Schedule management for projects in an agricultural tire industry
Lincon Lucio dos Reis; Maria do Carmo Assis Todorov
DOI: 10.22167/2675-6528-202601101
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The growing competitiveness in the agricultural tire sector highlighted the need to improve project planning and execution, aiming to mitigate delays, high costs, and low quality. The research objective was to identify and categorize projects in an industry within the sector, in order to develop schedule templates that would provide greater process clarity, guidance, and more realistic deadline forecasting. To this end, a descriptive case study was conducted at an American multinational tire company located in São Paulo, using a mixed approach of qualitative and quantitative data. Data collection involved questionnaires, meetings with experts, systematic observations, and documentary analysis of historical data. Projects were identified, correlated with the involved processes, and grouped into categories based on previously defined criteria. Subsequently, schedule templates were developed for each category, following the five stages of schedule management planning (planning, definition, sequencing, duration estimation, and development), applying techniques such as the Precedence Diagramming Method and PERT. The results demonstrated that project categorization provided greater clarity on their characteristics, revealing the predominance of incremental innovation projects and the existence of radical innovation projects. The templates allowed for process integration, structured planning, and identification of critical activities, contributing to more realistic deadline estimates and failure mitigation. It was concluded that the categorization and schedule development improved project and process clarity, optimized guidance, resulted in more realistic deadline forecasts, and increased reliability in project development, establishing a foundation for the company’s future planning.
Keywords: Agribusiness; Productive efficiency; Project management; PMBOK; Templates.
1. Introduction
The Brazilian agribusiness constitutes a fundamental pillar of the national economy, with a significant contribution to the Gross Domestic Product (GDP). The Brazilian Institute of Geography and Statistics (IBGE, 2025) reported a growth of 10.2% in the agricultural sector in the first quarter of 2025, boosting the national GDP by 2.9% in the same period. This performance reiterates the expansion potential of agribusiness, which may surpass the results of recent decades, as pointed out by Neves (2021). To solidify this trajectory, it is imperative to intensify investments in productive efficiency in the field, which includes modernizing the fleet of agricultural machinery with more technological equipment. The Brazilian Agricultural Research Corporation (Embrapa, 2022) highlights fleet renewal as a crucial strategy to increase productivity and reduce losses. In this context, the agricultural tire industry assumes a strategic role, as the performance of the equipment depends directly on the quality and suitability of its tires. However, the sector faces growing challenges, such as intense competitiveness and increased imports. The National Association of the Tire Industry (ANIP, 2024) warns of the threat of tires imported from Asia, which, with subsidies and lower prices, compromise the sustainability of national manufacturers. To mitigate these impacts and meet market demands, new product development must be agile, high-quality, and cost-controlled. The absence of detailed planning and effective schedule management can result in delays, cost increases, and low quality, as emphasized by Kerzner (2006).
Project management emerges as an essential discipline for navigating these complexities, offering methods and tools to optimize the product development lifecycle. The Project Management Body of Knowledge (PMBOK), from the Project Management Institute (PMI, 2017), is a global reference that structures best practices in project management, including schedule management. The latter encompasses crucial processes such as schedule management planning, defining and sequencing activities, estimating their durations, and developing the final schedule. Tools like the Precedence Diagramming Method (PDM) and the PERT (Program Evaluation and Review Technique) are applied to establish activity logic and predict deadlines more realistically, respectively (PMI, 2017). Project categorization, in turn, is a management strategy that allows organizations to understand the distinct characteristics of each project type, facilitating resource allocation and the choice of appropriate methodologies (Barbosa, 2009; Kerzner, 2015). However, many industries, including the agricultural tire segment, still face fragmented and isolated project planning. This disconnect between processes and the lack of standardization in defining project types and their respective schedules compromises efficiency, generating uncertainties in execution and deadline adherence, as observed by Moreira et al. (2010) and Carvalho and Rabechini Jr. (2018). This scenario highlights a gap in the systematic application of schedule management practices, which translates into difficulties in integrating processes, structuring planning, and consistently identifying critical activities.
The ineffectiveness in schedule management and the absence of standardization in agricultural tire sector project development processes result in planning failures, delays, and high costs, directly impacting companies’ competitiveness. The development of schedule templates, based on project categorization and PMI (2017) best practices, represents a strategic solution to optimize process clarity and deadline predictability. Therefore, the present study is justified by the need to improve project time management, providing a framework to guide planning and execution. The objective of this research was to identify and categorize projects in an agricultural tire industry, in order to develop schedule templates that would provide greater process clarity, guidance, and more realistic deadline prediction.
2. Material and Methods
The research was designed as a case study, adopting a mixed methodological approach. It was classified as descriptive, as it sought to analyze and detail development processes and projects, identifying characteristics and relationships between variables, according to Gil (2017). The nature of the data combined quantitative methods, used to estimate durations and sequencing of activities, with qualitative methods, based on process analysis and professional experience, which allowed for the categorization of projects and the construction of schedules.
The study was conducted in an American multinational tire sector company, located in São Paulo, SP, Brazil. The organization has approximately 1,600 employees and focuses on the production of agricultural and off-road tires, serving both the national and international markets. The documentary analysis period covered the last seven years of historical data, while primary data collection occurred in November 2025.
The unit of analysis consisted of the product development projects carried out by the company. The population of interest for primary data collection was the technical team involved in these projects. The sample for obtaining expert opinions and validation was composed of one faculty member and the technical team, which included one manager, one coordinator, five engineers, one technician, two technical assistants, and one intern. Only structured projects with a known scope and suitable for the traditional approach were considered.
Data collection integrated several techniques, including the application of a structured questionnaire, conducting meetings to obtain expert opinion, and systematic observation of ongoing processes. Additionally, a comprehensive documentary analysis of historical data from the last seven years was performed, encompassing project plans, procedures, and records, from initial development to final product release. The brainstorming technique was employed in meetings to detail activities.
The research execution was divided into two main parts: project categorization and schedule management. Project categorization involved four sequential steps. First, existing projects and processes were identified through documentary survey and validation with the area manager. Then, processes were correlated to projects, developing a relationship matrix in a meeting with the technical team.
The third stage of categorization consisted of defining the criteria and scales for classifying the projects, using a structured questionnaire applied in November 2025. Participants selected criteria and scales based on their experience, and could also suggest new ones. Finally, in the fourth stage, the projects were grouped into categories through an affinity analysis, considering the criteria and scales assigned in a meeting with the manager and the technical team.
The second part of the research focused on schedule management, based on the best practices of the Project Management Institute (PMI, 2017). This stage followed the five planning processes of schedule management: plan schedule management, define activities, sequence activities, estimate activity durations, and develop the schedule. The adopted methodology aimed to improve planning, deadline estimation, and activity control.
In the first phase of schedule management, schedule management was planned. This step established the guidelines for the development of templates, formalizing the start of the project through the elaboration of a Project Charter. Historical records and development documents were analyzed to align the schedule with practical standards and identified references, resulting in the Work Breakdown Structure (WBS) and the Schedule Management Plan.
The second phase, defining activities, involved breaking down the processes of each category into detailed activities. Collaborative meetings with the technical team were held, using the brainstorming technique to identify and organize all necessary activities. This approach allowed for the structuring of a list of activities compatible with the particularities of each project category, serving as a guide for execution and mitigating the non-compliance of essential steps.
In the third phase, sequencing activities, the dependency relationships between activities were established based on the Precedence Diagramming Method (PDM), according to PMI (2017) guidelines. This method classified relationships into four types: finish-to-start, finish-to-finish, start-to-finish, and start-to-start. The sequencing was defined from the analysis of data from previous projects and systematic observations, validated in meetings with the technical team, and recorded in a dependency table in Microsoft Excel.
The fourth phase, estimating activity durations, used the three-point Program Evaluation and Review Technique (PERT) method to predict the time needed for each activity. This method considers optimistic, most likely, and pessimistic estimates, giving more weight to the most probable scenario. The estimates were based on seven years of historical data from isolated planning and validated in meetings with the manager and those responsible for the processes, assuming a single executor as the standard parameter.
In the fifth and final planning phase, the schedule was developed. Schedule templates for each project category were created in the “Project Management” application on the 3DExperience platform. This tool allowed for the organization of activities with their respective durations and dependencies, as well as visualizing the project’s critical path. The development of the schedules provided an integrated view of the project, facilitating the identification of critical stages and deadline forecasting.
The developed schedule templates were submitted for review and validation by the manager and the technical team in a meeting held in February 2026. During this evaluation, it was found that the deadlines estimated before the template development showed significant variations, which was attributed to the lack of standardization in planning. A methodological limitation identified was the non-consideration of resource constraints, with the duration and dependency estimates developed assuming a single executor as the standard parameter.
3. Results and Discussion
This section details the research results, structuring them into two main parts: project categorization and schedule management, both based on the best practices of the Project Management Institute (PMI, 2017). The discussion of each finding is enriched by its intersection with academic literature, by the analysis of agreements and disagreements with renowned authors in the field, and by the exploration of practical implications for the studied organization.
Categorization of Projects
The first phase of the research focused on the categorization of product development projects, a crucial step for the standardization and optimization of the company’s internal processes. Initially, the projects and processes executed in development were identified, as detailed in Table 1 of the original study. This stage revealed a diversity of structured projects, with a well-defined scope, that align with the traditional project management approach. The exclusion of unstructured projects or those that would require agile or hybrid approaches reflects a conscious methodological delimitation, focused on the applicability of PMI (2017) tools for predictive contexts. The clarity in identifying these elements is, as Gil (2017) points out, the basis for any descriptive analysis, allowing for an understanding of the characteristics and relationships between the variables under study. For the company, this initial identification provided a panoramic view of its development portfolio, a prerequisite for any continuous improvement initiative and strategic resource allocation. The absence of a formal and standardized record of these projects and processes, prior to this study, generated inefficiencies and rework, as the team did not have a common reference base.
Subsequently, the stage of correlating processes to projects resulted in the elaboration of a matrix that mapped the processes directly involved in each type of project, as presented in Table 2 of the original document. This matrix is an invaluable artifact, as it transformed the fragmented perception of processes into an interconnected and transparent structure. The visualization of the relationships between projects and processes is fundamental for management, as it allows for the identification of bottlenecks, redundancies, and optimization opportunities. Project management literature, as emphasized by Valeriano (2005), highlights that understanding interdependencies is vital for project success. The matrix not only clarified these relationships for the technical team but also served as a communication tool, facilitating alignment between different departments and specialists. The immediate practical implication for the company is the ability to predict with greater accuracy the resources and competencies required for each new project, avoiding the underutilization or overload of teams and equipment, and promoting a culture of collaboration based on shared information.
The third stage consisted of defining the criteria and scales for project categorization, using a structured questionnaire that allowed participants (faculty and technical staff) to select and suggest criteria based on their experience, as detailed in Table 3 of the original study. The criteria of “Technical risk”, “Development complexity”, “Return on investment (benefit)”, and “Business impact”, with scales of “Low, medium, and high” or “Short, medium, and long”, were established as pillars for classification. Barbosa (2009) argues that project categorization is essential for organizations to understand the intrinsic characteristics of each project type, optimizing management. The technical team’s participation in this phase was crucial, as it ensured that the criteria were relevant and representative of the company’s operational reality, conferring greater validity and acceptance to the results. The practical implication is the creation of a common language for describing and evaluating projects, overcoming the subjectivity and individual interpretations that previously permeated decision-making. This allows management to evaluate new projects more objectively, allocating resources and defining execution strategies in a more informed and consistent manner.
The fourth and final stage of categorization culminated in the grouping of projects into categories, based on the assignment of criteria and scales, as illustrated in Table 4 of the original document. This affinity analysis resulted in the creation of four distinct categories (A, B, C, and D), as presented in Table 1.
Table 1. Groupings
|
Categories |
Description |
Projects |
|
A |
New product line |
Project 1 |
|
B |
New line extension |
Project 2 |
|
C |
Consolidated line extension |
Project 3 |
|
D |
Technology Extension |
Project 4, 5, 6 and 7 |
Source: Original research results
The grouping revealed that categories A (“New product line”) and B (“New line extension”) represent projects with higher technical risk, complexity, and investment demand, with longer development times. This finding corroborates Kerzner’s (2015) view that categorizing projects based on their complexity and impact is fundamental to guiding resource allocation and the application of management techniques. The predominance of projects in categories C (“Consolidated line extension”) and D (“Technology extension”) over the last 12 years, with approximately 346 new products, indicates an organizational strategy focused on incremental innovation, concentrating on improvements and optimizations of existing products. These projects, characterized by lower complexity and technical risk, tend to have greater predictability and less exposure to uncertainties, aligning with the portfolio management approach that seeks to balance high- and low-risk projects.
The distinction between categories A/B and C/D is crucial for the company. Projects in categories A and B, although less frequent (one per year, on average), are strategic for radical innovation and market expansion, requiring more robust planning and more intensive risk management. In contrast, projects in categories C and D, which are more numerous, demand standardized and efficient processes to ensure the agility and profitability of incremental innovation. The practical implication is the need to develop differentiated project management approaches for each category, recognizing that “one size does not fit all”. This means adapting the intensity of planning, the depth of risk analysis, and resource allocation according to the specific characteristics of each category, optimizing resource utilization and increasing the probability of success across the company’s entire project portfolio. Categorization, therefore, is not just a classification exercise, but a pillar for project governance and the formulation of innovation strategies.
Schedule Management
The second part of the research focused on schedule management, one of the pillars of project management, according to PMI (2017) best practices. This phase was divided into five planning processes, aiming to improve deadline estimation and activity control.
Plan Schedule Management
The first stage of schedule management resulted in the development of the Project Charter (TAP), which formalized the project’s initiation and established the foundations for schedule planning. Table 6 of the original document details the elements of the TAP, including the objective of developing schedule templates specific to each project category, the justification based on the lack of clarity and standardization, and the project’s assumptions and constraints. The formalization of the project through the TAP is an essential step, as highlighted by Vargas (2018), because the lack of adequate planning can lead to delays and excessive costs. For the company, the creation of the TAP represented a milestone, as it established a clear scope and aligned stakeholder expectations, mitigating the ambiguity and uncertainty that historically affected project initiation. The delimitation of the scope to only schedule planning processes, excluding monitoring and control, was a strategic decision to focus on the primary research objectives.
The Work Breakdown Structure (WBS) was developed to organize the project scope into a hierarchical structure, ranging from the categorization of projects to the registration of templates. Figure 1 illustrates this WBS.
Source: Original research results
Figure 1. Work Breakdown Structure (WBS)
The WBS (Work Breakdown Structure) is a fundamental tool for project management, as, according to PMI (2017), it breaks down the project work into smaller, more manageable components, facilitating the planning and execution of deliverables. The WBS developed for this study not only provided a visual representation of the scope but also served as a guide for the team, ensuring that all phases and deliverables were considered. Its practical application in the company lies in its ability to demystify the project’s complexity, making it more accessible and understandable for everyone involved. This promotes a shared understanding of what needs to be done, who is responsible, and how the different parts of the project fit together, which is vital for coordinating multidisciplinary teams and preventing communication failures.
The Schedule Management Plan, detailed in Table 2 of the original study, organized the main guidelines and methods for the elaboration of the schedules.
Table 2. Schedule Management Plan
|
Element |
Description |
|
Purpose of the Plan |
This schedule management plan defines guidelines and methods that will guide the development of schedule templates for each structured project category. |
|
Schedule template |
The schedules will be developed using the traditional approach applied to predictive projects, with a fixed and defined scope, employing the Precedence Diagramming Method (PDM) to establish the sequence of activities and the PERT method for three-point duration estimates (optimistic, most likely, and pessimistic). |
|
Schedule Management Processes |
The approach of this study is limited to the processes of the planning group (Plan Schedule Management, Define Activities, Sequence Activities, Estimate Durations, and Develop Schedule). |
|
Units of measurement |
Use of business days for duration estimates of all activities planned in the schedule. |
|
Level of Detail |
The activities must be detailed to the level necessary to allow for reliable estimates. |
|
Duration Parameters |
Estimates will be prepared assuming one person as a standard parameter. Estimates should be validated with the technical team and adjusted based on previous projects, using optimistic, most likely, and pessimistic values according to the PERT technique. |
|
Decision points |
Establish a gate at the end of the project phase for all project categories. This gate will be registered as a milestone in the schedule, with no duration, and will represent the formal decision point on the continuation or closure of the project, through the approval or rejection of the MR (project initiation document). |
|
Roles and Responsibilities |
Engineer (research author): conduct schedule management, apply techniques, tools, and develop templates. Manager: review and approve the schedule management plan, validating activities, sequences, and estimates. Engineers and technicians: provide information and participate in the validation of activities, sequencing, and estimates. |
Source: Original research results
This plan established that the schedules would be developed using a traditional approach for predictive projects, employing the Precedence Diagramming Method (PDM) for sequencing and the PERT (Program Evaluation and Review Technique) method for duration estimates. The choice of these methodologies aligns with the recommendations of Bernal (2016), who points to the PMI as one of the main international references for project management. The definition of business days as the unit of measurement and the detailing of activities to a level that allowed for reliable estimates are examples of the standardization introduced. The inclusion of “Gates” as formal decision points in the schedule is a robust practice that, according to Vargas (2018), ensures that the project only advances after the approval of critical milestones, minimizing risks and rework. The practical implications for the company are profound: the plan offers a clear and replicable structure for schedule planning, reducing dependence on tacit and individual knowledge. This not only improves the consistency and quality of planning but also facilitates the integration of new team members and the scalability of product development operations.
Define Key Activities
The second phase of schedule management, defining activities, involved decomposing the processes of each category into detailed activities. Table 8 of the original document presents the list of activities for the four project categories. This process was the result of collaborative work with the technical team, using the brainstorming technique to identify and organize all necessary tasks. The PMI (2017) emphasizes that defining activities is the process of identifying and documenting the specific actions to be performed to produce the project deliverables. The collaborative approach ensured that the activity list was comprehensive and compatible with the particularities of each project category, serving as a practical guide for execution and mitigating the risk of not completing essential steps. Before this study, the absence of a detailed and standardized list of activities led to diverse interpretations and, frequently, to the omission of critical steps, resulting in delays and the need for rework. The practical implication for the company is the creation of a clear roadmap for each type of project, which not only guides the team in execution but also serves as a basis for estimating resources and deadlines, and for progress evaluation. The standardization of activities also facilitates the training of new employees, reducing the learning curve and increasing the overall efficiency of the R&D department.
Sequence Activities
In the third phase, activity sequencing, the dependency relationships between activities were established based on the Precedence Diagramming Method (PDM), according to PMI (2017) guidelines. Table 9 of the original document details these dependencies for categories A, B, C, and D. The PDM classifies relationships into four types: finish-to-start (FS), finish-to-finish (FF), start-to-finish (SF), and start-to-start (SS), allowing for a logical structuring of the interdependence between project activities. Most activities presented a finish-to-start (FS) dependency relationship, which is characteristic of sequential processes where one stage must be completed for the next to begin. Monteiro (2018) emphasizes that the correct definition of activity sequencing is essential to ensure process efficiency and the quality of the final outcome.
A crucial aspect identified in this phase was the presence of “Gates” (formal decision points) in all project categories, as defined in the Schedule Management Plan. These “Gates” represent critical moments where the project is evaluated to determine its continuation or closure, depending on the approval of preceding activities. The inclusion of these decision milestones is a robust practice that, according to Wysocki (2020), is fundamental for effective project control, allowing for strategic interventions and minimizing the waste of resources on unviable projects. The practical implication for the company is the introduction of a quality and viability control mechanism at strategic points in the project lifecycle. This not only reduces the risk of investing in projects that do not meet requirements or have become unviable, but also promotes a culture of responsibility and accountability, where teams are encouraged to deliver high-quality results at each phase.
Despite the relevance of the sequencing, a methodological limitation identified was the non-consideration of resource constraints, with duration and dependency estimates elaborated assuming a single executor as the standard parameter. Although this simplification allowed focusing on the logic of activities, in practice, the allocation of multiple or limited resources can alter the critical path and the total project duration. However, the research treated parallel tasks as demanding distinct resources, especially in activities involving document approval or execution by suppliers. This approach, although simplified, still offers a basis for future resource optimization analyses, which could be explored in subsequent studies. The practical implication is that, although the templates provide a logical structure, the company must be aware that real-time resource management will require adjustments and additional considerations, especially in environments with high demand and shared resources.
Estimate Activity Durations
The fourth phase, estimating activity durations, used the three-point Program Evaluation and Review Technique (PERT) method to predict the time required for each activity. Equation (1) represents the triangular distribution adopted:
tE = (tO + 4·tM + tP) / 6 (1)
where tE is the expected duration, tM is the most likely duration, tO is the optimistic duration, and tP is the pessimistic duration (PMI, 2017). Table 10 of the original document presents the duration estimates for each activity by category, considering these three scenarios. The choice of the PERT method is justified by its ability to incorporate the uncertainty inherent in project duration estimates, providing a more realistic forecast than a single estimate. The basis for these estimates was seven years of historical data from isolated planning and project records, complemented and validated in meetings with the manager and those responsible for the processes. This approach, which combines historical data with expert opinion, is, according to Cavalcanti and Silveira (2016), a robust practice for risk management and improving the accuracy of estimates.
The practical implication for the company is the transition from optimistic and often unrealistic estimates to more robust and data-driven forecasts. Previously, the lack of standardization and reliance on ideal scenarios resulted in unreliable schedules and frequent delays. With PERT, the company now has a tool to quantify uncertainty and plan with greater resilience. This allows for better negotiation of deadlines with clients and suppliers, more efficient resource allocation, and the ability to proactively identify and mitigate delay risks. Furthermore, the documentation of these estimates creates a knowledge base that can be refined and improved in future projects, contributing to a continuous improvement cycle in Time Management.
Develop Schedule
In the fifth and final planning phase, schedule templates for each project category were developed in the “Project Management” application of the 3DExperience platform. This tool allowed for the organization of activities with their respective durations and dependencies, as well as visualization of the project’s critical path. Figure 2 presents the project template interface.
Source: Original research results
Figure 2. Project Templates
The use of an integrated platform like 3DExperience represents a significant advancement for the company. Kinoshita and Lira (2024) highlight that platforms like this contribute to more efficient schedule control and monitoring by centralizing information and enabling integrated project visualization. Although the tool was available, its prior non-use represented a missed opportunity to optimize management. The creation of templates provided an integrated view of the project, facilitating the identification of critical steps and deadline prediction. The practical implication is the standardization of the schedule creation process, ensuring that all projects within the same category follow a consistent logical and temporal structure. This reduces variability in planning, facilitates performance comparison between projects, and allows the team to focus on execution rather than spending excessive time on initial schedule structuring.
Figure 3 presents the Gantt chart for Category A projects, illustrating the distribution of activities, their durations, and the milestones defined in the management plan.
Source: Original research results
Figure 3. Category A Project Template
The Gantt chart, with the aid of the 3DExperience platform, allowed for the identification of the project’s critical path (highlighted in red). The critical path is the sequence of activities that determines the shortest possible project duration, and any delay in a critical path activity will delay the entire project (PMI, 2017). The chart analysis for Category A revealed that the MR Approval activity, although lengthy, is not part of the critical path due to the occurrence of parallel phases, such as FEA Simulation and Equipment, which have float. This finding is crucial as it allows management to focus its efforts on activities that truly impact the project’s final deadline, optimizing resource allocation and decision-making.
Gantt charts for Categories B, C, and D (Figures 6, 7, and 8 of the original document, respectively) were also developed, exhibiting distinct characteristics. In Category B, the total development timeframe is shorter than in Category A, due to the absence of the Research phase and a reduced number of steps in the Design, Industrialization, and Laboratory phases. This reflects the lower complexity and risk associated with “New line extension” projects. In Category C, the MR Approval activity is part of the critical path, unlike in categories A and B, due to the absence of the FEA Simulation phase. This difference highlights how the project structure directly influences the critical path and the need for attention to different activities. Category D, in turn, presents the shortest execution time, consistent with its low complexity level.
Carvalho and Rabechini Jr. (2018) and Wysocki (2020) highlight the effectiveness of the Gantt chart and the critical path method as essential tools for project planning and control. The visual clarity and simplicity of Gantt facilitate risk identification and progress communication. The practical implication for the company is the ability to proactively manage deadlines, identify critical activities, and optimize task sequencing. The visualization of the critical path allows the team and management to understand where efforts should be concentrated to avoid delays, ensuring that projects are delivered on time and within budget. Furthermore, the existence of “Gates” and “Milestones” in all templates, with a duration of zero days, reinforces the importance of decision points and the formal completion of project phases, providing rigorous control over the progress and quality of deliverables.
Review and Validation of Templates
The final stage of the research involved reviewing and validating the schedule templates with the manager and the technical team in a meeting held in February 2026. During this evaluation, it was found that the deadlines estimated before the template development showed significant variations, ranging from 3 to 6 months. This discrepancy can be attributed to the absence of standardization in previous planning, where not all processes and activities were properly considered and integrated. The lack of a well-defined sequencing of activities and the use of estimates based on optimistic scenarios resulted in unreliable forecasts, without considering margins or buffers, which frequently led to rework and project delays.
The validation of the templates by the technical team and management is a crucial outcome, as it confers credibility and internal acceptance to the developed tools. The recognition that integrated planning across processes contributes to more realistic and secure estimates, in addition to guiding and ensuring the execution of essential activities, validates the approach adopted in this study. The most immediate practical implication is the improvement of the predictability and reliability of project deadlines. By integrating all processes and activities into standardized templates, the company can significantly reduce delays and costs associated with rework. Furthermore, standardization facilitates communication between teams, as everyone works with a consistent and understandable information base. This promotes a more rigorous and data-driven planning culture, which is essential for competitiveness in a dynamic sector such as agricultural tires. Validation also paves the way for the effective implementation of these templates, transforming a theoretical tool into a practical management instrument.
Final Considerations
The present study achieved its main objective by identifying and categorizing projects in an agricultural tire industry and developing schedule templates, providing greater process clarity, better guidance, and more realistic deadline forecasting. Project categorization demonstrated the predominance of less complex and lower-risk projects, focused on incremental innovation, while also revealing the existence of radical innovation projects, which demand more robust planning. This distinction is fundamental for strategic resource allocation and the adaptation of management methodologies.
The development of specific schedule templates for each project category allowed for differentiated planning, adequately addressing activities, sequencing, duration estimates, and decision-making milestones. These templates integrated processes that were previously planned in isolation, contributing to more realistic deadline estimates and mitigating failures due to the absence of structured planning. The use of the 3DExperience platform and the application of methods such as the Precedence Diagram and PERT reinforce the robustness of the methodology.
This case study established a solid foundation for planning future projects in the company. However, the implementation of this change will require an adaptation period and continuous commitment from the team, especially during high-demand moments. The development and updating of schedules may become challenging, requiring organization and discipline. As future work, it is suggested to monitor and control project execution using the developed templates, in order to evaluate their effectiveness in practice and identify opportunities for continuous improvement. This application will allow refining the proposed models and consolidating a more mature and efficient project management culture within the organization.
4. Conclusion
It is concluded that the objective was achieved by identifying and categorizing projects in an agricultural tire industry and developing schedule templates. This approach provided greater process clarity, better guidance, and more realistic deadline forecasting. The categorization revealed the predominance of incremental innovation projects and the existence of radical innovation projects, allowing for differentiated planning and resource allocation. The templates, developed based on PMI best practices and using the Precedence Diagramming Method and PERT on the 3DExperience platform, integrated previously isolated processes, contributing significantly to more reliable deadline estimates and mitigating failures due to the absence of structured planning. Validation by the technical team confirmed the relevance and applicability of these tools for the company’s project management.
However, this study presented limitations, such as the non-consideration of resource constraints in duration estimates, which assumed a single executor as the standard. Furthermore, the effective implementation of the templates will require a period of adaptation and continuous commitment from the team, especially in high-demand scenarios, where the elaboration and updating of schedules can be challenging. For future work, it is suggested to monitor and control project execution using the developed templates, evaluating their effectiveness in practice. This evaluation will allow for the identification of continuous improvement opportunities, refinement of the proposed models, and consolidation of a more mature and efficient project management culture within the organization.
Bibliographic References
Associação Nacional da Indústria de Pneumáticos [ANIP]. 2024. Importação desleal de pneu ameaça empregos, investimentos e meio ambiente no país, alerta ANIP. Disponível em: <https://www.anip.org.br/releases/importacao-desleal-de-pneu-ameaca-empregos-e-investimentos-no-pais-alerta-anip/>. Acesso em 2 set. 2025
Barbosa, I. M. 2009. Uma proposta de um modelo de referência para categorização de projetos. Dissertação de Mestrado em Ciência da Computação. Centro de Informática de Pernambuco. Universidade Federal de Pernambuco, Recife, PE, Brasil.
Bernal, P. S. M. 2016. Gerenciamento de projeto na prática. 2ªed. Saraiva, São Paulo, SP, Brasil.
Carvalho, M.; Rabechini, R. 2018. Fundamentos em Gestão de Projetos: construindo competências para gerenciar projetos. 5ed. Atlas, São Paulo, SP, Brasil.
Cavalcanti, F. R. P.; Silveira, J A. N. 2016. Fundamentos de Gestão de Projeto: gestão de riscos. 1ed. Atlas, São Paulo, SP, Brasil. Disponível em: <https://integrada.minhabiblioteca.com.br/books/9788597005622>. Acesso em: 28 set. 2025.
Empresa Brasileira de Pesquisa Agropecuária [Embrapa]. 2022. Monitoramento de máquinas e equipamentos da frota agrícola da Secretaria de Agricultura e Meio Ambiente do município de Presidente Castello Branco, SC. Disponível em: <https://www.infoteca.cnptia.embrapa.br/infoteca/bitstream/doc/1149385/1/final10054.pdf>. Acesso em: 8 set. 2025.
Gil, A. C. 2017. Como Elaborar Projetos de Pesquisa. Atlas, São Paulo, SP, Brasil.
Instituto Brasileiro de Geografia e Estatística [IBGE]. 2025. Indicadores IBGE. Disponível em: <https://biblioteca.ibge.gov.br/visualizacao/periodicos/2121/cnt_2025_1tri.pdf>. Acesso em: 30 ago. 2025.
Kerzner, H. 2006. Gestão de Projetos: as melhores práticas. 2ed. Bookman, Porto Alegre, RS, Brasil.
Kerzner, H. 2015. Gerenciamento de Projetos: Uma Abordagem Sistêmica para Planejamento, Programação e Controle. 11ª ed. Blucher, São Paulo, SP, Brasil.
Kinoshita, L.; Lira, Y. C. 2024. Gestão de projetos utilizando PMBOK e 3D Experience. Trabalho de Graduação em Tecnólogo em Projetos de Estruturas Aeronáuticas. FATEC de São José dos Campos. Faculdade de Tecnologia de São José dos Campos, São José dos Campos, SP, Brasil.
Monteiro, P. M. de S. C. 2018. Otimização do gerenciamento de tempo em projetos com restrições de recurso e múltiplos modos de processamento: Estudo de caso na construção civil. Dissertação de Mestrado em Engenharia de Produção. Centro de Tecnologia, Universidade Federal de Paraíba, João Pessoa, PB, Brasil.
Moreira, A. M.; da Silva, R. S.; Palma, M. A. M. 2010. Análise de gerenciamento de tempo aplicado a um projeto de petróleo. Revista de Gestão e Projetos 1(2): 128-146.
Neves, M. F. 2021. Ferramentas para o futuro do agro: Estratégias para posicionar o Brasil como fornecedor mundial sustentável de alimentos, bioenergia e outros agroprodutos. 1ª ed. Gente, São Paulo, SP, Brasil.
Project Management Institute [PMI]. 2017. Um guia do conhecimento em gerenciamento de projetos [Guia PMBOK]. 6ed. Project Management Institute, Newtown Square, PA, USA.
Valeriano, Dalton. 2005. Moderno Gerenciamento de Projetos. Prentice Hall, São Paulo, SP, Brasil.
Vargas, R. V. 2018. Gerenciamento de Projetos: Estabelecendo Diferenciais Competitivos. 9ªed. Brasport, Rio de Janeiro, RJ, Brasil.
Wysocki, R.; 2020. Gestão eficaz de projetos: como gerenciar com excelência projetos tradicionais, ágeis e extremos. 1ed. Saraiva, São Paulo, SP, Brasil. Disponível em: <https://integrada.minhabiblioteca.com.br/books/9788571441002>. Acesso em: 10 jan. 2026.