Risk Management in Pharmaceutical Engineering Projects

Arthur Gonçalves Roza da Silva; Beatriz Cristina de Freitas

DOI: 10.22167/2675-6528-202600584

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

Engineering projects in the pharmaceutical industry are characterized by high technical complexity and strong dependence on regulatory requirements, factors that increase exposure to uncertainties capable of affecting deadlines, costs, and compliance of the production process. In this context, the structured application of risk management becomes essential to increase the predictability of critical implementation and validation stages. The study aimed to identify and analyze the main technical, operational, and quality risks present in the post-FAT validation phases of an Active Pharmaceutical Ingredient (API) plant implementation project, evaluating their impacts on the project schedule. For this purpose, a qualiquantitative approach was adopted, combining documentary analysis of validation records, on-site activity observation, and the application of risk management tools, including a probability and impact matrix, structured qualitative analysis, and quantitative simulation using the Monte Carlo method. The results showed that risks concentrated in the initial phases of the validation process, especially SAT and IQ, presented a greater potential for delaying the qualification cycle, due to the strong sequential dependence between stages. It was also identified that factors related to automation, critical system integrity, and document governance contributed significantly to schedule variability. It was concluded that the integration of qualitative and quantitative risk analysis methods contributes to improving decision-making and increasing planning reliability in highly complex pharmaceutical projects.

Keywords: Uncertainty analysis; Pharmaceutical industry; Schedule planning; Process validation.

1. Introduction

Pharmaceutical engineering projects are characterized by high technical complexity, intrinsic to the nature of the processes and products involved. This complexity is accentuated by the need for compliance with rigorous international regulatory requirements, which establish strict standards for quality, safety, and traceability in all phases of a venture’s lifecycle. In this scenario, effective management of deadlines and costs becomes a continuous challenge, as delays in critical activities, particularly in the qualification and validation stages of systems and equipment, can directly impact the overall project performance and the start of productive operation (Project Management Institute, 2021).

In complex industrial environments, the interdependence between various activities and systems is notable. Failures that occur in the initial phases of a project can propagate throughout the schedule, amplifying their effects in subsequent stages. This phenomenon is often described in the literature as the propagation or amplification of risks in complex projects, where adverse events tend to generate systemic impacts when they are not identified and addressed in advance (Williams, 2017). The absence of robust mechanisms and the strong dependence between phases make the schedule particularly sensitive to deviations in the initial stages, reinforcing the need for preventive risk prioritization.

In this context, risk management plays a central role in project planning and execution. The Project Management Institute (2021) defines risk as an uncertain event or condition that, if it occurs, can positively or negatively affect one or more project objectives. Unlike a problem, which is a situation that has already occurred and requires immediate corrective action, risk refers to a future possibility whose occurrence may compromise aspects such as schedule, cost, scope, or quality of the project.

Risk management involves a structured set of practices aimed at identifying, analyzing, and treating uncertain events that can influence project performance. This process includes the formalization of identified risks, the definition of responsible parties, classification according to uniform criteria, and continuous monitoring of their evolution throughout the venture’s lifecycle. Risk assessment considers the combination of the probability of occurrence and the potential impact, allowing for prioritization of those with the greatest capacity to affect project outcomes (Project Management Institute, 2021).

In the context of the pharmaceutical industry, risk management acquires additional relevance due to the rigorous regulatory requirements associated with Good Manufacturing Practices (GMP) and the qualification and validation processes of production systems. Failures in these stages can result in rework, significant schedule delays, and risks to regulatory compliance. The systematic identification of technical, operational, and organizational risks becomes fundamental to ensuring the robustness of the process for implementing new production facilities (ICH, 2023).

Furthermore, quantitative techniques have been increasingly used to support risk management in complex projects. Simulation methods, such as the Monte Carlo method, allow for the estimation of probabilistic delay scenarios and the evaluation of overall risk exposure in project schedules, contributing to more informed managerial decisions (Vanhoucke, 2016). In regulated environments, the adoption of structured risk management practices also contributes to strengthening organizational governance and supporting more consistent decision-making processes, as highlighted in recent literature on the growing complexity of projects and regulatory requirements (Aven, 2016).

Despite the high level of control in the pharmaceutical industry regarding quality and regulatory compliance, significant difficulties persist in the practical application of risk management in engineering projects. In many cases, teams focus their efforts on immediate compliance with regulatory requirements, while the systematic assessment of technical and operational risks associated with implementation and validation activities receives less attention. This gap highlights a recurring challenge in pharmaceutical project management: the need to more structurally integrate quality risk management practices with project management methodologies, especially in critical stages of the system and process validation cycle.

In this context, it becomes relevant to analyze how the structured application of risk management practices can contribute to improving the control of deadlines, costs, and quality in pharmaceutical engineering projects. To this end, the adoption of formal methodologies based on consolidated references, such as the PMBOK Guide (Project Management Institute, 2021) and the ICH Q9 (R1) Quality Risk Management guide (ICH, 2023), allows for the integration of technical, regulatory, and managerial aspects into a more robust governance model aligned with the demands of the pharmaceutical industry. The present study seeks to analyze the application of structured risk management practices in pharmaceutical engineering projects, focusing on the validation stages post-FAT (SAT, IQ, OQ, and PQ), evaluating their impacts on the control of deadlines, costs, and schedule predictability in an Active Pharmaceutical Ingredient (API) production plant.

2. Material and Methods

This is an applied research, descriptive in nature, aimed at analyzing a practical problem in an organizational environment. According to Gil (2019), applied research seeks to generate knowledge for the solution of specific problems, while descriptive studies characterize observable phenomena and relationships. The methodological approach adopted was quali-quantitative, combining research techniques for a comprehensive understanding of complex phenomena, associating contextual evidence with quantitative analyses of variables and impacts (Creswell, 2014).

The study was conducted in an Active Pharmaceutical Ingredient (API) production plant located in Europe. The analyzed project presented characteristics of a large-scale pharmaceutical undertaking, involving multiple production systems, critical utilities, and support infrastructure. The overall project timeline comprised approximately four years, covering the engineering, construction, commissioning, and validation phases.

Throughout the project period, various organizational areas participated, including engineering, quality assurance, validation, automation, and specialized suppliers. The focus of the analysis concentrated on the stages after FAT (Factory Acceptance Test), specifically SAT (Site Acceptance Test), IQ (Installation Qualification), OQ (Operational Qualification), and PQ (Performance Qualification), due to them being critical and sequential phases that directly impact the schedule.

Data collection involved documentary analysis of technical reports, validation records, and project documents, to map practices and identify non-conformities. Direct observation of validation activities at the plant was carried out, with systematic recording of operational routines, deviations, and team interactions. Risk management tools were applied, such as probability × impact matrix, qualitative analysis by categories, and quantitative methods based on simulation and sensitivity analysis, aiming to estimate the criticality of risks and their effects. Evidence triangulation was performed by combining these techniques.

The methodological development was structured in stages aligned with the risk management process, focusing on planning, identification, and qualitative and quantitative analyses. To consolidate the scope of the validation phases and identify interfaces, a Project Work Breakdown Structure (WBS) was developed, which related critical validation activities to risk sources. This structure served as the basis for the Risk Breakdown Structure (RBS), which organized risks into technical, quality, regulatory, organizational, schedule, document governance, and external categories, allowing for a hierarchical visualization of risk sources and the establishment of traceability.

The qualitative analysis classified risks according to their probability of occurrence and potential impact on project objectives, focusing on schedule, product quality, and regulatory compliance. For this classification, standardized criteria were defined for impact assessment (Small, Moderate, Large, Severe) and probability (Unlikely, Possible, Likely, Very Likely). Based on these criteria, risks were evaluated comparably, creating the basis for the individual risk register and its subsequent consolidation in the FMEA matrix.

Quantitative analysis estimated the probabilistic impact of risks on the project schedule. The modeling was performed by Monte Carlo simulation, applied to the validation stages schedule, using statistical simulation software and 10,000 iterations to estimate the probabilistic distribution of the total delay (Vanhoucke, 2016). The impacts of risks were modeled by a triangular distribution (minimum, most likely, and maximum). Correlation assumptions between risks, using Gaussian copula, represented the propagation of delays between sequential phases. The convergence of the simulation was verified by the stability of the schedule percentiles (P50, P80, P90, and P95).

The research observed the ethical principles applicable to studies in an organizational environment. According to the institutional opinion of the ECF, submission to the Research Ethics Committee (CEP) was waived. Confidentiality measures, anonymization of sensitive data, and restricted access to the analyzed information were adopted, ensuring the integrity and privacy of the collected data.

3. Results and Discussion

The results of risk management, applied to the validation project of an Active Pharmaceutical Ingredient (API) plant, revealed that the project’s exposure to uncertainties is a product of the complex interaction between technical, organizational, and governance factors. This interaction manifests throughout the entire validation cycle, from the planning phases to the execution of qualifications. Documentary analysis of previous projects, for example, demonstrated a recurrence of problems such as supplier delays, concentration of technical knowledge in a few individuals, and schedule compression due to organizational pressures. Such findings indicate that a significant portion of risks does not arise solely during the execution of validation activities but is influenced by decisions and conditions established in the initial project planning and implementation stages.

From consultations of project documents, meeting minutes, and tracking spreadsheets, it was identified that recurring problems with potential impact on the project schedule and stability can be grouped into three main categories. The first refers to supplier delays, which frequently compromise the sequence of activities. The second category involves the concentration of technical knowledge in a limited number of professionals, creating failure points and dependencies. Finally, the underestimation of deadlines, driven by strategic pressures, constitutes the third category. These factors, structural and planning in nature, can significantly amplify risks during the execution of validation activities, as observed in the literature on complex project management (Williams, 2017).

To integrate risk management into validation activities and prevent it from being treated as an isolated process, the planning was structured through a Work Breakdown Structure (WBS). This WBS detailed the post-FAT validation phases, which include Factory Acceptance Test (FAT), Site Acceptance Test (SAT), Installation Qualification (IQ), Operational Qualification (OQ), and Performance Qualification (PQ), and their respective sub-activities. The WBS allowed for a clear visualization of the interfaces between critical activities and potential risk sources, establishing a solid foundation for the development of the Risk Breakdown Structure (RBS), which favored the alignment between project planning, execution, and control.

The mapping of risks resulted in their organization into distinct categories, encompassing technical, quality, regulatory, organizational, schedule, document governance, and external aspects. In the technical category, risks such as incorrect installation of critical systems and inadequate validation of automation systems (PLC/SCADA) were identified. In terms of quality, non-compliance with acceptance criteria and excessive variability in PQ batches were highlighted. Regulatory risks included insufficient documentary evidence, while organizational risks pointed to inadequate team training. Supplier delays were classified as external risks, and failures in document traceability represented governance risks, evidencing the breadth of uncertainty sources in the project.

The Risk Breakdown Structure (RBS) enabled a hierarchical visualization of the various risk sources, allowing identified events to be traced back to the affected validation phases and responsible areas. This structure served as the foundation for the qualitative risk analysis, which sought to classify each event based on its probability of occurrence and potential impact on project objectives, such as schedule, product quality, and regulatory compliance. For this classification, standardized evaluation criteria were established, categorizing the impact into levels of minor, moderate, major, and severe, and the probability into unlikely, possible, probable, and very probable, according to risk management references (Project Management Institute, 2021).

The qualitative analysis, supported by the probability and impact matrix, allowed for the prioritization and organization of risks into a Failure Mode and Effects Analysis (FMEA) Matrix. The highest criticality risks, with a score of 16 (probability 4 x impact 4), included failure in the critical system’s compliance with the approved URS (SAT), integrity failures in critical utilities such as purified water and clean steam (SAT), automated systems (PLC/SCADA) without adequate qualification (OQ), and critical alarms and interlocks not adequately tested (OQ). These findings underscore the importance of proactively addressing technical compliance issues and the robustness of critical systems from the initial project phases.

Other relevant risks identified in the FMEA, with a score of 9 (probability 3 x impact 3), were incomplete or inconsistent technical documentation during SAT and incorrect installation of critical systems identified late in SAT. Risks with a score of 8 (probability 2 x impact 4) included construction materials incompatible with the API or process (IQ), OQ tests not covering worst-case conditions, and failures to meet CQAs acceptance criteria (PQ). The concentration of criticality in technical and documentary risks, especially those related to compliance with URS and the integrity of critical utilities, reinforces the need for rigorous and systematic control in these areas.

Following qualitative prioritization, a quantitative analysis was performed, aiming to estimate the probabilistic impact of risks on the project schedule. The quantitative modeling was structured based on assumptions of chaining between phases, correlation between risks, and probabilistic representation of impacts. The results were reported in business days, with correlation applied via Gaussian copula for blocks by stage and specific links. The total delay was calculated as the sum of delays per stage (SAT, IQ, OQ, PQ), and the impacts of risks were modeled by a triangular distribution, considering minimum, most likely, and maximum values in business days, an approach suitable for situations with limited historical data but with expert estimates (Vanhoucke, 2016).

Each risk was parameterized with minimum, most likely, and maximum delay values. For example, integrity failures in critical utilities (B SAT) presented a minimum delay of 64.29 business days, most likely 85.71 business days, and a maximum of 128.57 business days. Failures in critical system compliance with the approved URS (A SAT) and automated systems without adequate validation (L OQ) had minimum delays of 42.86 business days, most likely 64.29 business days, and a maximum of 85.71 business days. This data, from the Monte Carlo input base, allowed for the quantification of the potential variability of each risk event and its contribution to the overall project delay.

The Monte Carlo simulation, performed with 30,000 iterations, estimated the probabilistic distribution of the total project delay. The average total delay was 172.64 business days, with a standard deviation of 75.34 business days. The schedule percentiles indicated a 50% probability of the delay being less than 173.40 business days (P50), an 80% probability of it being less than 237.40 business days (P80), a 90% probability of it being less than 271.01 business days (P90), and a 95% probability of it being less than 296.99 business days (P95). The maximum simulated delay was 428.37 business days, demonstrating the wide range of possible scenarios and the importance of considering different contingency levels in planning.

The probabilistic interpretation of the simulation results revealed that the choice of percentile used in planning directly influences the level of risk exposure. The P50 percentile, although useful as a central reference, represents a median scenario in which there is approximately a 50% probability of the delay being less than the estimated value. Operating with P50, therefore, implies accepting a significant probability of exceeding the planned deadline. In contrast, more conservative percentiles, such as P80 or P90, represent scenarios with a lower probability of delay but require a larger contingency reserve. The difference between P50 and P90 highlights the magnitude of the accumulated uncertainty in the schedule, indicating that decisions based solely on median scenarios may underestimate risk exposure.

The analysis of the results by validation stage showed that SAT presented the highest delay percentiles, with P50 of 80.53 business days and P95 of 134.39 business days, followed by OQ, with P50 of 57.00 business days and P95 of 95.30 business days. IQ also showed a significant contribution, with P50 of 18.46 business days and P95 of 81.26 business days. The PQ stage, in turn, presented lower percentiles, with P50 of 7.32 business days and P95 of 95.61 business days. These data indicate that failures in the initial phases, especially SAT and OQ, exert a disproportionate influence on the total project delay, reinforcing the need for risk management focused on these critical stages.

Sensitivity analysis allowed the identification of events with the greatest contribution to the expected schedule delay. Integrity failures in critical utilities (B SAT) were the main contributor, with an expected delay of 46.73 business days and a mean probability of occurrence of 0.50. Next, automated systems (PLC/SCADA) without adequate validation (L OQ) contributed 32.44 business days of expected delay and a probability of 0.50. Failure in the critical system’s compliance with the approved URS (A SAT) and critical alarms and interlocks not adequately tested (M OQ) were also significant contributors, with expected delays of 32.17 and 19.75 business days, respectively, both with a probability of 0.50. These results highlight the criticality of technical and automation aspects for schedule predictability.

Axis 1 – Risk propagation in sequential projects

The results showed that risks concentrated in the initial phases of the validation cycle, especially SAT and IQ, have a greater potential for propagating delays throughout the schedule. This behavior is consistent with the literature on sequential dependency in complex industrial projects, which describes the phenomenon of “risk amplification” (Williams, 2017). In cascade project structures, such as pharmaceutical validation, the strong interdependence between deliverables causes initial failures to tend to amplify their effects in subsequent stages. The absence of robust buffers and sequential dependency make the schedule particularly sensitive to deviations in the initial phases, reinforcing the need for preventive risk prioritization.

Axis 2 – Qualitative-quantitative integration

One of the main methodological results of this study was the demonstration of the effectiveness of the integration between qualitative and quantitative risk analysis. The combination of the FMEA Matrix with Monte Carlo simulation allowed the conversion of qualitative probability and impact classifications into probabilistic estimates of schedule delay. This hybrid approach expanded the predictive capacity of risk management and reduced the exclusive dependence on qualitative judgments, which are often criticized for their subjectivity. By integrating these two analytical perspectives, the developed model provided a more robust basis for risk prioritization and decision-making in complex projects, aligning with best practices in project management (Project Management Institute, 2021).

Axis 3 – Governance and organizational factors

Root cause analysis revealed that a significant portion of risk exposure stems from organizational factors, including schedule pressure, concentration of technical knowledge in a few professionals, and weaknesses in document governance. These factors indicate that, in regulated environments such as the pharmaceutical industry, risk is not only technical but also structural and decision-making in nature. Literature on project management in complex environments suggests that decisions driven solely by deadline goals can increase overall risk exposure, contradicting the proportionality principle advocated by Quality Risk Management (ICH, 2023).

Axis 4 – Managerial implications

From a managerial perspective, the results indicate that decisions to advance between validation phases should be conditioned on formal readiness criteria, known as “readiness gates”, based on a quantitative risk assessment. The use of more conservative percentiles, such as P80 or P90, for defining contingencies, allows for decisions more aligned with the organizational risk appetite. This practice contributes to reducing schedule surprises and increasing the strategic predictability of the project, providing a robust tool for proactive uncertainty management in pharmaceutical engineering projects.

The recommended mitigation actions, developed based on the identified risks, translate the main findings into operational measures applicable throughout the validation phases. For failure in the critical system compliance with the URS, for example, it is recommended to reinforce URS-SAT traceability and perform worst-case tests. For integrity failures in critical utilities, it is suggested to execute integrity tests and qualify loops. Incomplete technical documentation requires freezing the baseline and controlling versions. These recommendations were structured considering the criticality of each event and the sequential nature of the SAT-IQ-OQ-PQ process, aiming to reduce the probability of occurrence and the potential impact on schedule, quality, and regulatory compliance.

This study, however, presents some limitations that should be considered when interpreting the results. The first limitation lies in the dependence on the assumptions adopted in the quantitative modeling, especially regarding the probability distributions used and the correlations between risks. The second limitation is related to the generalization of the results, as the model was applied to a single API implementation project, even though it was supported by historical records from previous projects. Furthermore, part of the estimates used in the simulation was based on expert judgment, a common characteristic in applied studies, but which requires caution when extrapolating the results to other contexts.

In summary, the structured application of risk management in the validation process of an API project proved to be a relevant tool for increasing the predictability and control of the schedule. Risks concentrated in the initial phases, such as SAT and IQ, showed a greater potential for propagating delays due to the strong sequential dependency between the stages. Factors such as automation, integrity of critical systems, and document governance were identified as significant contributors to schedule variability. The integration of qualitative and quantitative risk analysis methods, including FMEA and Monte Carlo simulation, enhanced the decision-making process and increased the reliability of planning in highly complex pharmaceutical projects, responding to the objective of identifying and analyzing the main risks and their impacts on the schedule.

4. Conclusion

The present study aimed to identify and analyze the main technical, operational, and quality risks inherent in the post-FAT validation phases of an Active Pharmaceutical Ingredient (API) plant implementation project, evaluating their impacts on the schedule. It was verified that the risks concentrated in the initial stages of the validation cycle, notably SAT and IQ, presented a greater potential for propagating delays throughout the schedule, due to the strong sequential dependency between activities. It was identified that factors related to automation, the integrity of critical systems, and document governance contributed significantly to schedule variability. The integration of qualitative methods, such as the FMEA Matrix, and quantitative methods, through Monte Carlo simulation, proved effective in converting probability and impact classifications into probabilistic delay estimates, enhancing the predictive capability of risk management. This approach contributed to a more robust decision-making process and increased the reliability of planning in highly complex pharmaceutical projects.

However, this study presented limitations related to the dependence on the premises adopted in quantitative modeling, especially regarding probability distributions and correlations between risks, in addition to the application of the model to a single project, which restricts the generalization of the results. For future studies, it is suggested to apply the model to different types of pharmaceutical projects, expand the historical database for simulations, and investigate the integration between risk analysis and financial evaluation of schedule contingencies. In summary, the structured application of risk management, combined with a quali-quantitative analysis, offers a valuable tool for proactive uncertainty management, strengthening predictability and control in pharmaceutical engineering projects in regulated environments.

Bibliographic References

Aven, T. 2016. Risk assessment and risk management: Review of recent advances on their foundation. European Journal of Operational Research, v. 253, n. 1, p. 1–13.

Creswell, J. W. 2014. Research design: qualitative, quantitative and mixed methods approaches. Sage Publications, Thousand Oaks, CA, USA.

Gil, A. C. 2019. Métodos e técnicas de pesquisa social. Atlas, São Paulo, SP, Brasil.

International Conference for Harmonisation of Technical Requirements for Pharmaceuticals for Human Use [ICH]. 2023. Guideline Q9 (R1) on quality risk management. Disponível em: <https://www.ema.europa.eu/en/documents/scientific-guideline/international-conference-harmonisation-technical-requirements-registration-pharmaceuticals-human-use-ich-guideline-q9-r1-quality-risk-management-step-5-revision-2_en.pdf>. Acesso em: 01 dez. 2025.

Project Management Institute [PMI]. 2021. Um guia do conhecimento em gerenciamento de Projetos (Guia PMBOK). 7ed. Project Management Institute Inc, Newtown Square, Pensilvânia, EUA.

Vanhoucke, M. 2016. Integrated project management and control: first comes the theory, then the practice. International Journal of Project Management, v. 34, n. 5, p. 862–873.

Williams, T. 2017. The nature of risk propagation in complex projects. International Journal of Project Management, v. 35, n. 6, p. 1083-1095.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.