Scope Change Management for Industrial Electrical Installations
Adalberto Plinio da Silva Gorni; Everton Gomede
DOI: 10.22167/2675-6528-202600486
Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
Industrial project management is influenced by several factors that impact deadlines and costs, with scope changes being a critical element when not controlled. This study analyzed the impacts of the absence of structured scope change management on the performance of industrial electrical installation projects. The methodology employed a comparative case study, with a quantitative and qualitative approach, of two projects executed by the same company in the interior of São Paulo. Data collection occurred through documentary analysis, including schedules, site reports, change logs, and cost data. The results indicated that Project 01, which applied formal change control practices, achieved superior performance, with a reduction in execution time and cost savings. In contrast, Project 02, without structured change management, suffered scope additions, resulting in a significant increase in deadlines and elevated costs. It was concluded that the absence of change control compromises project performance, affecting deadlines and costs, and reinforcing the importance of structured processes to increase predictability, control, and efficiency in industrial projects.
Keywords: Change control; Project performance; Case study; Project Management; Electrical installations.
1. Introduction
Project management is a fundamental discipline for organizations seeking to achieve their strategic objectives through the execution of unique endeavors. The successful delivery of projects, particularly in complex environments such as industrial engineering, depends significantly on effective planning and control mechanisms. The industrial sector, characterized by intricate processes, demanding schedules, and substantial capital investments, presents specific challenges for project managers. Ensuring that projects meet their objectives in terms of deadline, cost, and quality is essential for competitiveness and operational efficiency.
Among the various areas of knowledge in project management, scope management stands out as a crucial element. It encompasses the processes required to ensure that a project includes all the work required, and only the work required, for its successful completion (Project Management Institute [PMI], 2021). However, the dynamic nature of industrial projects frequently results in changes and additions to the initial scope, which, if not properly managed, can severely compromise project outcomes.
Projects that do not adopt a structured approach to scope management often face negative impacts on their performance. Such projects tend to experience adverse effects on deadlines and costs, as evidenced by Bonato et al. (2021). Common causes for these deviations include poorly defined initial scope, unrealistic schedules, execution failures, and critically, the absence of a robust change control mechanism (Malsam, 2024). These factors, in combination, create an environment where project objectives become difficult to achieve.
The Project Management Institute (PMI, 2021) emphasizes the need for continuous monitoring to prevent changes or new work from being added to the initial supply scope in a detrimental way. This proactive approach requires a formal change control process. Such a process typically involves key stakeholders, such as the project manager, a Change Control Board (CCB), and the change requester. The primary function of this control is to rigorously assess the implications of any proposed modification on the project’s timelines, costs, and resource requirements before its formal approval.
Following a thorough review and formal approval, all changes or new services must be effectively communicated to all stakeholders. Furthermore, these approved modifications need to be cohesively integrated into the project’s existing planning documentation. This systematic approach is vital for maintaining project integrity and ensuring everyone involved is aligned with the updated parameters. Without a structured process, projects are susceptible to what is termed “scope creep”.
Scope creep occurs when changes are incorporated into the project’s delivery scope without prior and comprehensive analysis, and without the subsequent adjustment of necessary costs, deadlines, and resources by the project team (PMI, 2021). The absence of this critical step can lead to uncontrolled scope growth, often resulting in unforeseen expenses, schedule delays, and a general deterioration of project performance. Therefore, avoiding these distortions is fundamental to ensuring the success and efficiency of any undertaking.
Although the project management literature emphasizes the importance of change control as an essential practice for maintaining the scope baseline, a gap is observed in the practical approach to these concepts in industrial engineering projects. Specifically, there is a scarcity of comparative analyses based on real data that quantitatively evidence the precise impacts of the absence of this control on project performance. This gap limits the empirical understanding of how the lack of structured change management translates directly into tangible deviations in project outcomes.
The absence of a structured scope change management process can result in significant negative impacts on project performance, reflected in increased costs and extended execution deadlines. Thus, this work justifies its relevance by contributing to the practical understanding of the effects of scope control on project outcomes and to the improvement of planning and control practices in organizational environments. Given this scenario, the general objective of this study is to analyze the impacts of scope change management – or the absence thereof – on the performance of industrial projects, focusing on aspects of deadline and cost.
2. Material and Methods
This research, of an applied nature, sought to generate knowledge aimed at solving practical problems related to scope change management in industrial projects (Gil, 2022). It was characterized as qualitative with quantitative support, involving the interpretive analysis of phenomena, complemented by numerical data on deadlines and costs (Lakatos and Marconi, 2021). The study was classified as descriptive and explanatory, seeking to describe the characteristics of the projects and explain the impacts of the absence of structured scope change control (Köche, 2016).
The research strategy adopted was a comparative case study, focused on the analysis of two real industrial electrical installations projects. The unit of analysis was a service provider organization specialized in installation, maintenance, and technical support in industrial electrical systems, located in the interior of the state of São Paulo. Its activity is focused on meeting the demands of the industrial sector, contributing to the electrical infrastructure of production processes.
The selection of Projects 01 and 02 was intentional, aiming for a comparative analysis between different levels of scope change control and their impacts. Both were chosen for presenting similar characteristics regarding the nature of the activities, including industrial electrical installation services, material supply, infrastructure assembly, cable laying, and equipment installation.
Data collection occurred during the execution period of the analyzed projects. For Project 01, it covered January and February 2024, and for Project 02, April to August 2025. Technical and managerial documents from both projects were analyzed, encompassing all phases, from planning to the completion of activities. The collection instruments included technical and commercial proposals, schedules, daily site reports, photographic reports, scope change records, and cost control spreadsheets.
Approximately 138 documents were examined, with 29 related to Project 01 and 109 to Project 02. The documents were prepared by different agents involved in the projects, such as engineering, commercial, field supervisors, and planning teams. Schedules and control reports were produced by the planning team, while daily and photographic reports were prepared by the field teams during the execution of activities.
The reliability of the data was ensured by the use of official project documents, systematically registered throughout the execution. Information triangulation was performed between different sources, such as daily reports, photographic records, and planning data, allowing for cross-validation and reduction of inconsistencies. The author directly participated in the project execution, providing in-depth analysis. To mitigate the potential risk of bias, the analysis was predominantly based on formal documentary records, prioritizing objective evidence.
Project 01 was executed in a sugar-energy industry, located in the northern region of São Paulo. Its supply scope comprised materials, labor for electrical infrastructure installation, electrical cable laying, and electrical panel assembly and installation. During execution, a structured integrated change control process was applied, with the objective of ensuring that scope changes were registered, analyzed, and approved beforehand.
Project 02 was also carried out in a sugar-energy industry, located in the interior of São Paulo. The scope of this project included materials, labor for the installation of electrical and pneumatic infrastructure, cable laying and connection, development of automation logic, and assembly and installation of an electrical panel for motor activation. In this project, the absence of formal change control during the execution of activities was observed.
For both projects, the Work Breakdown Structure (WBS) was used to decompose the scope into its main components and deliverables, facilitating visualization and planning. For Project 01, a change management spreadsheet was employed to record, analyze, and track change requests, supporting decision-making. In Project 02, a similar spreadsheet was used for recording changes, but with a documentary character, without a structured analysis and control function.
3. Results and Discussion
The comparative analysis of industrial electrical installation projects revealed substantial differences in performance, directly related to the presence or absence of structured scope change management. The findings indicate that the application of formal change control processes contributes significantly to project predictability and success, while the lack of these mechanisms can lead to considerable deviations in deadlines and costs. This initial finding aligns with the perspective of the Project Management Institute (PMI, 2021), which emphasizes the need for continuous monitoring to avoid detrimental additions to the initial scope.
In Project 01, strict control of costs and labor was observed, exceeding initial expectations. Total costs showed a saving of R$ 26,144.88 compared to the plan, and the execution deadline was reduced by five days. This superior performance was attributed to the clear and detailed definition of the supply scope requirements, as well as the effective alignment among all stakeholders. These factors were crucial for efficient control of activities and resources, preventing the inclusion of unforeseen work or unmanaged changes to the original scope.
The execution of Project 01 demonstrated that the start and end dates were maintained as planned, and the actual progress exceeded expectations, culminating in the cessation of activities five business days earlier than scheduled. The interruption, which occurred on February 7, 2024, was planned from the outset to await the completion of third-party services. This anticipation in the conclusion of activities generated additional savings, positively impacting expenses such as accommodation, food, and travel for the allocated collaborators, reinforcing the efficiency achieved by the project.
The application of a structured integrated change control process was a determining factor for the success of Project 01. This procedure ensured that all proposed changes to the scope were duly recorded, analyzed, and approved before their implementation. Such a systematic approach allowed for the maintenance of the scope baseline, preserving the initial plan and avoiding the inclusion of unforeseen activities that could lead to deviations in the results, according to the project management guidelines (PMI, 2021).
In contrast, Project 02 faced significant challenges due to the absence of structured scope change management. The initial needs and requirements were not well-defined, resulting in incorrect information about the quantity of valves to be installed. This failure led to changes and additions of services and materials that negatively impacted the project’s performance, resulting in additional costs of R$ 53,292.15 and an extension of the execution period from 40 to 83 days.
Project 02, although it started with only one day’s delay and showed a quick initial recovery, soon encountered rework and the need for new activities due to poorly defined requirements. The inclusion of ten valves and two flow transmitters in the scope, without prior analysis, led to the acquisition of additional materials and consequent team idleness, as the delivery deadline for these materials was not immediate, compromising the execution’s fluidity.
The staggered deliveries and interruptions in the progress of activities were striking characteristics of Project 02. Although an interruption between May 27 and June 13, 2025, was planned to await the delivery of a panel, this pause did not occur. Furthermore, the absence of fieldwork between September 3 and October 3, 2025, due to the development of automation logic impacted by scope changes, contributed to the widespread delay and management complexity.
As demonstrated, Project 02 experienced a considerable delay in delivery, which, in turn, impacted the start of other projects that depended on the same allocated resources. The lack of a formal change control process resulted in the incorporation of new demands into the scope without prior impact analysis or formal approval, leading to an increase in the quantity of materials, additional labor, and extension of the execution deadline, evidencing the difficulties in controlling the initial planning.
The comparison between the two projects highlights the critical importance of scope change management. Project 01, with applied change control and well-defined initial planning, achieved a five-day reduction in schedule and savings of R$ 26,144.88. In contrast, Project 02, without structured change control, experienced a 43-day increase in schedule and an additional R$ 53,292.15 in costs, demonstrating that the absence of formal change management severely compromised performance.
The analysis of scope management practices in the two projects reinforces these findings. In Project 01, the clear and documented definition of scope, the presence of a scope management plan, and the realistic schedule contributed to alignment, control, and schedule reduction. In Project 02, however, the partial definition of scope, the absence of an explicit management plan, and a weakened schedule resulted in the inclusion of unforeseen activities, difficulty in monitoring, and unavoidable delays.
The change control process, periodic scope review, and stakeholder communication also proved crucial. Project 01, by consistently applying these practices, avoided unauthorized changes, maintained alignment, and ensured adequate communication. On the other hand, the absence of these elements in Project 02 led to uncontrolled scope creep, deviations not identified in time, and unmanaged changes, corroborating the importance of structured processes for project predictability.
The percentage variation in project performance corroborates the qualitative observations. Project 01 showed a variation of approximately -22.73% in days worked and -24.65% in costs, indicating a significant gain in efficiency. In contrast, Project 02 registered a variation of approximately +107.5% in schedule and +52.84% in costs, evidencing significant delays and a relevant increase in expenses, which aligns with the conceptualization of scope creep (PMI, 2021).
These results confirm that scope creep, characterized by the uncontrolled increase of work without due adjustments in time, cost, and resources, is a critical factor for project failure, as pointed out by Gupta (2025). Although changes may arise, the way they are managed is decisive. The absence of a formal change control process in Project 02 potentiated the negative impacts, significantly amplifying deviations from the initial plan.
It is important to recognize that project performance is influenced by multiple variables, including the quality of planning, resource availability, schedule control, and efficiency in activity execution (Kerzner, 2022). External factors, such as material supply deadlines, operational constraints, and production environment conditions, can also impact execution. However, integrated risk and change management is essential to mitigate these impacts (Vargas, 2023), and the absence of structured control in Project 02 amplified vulnerability to these variables.
In summary, the study demonstrated that the presence of structured scope change management, as observed in Project 01, results in superior performance, with reduced deadlines and controlled costs, while the absence of such control, as in Project 02, leads to significant delays and increased costs. The findings reinforce the importance of formal planning, control, and communication processes to ensure the predictability, efficiency, and success of industrial electrical installation projects, directly responding to the objective of analyzing the impacts of scope change management.
4. Conclusion
This study analyzed the impacts of scope change management – or lack thereof – on the performance of industrial projects, focusing on schedule and cost aspects. It was found that the application of structured scope change management resulted in superior performance, as observed in Project 01, which showed a reduction of five days in execution time and savings of R$ 26,144.88 in costs. In contrast, the absence of formal change control, evidenced in Project 02, led to an increase of 43 days in the schedule and an additional R$ 53,292.15 in costs. These findings demonstrate that the formalization of scope change control directly influences the predictability and efficiency of projects, contributing to the improvement of planning and control practices in organizational environments.
Although scope change control is a central factor, it is recognized that project performance is influenced by multiple variables, such as the quality of planning, resource availability, and external factors, which can be mitigated by integrated risk and change management. The author’s direct participation in project execution, while deepening the analysis, represents a potential limitation of bias, mitigated by the prioritization of formal documentary records. For future studies, it is suggested to expand the sample to a larger number of projects in order to increase the reliability of the results. It is also recommended to investigate the application of the approach in different industrial sectors and the development of a structured model or checklist for standardized change control, in addition to exploring quantitative performance indicators before and after the implementation of formal change management processes.
Bibliographic References
Bonato, S. V; Gandin, F. F; Ribeiro, L. M; JUNIOR, E. F. Z. P. (2021). Escritório de gerenciamento de projetos: proposta para uma empresa do ramo industrial de rodovias e extração de minério. Brazilian Journal of Production Engineering, v. 7, n. 2, p. 111-127.
Gil, A. C. (2022). Como elaborar projetos de pesquisa. 7. ed. Atlas, São Paulo, SP, Brasil.
Gupta, M. (2025). 7 estratégias eficazes para evitar o aumento descontrolado do escopo no gerenciamento de projetos. Disponível em: https://www.saviom.com/blog/what-is-scope-creep-and-how-to-avoid-it-in-project-management/. Acesso em: 08 de dezembro de 2025.
Kerzner, H. (2022). Project Management: a systems approach to planning, scheduling and controlling. 13. ed. John Wiley & Sons, Hoboken, NJ, Estados Unidos da América.
Köche, J. C. (2016). Fundamentos de metodologia científica: teoria da ciência e prática da pesquisa. 34. ed. Vozes, Petrópolis, RJ, Brasil.
Lakatos, E. M.; Marconi, M. A. (2021). Fundamentos de metodologia científica. 9. ed. Atlas, São Paulo, SP, Brasil.
Malsam, W. (2024). O que é o aumento do escopo e como posso evita-lo? Disponível em: https://www.projectmanager.com/blog/5-ways-to-avoid-scope-creep. Acesso em: 03 de dezembro de 2025.
Project Management Institute [PMI]. (2021). Um guia do conhecimento em gerenciamento de projetos. 7ed. Project Management Institute, Newtown Square, PA, Estados Unidos da América.
Vargas, R. V. (2023). Gerenciamento de projetos: estabelecendo diferenciais competitivos. 9. ed. Brasport. Rio de Janeiro, RJ, Brasil.