle to conduct the initiative in an organized manner. The research adopted an action-research approach, with the researcher’s direct participation in the initiation, planning, execution, and closure stages of the project. To ensure that the use of the indicator reflected an improvement in production delivery according to the plan, the data collection method and the methodology for its routine treatment were defined. The results indicated that the application of the project lifecycle phases increased data reliability, enhanced team engagement, and allowed for the identification of previously unmeasured production losses. An increase of 11.75% in the OEE indicator and a significant improvement in production delivery were observed. It was concluded that the formalization of OEE implementation as a project promoted integration between areas, process standardization, and the sustainability of its use in managing production processes.
Keywords: Lifecycle; Operational efficiency; Project management; Continuous improvement; Industrial production.
1. Introduction
The contemporary industrial environment is characterized by intense competitiveness, which demands that organizations adopt structured performance measurement systems. Such systems are crucial for supporting control and continuously improving production processes (Kaplan; Norton, 1997). In this context, the sustainability of organizational results intrinsically depends on systematic routine management, which is based on rigorous monitoring of indicators, comparison with pre-established goals, and proactive action on deviations identified in the process (Falconi, 2013).
Faced with this pressing need, the “Overall Equipment Effectiveness” (OEE) indicator has been consolidated as a widely used tool to evaluate the operational performance of equipment. Its application allows for the identification and quantification of the various losses that negatively impact the production process (Busso, 2012). OEE emerged in the context of “Total Productive Maintenance” (TPM) and was conceived to analyze the overall efficiency of equipment, considering losses related to three fundamental dimensions of operation (Nakajima, 1988).
The three dimensions of OEE are availability, performance, and quality. Availability refers to the proportion between the time the equipment was effectively productive and the time it was able to operate, encompassing losses associated with downtimes, whether planned or unplanned. Performance, in turn, assesses the production rate, comparing the actual operation with the standard time established by process engineering and identifying speed reductions. Quality, on the other hand, measures the proportion of conforming products, considering losses due to scrap and rework (Chirardia, 2004). This integrated approach offers a holistic view of production efficiency.
The complexity inherent in the implementation of OEE requires structured management so that the indicator is effectively incorporated into the production routine. In this sense, treating it as an organizational project is the most appropriate approach. Projects are essential mechanisms that organizations use to enable changes and achieve specific strategic objectives (Vargas, 2016). Project management, therefore, involves detailed planning, resource control, and systematic coordination of activities throughout their execution, aiming to ensure the achievement of the proposed results (Kerzner, 2017).
Project management is structured in process groups that guide the conduct of activities throughout the project lifecycle. These groups comprise the initiation, planning, execution, and closure phases, as outlined by the “Project Management Institute” (PMI, 2017). This structure provides a set of practices, techniques, and tools that are fundamental to assisting in the planning and conduct of initiatives aimed at organizational improvement (Gomes, 2006), ensuring a methodological and consistent approach.
Another critical factor for the success of any project is stakeholder management. The proactive identification and engagement of individuals who can influence or be impacted by the project are fundamental to ensuring organizational alignment and the necessary support for implementing the proposed changes (PMI, 2017). In the specific context of OEE implementation, this aspect gains even more relevance, as it significantly contributes to the integration between the production area and the various support sectors, promoting collaboration and minimizing resistance.
Performance measurement, from a broader perspective, is understood as the quantification of the efficiency and effectiveness of organizational actions. It plays a crucial role in guiding behaviors and supporting the implementation of business strategies (Neely et al., 1995). From this viewpoint, the use of indicators in decision-making transcends the mere availability of data, requiring the adoption of methods that guide their analysis and application. Among these methods, the PDCA cycle (“Plan, Do, Check, Act”) stands out, enabling the transformation of information into improvement actions, contributing to more consistent decisions and the continuous enhancement of processes (Deming, 1986).
Despite the undeniable importance of performance indicators for industrial management, many companies still face difficulties in obtaining reliable data and effectively using this information to support decision-making. In several cases, this problem manifests as a discrepancy between planned production and effectively realized production. This practical gap indicates an inefficiency that compromises the organization’s competitiveness and responsiveness.
Faced with this scenario, a company with low adherence between the planned and the executed decided to implement the OEE indicator as a way to understand the losses in the production process and, consequently, improve its performance. Thus, this work aims to structure the implementation of the OEE indicator in a production process, using an approach based on project management, based on the project life cycle, seeking to ensure its consistent and sustainable use over time.
2. Material and Methods
The present study was characterized as a research of an applied and explanatory nature, seeking to solve a practical problem in a specific organizational environment and identify the factors that contribute to a given phenomenon (Cervo et al., 2007). The research was conducted in a furniture industry, located in the Zona da Mata mineira.
Action research was adopted as the methodological design, with the researcher’s direct participation in the investigated reality and in the change process (Gil, 2008; Thiollent, 2011). This approach allowed for planned interventions and the active implementation of the proposed actions, structured based on project management practices.
A mixed-methods approach was used (Creswell, 2010). The quantitative aspect focused on the analysis of the Overall Equipment Effectiveness (OEE) of the eleven selected machines and the production plan fulfillment index, comparing results before and after implementation. The qualitative approach was based on participant observation, records of project meetings and PDCA groups, and the perceptions of those involved.
To organize the project stages, a Work Breakdown Structure (WBS) was developed, which allowed the scope to be decomposed into hierarchical levels, facilitating the planning, execution, and control of activities (Kerzner, 2017). The project followed the phases of initiation, planning, execution, and closure, as outlined by the Project Management Institute (PMI, 2017).
In the initiation phase, the need to implement OEE on machines with the greatest impact on production delivery was formalized. Stakeholders were identified in a meeting with factory leadership (quality, maintenance, PPC), using the “brainstorming” technique (PMI, 2017). Risks such as low operator experience and unreliable data were identified as inputs for planning.
The planning phase involved defining activities, resources, deadlines, and responsibilities (Maximiano, 2014). The software “Syneco Production” was selected for automatic collection of OEE data, installing counting devices (sensors) on the eleven machines, connected to an industrial network. The system was run on servers to automatically store, process, and calculate the indicators.
The PDCA cycle was defined as a work method for the treatment and analysis of results, incorporating it into the factory’s routine for continuous improvement (Deming, 1986; Ishikawa, 1993). A detailed schedule was developed, with an estimated duration and definition of responsibilities, which was verified weekly in meetings with the factory leadership.
The execution phase consisted of implementing the OEE monitoring system on the selected machines. It included the installation and parameterization of sensors, software configuration, and operator training. Connecting the machines to the “Syneco” software was the first activity of this stage (Kerzner, 2017).
In parallel, operators recorded the justifications for the downtimes in the system. The stoppages were classified into categories such as mechanical corrective, electrical corrective, scheduled breaks, setup, lack of material, and operational adjustments. The data were consolidated daily by the system, which calculated the OEE from its three components: availability, performance, and quality.
The data analysis occurred in weekly meetings with the participation of the production, maintenance, and quality areas. In these meetings, identified deviations were addressed through the PDCA cycle, with definition of actions and monitoring of results. The closing phase included the consolidation of results, performance evaluation, and recording of lessons learned (Maximiano, 2014).
Guidelines were established for incorporating indicator tracking into operational routine, aiming to ensure the continuity of monitoring and support decision-making. Lessons learned, challenges, and success factors were recorded for future expansions of monitoring to other factory machines.
3. Results and Discussion
The implementation of the Overall Equipment Effectiveness (OEE) indicator in the furniture factory provided enhanced visibility into productive performance, revealing significant improvement opportunities. This scenario was particularly relevant due to the plant’s early stage of operations and the operators’ still limited experience. Detailed analysis of the results demonstrated that structuring the initiative through the different phases of the project lifecycle contributed decisively to the effective implementation of OEE, allowing the project to be executed in a relatively short period and with strict adherence to the previously established schedule. This systematic approach, as advocated by the Project Management Institute (PMI, 2017), was fundamental to the initiative’s success.
Initiation
In the initiation phase, the analysis of identified risks revealed that human factors held as much relevance as the technical aspects of the project. The operators’ limited experience, combined with initial resistance to changes in work routine, indicated that the implementation of performance indicators transcends the mere adoption of technology, crucially depending on cultural and behavioral factors. This perception aligns with Kerzner’s (2017) view, which emphasizes the direct relationship between project success and stakeholder alignment, as well as the effective management of their expectations throughout the entire implementation process.
During this initial stage, strategic actions were implemented to identify and align the stakeholders involved in the project. Meetings were held with managers to establish the scope, define primary needs, and ensure alignment regarding the use of information generated by OEE. The maintenance area was engaged from the beginning through periodic alignments, ensuring the necessary technical support for the equipment. Additionally, continuous communication was established with the Production Planning and Control (PPC) and Quality areas, facilitating data monitoring and supporting both production planning and process standards control.
The identification of stakeholders and their engagement strategies were crucial for the project’s progress. Managers, with a high level of influence and interest, were directly involved in discussions about infrastructure and data utilization. Operators, with medium influence and high interest, received training and frequent communication. Maintenance, with medium influence and interest, participated in weekly alignments. PCP and Quality, both with high interest, had their collected data shared to support their respective functions. These actions contributed significantly to interdepartmental alignment and the organization of subsequent project stages, minimizing resistance and uncertainties (Maximiano, 2014).
It was observed that teams involved from the project’s inception showed less resistance during the implementation phase. This behavior reinforces the importance of early stakeholder engagement, as highlighted by the PMI (2017) as a critical success factor in projects. The need for constant communication between different areas also proved essential, evidencing the relevance of integration among those involved to mitigate uncertainties and manage risks throughout the project lifecycle, according to Maximiano’s (2014) perspective on project management.
Planning
The planning phase involved the detailed definition of activities, resource allocation, deadline establishment, and responsibility assignment, outlining the guidelines for project execution (Maximiano, 2014). In this stage, the actions necessary for the implementation of the OEE indicator were carefully organized, aiming to ensure stricter control and effective alignment among all involved areas. The selection of the 11 most critical machines for monitoring was a strategic point, concentrating efforts on the equipment that had the greatest impact on the factory’s productive performance.
The prioritization of the most critical machines proved to be a correct decision, as it allowed resources to be focused on the points of greatest impact on productive performance. It was found that most of the losses were concentrated in a small number of equipment, which is in line with the principle of problem prioritization, widely discussed in quality literature by authors such as Falconi (2013). This approach optimized resource use and directed improvement actions to where they would have the greatest effect on the factory’s overall efficiency, maximizing the project’s return on investment.
The definition of the data collection infrastructure also highlighted the complexity inherent in the digitalization of the industrial environment. The incorporation of digital technologies in industry, as pointed out by Schwab (2016), is not restricted solely to investments in systems, but requires profound adaptations in processes and organizational culture. The process of collecting and calculating OEE, using the “Syneco Production” software, begins with counting devices and sensors installed on the machines, which transmit data to an industrial communication network. This data is then processed to calculate OEE and presented on dashboards for monitoring.
Data reliability is a crucial aspect, and inadequate sensor installation or incorrect part counting could significantly compromise the indicator’s calculation. For this reason, during planning, the positioning of each sensor was meticulously defined, taking into account the operational particularities of each machine. This stage highlighted the importance of conducting the OEE indicator implementation based on the project lifecycle, allowing for the anticipation and mitigation of problems that could arise if the mapping and configuration were not detailed and precise, ensuring the integrity of the information.
The adoption of the PDCA cycle (Plan, Do, Check, Act) as a basis for data treatment and analysis proved to be an adequate and effective methodology. According to Deming (1986), the continuous improvement of processes depends on successive cycles of planning, execution, verification, and action. The integration between OEE monitoring and PDCA application enabled the transformation of raw data into structured improvement actions. The PDCA cycle was used to organize actions into multifunctional groups, involving managers, operators, and support areas, allowing for the definition of goals, execution of activities, verification of results, and implementation of necessary adjustments, promoting systematic control and structured problem identification (Ishikawa, 1993).
Based on this detailed planning, a schedule was developed that estimated the duration of activities and defined responsibilities, contributing to the organization and control of the project implementation. This schedule was reviewed weekly in meetings with factory leadership and those responsible for actions, ensuring the project remained on track and that any deviations were promptly identified and corrected. This practice of continuous monitoring was essential to maintain alignment and communication between teams, ensuring the fluidity and effectiveness of the execution of subsequent steps.
Execution
The project execution phase consisted of implementing the OEE indicator monitoring system on the previously selected machines. This included the installation and parameterization of sensors, the configuration of the “Syneco Production” software, and the training of operators for the correct use of the tool. Connecting the machines to the software was the first activity, establishing the technological basis for automatic data collection. This initial step was crucial for transforming planning into operational reality, in accordance with the project management principles outlined by Kerzner (2017), who emphasizes resource coordination and the fulfillment of deliverables.
During implementation, it was found that technical execution represented only part of the challenge, with the adaptation of operational routine being an equally critical factor. Initially, inconsistencies were identified in the collected data, requiring technical tests and adjustments to the machines, especially related to sensor positioning and adaptation to specific operating conditions. The variability of the production process demanded changes in the data collection logic, demonstrating that the implementation of solutions in industrial environments requires flexibility and adaptability, a point emphasized by Kerzner (2017) regarding project management in dynamic contexts.
Resistance was observed from operators regarding the correct recording of downtime, especially during periods of high production demand, where the priority was the execution of activities over data collection. This behavior highlighted a conflict between operations and the data recording discipline, temporarily impacting the consistency of analyses. Resistance to change is a common phenomenon in organizational transformation processes, as pointed out by Kotter (1997), requiring proactive leadership to engage teams and overcome the cultural challenges inherent in implementing new practices.
In this context, the leadership’s performance and the execution of training were fundamental to consolidating the use of the monitoring system. With the team’s maturation, a significant improvement in the quality of records and greater adherence to established procedures were observed. This evolution resulted in the reduction of unjustified downtime, which fell from 995 in March to 87 in December, indicating a notable increase in information reliability. This outcome reinforces the importance of operational discipline and process standardization for the effectiveness of management systems, as discussed by Falconi (2013), and the relevance of stakeholder management techniques.
In parallel, the PDCA cycle was employed as a structuring tool for addressing identified deviations. Its application occurred in the weekly OEE monitoring meetings, which involved the production, maintenance, and quality teams. Data collected by the software were analyzed at the beginning of each meeting, allowing the identification of the main losses of the period. Based on these analyses, corrective actions were defined, assigned to those responsible, and monitored throughout the following week, ensuring that problems were addressed systematically and effectively, promoting continuous improvement.
In subsequent meetings, the results of the implemented actions were verified, making it possible to evaluate the effectiveness of the interventions and, when applicable, the standardization of improvements. Throughout the implementation period, four complete PDCA cycles were carried out. The evolution of the OEE indicator, which increased from 48.58% in March to 60.33% in December, with peaks of 65.33% in November, evidenced the effectiveness of the method’s application. This 11.75% increase in the OEE indicator demonstrates that deviations were identified and addressed in a structured manner, contributing to process improvement and increased organizational efficiency, according to Deming (1986).
To evaluate the performance of Overall Equipment Effectiveness, the world-class OEE concept of 85% is used as a reference, an ideal standard to be achieved by organizations (Silva, 2020). Despite the evolution observed in the OEE indicator, the results still indicate that the factory’s production process requires continuity in improvement efforts. Thus, the execution phase was characterized not only by the implementation of the technological solution but also by the structured application of continuous improvement methods and the consolidation of new operational standards, fundamental elements for sustaining results over time.
Closing
The project closure phase consisted of finalizing activities, including consolidating the results obtained, evaluating overall performance, and recording lessons learned. This stage is crucial to ensure proper project closing and generate valuable input for future initiatives (Maximiano, 2014). The data compiled during the execution phase were associated with the evolution of the production delivery outcome, allowing for a comprehensive analysis of the impact of OEE implementation on the factory’s operational performance.
In the months prior to the systematic monitoring of the OEE indicator, specifically from January to March, a downward trend was observed in the production delivery rate, with values ranging from 78.97% in January to 75.32% in March. From April onwards, however, with the implementation and systematic monitoring of machine efficiency, the production delivery rate showed consistent improvement, reaching 96.31% in October and 92.05% in December. This increase in production delivery demonstrates that the identification and treatment of process bottlenecks, facilitated by OEE, were effective in boosting performance.
A closing meeting was held with the participation of the leadership from all involved areas to analyze the data and validate the gains achieved. After this analysis, the OEE indicator implementation project was considered effective in the factory’s production process. The difficulties encountered throughout the process were recorded in a specific document, which will serve as a reference for future consultation, allowing the acquired knowledge to be capitalized on in new initiatives and in the expansion of monitoring to other factory machines, according to the guidelines established for continuous management.
In summary, structuring the implementation of OEE as a project, following the lifecycle of initiation, planning, execution, and closure, proved to be an effective approach to enhance operational efficiency. The results showed an 11.75% increase in the OEE indicator and a significant improvement in production delivery, driven by increased data reliability, team engagement, and precise identification of production losses. This methodology not only introduced a measurement tool but also promoted integration between areas, process standardization, and the sustainability of its use in continuous production management.
4. Conclusion
This study sought to structure the implementation of the Overall Equipment Effectiveness (OEE) indicator in a furniture factory, using the project lifecycle to ensure its consistent and sustainable use. It was found that the application of the project lifecycle phases was crucial for the initiative’s success, resulting in an 11.75% increase in the OEE indicator, which rose from 48.58% to 60.33%. In parallel, a significant improvement was observed in the production delivery rate, which evolved from 75.32% to 92.05%, with peaks of 96.31%. The systematic approach allowed for increased data reliability, elevated team engagement, and the identification of productive losses that were previously unmeasured. The formalization of OEE implementation as a project proved to be a relevant practical contribution, transforming the measurement tool into an operational management instrument that promoted integration between areas, process standardization, and the sustainability of its use in the production routine.
Despite the positive results, the study presents some limitations. The project was conducted in an environment in the initial phase of operational stabilization, which made it difficult to isolate the impact of OEE from other natural factors of production process maturation. Additionally, seasonal variations in demand and product mix at the factory compromised consistent comparison between the analyzed periods. Another limitation lies in its application to a single production unit and a specific set of equipment, which restricts the generalization of results to other industrial contexts. The monitoring period, limited to ten months, did not allow for the evaluation of long-term effects on operational performance. For future studies, it is suggested to expand OEE monitoring to other factory machines and conduct longitudinal research that assesses the indicator’s impact in more stable operational scenarios and over longer periods, in order to consolidate the understanding of its sustainability and generalization.
Bibliographic References
Busso, C.M. 2012. Análise da eficiência global de equipamentos (OEE) em sistemas produtivos. Dissertação (Mestrado em Engenharia de Produção), Universidade Federal de Santa Catarina, Florianópolis, SC, Brasil.
Chirardia, A. 2004. Utilização do indicador de eficiência global de equipamentos na gestão e melhoria contínua dos equipamentos: um estudo de caso na indústria automobilística. Dissertação (Mestrado em Engenharia de Produção), Universidade Federal do Rio Grande do Sul, Porto Alegre, RS, Brasil.
Falconi, 2013 [Referência completa não encontrada no documento original]
Kaplan, R.S.; NORTON, D.P. 1997. The Balanced Scorecard: translating strategy into action. Boston, MA, USA: Harvard Business School Press.
Kerzner, H. 2017. Project management: a systems approach to planning, scheduling, and controlling. 12. ed. Hoboken, NJ, USA: John Wiley & Sons.
Nakajima, S. 1989. Introduction to TPM: total productive maintenance. Cambridge, MA, USA: Productivity Press.
Project Management Institute [PMI]. 2017. A guide to the project management
Vargas, R.V. 2016. Gerenciamento de projetos: estabelecendo diferenciais competitivos. 8. ed. Rio de Janeiro, RJ, Brasil: Brasport.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq