October 26, 2026
Activity schedule management in small architectural offices
Alícia Dantas Galdino Duarte; Pedro Henrique Fabri Zanini
DOI: 10.22167/2675-6528-202600499
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Project management in the architecture sector has faced significant challenges related to meeting deadlines and organizing internal processes. The study aimed to investigate planning failures in small offices and propose an assertive schedule model for interior design projects. The methodology employed consisted of a mixed-methods case study, which used quantitative research with professionals in the field and qualitative interviews with an office manager. The results indicated low project management maturity in the sector, revealing that 70% of the interviewed architects did not use phased structured schedules and 80% did not monitor the time spent on operational tasks. In the specific case study, excessive centralization of functions in the coordinator and dependence on generic tools, such as Excel, were identified, compromising the predictability of deliverables. As a solution, the implementation of a Gantt Chart based on the Work Breakdown Structure (WBS) was proposed. The application of a 30-day baseline schedule, combined with task redistribution among the team, proved effective in reducing bottlenecks in the preliminary design phase and protecting the workflow against scope changes. It was concluded that process standardization and the adoption of control milestones are essential to ensure operational efficiency in architecture offices.
Keywords: Operational efficiency; Architecture Office; Project Management; Gantt Chart; Interior Design.
1. Introduction
After the Industrial Revolution, at the end of the 19th century, European companies recognized the need for more efficient organizational methods to ensure service quality and meet deadlines. This context drove the emergence of project management principles, with an important milestone being the creation of the Gantt chart in 1910 by Henry Gantt, an innovation widely disseminated and significant for the field.
Project management, defined as the application of knowledge and techniques to plan and control activities (CARVALHO; RABECHINI, 2011), is based on the “Triple Constraint”: scope, cost, and time. Changes in one of these pillars affect the others, demonstrating that ineffective schedule management compromises deadlines, financial viability, and quality. Such deficiency can lead to rework, scope creep, customer dissatisfaction, budget overruns, and project failure (PMBOK, 2017).
In Brazil, “time” management constitutes one of the biggest challenges for architecture and civil construction offices. In interior projects, the planning of the activity schedule is crucial for balancing creative demands and deadline limitations. However, there is a perceived gap in the adoption of effective time management practices.
The implementation of schedules in small architecture offices is hindered by the hybrid nature of work. Interior design projects, being intellectual and creative services, are frequently interrupted by external variables, such as client approvals or supplier volatility. This dynamic generates “critical uncertainty,” where the lack of control results in the loss of mastery over the professional’s productive capacity and profitability.
Quantitative research revealed low management maturity in the sector. Seventy percent of the architects interviewed do not use phased structured schedules, and eighty percent do not monitor the time spent on operational tasks. This lack of standardization and control leads to unstructured deadline estimations, resulting in bottlenecks and delays. The preliminary design phase, in particular, is identified as the most vulnerable to delays, due to scope fluctuations arising from the validation of client expectations.
The case study identified excessive centralization of functions in the coordinator and dependence on generic tools, such as Excel. This approach compromises the predictability of deliverables and the clarity of internal productivity, resulting in overload and delays. The lack of historical time recording and the absence of process standardization are crucial challenges, indicating that technical and creative expertise is not always complemented by effective operational control methods (Vargas, 2016; Cleland; Ireland, 2007).
To mitigate these challenges, visual management methodologies are essential. The Gantt Chart, a traditional and effective tool, allows for the visualization of precedence between stages and the monitoring of the critical path (PMI, 2017). Although the Kanban Method (ANDERSON, 2011) is useful for continuous flows, interior projects, with their rigid critical path and interdependencies (detailing, rendering), benefit more from the Gantt structure, especially when based on the Work Breakdown Structure (WBS) (Vargas, 2016).
Given the need for professionalization of management in interior architecture and the gap in the application of structured schedules in small offices, this study is justified by the search for a model that protects profitability and design quality. Thus, the objective of this work is to investigate planning failures in small architecture offices and propose an assertive schedule model for interior projects, capable of conferring predictability and efficiency to the design process.
2. Material and Methods
The present study adopted a mixed methodological approach, combining quantitative and qualitative elements to investigate planning failures in small architecture firms and propose a schedule model. The research was structured in five main phases, ranging from theoretical review to data triangulation. This design allowed for a comprehensive understanding of the problem, confronting theory with observed market practices and a specific case study.
The first phase consisted of a literature review, with the survey and analysis of theoretical references on project management, scheduling methods, and interior project management. This stage aimed to scientifically ground subsequent methodological decisions and establish a solid conceptual basis for the comparison between theoretical principles and identified practices.
The second phase was a case study, focused on the analysis of a small-sized architecture firm. An operational diagnosis was carried out through an on-site visit, analyzing activities, deadlines, number of collaborators, and task division. The team consisted of two architects and an intern, and the analysis of assignments revealed a centralization of activities with Architect II, who acted as coordinator.
Next, the stages of the design process were defined, identifying and detailing eleven main activities, from client contact to final delivery. For the diagnosis of time and workload, the average time spent on each activity was measured. Control spreadsheets, specifically the Excel software, were used to record and compare the planned time with the executed time in eleven interior design projects delivered in the first half of 2025.
The third phase involved a quantitative survey to understand the reality of the interior architecture market. A structured form was applied, via Google Forms, to ten architects, including self-employed professionals and managers of small offices (two to five collaborators). Data collection occurred between March 9th and 11th, 2026, with the objective of identifying management patterns, scheduling tools, and difficulties faced.
The fourth phase consisted of a qualitative research, carried out through a structured interview with the coordinator of the studied architecture office. The purpose was to validate the previously collected data and deepen the understanding of the office’s operational dynamics, from the coordination perspective, identifying the influences of decisions on the workflow and the barriers to efficiency.
The fifth and final phase of the research consisted of triangulating the data collected in the previous stages. This comparative analysis was fundamental for decision-making regarding the most appropriate management methodology for small-sized architecture offices. Based on this triangulation, the development of an assertive schedule model for interior design projects was proceeded.
For the structuring of the proposed schedule, the concept of Project Breakdown Structure (WBS) was applied, as suggested by Vargas (2016). This approach allowed for the identification and categorization of interior project tasks into transversal processes, which occur continuously, and sequential processes, which obey a strict order of precedence. The development of the baseline schedule considered a thirty-day cycle, dimensioned from the operational limitations identified in the case study.
Additionally, to mitigate the workload identified for the office coordinator, a redistribution of tasks among the team was proposed. This proposal was based on resource efficiency (CLELAND; IRELAND, 2007), aiming to optimize workflow and protect the schedule against scope changes. The developed methodology sought to provide predictability and efficiency to the interior design project process, aligning with PMI (2017) principles for visualizing interdependencies and anticipating bottlenecks.
3. Results and Discussion
Project management in the interior design sector, especially in small offices, revealed a scenario of low managerial maturity, characterized by a predominantly intuitive and reactive approach. The research findings indicated significant flaws in schedule planning and control, directly impacting the predictability of deliverables and operational efficiency. The investigation sought to understand the roots of these challenges and propose a more assertive time management model, aligned with the particularities of the creative and technical process of architecture.
The quantitative research, conducted with ten architects, revealed a substantial gap in the adoption of structured management practices. It was found that 70% of the professionals interviewed did not use phase-based schedules to estimate deadlines. This lack of standardization contrasts with the guidelines of the Project Management Institute (PMI, 2017), which emphasize the schedule as a fundamental tool for defining the temporal horizons of a project, ensuring the viability and quality of deliverables. The predominance of unstructured estimates justifies the recurring bottlenecks and delays observed in the sector.
Additionally, informality extends to activity control, with 30% of respondents admitting to not using any formal monitoring method. The preliminary design phase was identified by 60% of professionals as the most vulnerable to delays, a result consistent with the creative and iterative nature of this stage, where client expectation validation frequently generates scope fluctuations. The management of these scope changes also proved fragmented: 40% performed formal schedule adjustments, 10% applied additional fee charges, and 50% had no defined standard, evidencing a vulnerability in contractual management.
One of the most critical data points from quantitative research was the finding that 80% of professionals do not measure the time spent per task. This oversight prevents the creation of performance indicators (KPIs) and the precise calculation of profitability, as recommended by Vargas (2016), who points to the definition and recording of activities as foundations for realistic schedules. Without historical time tracking, the team perceives the implementation of management software as bureaucracy, rather than strategic support, compromising the project’s final performance (Cleland; Ireland, 2007).
The qualitative research, through an interview with the coordinator of the studied architecture office, deepened the understanding of the operational dynamics. An excessive centralization of activities was observed in Architect II, who accumulated technical, supervisory, and service functions. The estimation of deadlines was based on the project typology, with commercial services demanding 20 days and residential ones varying between 30 and 45 days. The coordinator confirmed that the preliminary design was the main bottleneck, due to frequent scope changes requested by clients, which impacted the planned schedule.
Information management in the office lacked robust tools, being limited to the use of Excel spreadsheets. An attempt to implement Trello software did not gain team adherence, due to the difficulty of adapting the tool to the different natures of projects. The absence of monitoring the time spent by each collaborator on their tasks prevented a clear view of internal productivity, resulting in a sharp oscillation in the workload of the 11 projects delivered in the first half of 2025. This dynamic generated a “cascade effect”, where modifications in one project reduced the available time for other ongoing contracts.
Another critical point identified was the underutilization of standardization resources, such as the block and template library, whose use was not uniform among collaborators. The coordinator emphasized that the biggest challenge lay in the organization of internal processes and in the need to understand the real duration of each task for assertive delivery promises. In summary, management was based on intuition and service typology, to the detriment of precise metrics, reinforcing the need for a management model that was rigorous, yet adaptable to the demands of a small-sized office.
Given this diagnosis, data triangulation allowed the identification of the Gantt Chart as the most suitable tool for the reality of small-sized architecture offices focused on interiors. Although the Kanban method (Anderson, 2011) is effective for continuous flows, interior design projects have a rigid critical path, with stages such as detailing and rendering depending on the preliminary design approval. The Gantt model, based on PMI (2017) principles, allows visualization of the interdependence between processes and anticipation of bottlenecks, being more appropriate for this context.
For the structuring of the proposed schedule, the concept of Project Breakdown Structure (WBS) was applied, as suggested by Vargas (2016). This approach allowed for the identification of two types of tasks: transversal processes, such as customer service and social media management, which occur continuously throughout the project lifecycle; and sequential processes, which include technical stages like survey, briefing, 3D modeling, rendering, and detailing, obeying a strict order of precedence.
The proposed baseline schedule was sized for a 30-day cycle, considering the operational limitations identified in the case study. Client Contact, Measurement Survey, and Briefing activities are allocated in the first week. 3D modeling and detailing, identified as the most critical phases, each consume two weeks. Image and video rendering is scheduled for 48 hours, while the preliminary design presentation, a crucial control milestone, has an average duration of one hour and thirty minutes. The final project delivery is allocated in the fourth week, with a duration of two hours.
This workflow establishes 3D modeling as the start of the creative phase and the presentation of the preliminary design as a control milestone. To mitigate the “cascade effect” of scope changes, the methodology foresees an extension of the deadline by up to one week, preventing delays in one project from contaminating other active contracts. To enable this workflow and reduce the coordinator’s overload, a redistribution of tasks based on resource efficiency was proposed (Cleland; Ireland, 2007).
The activity distribution proposal assigns the Architect I and the Coordinator to Client Contact, while the Measurement Survey is shared between the Coordinator and the Intern. The Architect I is responsible for the Briefing. The entire team works on 3D modeling and, subsequently, on the preliminary design presentation. The Coordinator handles image and video rendering, and the detailing is divided between the Coordinator and the Intern. The final project delivery involves the entire team, and Social Media and Accounting activities are continuously assigned to the Architect I.
This transition from intuitive management to a critical path-based schedule, with a balanced separation of assignments, allows the office to protect its profitability and maintain project quality. The simultaneous execution of projects becomes viable without compromising contractual deadlines. In summary, strict adherence to this operational sequence functions as a control instrument that transforms abstract planning into predictable and professional execution, conferring greater efficiency and predictability to the interior design project process.
4. Conclusion
This study investigated planning failures in small architectural offices, seeking to propose an assertive schedule model for interior design projects, capable of conferring predictability and efficiency to the design process. Low management maturity was observed in the sector; most professionals did not use phase-structured schedules to estimate deadlines, nor did they monitor time spent on operational tasks. In the case study, excessive centralization of functions in the coordinator and dependence on generic tools, such as Excel, were identified, which compromised the predictability of deliverables. The preliminary design phase, in particular, proved to be the most vulnerable to delays due to scope fluctuations, and the management of these changes was fragmented, without defined standards. The absence of historical time records prevented precise calculation of productivity and profitability, reinforcing the need for effective operational control methods.
As a solution, the implementation of a Gantt Chart based on the Project Breakdown Structure (WBS) was proposed, with a 30-day baseline schedule and task redistribution. This approach proved effective in reducing bottlenecks in the pre-design phase and protecting the workflow against scope changes, allowing for simultaneous project execution without compromising contractual deadlines. The study’s main contribution lies in demonstrating that process standardization and the adoption of control milestones are essential to ensure operational efficiency and financial sustainability in small architectural firms, protecting profitability and design quality. The professionalization of management, therefore, does not inhibit creativity but safeguards it, providing greater predictability and professionalism to the interior design process. For future work, it is suggested to investigate cloud-based management software that allows for the automation of these schedules, facilitating team adherence.
Bibliographic References
ANDERSON, D. J. (2011). Kanban: Mudança Evolucionária de Sucesso para seu Negócio de Tecnologia. São Paulo: Blue Hole Press.
CARVALHO, M. M.; RABECHINI JÚNIOR, R. (2011). Fundamentos em gestão de projetos. 3. ed. São Paulo: Atlas.
CLELAND, D. I.; IRELAND, L. R. (2007). Gerenciamento de projetos. 2. ed. São Paulo: LTC.
PROJECT MANAGEMENT INSTITUTE [PMI]. (2017). Guia do Conhecimento em Gerenciamento de Projetos: Guia PMBOK. 6. ed. [S. l.]: PMI.
VARGAS, R. V. (2016). Gerenciamento de projetos: Estabelecendo diferenciais competitivos. 8. ed. São Paulo: Brasport.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq