Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The modernization of public tenders in Brazil, driven by Law no. 14.133/2021, sought greater transparency and efficiency in resource management. The study analyzed the main changes and impacts of this legislation on the contracting of engineering services through electronic bidding, focusing on the participation of companies without technical capacity in the bidding phase and its effects on price formation and the efficiency of tender processes. To this end, an applied, descriptive, and exploratory research was conducted, using multiple case studies and documentary analysis of three tender processes from small municipalities in Minas Gerais. Data were collected from public portals and analyzed based on variables such as reference values, submitted proposals, discount percentages, number of participants, disqualifications, and duration of the tenders. The results showed that the inversion of phases, by allowing the participation of companies without prior qualification, favored the submission of aggressive proposals, generating distortions in price formation, increased delays, and risks of non-executability. In contrast, the adoption of prior qualification contributed to greater competitive balance and better alignment of proposals with market values. It was concluded that the effectiveness of the legislation depends on how it is applied, and it is recommended to consider the complexity of the object in defining the order of the phases.
Keywords: Electronic competition; Administrative efficiency; Prior qualification; Infeasibility; Engineering services.
1. Introduction
Public works are fundamental for national development, encompassing activities such as renovation, recovery, expansion, or construction of public heritage (TCU, 2014). In Brazil, the modernization of public bidding processes has become essential to ensure greater transparency, efficiency, and control over public resources. This need intensified particularly after the implementation of Law no. 14.133/2021, which sought to address historical challenges in public contracting.
The concept of public bidding is defined as an administrative procedure through which the public administration seeks to meet its needs, allowing all interested parties to submit proposals under specific conditions (Di Pietro, 2020). The purpose of the bidding process is to select the most advantageous proposal for the public administration (Mascena, 2017). The new Law no. 14.133/2021 (Brazil, 2021) introduced several changes aimed at improving the implementation of these processes, centralizing them and unifying their disclosure through platforms such as the National Public Procurement Portal (Toledo, 2021).
Historically, public procurement in Brazil, previously governed by Law no. 8.666/1993 (Brazil, 1993), has been associated with challenges such as bureaucracy, corruption, and diversion of public funds. The evolution of bidding processes has consistently sought to increase formalization and introduce stricter rules to combat these issues (Alves, 2021). Although bureaucracy can be seen as an obstacle to administrative agility, its correct implementation is crucial for transparent processes, ensuring that public interests are respected and minimizing corruption risks. Thus, continuous monitoring of the new law’s application is vital for improvements, oversight, optimization, and quality in public procurement.
Despite the advances, the current model of electronic bidding, especially regarding phase inversion, presents specific challenges. This inversion allows companies to participate in the bidding phase without prior technical qualification, which can lead to the submission of aggressive proposals. Such dynamics can distort price formation, increase process slowness, and elevate the risks of contractual non-performance. This scenario can generate a “false economy,” where apparently lower prices do not result in an effective reduction of public costs, but rather in an increase of contractual risks, such as delays, abandonment of works, and the need for re-contracting and administrative rework. These issues highlight a possible fragility in the relationship between the planning of acquisition requirements and their application during the conduct of the bidding process, impacting the quality of competition.
The effectiveness of the new legislation depends directly on how it is applied, making it essential to consider the complexity of the object when defining the order of phases. Understanding these dynamics is crucial to ensure that public works projects are executed by truly qualified suppliers, resulting in more efficient and effective public procurement. Thus, the objective of the study was to analyze the procurement management of public works in the state of Minas Gerais, through electronic bidding, focusing on the participation of companies without technical capacity in the bidding phase and their impacts on efficiency and price formation in bidding processes.
2. Material and Methods
The research conducted was characterized as applied, with a descriptive and exploratory methodological approach, according to the classification proposed by Gil (2010). To achieve the study’s objective, the strategy of multiple case studies was employed, complemented by a documentary analysis. This approach allowed for an in-depth investigation of contemporary phenomena in their real contexts, aligning with Yin’s (2015) methodological guidelines.
The unit of analysis consisted of three specific bidding processes, conducted in the electronic bidding modality, related to public works. These contests were carried out by city halls located in the state of Minas Gerais, in small municipalities, with populations ranging between 3,000 and 12,000 inhabitants. The processes studied included works in Brás Pires, Senador Firmino, and Lima Duarte, covering both standard models and an exception model.
The selection of bidding processes was based on specific criteria: the occurrence of disqualification and declassification of companies, the similarity in the size of the municipalities involved, and the adherence of the auctioned objects to the research focus. These criteria aimed to enable an effective comparison between the analyzed cases, allowing for the identification of relevant patterns and dynamics.
Data collection was carried out through documentary analysis, using public domain information. The database was formed from documents accessible on transparency portals, official gazettes, and electronic bidding platforms, such as Licitar Digital (2026) and BLL (2026).
The collected data were organized into a summary table and descriptive graphs. The analyzed variables included the reference value of the work, the final proposal values, the discount percentages, the number of participants, the number of disqualified companies, the duration of the process, and the reasons for disqualification. These indicators were fundamental for constructing a comparison between the studied processes.
For the analysis, the “Project Management Body Of Knowledge” [PMBOK] Guide (PMI, 2017) was adopted as a reference, focusing on the area of procurement management. This framework allowed for the examination of bidding processes from the perspective of planning, conducting, and controlling acquisitions, complementing the normative analysis based on Law No. 14.133/2021 (Brazil, 2021).
In procurement planning, the elements present in the tender documents and public documents were analyzed, such as the object of the contract, reference value, qualification requirements, and established conditions, verifying their adequacy to the nature and complexity of the works. For the conduct, the selection of suppliers and the competitive dynamics were analyzed, considering participants, proposal values, discounts, phase order, and disqualifications, aiming to verify the effects on price formation and the effectiveness of the contracting.
In the procurement control stage, the recorded results were evaluated, considering the duration of the bidding process, the need for due diligence, rework in the analysis of documents and proposals, reasons for disqualification or exclusion, and identified risks to contracting efficiency, including impacts related to the infeasibility of proposals.
The data analysis was carried out through a comparative approach between cases, seeking to identify recurring patterns in price formation, bidder participation, and the outcome of tenders, in line with the social research procedures described by Gil (2017). Additionally, a normative analysis was conducted, based on Law no. 14.133/2021 (Brazil, 2021), and a literature review to deepen the understanding of the central concepts and previous studies on the new legislation. To protect the identity of the companies involved, all publicly collected information was presented anonymously.
3. Results and Discussion
The analysis of the bidding processes revealed distinct patterns in the conduct of electronic tenders, with direct implications for efficiency and price formation. In two of the three processes examined, a predominance of the lowest price criterion was observed, without an in-depth evaluation of the competitors’ spreadsheets. This approach resulted in delays in the delivery of works, increased administrative slowness and, in some cases, the need to initiate new bidding processes for the completion of projects. In contrast, the third process demonstrated a differentiated approach, with the technical qualification phase preceding the bidding phase, which positively impacted the outcome of the tender.
The protection of the identity of the companies involved in the contests was ensured, with the collected information being presented publicly and anonymously. The multiple case study methodology, following Yin’s (2015) guidelines, allowed for an in-depth and comparative analysis of competitive dynamics, pricing patterns, and contest outcomes. This approach was complemented by the normative analysis of Law no. 14.133/2021 (Brazil, 2021) and by confrontation with the principles of Procurement Management from the PMBOK (PMI, 2017), offering an integrated perspective between project management and public procurement.
Process 1
The first bidding process analyzed, concerning the construction of a roof and changing rooms in Brás Pires, occurred in the electronic bidding modality, with the lowest price judgment criterion. The reference value of the work was established at R$ 640,730.22. During the bidding phase, several proposals were submitted, with the winning one offering a final value of R$ 195,000.00, which represented a significant discount of 69.57% compared to the reference value. This sharp discrepancy between the estimated value and the final proposal raised questions about the feasibility of the offer and the sustainability of the contract.
The distribution of discounts presented by suppliers evidenced a pattern of aggressive proposals, with several bidders offering reductions greater than 25% of the reference value. This dynamic, although apparently advantageous for public administration, may indicate pricing patterns potentially incompatible with the execution of the object. Law no. 14.133/2021 (Brazil, 2021) advocates that the acceptance of proposals should not be limited to the lowest price, requiring verification of economic viability and rigorous analysis of justifications for proposals with indications of inexecutability.
The slowness of the bidding process was a critical point, attributed to the participation of companies that did not have the qualification documentation in accordance with the Requirements in the bidding phase. Four suppliers were disqualified or deemed ineligible. Supplier 16, with a discount of 69.57%, was disqualified for not submitting the updated proposal and the requested feasibility declaration. Supplier 15, with a 34.14% discount, was deemed ineligible for presenting a technical capacity certificate incompatible with the object and for the absence of proof of the technical responsible’s link and registration with the professional council (CREA), thus failing to meet the technical qualification requirements.
Additionally, Supplier 14, who offered a 26.65% discount, was disqualified after an analysis by the engineering department which verified the non-conformity of its Technical Record Certificate (CAT) with the tender’s requirements. Similarly, Supplier 13, with a 26.47% discount, was also disqualified due to the inadequacy of its CAT. These cases illustrate the fragility in the relationship between the planning of acquisition requirements and their application during the conduct of the bidding process, according to the perspective of Procurement Management from the PMBOK (PMI, 2017), where the planning stage is crucial for defining the qualification criteria.
The presence of companies without real execution conditions in the bidding phase, even if subsequently disqualified, distorted the competitive dynamic. By submitting aggressive bids, these companies pressured prices to artificially low levels, leading other bidders to adjust their offers in response to technically unsustainable competition. This phenomenon resulted in a “false economy”, where bids with discounts significantly higher than 25% of the reference value did not generate effective public cost reduction, but rather increased contractual risks, such as delays, abandonment of work, and the need for re-contracting and administrative rework.
Process 2
The second process analyzed, for the construction of the headquarters of the Municipal Health Secretariat in Senador Firmino, was also an electronic bidding with phase inversion. The reference value of the tender was R$ 485,812.82. The winning bid, for R$ 347,000.00, represented a discount of 28.57% compared to the value estimated by public administration. As in the first case, this process also showed a pattern of proposals with aggressive discounts, indicating the presence of potentially unfeasible offers.
The analysis of the proposals revealed that more than one company offered a discount greater than 25% of the reference value of the work, which reinforces the pattern of risk of infeasibility. The competitive dynamic, by allowing the participation of companies without prior qualification, resulted in an increase in administrative diligence and process slowness. The verification of documentation and the qualification of bidders, which should have been smoother stages, became bottlenecks due to the need to analyze and justify proposals with values well below market.
In this tender, five companies were disqualified or eliminated. Supplier 12, with a 28.57% discount, was disqualified for not presenting the updated proposal and the feasibility declaration. Supplier 11, with a 28.39% discount, was disqualified due to irregularities in the corporate structure and absence of proof of business continuity. Supplier 10, with a 23.86% discount, was disqualified for not presenting a technical responsibility certificate issued by CREA/CAU, with the registration of the responsible technician. Supplier 9, with a 21.80% discount, was disqualified for not sending the requested documents within the deadline. Supplier 8, with a 20.73% discount, was disqualified for presenting an expired federal regularity certificate.
The occurrence of multiple disqualifications and debarments, even after the bidding phase, reaffirms the perception that phase inversion can compromise the efficiency and quality of contracting. The participation of companies that do not meet the technical, economic, or legal qualification requirements in the competitive phase generates administrative rework and prolongs the total time of the bidding process. This dynamic, instead of promoting agility, contributes to slowness and uncertainty regarding the effective contracting of a qualified supplier, negatively impacting Procurement Management (PMI, 2017).
Process 3
The third bidding process examined, concerning street paving in Ibitipoca, in the municipality of Lima Duarte, presented a distinct approach. With a reference value of R$ 1,523,227.41, this tender adopted prior bidder qualification, meaning the qualification phase preceded the bidding phase. The winning bid was R$ 1,489,000.00, resulting in a 2.25% discount compared to the reference value. This percentage difference, significantly smaller compared to previous processes, suggests a more balanced competitive environment and bids more aligned with market values.
The prior qualification allowed for effective filtering of companies, ensuring that only bidders with adequate technical capacity, fiscal regularity, and economic qualification participated in the bidding phase. Initially, nine companies participated in the process. After the qualification stage, five companies were disqualified for various reasons. Supplier 5 did not prove the minimum technical capacity for the item “Soil Subgrade Regularization and Compaction”. Supplier 6 did not prove operational technical qualification in items of greater relevance. Supplier 7 did not prove the required operational and professional technical qualification.
Furthermore, Supplier 8 presented an expired federal regularity certificate, and Supplier 9 did not present economic qualification as required in the Requirements, submitting only the balance sheet and trial balance for 2025. The high number of disqualifications at this initial stage reinforces the importance of qualification as a filtering mechanism. By being carried out beforehand, this step contributed to the formation of a more equitable competitive environment, reducing the influence of proposals that would not be technically and contractually sustainable, avoiding the price distortion observed in other cases.
The difference between the reference value and the discounts applied in this process, with a maximum discount of 2.25%, demonstrates that prior qualification restricts participation in the competitive phase to companies effectively capable of executing the object. This dynamic results in more consistent proposals aligned with market values, significantly minimizing the risk of non-executability. The conduct of procurements, from the PMBOK perspective (PMI, 2017), is optimized when the planning of requirements and supplier qualification are rigorously applied before the price competition, ensuring that the most advantageous proposal is also the most feasible.
The comparison between the three processes, as summarized, reveals that the order of the phases of the bidding process directly influences the quality of competition and the efficiency of the tender. In processes 1 and 2, where qualification occurred after the bidding phase, a larger number of participants (16 and 12, respectively) and a high number of disqualifications (4 and 5) were observed. Furthermore, the duration of these processes was considerably longer (49 and 34 days), and the average discounts were significant (69.57% and 28.57%), indicating the influence of unqualified companies on price formation.
In contrast, Process 3, which adopted prior qualification, presented a smaller number of participants (9), but with a disqualification rate (5) that occurred before the bidding phase, filtering out competitors. The duration was significantly shorter (13 days), and the highest discount recorded was only 2.25%. This difference highlights that prior qualification contributed to greater competitive balance, with proposals more aligned with market values, resulting in better performance and greater procedural agility, in accordance with the principles of administrative efficiency and project management (PMI, 2017).
The results indicate that increasing competitiveness, when not accompanied by effective mechanisms for prior qualification of bidders, can result in only apparent competition, compromising the efficiency and quality of the procurement. The comparative analysis of cases demonstrated that the prior evaluation of qualification requirements, especially regarding objects of greater technical complexity, can facilitate the competitive phase among suppliers truly qualified for the execution of the object. The implementation of the processes of planning, conducting, and controlling procurements, according to the PMBOK, is fundamental to understanding the bidding process as an integral part of the management of a public works project.
In summary, the research showed that phase inversion, by allowing companies without prior qualification to participate in the bidding phase, favored the submission of aggressive proposals, generating distortions in price formation, increased delays, and risks of non-executability. On the other hand, the adoption of prior qualification contributed to greater competitive balance and better adherence of proposals to market values, resulting in more efficient processes with a lower risk of contractual failures. The effectiveness of Law no. 14.133/2021 (Brazil, 2021) therefore depends on how it is applied, making it crucial to consider the complexity of the object in defining the order of the phases of the bidding process to ensure the selection of the most advantageous and feasible proposal.
4. Conclusion
This study analyzed the management of public works acquisitions in the state of Minas Gerais, through electronic bidding, focusing on the participation of companies without technical capacity in the bidding phase and their impacts on efficiency and price formation in bidding processes. It was found that the inversion of phases, by allowing the participation of bidders without prior qualification, favored the submission of excessively aggressive proposals. This dynamic generated significant distortions in price formation, increased the slowness of processes, and raised the risks of contractual non-executability, resulting in a “false economy” that compromised the effectiveness of contracting. In contrast, it was observed that the adoption of prior qualification contributed to a more balanced competitive environment, with proposals more aligned with market values, and to greater agility and efficiency in the contests.
The main contribution of this study lies in demonstrating that the effectiveness of Law no. 14.133/2021 is intrinsically linked to how its provisions are applied, especially regarding the order of the bidding process phases. It is suggested that the complexity of the object is fundamental for defining the sequence of qualification and bidding, aiming to ensure the selection of the most advantageous and feasible proposal. As a limitation, it should be noted that the analyzed sample, restricted to small municipalities in Minas Gerais, may influence the generalization of the findings. For future studies, it is recommended to expand the sample to other contexts and investigate additional factors that impact the efficiency of public procurement, such as the qualification of public agents and the use of technological tools to support proposal analysis.
Bibliographic References
Alves, A.P.G. 2021. A evolução histórica das licitações e o atual processo de compras públicas em situação de emergência no Brasil. Regen: Revista de Gestão, Economia e Negócios 1 (2): 40-60.
Bll Compras. 2026. Bll Compras | A maior plataforma de licitações do país. Disponível em: <https://bll.org.br>. Acesso em: 21 Ago. 2026.
Brasil. 1993. Lei n. 8.666, de 21 de junho de 1993. Lei de Licitações e Contratos Administrativos. Brasília, DF, Brasil.
Brasil. 2021. Lei n. 14.133, de 1º de abril de 2021. Lei de Licitações e Contratos Administrativos. Brasília, DF, Brasil.
Di Pietro, M.S.Z. 2020. Direito administrativo. 33ed. Forense, Rio de Janeiro, RJ, Brasil.
Gil, A.C. 2010. Como elaborar projetos de pesquisa. 5ed. Atlas, São Paulo, SP, Brasil.
Gil, A.C. 2017. Métodos e técnicas de pesquisa social. 6ed. Atlas, São Paulo, SP, Brasil.
Licitar Digital. 2026. Licitar Digital: a plataforma de compras públicas mais inovadora do Brasil. Disponível em: <https://licitar.digital>. Acesso em: 21 Ago. 2026.
Mascena, E. 2017. Licitação conceito e finalidade. Disponível em: <https://www.jusbrasil.com.br/artigos/licitacao-conceito-e-finalidade/437367557/licitacao-conceito-e-finalidade>. Acesso em: 14 mar. 2022.
Project Management Institute [PMI]. 2017. Guia do Conhecimento em Gerenciamento de Projetos (Guia PMBOK). 6ed. Project Management Institute, Newton Square, Pennsylvania, Estados Unidos da América.
Toledo, F.A. 2021. Algumas das principais mudanças da nova Lei de Licitações. Consultor Jurídico. Disponível em: <https://www.conjur.com.br/2021-out-03/toledo-algumas-principais-mudancas-lei-licitacoes/>. Acesso em: 18 mar. 2025.
Tribunal de Contas da União [TCU]. 2014. Obras Públicas: recomendações básicas para a contratação e fiscalização de obras de edificações públicas. 4ed. Brasília, DF, Brasil. p. 9.
Yin, R.K. 2015. Estudo de caso: Planejamento e métodos. 5ed. Bookman, Porto Alegre, RS, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform