Stakeholder Management in Environmental Remediation Projects: Framework Applied to Scenarios of High Regulatory and Social Pressure
Adinéia Ferreira de Souza; Décio Henrique Franco
DOI: 10.22167/2675-6528-202600474
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Environmental remediation projects in contaminated urban areas impose a stakeholder landscape of singular complexity, marked by multiple actors with divergent interests, a multi-layered regulatory framework, and growing social pressure. Faced with this scenario, the work proposed a structured framework for stakeholder management, calibrated to the specificities of the Brazilian environmental context and aligned with the guidelines of the PMBOK® Guide (6th and 7th editions), CETESB standards, and CONAMA resolutions. The research adopted a qualitative approach of an applied nature, combining a systematic literature review, documentary analysis, and the construction of a hypothetical composite case study. The case depicted a thermal remediation project using electrical resistance heating (ERH) combined with soil vapor extraction (SVE), in an industrialized urban area in the city of São Paulo, with 10,000m² affected by Organochlorine Compounds. The framework was organized into five dimensions: Identification, Classification, Engagement, Conflict Mitigation, and Monitoring, with specific performance indicators for environments of high socio-environmental complexity. The results demonstrated that the absence of structured engagement strategies is not merely an institutional relations problem, but a risk vector that compromises deadlines, costs, and the technical effectiveness of the remediation. It was concluded that the framework offers a systematic and adaptable approach to managing the complexity of human interactions in critical projects, compatible with the regulatory and operational demands of the Brazilian scenario.
Keywords: CETESB; Electrical resistance heating; Stakeholder engagement; PMBOK®; Environmental remediation.
1. Introduction
Environmental remediation projects in contaminated urban areas represent a complex challenge that transcends the mere application of technical solutions. Intervention in sites with historical environmental liabilities, often located in densely populated areas, imposes a delicate intersection between technical, political, and social aspects. Such projects not only aim to recover the environmental quality of soil and groundwater but also face scientific uncertainties regarding the extent of contamination and documented public health risks. The complexity is amplified by the presence of communities that often become aware of the magnitude of the problem only when interventions begin.
This scenario creates a particularly volatile stakeholder landscape, characterized by frequently conflicting interests. The company responsible for the contamination seeks remediation with maximum efficiency and optimized cost, while the community demands safety assurances for its health and property. Regulatory bodies, in turn, oversee strict compliance with environmental legislation, and shareholders focus on mitigating financial risks associated with the liability. Managing these multiple expectations and demands thus becomes a structuring element for the project’s success.
In this context, stakeholder management ceases to be a secondary activity and assumes a central role. International literature is consistent in indicating that most failures in complex projects do not stem from technical deficiencies, but rather from inadequate alignment processes among the various actors involved (Flyvbjerg; Gardner, 2022; Pinto, 2018). When communities do not trust the entrepreneur, they may involve the Public Prosecutor’s Office. Regulators with doubts about the technical approach may require additional studies, delaying execution. Investors misinformed about residual risks may withdraw funding at critical moments.
In Brazil, the regulatory framework for environmental remediation is complex and fragmented, operating across multiple federal and state layers. The Environmental Company of the State of São Paulo (CETESB) acts as the primary oversight agency in the State of São Paulo, establishing a normative environment that demands transparency and continuous communication with affected communities. The obligations of the party responsible for contamination extend even after the completion of field interventions. CONAMA Resolution No. 420/2009 defines the quality parameters for soil and groundwater, while Laws No. 9.605/1998 and No. 6.938/1981 consolidate the framework of legal responsibility that permeates the actions of all involved.
The application of advanced remediation technologies, such as thermal remediation by electrical resistance heating (ERH) combined with soil vapor extraction (SVE), in densely populated urban areas, like the city of São Paulo, adds layers of complexity. Such projects, which can cover significant extensions like 10,000 square meters and involve the removal of organochlorine compounds, demand robust infrastructure and generate specific operational impacts. These include the need for coordination with energy utility companies for high voltage demands, as well as potential noise, vibrations, and odors that can directly affect the neighborhood, including schools and recreational areas. The management of these aspects, often seen as purely technical, has an intrinsic social and regulatory dimension, requiring an integrated approach.
Project management, as outlined by the PMBOK® Guide (PMI, 2017; PMI, 2021), recognizes the importance of managing stakeholders for the success of the undertaking. However, the generic nature of these guides does not address the specificities of environmental remediation projects in the Brazilian context, which require an adaptation of the guidelines to meet CETESB standards and CONAMA resolutions. The identification and classification of stakeholders, based on models such as the salience model (Mitchell; Agle; Wood, 1997), become essential tools for prioritizing engagement and mitigating conflicts.
Given the complexity inherent in environmental remediation projects in urban settings with high regulatory and social pressure, and the gap in a stakeholder management framework adapted to the Brazilian context, this work is justified by the need to provide practical and structured guidelines. The objective of this study is to propose a stakeholder management framework for environmental remediation projects, applying it to scenarios of high regulatory and social pressure, aligned with the guidelines of the PMBOK® Guide, CETESB standards, and CONAMA resolutions, in order to optimize engagement and mitigate risks.
2. Material and Methods
The methodology adopted for this study was characterized as a research of an applied nature, with a qualitative approach, of an exploratory and descriptive character. The central objective was to propose a stakeholder management framework, which required the combination of different research strategies. The main stages involved a systematic literature review, documentary analysis, and the construction of a hypothetical composite case study. These procedures were outlined to ensure the theoretical foundation and practical applicability of the proposed framework.
The systematic literature review was conducted in the Scopus, Web of Science, and Google Scholar databases, covering publications between 1984 and 2024. The keywords used included terms such as “stakeholder management”, “remediation of contaminated areas”, and “environmental project management”. The inclusion criteria were texts published in peer-reviewed journals or reference works, which explicitly addressed stakeholder management in an environmental context, as well as empirical studies or framework proposals with transparent methodology. Opinion pieces, duplicates, and studies without full-text access were excluded.
The documentary analysis comprised three categories of primary sources. The first included norms and regulations, such as the PMBOK® Guide (PMI, 2017; PMI, 2021), Agile Practice Guide (PMI, 2017), CETESB Board Decisions (DD-045/2014/P/C, DD-038/2017/E/C, DD-056/2022/P/C), CONAMA Resolution 420/2009, Laws No. 9.605/1998 and No. 6.938/1981, and ANEEL Normative Resolution No. 1.000/2021. The second category consisted of documents from international reference projects, such as reports from Crossrail/Elizabeth Line and the USEPA Superfund Program. The third covered documented cases of environmental remediation in national territory, focusing on public processes from CETESB.
For the application of the framework, a hypothetical composite case study was developed, a technique recognized in qualitative research (Yin, 2015). The case depicted a thermal remediation project using Electrical Resistance Heating (ERH) combined with Soil Vapor Extraction (SVE) in an industrialized urban area in the city of São Paulo. The area of approximately 10,000 square meters was affected by Organochlorine Compounds, with an industrial history that ended in the 1990s. Technical parameters, such as the extent of the contamination plume and VOC concentrations, were defined based on representative data from technical literature and in accordance with CETESB and CONAMA standards.
The composition of the stakeholder field was built from the typology identified in the literature review and validated by triangulation with similar publicly documented projects. 23 stakeholder groups were identified, grouped into five functional categories: regulators and supervisors, directly affected community, social representation entities, institutional actors, and parties with direct economic interest. The identification and analysis of stakeholders followed the method of Knowledge Area 13 of the PMBOK® 6th edition, complemented by the saliency model of Mitchell, Agle, and Wood (1997), which classified stakeholders based on the attributes of Power, Legitimacy, and Urgency.
The proposed framework was structured into five interconnected dimensions: Identification, Classification, Engagement, Conflict Mitigation, and Monitoring. Stakeholder identification was treated as a continuous process, with quarterly review of the register. Stakeholder classification, using the Saliency Model and the PMBOK® Power x Interest Matrix, guided the definition of engagement strategies. The Engagement Plan, incorporated into the Project Management Plan, defined for each group the level of engagement, communication method and frequency, responsible party, and satisfaction indicators.
For community stakeholders, the creation of a Community Monitoring Committee (CAC), with monthly meetings and a direct channel with CETESB for questions and complaints, was recommended. The operational impacts communication plan, covering noise, vibration, odors, and road access restrictions, integrated the CAC’s responsibilities, with protocols for advance notification and rapid response channels. For environmental regulators, the plan included bimonthly technical meetings with CETESB and monthly progress reports, as required by Board Decisions DD-045/2014/P/C and DD-038/2017.
Dimension IV of the framework addressed conflict mitigation and management, proposing a three-level Conflict Management Protocol with defined timelines and responsibilities for each escalation. The prevention of structural conflicts was based on establishing realistic expectations, creating formal complaint and feedback mechanisms, and monitoring warning signs. Dimension V established monitoring and Key Performance Indicators (KPIs) to measure the quality of engagement and the impact of stakeholder dynamics on the project schedule and costs.
Methodological limitations included the use of a hypothetical case, necessary to preserve the confidentiality of real projects, which restricts the direct generalization of results. Engagement strategies were evaluated based on theoretical consistency and analogies with real cases, without experimental field validation. It was recognized that stakeholder dynamics depend on local geopolitical, economic, and cultural factors, positioning the framework as an adaptable starting point, rather than a static protocol of universal application.
3. Results and Discussion
This section details the research findings, which culminated in the proposition of a structured framework for stakeholder management in environmental remediation projects, specifically calibrated for scenarios of high regulatory and social pressure in Brazil. The results demonstrate that the absence of structured engagement strategies represents a significant risk vector, compromising the technical effectiveness, deadlines, and costs of the projects. The analysis of data from the hypothetical composite case study, along with the bibliographic and documentary review, allowed for the identification of the inherent complexities of these projects and the development of an adaptable model that integrates the guidelines of the PMBOK® Guide, CETESB standards, and CONAMA resolutions.
The proposed framework is organized into five interconnected dimensions: Identification, Classification, Engagement, Conflict Mitigation, and Monitoring, each with specific performance indicators. This structure aims to provide a systematic approach to managing human interactions in critical projects, recognizing that stakeholder management is a continuous and dynamic process, not a one-off activity. The application of the model to a simulated thermal remediation scenario in an industrialized urban area of São Paulo allowed for the exploration of the relevance and applicability of each dimension.
Case Study Description
The hypothetical composite case study simulated a remediation project in a deactivated industrial area, located in a densely populated neighborhood in the city of São Paulo. The site, approximately 5,000 square meters, was historically used for dry cleaning activities, resulting in soil and groundwater contamination by tetrachloroethene (PCE) and trichloroethene (TCE). The contamination plume extends over an area of about 10,000 square meters, reaching depths of up to fifteen meters, with concentrations exceeding the maximum values allowed by CONAMA Resolution No. 420/2009 for soil and groundwater.
The project area is surrounded by sensitive receptors, including a middle-class residential complex to the east, a primary school with approximately 500 students to the west, a municipal park to the north, and a busy arterial road to the south. The proximity of these receptors significantly increases the project’s complexity, not only due to the potential for human exposure to contaminants but also because of social sensitivity and the need to ensure the safety and well-being of the population during remediation operations, as highlighted in the Board Decision No. 038/2017/C from CETESB.
The remediation technology selected for the case was Electrical Resistance Heating (ERH), combined with a Soil Vapor Extraction (SVE) system. ERH, proven effective in removing organochlorinated compounds, involves installing electrodes in the subsurface to heat the soil and water between 70°C and 90°C, volatilizing the contaminants which are then extracted and treated at the surface by the SVE system. The implementation of ERH requires a robust electrical infrastructure, with an approximate energy demand of 440V and high power, requiring coordination with the local energy utility.
The estimated project timeline is 36 months, comprising four months for infrastructure installation, eight months for effective remediation, and a 24-month post-remediation monitoring period, in accordance with CETESB guidelines and CONAMA regulations. The need to install extraction and monitoring wells beyond the boundaries of the impacted land means that the maintenance and monitoring of these points will directly affect the local community, adding a layer of complexity to project management.
The technical parameters adopted in the hypothetical case, such as TCE and PCE concentrations and the electrical demand of the ERH technology, are consistent with the ranges documented by Leite, Shinzato, and Freitas (2020) for thermal remediation projects in tropical soils contaminated by organochlorine compounds. The scarcity of national technical literature on specific ERH projects, with less than 1% of contaminated areas in the State of São Paulo using this technique until 2019, reinforces the methodological relevance of constructing a hypothetical composite case for academic analysis.
Identification and Analysis of Stakeholders
The identification and analysis of stakeholders were carried out following the method recommended by Knowledge Area 13 of the PMBOK® 6th edition, which foresees sequential processes of identification, planning, management, and monitoring of engagement. This approach was complemented by the salience model of Mitchell, Agle, and Wood (1997), which classifies stakeholders based on the attributes of Power, Legitimacy, and Urgency. Power refers to the ability to influence the project through legal, political, economic, or social mobilization channels; Legitimacy concerns the social and legal recognition of the group’s interest; and Urgency expresses the temporal pressure and criticality of the demands.
The application of these models allowed the identification of 23 groups of stakeholders, distributed into five functional categories. The first category, Regulators and Supervisors, included the Ministry of Environment, the State Environmental Agency (CETESB), the Public Prosecutor’s Office, and ANEEL. The second, Directly Affected Community, encompassed residents of the housing complex, parents and guardians of schoolchildren, visitors to the public park, and owners of commercial properties in the vicinity. The third, Social Representation Entities, comprised residents’ associations, environmental NGOs, digital activism groups, and local and regional press.
The fourth category, Institutional Actors, included the Municipal Government (Secretariat of Environment and Secretariat of Health/Sanitary Surveillance), the Traffic Engineering Company (CET), the Municipal Chamber and councilors, and universities and researchers. Finally, the fifth category, Parties with Direct Economic Interest, involved the Legal and Financial Responsible Party, the Contractor specialized in ERH, the environmental Consultancy, the creditor bank, the local electric power concessionaire, and the contractor’s suppliers and subcontractors. This initial categorization is fundamental for understanding the complexity of the actor field.
The application of the Salience Model revealed that environmental regulators, such as CETESB and the State Public Prosecutor’s Office, occupy positions of definitive or dominant stakeholders. They possess high formal power, irrefutable legitimacy, and high urgency, being capable of determining the pace and parameters of remediation, approving plans, and issuing infraction notices. The relationship with CETESB, for example, is a permanent interface throughout the entire project lifecycle, requiring proactive communication and detailed progress reports, according to Board Decisions DD-038/2017 and DD-056/2022.
The surrounding community, although heterogeneous, represents a set of stakeholders with high legitimacy and urgency, but variable power. Residents, school users, and parkgoers share a central interest in health protection. Individually, their power is limited, but collectively, especially when mobilized by associations or supported by the Public Prosecutor’s Office, they can generate significant pressure on the project’s schedule and reputation. The literature, as pointed out by Freeman (1984) and Flyvbjerg and Gardner (2022), is clear in indicating that excluding communities from the decision-making process does not eliminate their influence, but rather makes it confrontational.
The company legally responsible for the contamination and the main funder of the remediation was classified as a definitive stakeholder. Its interests are often contradictory, seeking the conclusion of the remediation to extinguish environmental liability at the lowest possible cost and timeframe, which may conflict with technical and regulatory requirements. This internal conflict represents a subtle source of risk, as pressure for aggressive financial targets can compromise the technical quality of the intervention and, paradoxically, prolong the regulatory process due to non-compliance.
The local electric power concessionaire was classified as a dominant stakeholder due to the asymmetry of its attributes. Although it holds exclusive technical power over the electrical infrastructure and legitimacy as a public service concessionaire, its degree of urgency regarding the remediation project is low. The concessionaire is required to make specific adjustments to the distribution network to meet the ERH system specifications, but it has no autonomous interest in the project’s success or timeline. Its early engagement is necessary to incorporate ANEEL’s regulatory deadlines into the project schedule and avoid stoppages in the mobilization phase.
Main Conflicts, Risks, and Tensions
The analysis of the stakeholder field allowed the identification of seven axes of conflicts and tensions that are recurrent in highly complex environmental remediation projects. The first axis is the asymmetry of information and risk perception. The technical complexity of remediation and the nature of the contaminants are often misunderstood by the lay community, which can lead to a distorted perception of health and safety risks. The lack of knowledge about soil heating processes and vapor treatment can generate fear and distrust, catalyzing community opposition and the search for intervention by external bodies, such as the Public Prosecutor’s Office.
The second axis refers to divergent temporal horizons. The owning company seeks rapid and efficient remediation to minimize liabilities and costs. CETESB requires a rigorous process, which can be time-consuming, to ensure environmental protection. The community, in turn, desires an immediate solution to perceived risks and the cessation of disturbances from the work. The divergence of these temporal horizons generates frustrations and pressures on the project schedule, requiring clear communication about the steps and the expected duration of each phase to avoid different assessments of progress.
The third axis is political instability. Remediation projects, with a minimum duration of three years, can span municipal or state electoral cycles. Changes in city hall management or CETESB’s direction can alter priorities, require renegotiation of informal agreements, and introduce new stakeholders with unknown positions. Managing this phenomenon requires formal mechanisms for renewing the social contract with political stakeholders at each cycle, ensuring the continuity of engagement strategies and project stability.
The fourth axis is diffuse responsibility. In remediation projects, multiple organizations share responsibilities for the same problem, creating zones of ambiguity that external stakeholders may interpret as omission or collusion. Clear distribution of responsibilities is essential for the stakeholder field to perceive the project as managed with integrity and transparency, avoiding the erosion of trust and the escalation of conflicts due to uncertainty about who is responsible for each aspect of the remediation.
The fifth axis is amplification through social media and digital activism. Cases like the Dakota Access Pipeline demonstrate that local conflicts in environmental projects can be rapidly internationalized through social media and articulation with global non-governmental organizations. Remediation projects involving vulnerable communities have high visibility potential, and public narrative management becomes a strategic component of risk management, requiring proactive and transparent communication to prevent misinformation and negative mobilization.
The sixth axis is the incompatibility of the electrical infrastructure with the residential environment. The need to adapt the distribution network for the supply of energy at industrial voltage introduces a specific and often underestimated schedule risk vector. The concessionaire operates with its own administrative procedures and deadlines regulated by ANEEL, which do not always coincide with the project’s mobilization calendar. Delays in the approval of the electrical adaptation project translate directly into delays in the start of the operation phase, with a cascading effect on regulatory milestones and fixed costs.
The seventh axis concerns the operational nuisances specific to the applied technology. Thermal remediation generates daily tensions with the neighborhood in a densely populated urban environment. Noise and vibration from equipment, including vacuum pumps and air treatment systems, can cause significant discomfort during rest periods or proximity to schools. The perception of electrical risk associated with high voltage and concern for facility safety are constant sources of unease. Odor generation, even when controlled, can occur during peak operational times, leading to complaints and, in more acute cases, panic. Road closures for the transport of heavy equipment and infrastructure assembly impact local traffic and access to residences and businesses during the mobilization phase. These factors, which individually seem of low magnitude, accumulated over months, have the capacity to severely deteriorate the project’s relationship with the community and escalate to political pressure or action by the Public Prosecutor’s Office.
Proposed Stakeholder Management Framework
The proposed stakeholder management framework is based on the principles of PMBOK® 7th edition, which treats stakeholder engagement as a fundamental principle, and on the theoretical frameworks of Mitchell, Agle, and Wood (1997), Freeman (1984), and Eskerod and Jepsen (2013), in addition to CETESB’s regulatory requirements for remediation projects. It is structured into five interconnected dimensions that guide the project manager from initial identification to continuous monitoring of engagement, providing a systematic and adaptable approach to managing the complexity of human interactions in critical projects.
Dimension I – Identification
Stakeholder identification should be treated as a living and continuous process, not as a one-time initial survey. In the remediation project under analysis, the initial identification was conducted during the preliminary environmental assessment and risk assessment phases, as recommended by CETESB guidelines, and before the start of remediation. The stakeholder register should be reviewed quarterly throughout the operation phase, allowing for the mapping of potential interested parties that emerge throughout the project and the adaptation of engagement strategies.
Sources for identification include brainstorming with the project team and external experts, documentary analysis of licenses, environmental impact studies and public records, interviews with experts and community leaders, and analysis of previous similar projects. The identification of the electric power concessionaire, for example, should occur during the technical planning phase of the ERH system, when the electrical demand parameters are defined, so that the regulatory deadlines of the electricity sector are incorporated into the schedule with sufficient advance notice, avoiding future delays.
Dimension II – Classification
The classification of stakeholders adopts the Salience Model as a central instrument, complemented by the PMBOK® Power x Interest Matrix. The Salience Model helps answer who matters and why, while the Power x Interest Matrix guides the definition of how to relate to each group. This approach allows for prioritizing engagement and allocating resources efficiently, focusing on stakeholders with greater power, legitimacy, and urgency.
In the context of the case study, the classification resulted in differentiated engagement strategies. For CETESB, the Legal Responsible Company, and the Public Prosecutor’s Office, management should be close and continuous. For funders, the municipal government, and the energy utility company, the strategy is to maintain satisfaction. Residents, school users, and neighborhood associations should receive regular information. For distant NGOs and the media, monitoring should be periodic during normal project phases, intensifying during moments of greater visibility or potential conflict.
Dimension III – Engagement Plan
The Engagement Plan is the central operational document for stakeholder management and must be incorporated into the Project Management Plan. For each identified group, the plan defines the current and desired engagement level, the communication method and frequency, the relationship owner, satisfaction indicators, and the escalation plan in case of conflict. This plan is dynamic and must be adjusted according to the project’s evolution and stakeholder dynamics.
For community stakeholders, the framework recommends the creation of a Community Monitoring Committee (CAC), composed of representatives from residents, the school, neighborhood associations, and at least one independent technical expert appointed by the community. The CAC should meet monthly during the operation phase, receive monitoring reports in accessible language, and have a direct channel with CETESB for communicating doubts or complaints. A plan for communicating operational impacts, covering noise, vibration, odors, risk perceptions, and road access restrictions, is part of the CAC’s responsibilities, with clear protocols for advance notification of predictable events and rapid response channels for unforeseen occurrences.
For environmental regulators, the plan foresees bimonthly technical meetings with CETESB, monthly progress reports in the format required by DD-045/2014/P/C, and compliance with the social communication obligations established by DD-038/2017. The implementation of an early warning system to communicate deviations before they become formal non-conformities is a practice that builds regulatory trust over time, facilitating the approval of critical project stages, such as the Intervention Plan and the Post-Remediation Monitoring Plan.
Dimension IV – Mitigation and Conflict Management
Dimension IV specifically addresses mechanisms for conflict prevention, early detection, and resolution. The framework proposes a three-level Conflict Management Protocol. At the first level, operational conflict is handled directly by the stakeholder relationship manager, with a seven-business-day deadline for resolution. At the second level, escalated conflict is managed by the project manager, involving the sponsor and possible technical mediation by an independent specialist, with a fifteen-day deadline.
At the third level, structural conflict triggers the project governance committee, potentially involving external mediation, formal communication with the regulator, and, as a last resort, arbitration or judicial proceedings. The prevention of structural conflicts relies on three fundamental practices: establishing realistic expectations from the mobilization phase, communicating the technical limitations of remediation and the project’s success criteria; creating formal complaint and feedback mechanisms; and monitoring warning signs, such as a drop in participation in community meetings, an increase in informal complaints about noise or odors, and negative coverage in local media, intervening proactively before the situation escalates.
Dimension V – Monitoring and Performance Indicators
The fifth dimension closes the cycle by establishing how stakeholder management performance will be measured and how the results will be fed back into the previous dimensions. Monitoring operates on two levels: the relational level, which covers satisfaction, engagement level, and quality of interactions, and the impact level, which measures the effects of stakeholder dynamics on project performance in terms of schedule, cost, and technical quality. The proposed key performance indicators (KPIs) include, for identification, the percentage of new stakeholders identified versus the previous review, with a target of less than 5% per quarterly review.
For engagement, the satisfaction index per group (scale of one to five) is monitored bimonthly, with a target of above 3.5 in the overall average. Communication is evaluated by the attendance rate at CAC meetings, with a target of above 60% of those summoned monthly. Conflicts are measured by the number of conflicts escalated to level two and three per quarter, with a target of zero at level three. Operational impact is monitored by the number of formal complaints about noise, odors, or safety per month, with a target of a decreasing trend after the third month. Project impact is evaluated by the days of delay attributable to stakeholder conflicts, with a target of less than 5% of the total monthly schedule. Finally, the environmental regulatory aspect is monitored by the number of notifications and infraction notices issued by CETESB, with a target of zero on a continuous basis.
Comparison with Literature and Critical Analysis
The proposed framework dialogues with the main references in the field and complements them in specific aspects related to the Brazilian context of environmental remediation. Regarding the PMBOK® 7th edition, the framework broadens the perspective of principles by operationalizing them in protocols adapted to CETESB’s regulatory cycle and specific sector regulations, gaps that the guide, by its generic nature, cannot fill. Regarding the seminal work of Mitchell, Agle, and Wood (1997), the framework incorporates the Salience Model as a dynamic prioritization tool, reviewed quarterly, instead of being applied punctually in the initiation phase, recognizing the evolving nature of the field of stakeholders.
Compared to the model adopted in Crossrail/Elizabeth Line, the proposed framework is structurally leaner and calibrated to the budgetary reality of medium-sized remediation projects. While Crossrail maintained professionals dedicated exclusively to relationships with residents and merchants, the proposed framework foresees this function being performed by a community relations manager, a figure included in the Engagement Plan with equivalent responsibilities, but without requiring a large team. The Crossrail experience also informs the structure of the proposed Community Monitoring Committee (CAC), which fulfills the analogous function of meeting monthly with community representatives, receiving reports translated into accessible language, and maintaining a direct channel with CETESB for recording doubts and complaints, using continuous information as an antidote to distrust.
The most relevant criticism that can be directed at the framework is the one that Friedman and Miles (2002) formulate about stakeholder management in general, which points to the distance between discourse and practice. Organizations frequently elaborate detailed engagement plans that do not translate into genuine relationships of listening and co-creation. In the context of remediation projects, this distance is particularly dangerous because affected communities have a historical experience of being informed without being heard. The framework by itself does not eliminate this risk, which suggests the importance of including mechanisms for auditing the Engagement Plan as a mandatory governance component to ensure the effectiveness of actions.
In summary, the research results demonstrate that the proposed stakeholder management framework offers a systematic and adaptable approach to managing the complexity of human interactions in environmental remediation projects. By integrating best practices in project management with the regulatory and social specificities of the Brazilian context, the framework addresses the technical and operational challenges of thermal remediation in urban environments, such as energy demand and operational nuisances, and promotes proactive and transparent engagement, essential for mitigating risks and ensuring the social legitimacy of the project.
4. Conclusion
This study proposed a stakeholder management framework for environmental remediation projects, specifically in scenarios of high regulatory and social pressure, aligned with the guidelines of the PMBOK® Guide, CETESB standards, and CONAMA resolutions. It was found that the absence of structured engagement strategies constitutes a substantial risk vector, compromising deadlines, costs, and the technical effectiveness of remediation. The developed framework is organized into five interconnected dimensions – Identification, Classification, Engagement, Conflict Mitigation, and Monitoring – each with specific performance indicators. It was observed that this structure offers a systematic and adaptable approach to managing the complexity of human interactions in critical projects, integrating best project management practices with the regulatory and social particularities of the Brazilian context. The framework addresses the technical and operational challenges of thermal remediation in urban environments, such as energy demand and operational nuisances, promoting proactive and transparent engagement, essential for mitigating risks and ensuring the social legitimacy of the project.
The main contribution of this work lies in offering a practical and structured model to optimize stakeholder engagement and mitigate risks in complex urban environmental remediation projects in Brazil. However, limitations arising from the hypothetical nature of the case study and the absence of experimental field validation restrict the direct generalization of the results. It is recognized that the effectiveness of the framework depends on translating engagement plans into genuine listening and co-creation relationships, suggesting the need for auditing mechanisms. For future studies, it is recommended to apply this framework to real ongoing projects in order to test its indicators in different contexts and improve its protocols based on empirical evidence, consolidating its precision and scope.
Bibliographic References
CETESB COMPANHIA AMBIENTAL DO ESTADO DE SÃO PAULO. Decisão de Diretoria DD-045/2
CONAMA CONSELHO NACIONAL DO MEIO AMBIENTE. Resolução n.º 420, de 28 de dezembro de 2009. Dispõe sobre critérios e valores orientadores de qualidade do solo quanto à presença de substâncias químicas. Brasília: CONAMA, 2009.
FLYVBJERG, B.; GARDNER, D. How big things get done: the surprising factors that determine the fate of every project. New York: Currency, 2022.
MITCHELL, R. K.; AGLE, B. R.; WOOD, D. J. Toward a theory of stakeholder identification and salience: defining the principle of who and what really counts. Academy of Management Review, New York, v. 22, n. 4, p. 853–886, 1997.
PINTO, J. K. Project management: achieving competitive advantage. 4. ed. Hoboken: Pearson, 2018.
PMI PROJECT MANAGEMENT INSTITUTE. A guide to the project management body of knowledge (PMBOK® Guide). 6th ed. Newton Square: PMI, 2017.
PMI PROJECT MANAGEMENT INSTITUTE. A guide to the project management body of knowledge (PMBOK® Guide). 7th ed. Newton Square: PMI, 2021.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq