Activity schedule management in small architectural offices

Alícia Dantas Galdino Duarte; Pedro Henrique Fabri Zanini

DOI: 10.22167/2675-6528-202600499

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Project management in the architecture sector has faced significant challenges related to meeting deadlines and organizing internal processes. The study aimed to investigate planning failures in small offices and propose an assertive schedule model for interior design projects. The methodology employed consisted of a mixed-methods case study, which used quantitative research with professionals in the field and qualitative interviews with an office manager. The results indicated low project management maturity in the sector, revealing that 70% of the interviewed architects did not use phased structured schedules and 80% did not monitor the time spent on operational tasks. In the specific case study, excessive centralization of functions in the coordinator and dependence on generic tools, such as Excel, were identified, compromising the predictability of deliverables. As a solution, the implementation of a Gantt Chart based on the Work Breakdown Structure (WBS) was proposed. The application of a 30-day baseline schedule, combined with task redistribution among the team, proved effective in reducing bottlenecks in the preliminary design phase and protecting the workflow against scope changes. It was concluded that process standardization and the adoption of control milestones are essential to ensure operational efficiency in architecture offices.

Keywords: Operational efficiency; Architecture Office; Project Management; Gantt Chart; Interior Design.

1. Introduction

After the Industrial Revolution, at the end of the 19th century, European companies recognized the need for more efficient organizational methods to ensure service quality and meet deadlines. This context drove the emergence of project management principles, with an important milestone being the creation of the Gantt chart in 1910 by Henry Gantt, an innovation widely disseminated and significant for the field.

Project management, defined as the application of knowledge and techniques to plan and control activities (CARVALHO; RABECHINI, 2011), is based on the “Triple Constraint”: scope, cost, and time. Changes in one of these pillars affect the others, demonstrating that ineffective schedule management compromises deadlines, financial viability, and quality. Such deficiency can lead to rework, scope creep, customer dissatisfaction, budget overruns, and project failure (PMBOK, 2017).

In Brazil, “time” management constitutes one of the biggest challenges for architecture and civil construction offices. In interior projects, the planning of the activity schedule is crucial for balancing creative demands and deadline limitations. However, there is a perceived gap in the adoption of effective time management practices.

The implementation of schedules in small architecture offices is hindered by the hybrid nature of work. Interior design projects, being intellectual and creative services, are frequently interrupted by external variables, such as client approvals or supplier volatility. This dynamic generates “critical uncertainty,” where the lack of control results in the loss of mastery over the professional’s productive capacity and profitability.

Quantitative research revealed low management maturity in the sector. Seventy percent of the architects interviewed do not use phased structured schedules, and eighty percent do not monitor the time spent on operational tasks. This lack of standardization and control leads to unstructured deadline estimations, resulting in bottlenecks and delays. The preliminary design phase, in particular, is identified as the most vulnerable to delays, due to scope fluctuations arising from the validation of client expectations.

The case study identified excessive centralization of functions in the coordinator and dependence on generic tools, such as Excel. This approach compromises the predictability of deliverables and the clarity of internal productivity, resulting in overload and delays. The lack of historical time recording and the absence of process standardization are crucial challenges, indicating that technical and creative expertise is not always complemented by effective operational control methods (Vargas, 2016; Cleland; Ireland, 2007).

To mitigate these challenges, visual management methodologies are essential. The Gantt Chart, a traditional and effective tool, allows for the visualization of precedence between stages and the monitoring of the critical path (PMI, 2017). Although the Kanban Method (ANDERSON, 2011) is useful for continuous flows, interior projects, with their rigid critical path and interdependencies (detailing, rendering), benefit more from the Gantt structure, especially when based on the Work Breakdown Structure (WBS) (Vargas, 2016).

Given the need for professionalization of management in interior architecture and the gap in the application of structured schedules in small offices, this study is justified by the search for a model that protects profitability and design quality. Thus, the objective of this work is to investigate planning failures in small architecture offices and propose an assertive schedule model for interior projects, capable of conferring predictability and efficiency to the design process.

2. Material and Methods

The present study adopted a mixed methodological approach, combining quantitative and qualitative elements to investigate planning failures in small architecture firms and propose a schedule model. The research was structured in five main phases, ranging from theoretical review to data triangulation. This design allowed for a comprehensive understanding of the problem, confronting theory with observed market practices and a specific case study.

The first phase consisted of a literature review, with the survey and analysis of theoretical references on project management, scheduling methods, and interior project management. This stage aimed to scientifically ground subsequent methodological decisions and establish a solid conceptual basis for the comparison between theoretical principles and identified practices.

The second phase was a case study, focused on the analysis of a small-sized architecture firm. An operational diagnosis was carried out through an on-site visit, analyzing activities, deadlines, number of collaborators, and task division. The team consisted of two architects and an intern, and the analysis of assignments revealed a centralization of activities with Architect II, who acted as coordinator.

Next, the stages of the design process were defined, identifying and detailing eleven main activities, from client contact to final delivery. For the diagnosis of time and workload, the average time spent on each activity was measured. Control spreadsheets, specifically the Excel software, were used to record and compare the planned time with the executed time in eleven interior design projects delivered in the first half of 2025.

The third phase involved a quantitative survey to understand the reality of the interior architecture market. A structured form was applied, via Google Forms, to ten architects, including self-employed professionals and managers of small offices (two to five collaborators). Data collection occurred between March 9th and 11th, 2026, with the objective of identifying management patterns, scheduling tools, and difficulties faced.

The fourth phase consisted of a qualitative research, carried out through a structured interview with the coordinator of the studied architecture office. The purpose was to validate the previously collected data and deepen the understanding of the office’s operational dynamics, from the coordination perspective, identifying the influences of decisions on the workflow and the barriers to efficiency.

The fifth and final phase of the research consisted of triangulating the data collected in the previous stages. This comparative analysis was fundamental for decision-making regarding the most appropriate management methodology for small-sized architecture offices. Based on this triangulation, the development of an assertive schedule model for interior design projects was proceeded.

For the structuring of the proposed schedule, the concept of Project Breakdown Structure (WBS) was applied, as suggested by Vargas (2016). This approach allowed for the identification and categorization of interior project tasks into transversal processes, which occur continuously, and sequential processes, which obey a strict order of precedence. The development of the baseline schedule considered a thirty-day cycle, dimensioned from the operational limitations identified in the case study.

Additionally, to mitigate the workload identified for the office coordinator, a redistribution of tasks among the team was proposed. This proposal was based on resource efficiency (CLELAND; IRELAND, 2007), aiming to optimize workflow and protect the schedule against scope changes. The developed methodology sought to provide predictability and efficiency to the interior design project process, aligning with PMI (2017) principles for visualizing interdependencies and anticipating bottlenecks.

3. Results and Discussion

Project management in the interior design sector, especially in small offices, revealed a scenario of low managerial maturity, characterized by a predominantly intuitive and reactive approach. The research findings indicated significant flaws in schedule planning and control, directly impacting the predictability of deliverables and operational efficiency. The investigation sought to understand the roots of these challenges and propose a more assertive time management model, aligned with the particularities of the creative and technical process of architecture.

The quantitative research, conducted with ten architects, revealed a substantial gap in the adoption of structured management practices. It was found that 70% of the professionals interviewed did not use phase-based schedules to estimate deadlines. This lack of standardization contrasts with the guidelines of the Project Management Institute (PMI, 2017), which emphasize the schedule as a fundamental tool for defining the temporal horizons of a project, ensuring the viability and quality of deliverables. The predominance of unstructured estimates justifies the recurring bottlenecks and delays observed in the sector.

Additionally, informality extends to activity control, with 30% of respondents admitting to not using any formal monitoring method. The preliminary design phase was identified by 60% of professionals as the most vulnerable to delays, a result consistent with the creative and iterative nature of this stage, where client expectation validation frequently generates scope fluctuations. The management of these scope changes also proved fragmented: 40% performed formal schedule adjustments, 10% applied additional fee charges, and 50% had no defined standard, evidencing a vulnerability in contractual management.

One of the most critical data points from quantitative research was the finding that 80% of professionals do not measure the time spent per task. This oversight prevents the creation of performance indicators (KPIs) and the precise calculation of profitability, as recommended by Vargas (2016), who points to the definition and recording of activities as foundations for realistic schedules. Without historical time tracking, the team perceives the implementation of management software as bureaucracy, rather than strategic support, compromising the project’s final performance (Cleland; Ireland, 2007).

The qualitative research, through an interview with the coordinator of the studied architecture office, deepened the understanding of the operational dynamics. An excessive centralization of activities was observed in Architect II, who accumulated technical, supervisory, and service functions. The estimation of deadlines was based on the project typology, with commercial services demanding 20 days and residential ones varying between 30 and 45 days. The coordinator confirmed that the preliminary design was the main bottleneck, due to frequent scope changes requested by clients, which impacted the planned schedule.

Information management in the office lacked robust tools, being limited to the use of Excel spreadsheets. An attempt to implement Trello software did not gain team adherence, due to the difficulty of adapting the tool to the different natures of projects. The absence of monitoring the time spent by each collaborator on their tasks prevented a clear view of internal productivity, resulting in a sharp oscillation in the workload of the 11 projects delivered in the first half of 2025. This dynamic generated a “cascade effect”, where modifications in one project reduced the available time for other ongoing contracts.

Another critical point identified was the underutilization of standardization resources, such as the block and template library, whose use was not uniform among collaborators. The coordinator emphasized that the biggest challenge lay in the organization of internal processes and in the need to understand the real duration of each task for assertive delivery promises. In summary, management was based on intuition and service typology, to the detriment of precise metrics, reinforcing the need for a management model that was rigorous, yet adaptable to the demands of a small-sized office.

Given this diagnosis, data triangulation allowed the identification of the Gantt Chart as the most suitable tool for the reality of small-sized architecture offices focused on interiors. Although the Kanban method (Anderson, 2011) is effective for continuous flows, interior design projects have a rigid critical path, with stages such as detailing and rendering depending on the preliminary design approval. The Gantt model, based on PMI (2017) principles, allows visualization of the interdependence between processes and anticipation of bottlenecks, being more appropriate for this context.

For the structuring of the proposed schedule, the concept of Project Breakdown Structure (WBS) was applied, as suggested by Vargas (2016). This approach allowed for the identification of two types of tasks: transversal processes, such as customer service and social media management, which occur continuously throughout the project lifecycle; and sequential processes, which include technical stages like survey, briefing, 3D modeling, rendering, and detailing, obeying a strict order of precedence.

The proposed baseline schedule was sized for a 30-day cycle, considering the operational limitations identified in the case study. Client Contact, Measurement Survey, and Briefing activities are allocated in the first week. 3D modeling and detailing, identified as the most critical phases, each consume two weeks. Image and video rendering is scheduled for 48 hours, while the preliminary design presentation, a crucial control milestone, has an average duration of one hour and thirty minutes. The final project delivery is allocated in the fourth week, with a duration of two hours.

This workflow establishes 3D modeling as the start of the creative phase and the presentation of the preliminary design as a control milestone. To mitigate the “cascade effect” of scope changes, the methodology foresees an extension of the deadline by up to one week, preventing delays in one project from contaminating other active contracts. To enable this workflow and reduce the coordinator’s overload, a redistribution of tasks based on resource efficiency was proposed (Cleland; Ireland, 2007).

The activity distribution proposal assigns the Architect I and the Coordinator to Client Contact, while the Measurement Survey is shared between the Coordinator and the Intern. The Architect I is responsible for the Briefing. The entire team works on 3D modeling and, subsequently, on the preliminary design presentation. The Coordinator handles image and video rendering, and the detailing is divided between the Coordinator and the Intern. The final project delivery involves the entire team, and Social Media and Accounting activities are continuously assigned to the Architect I.

This transition from intuitive management to a critical path-based schedule, with a balanced separation of assignments, allows the office to protect its profitability and maintain project quality. The simultaneous execution of projects becomes viable without compromising contractual deadlines. In summary, strict adherence to this operational sequence functions as a control instrument that transforms abstract planning into predictable and professional execution, conferring greater efficiency and predictability to the interior design project process.

4. Conclusion

This study investigated planning failures in small architectural offices, seeking to propose an assertive schedule model for interior design projects, capable of conferring predictability and efficiency to the design process. Low management maturity was observed in the sector; most professionals did not use phase-structured schedules to estimate deadlines, nor did they monitor time spent on operational tasks. In the case study, excessive centralization of functions in the coordinator and dependence on generic tools, such as Excel, were identified, which compromised the predictability of deliverables. The preliminary design phase, in particular, proved to be the most vulnerable to delays due to scope fluctuations, and the management of these changes was fragmented, without defined standards. The absence of historical time records prevented precise calculation of productivity and profitability, reinforcing the need for effective operational control methods.

As a solution, the implementation of a Gantt Chart based on the Project Breakdown Structure (WBS) was proposed, with a 30-day baseline schedule and task redistribution. This approach proved effective in reducing bottlenecks in the pre-design phase and protecting the workflow against scope changes, allowing for simultaneous project execution without compromising contractual deadlines. The study’s main contribution lies in demonstrating that process standardization and the adoption of control milestones are essential to ensure operational efficiency and financial sustainability in small architectural firms, protecting profitability and design quality. The professionalization of management, therefore, does not inhibit creativity but safeguards it, providing greater predictability and professionalism to the interior design process. For future work, it is suggested to investigate cloud-based management software that allows for the automation of these schedules, facilitating team adherence.

Bibliographic References

ANDERSON, D. J. (2011). Kanban: Mudança Evolucionária de Sucesso para seu Negócio de Tecnologia. São Paulo: Blue Hole Press.

CARVALHO, M. M.; RABECHINI JÚNIOR, R. (2011). Fundamentos em gestão de projetos. 3. ed. São Paulo: Atlas.

CLELAND, D. I.; IRELAND, L. R. (2007). Gerenciamento de projetos. 2. ed. São Paulo: LTC.

PROJECT MANAGEMENT INSTITUTE [PMI]. (2017). Guia do Conhecimento em Gerenciamento de Projetos: Guia PMBOK. 6. ed. [S. l.]: PMI.

VARGAS, R. V. (2016). Gerenciamento de projetos: Estabelecendo diferenciais competitivos. 8. ed. São Paulo: Brasport.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.