Schedule management for SCADA system implementation in photovoltaic power plants

Leonardo Matheus de Souza; Maria do Carmo Assis Todorov

DOI: 10.22167/2675-6528-202601069

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

Project management in engineering has traditionally faced challenges with deadlines and costs in a globalized scenario, driving the search for more adaptive and optimized methods. The study aimed to propose improvements in the implementation processes of SCADA systems in photovoltaic plants, through the application of agile methods, aiming to increase productivity and organization for meeting established deadlines. A qualitative approach was adopted, with a technical procedure based on a case study. A bibliographic survey was conducted and empirical data were collected through a semi-structured questionnaire, applied to professionals from an engineering and telecommunications company involved in the implementation of the SCADA system. The analysis identified challenges in interdepartmental communication, in information validation with clients, and in activity standardization, especially in the commissioning phase. As improvement proposals, the implementation of a pre-mobilization checklist for information validation with the client, weekly alignment meetings between areas to discuss doubts and optimize the workflow, and the restructuring of work packages to anticipate configurations were highlighted. Furthermore, the adoption of a standard tool, such as Trello, and the application of the Scrumban methodology for visual and sequential task management were recommended, promoting greater transparency and organization. The proposed improvements aimed to enhance communication, reduce development time and rework, and elevate the quality of the final product. It was concluded that the combination of elements from traditional management with agile practices offers a balanced and effective approach to SCADA project management, considering both the need for flexibility and the contractual control inherent in these ventures.

Keywords: Communication; Hybrid Management; Agile Methodology; Productivity; Scrumban.

1. Introduction

Project management in engineering has historically been a fundamental pillar for the development of infrastructures and technologies. However, the contemporary globalized scenario, characterized by rapid technological innovations and increasing pressure for efficiency and cost reduction, imposes significant challenges to traditional approaches. The complexity of modern projects, especially those involving the integration of SCADA (Supervisory Control and Data Acquisition) systems in dynamic sectors such as photovoltaic energy, demands more adaptive and optimized methodologies. SCADA systems, as described by Boyer (2004), are essential for remotely monitoring and controlling facilities, enabling the acquisition of critical data and the execution of control commands. In the context of photovoltaic power plants, the effective implementation of SCADA is crucial for optimizing energy production, early fault detection, and efficient operation management. The solar energy sector, in particular, has experienced exponential growth, with the deployment of hundreds of plants totaling gigawatts of monitored capacity, underscoring the criticality of efficient SCADA systems and robust implementation processes.

Traditionally, project management has been guided by predictive approaches, which emphasize detailed and sequential planning of all phases before the start of execution (PMI, 2017). Although effective for projects with a well-defined scope and little uncertainty, these methodologies reveal limitations in volatile environments, where changes in requirements and market conditions are frequent. In response to this dynamic, Agile methodologies emerged, prioritizing flexibility, collaboration, and iterative delivery of value (Maschk, 2022). The Agile Manifesto (Beck, 2001) establishes principles such as valuing individuals and interactions over processes and tools, working software over comprehensive documentation, customer collaboration over contract negotiation, and responding to change over following a rigid plan. These approaches promote greater adaptability, risk reduction, and better alignment with customer expectations, being particularly relevant for projects involving software and hardware development, as is the case with SCADA systems. The adoption of Agile practices has demonstrated potential to increase organizational productivity and responsiveness (Gido et al., 2019).

Despite the recognition of the benefits of agile approaches, many engineering projects still face persistent challenges. Industry reports indicate that a significant portion of projects, such as 58.5%, exhibit problems with poorly defined scope, and 54.2% are impacted by constant scope changes, common characteristics in information technology and engineering projects (PMI, 2017). Such problems frequently result in delays, budget overruns, and rework, compromising final quality and customer satisfaction. In the specific context of implementing SCADA systems in photovoltaic power plants, technical complexity, the need for integration between different engineering disciplines, and interaction with multiple suppliers and clients can exacerbate these difficulties. Practical experience in the sector reveals that interdepartmental communication, information validation with clients, and standardization of activities, especially during the commissioning phase, are critical points that often lead to inefficiencies and delays.

Given the scenario of increasing demand for photovoltaic power plant projects and the inherent complexity in implementing SCADA systems, it becomes imperative to investigate and propose improvements in management processes that can mitigate the identified challenges. The search for a balance between the structure of traditional management and the flexibility of agile methodologies, known as hybrid management, presents itself as a promising alternative to optimize the execution of these ventures. Thus, this study is justified by the need to enhance efficiency and predictability in the delivery of SCADA projects, contributing to the sustainability and competitiveness of companies in the sector. The objective of this research is to propose improvements in the implementation processes of SCADA systems in photovoltaic power plants, through the application of agile methods, aiming to increase productivity and organization for the fulfillment of established deadlines.

2. Material and Methods

The present research adopted a qualitative approach, characterized as a case study, according to the nature of the problem investigated. This type of approach allows for an in-depth understanding of phenomena in their natural context, exploring the perceptions and experiences of the individuals involved. The study was exploratory in nature, aiming to provide greater familiarity with the problem and identify assumptions or propositions for future investigations, as advocated by Gil (2002). The choice of a case study allowed for a detailed analysis of the implementation processes of SCADA systems in photovoltaic plants within a specific organization, offering valuable insights into project management practices.

The study was conducted in a company in the engineering and telecommunications sector, specializing in the photovoltaic market since two thousand and twenty, with approximately one hundred employees. This organization had already delivered SCADA systems to more than twenty clients, totaling about three hundred implemented plants and one point four Gigawatts-peak (Gwp) monitored by April two thousand and twenty-six. The unit of analysis consisted of the implementation processes of SCADA systems in photovoltaic plants, focusing on the activities and interactions of the responsible professionals. The empirical data collection occurred specifically in the period of January two thousand and twenty-six, concentrating on the operations of the analyzed company.

The population of interest for this research comprised employees of the company who directly work on the implementation of SCADA systems. The sample consisted of eight professionals, intentionally selected due to their fundamental role and practical experience in the stages of communication, field installation, and software development. The participants included an Implementation and Technical Support Coordinator, a Commercial Coordinator, an Operations Director, a Development Manager, a Project Owner, a Support Analyst three, a Support Technical Assistant, and a Support Supervisor. The diversity of roles and sectors aimed to capture a comprehensive range of perspectives on the challenges and opportunities in the implementation process.

For data collection, a comprehensive bibliographic survey was initially used. This stage involved consulting books, scientific articles, and already published documents, focusing on agile methodologies, project management, and specifically, on the implementation of SCADA systems in photovoltaic power plants. The objective was to establish a solid theoretical basis for understanding the research problem, identify best industry practices, and support the analysis of the empirical data collected. The review allowed the study to be contextualized within existing knowledge and guided the formulation of research questions.

Complementary to the bibliographic survey, empirical data collection was carried out through a semi-structured questionnaire, composed of open-ended questions, as detailed in Appendix A of the original work. This instrument was applied to the eight selected professionals from the sample, allowing for the acquisition of both objective and subjective data. The semi-structured nature of the questionnaire facilitated the exploration of perceptions, challenges, values, and practices observed in the execution of SCADA implementation projects, according to the methodology of social science interviews (Quaresma and Boni, 2005). The questions were designed to identify opportunities for optimizing time and effort, without compromising the quality of deliverables.

The research execution followed sequential and interconnected steps. Firstly, the theoretical conceptual structure was defined and the case study was planned. Next, the semi-structured questionnaire was structured, based on literature recommendations and research objectives. After the instrument’s validation, it was applied to the interviewees, and empirical data was collected. Subsequently, the collected data were analyzed and related to the theoretical implications identified in the literature review, culminating in the elaboration of the final report. This process aimed to ensure coherence between the study’s objectives, methodology, and conclusions.

The treatment and analysis of the collected data were carried out qualitatively, seeking to identify patterns, emerging themes, and opportunities for improvement in the implementation processes of SCADA systems. The responses obtained through the semi-structured questionnaire were interpreted in conjunction with the literature review, allowing for conceptual triangulation between theory and observed practice. The focus of the analysis was to identify critical points, inefficiencies, and challenges faced by the team, as well as gaps in communication and standardization. This process supported the proposal of improvements based on agile methods, aiming to optimize productivity and project organization.

Regarding the ethical aspects, the research was conducted based on obtaining information directly from company collaborators, ensuring the confidentiality of responses and the protection of participant identity. Although the original term paper does not explicitly detail formal ethical procedures, such as free and informed consent terms, data collection was carried out in a manner that respects the privacy and autonomy of the interviewees. No explicit methodological limitations were identified or declared in the original document that could compromise the internal or external validity of the research findings, maintaining fidelity to the information presented.

3. Results and Discussion

The interpretation and presentation of the results of this research were carefully structured, starting with an in-depth literature review, followed by the application of a semi-structured questionnaire to professionals in the analysis unit. To contextualize the findings, it is essential to understand that all SCADA system implementation projects in Photovoltaic Plants (UFVs) at the studied company follow a standardized Project Breakdown Structure (WBS), as illustrated in Figure 1. This WBS serves as the basis for organizing activities and allocating resources, outlining the main project phases, from commercial definition to final commissioning. Clarity in the project structure is a prerequisite for any performance analysis and for proposing improvements, as it allows for the identification of critical points and interdependencies between tasks.

Source: Original research results

Figure 1. WBS (Work Breakdown Structure)

The work packages detailed in Table 1 complement the WBS (Work Breakdown Structure), providing a granular view of activities, their precedences, and estimated durations. The estimation of activity durations, as presented in Table 1, was based on prior experience in similar projects and consultation with experts, such as the implementation coordinator and installation technicians. This estimation method is corroborated by Mattos (2010), who emphasizes that activity durations are influenced by factors such as team experience, the degree of service knowledge, and available logistical support. The accuracy of these estimates is crucial, as they form the basis for calculating the total project schedule and identifying the critical path.

Table 1. Work Packages and estimated time

Work Package Code

Code – Activity

precedence

Duration (Days)

1.1, 1.2 and 1.3

A – Define with the client the network topology, scope, and equipment to be supplied

—

15

2.1, 2.2, 2.3 and 2.4

B – Based on the base documentation sent by the client and the contracted scope, generate the deliverables such as IP List, Equipment List, Communication Detailing, and Automation Descriptive Memorial

A

10

3.1 and 3.3

C – Perform IP configuration according to the List prepared by Implementation and forward to dispatch for collection

B

7

3.2

D – Register the plant in the supervisory system before mobilization, according to the implementation information.

B

1

4.1, 4.2 and 4.3

And – Perform the installation of the Contractor’s supply equipment as per the forwarded documents

C

3

5.1, 5.2 and 5.3

F – Perform VPN Closure, connectivity tests, create and validate data acquisition processes as informed by the deployment

And

4

5.4

G – After validation of the processes, upload data to the SCADA system in the cloud

D, F

1

Source: Original research results

The critical path methodology, widely used in project management, according to Barcaui et al. (2019), was applied to determine the sequence of activities that cannot be delayed without impacting the total project deadline. Activities that make up this sequence are classified as critical, while others are non-critical. The development of a precedence network, which establishes the order of execution of activities and their interdependencies, is a fundamental step. Polito (2015) warns about the importance of correctly defining dependency relationships, as errors at this stage can significantly increase the risk of delays. The most common precedence relationships, such as finish-to-start, where one activity can only begin after its predecessor is completed, are predominant in the diagram of the project in question, according to Mattos (2010). Figure 2 illustrates the scheduling of activities and the critical path, revealing that the total duration of the SCADA system planning and implementation is 40 days, resulting from the sum of the durations of critical activities A, B, E, F, and G, which are in sequential order. The early finish date (EF) of an activity is equivalent to the early start date (ES) of its successor, which simplifies the analysis, although it does not imply that the activity will be completed exactly on that date.

Source: Original research results

Figure 2. Program of activities and critical path

One of the first points of investigation with the interviewees was the effectiveness of “Kick-Off” meetings in defining scopes, deadlines, and specificities of the plants. The commercial coordinator (interviewee 2) indicated that, although pre-Kick-Off alignment meetings are held to define contractual deadlines and scope, clients often lack knowledge about all the necessary steps for the implementation of the supervisory system, which can lead to unmapped specificities. This finding highlights a critical gap in initial communication and expectation management, which, if not addressed, can compromise the project’s integrity from its inception. The lack of mutual and detailed project understanding among all stakeholders, especially the client, can generate ambiguities that manifest as poorly defined scope issues and constant changes, recurring characteristics in software development projects, as pointed out by PMI (2017). Literature, such as Gido et al. (2019), emphasizes that stakeholder validation is an essential factor for project success, and the absence of robust alignment from the outset can undermine this validation.

The support coordinator (interviewee 1) revealed a significant problem: the support team does not participate in Kick-Off meetings. The responsibility of receiving, interpreting, and relaying information from the commercial sector falls on the implementation coordinator. This practice is problematic because support is the sector that deals directly with the configuration and validation of equipment in the field, and the absence of their prior knowledge in electrical engineering hinders the analysis of projects forwarded by clients. The interpretation and relay of information by the implementation coordinator, although necessary, introduce a potential failure point in the transmission of critical details, such as the plant’s installed capacity, inverter models, trackers, relays, and multimeters, all with native communication protocols and maps that require correct interpretation for data acquisition in SCADA. The absence of support in these initial meetings not only delays the plant registration and equipment validation phase but also creates excessive dependence on the implementation coordinator to resolve doubts, as reported by the technical support assistant (interviewee 7), who emphasizes the slowness in information feedback. The operations director (interviewee 3) agrees that the support team needs to ask the right questions to align specificities, but this presupposes a level of knowledge that can only be acquired through active participation in the initial phases. Pahl et al. (2005) emphasize the need for active leadership participation to enable the alignment of the technical team with the client. As a improvement proposition, it is suggested to implement weekly alignment meetings, lasting 1:30h, involving all areas, to discuss doubts and ensure that support has a direct channel for clarifications with the implementation coordinator. This measure aims to improve interdepartmental communication, reduce dependence on a single point of contact, and ensure that all project specificities are proactively understood and addressed, mitigating risks of delays and rework.

The frequency of changes in projects under development was another point of consensus among the interviewees, who unanimously responded “sometimes”. This occurrence is attributed to variability in client organization: while some clients standardize the construction of their plants, facilitating scope definition and SCADA implementation, others do not have such standardization. This inconsistency results in unmapped inconsistencies during the field installation stage. The operations director (interviewee 3) exemplified this situation, mentioning the need for remobilization for a plant and multiple meetings to close an addendum due to an incorrect scope definition, generating wear and tear and increasing implementation time. This scenario validates the perspective of Gido et al. (2019) on the importance of stakeholder validation for project success. In unstable and unpredictable environments, the adaptive approach, according to Marques Junior and Plonski (2011), is more effective, as it allows management to adapt to the differences of each project. As an improvement proposition, the company should request a pre-mobilization checklist, including plant photos, and hold an alignment meeting with the contractor as soon as the plant is ready for mobilization. This meeting should validate the information gathered and expose the possible consequences of inconsistencies, such as increased installation time or execution infeasibility, with additional costs being borne by the client. This proactive approach not only aligns expectations but also encourages the client to provide accurate and complete information, reducing the probability of surprises and rework in later project phases. The standardization of deliverables and the clear division of work packages, as suggested by the Agile Manifesto (2001) and Sutherland (2016), also contribute to mitigating instability, ensuring that teams have a solid foundation for their activities.

The commissioning phase was unanimously identified by the interviewees as the stage where most delays occur. This problem is directly linked to the dependency on the fulfillment of predecessor activities by the client. The non-completion of these activities impacts the validation of data acquisition from the equipment. The operations director (interviewee 3) cited communication problems in the field that prevent satisfactory commissioning, resulting in its fractional or remote execution. This scenario reinforces the need for an adaptive approach in unstable environments, as advocated by Marques Junior and Plonski (2011), where project management is adjusted to deal with the particularities of each situation. To mitigate these delays, it is proposed that, in case of pending issues in the field that affect commissioning, the company gather the entire work team to list the failure points and monitor their correction with the client. At the end of the field installation, a detailed installation and testing report, with photographic evidence, must be sent to the client. This report should point out all the client’s pending issues that will impact commissioning, establishing a deadline for correction. Continuous monitoring via email and alignment meetings in critical cases, with the support team, will ensure that pending issues are resolved efficiently, minimizing the impact on the schedule. This practice not only increases transparency but also holds the client accountable for their obligations, promoting more effective collaboration and reducing the risks of delays.

Regarding the optimization of critical steps, there was a consensus among the interviewees that the field installation step offers the greatest opportunity for time optimization. The support coordinator (interviewee 1) suggested a specific improvement: to break down work package 5.3 (configuration of processes for data acquisition), which previously occurred during the installation step, and migrate it to the equipment separation step (now 3.2). This strategic change is enabled when support has the communication architecture, the IPs of the monitored equipment, the Modbus addresses, and the standardized reading maps in advance. With this pre-configured information, the Remote Terminal Unit (RTU) can be shipped with all data acquisition processes already configured, eliminating the time currently spent in the field for this configuration. Figure 3 presents the updated WBS (Work Breakdown Structure), reflecting this suggestion.

Source: Original research results

Figure 3. WBS – Updated Work Breakdown Structure as per suggestion

This workflow restructuring represents a practical application of the principles of agile methods, which seek continuous optimization and waste reduction. By anticipating data configuration for an earlier phase, the company not only optimizes mobilization and field installation time but also reduces the complexity of on-site activities, minimizing potential errors and rework. The literature, such as Sutherland (2016) and the Agile Manifesto (2001), emphasizes the importance of continuous engagement and collaboration with the client, through constant feedback cycles, to optimize the schedule and ensure project assertiveness. The standardization of deliverables and the clear division of work packages, as advocated by the PMI (2017), are also crucial for reducing rework and ensuring compliance, positively impacting schedule performance and delivery quality. The proposal to migrate the configuration of reading processes to the equipment separation stage is a clear example of how standardization and task anticipation can generate significant gains in productivity and efficiency, aligning with best project management practices.

Still on the optimization of critical steps, the initial phases of implementation, such as commercial definition (15 days) and project elaboration (10 days), were identified as the longest in the process. To optimize time in commercial definition, literature, especially Sutherland (2016) and the Agile Manifesto (2001), suggests continuous customer engagement through Sprints and Reviews during negotiation. Prioritizing customer collaboration over contract negotiation allows for constant feedback cycles, building trust and avoiding project deviations. This not only optimizes the schedule but also ensures the final product is more aligned with customer expectations. For the project elaboration phase, standardization is key, according to PMI (2017), which highlights how standardization reduces rework and ensures compliance, improving schedule performance and deliverable quality. Creating models and templates for project elaboration, for example, can significantly accelerate this phase, ensuring that technical and operational requirements are consistently met.

The question about the frequency of compliance with the initial schedule and the impact of changes revealed that, most of the time, the schedule is not met, and changes primarily impact scope and cost. The commercial coordinator (interviewee 2) explained that the board’s priority is to deliver the requested scope, even if it entails increased costs, whether due to additional materials, hotel per diems, or allocation of man-hours from the support team for remote commissioning. This finding underscores the classic project management dilemma between scope, cost, and time, where flexibility in one of these pillars generally requires concessions in the others. In the context of SCADA projects, where technical complexity and client expectations are high, change management becomes a constant challenge. The adaptive approach, according to Marques Junior and Plonski (2011), is particularly relevant here, as it allows management to adjust to changes, rather than trying to follow a rigid plan that will inevitably be altered. The improvement proposition, therefore, should focus on more structured change management, which assesses the impact of changes on scope, cost, and time transparently, involving the client in decision-making and ensuring that additional costs are duly negotiated and documented.

The company studied does not adopt a standard tool for project management, allowing each collaborator to use the tool of their preference. Table 2, which details the tools used by the interviewees, reveals a variety of options, including Planner, RD Station, Excel, Jira, Trello, and others.

Table 2. Tools used by collaborators

Interviewee

tool

Function

1

Organizer

Technical Support Coordinator

2

RD Station

Commercial Coordinator

3

Excel

Director of Operations

4

Jira and Trello

Development Manager

5

Jira and Trello

Owner of the Project

6

Organizer

Support Analyst 3

7

Organizer

Assistant – Support Analyst 1

8

Trello

Support Supervisor

Source: Original research results

This diversity, although it may seem flexible, in practice, hinders optimized project progress monitoring, as Gido et al. (2019) highlight the need for close monitoring in the execution phase. The lack of a unified tool prevents a consolidated view of activities, generates information silos, and complicates coordination between teams. As a proposition for improvement, the adoption of a standard tool for project management that can be used by all team members is recommended. “Trello” was the tool most recognized by the interviewees, and its choice is justified by its simple, intuitive interface and by being free software. The implementation of a standard tool like Trello would promote greater transparency, facilitate communication, and allow for more effective progress monitoring, aligning with the principles of visual management advocated by Deunizio (2020) and the Agile Manifesto (2001).

The need for activity prioritization also revealed significant differences between the teams. Respondents from the development sectors (2, 3, and 5) stated that their activities rarely require prioritization, and when it occurs, it affects other tasks. The Project Owner (respondent 4) explained that the SCADA system is standardized for all clients, and the weekly development meetings aim to accommodate client suggestions and prioritize relevant deliverables, but new prioritizations are rarely accepted after deadlines are agreed upon. In contrast, respondents from the support sector (1, 6, 7, and 8) reported that frequent prioritizations occur in their activities. Support analyst 3 (respondent 6) emphasized that “prioritizations of certain tasks are constantly demanded, directly affecting schedules and plans already made. And, when everything is a priority, the concept of priority itself is lost, causing every task/project to receive the same attention.” This situation is aggravated by the fact that the monitoring of pending commissions, which are unstable activities susceptible to adaptations, is the responsibility of the support team. The lack of clear and centralized priority management generates inefficiency and frustration. As a proposed improvement, prioritization should come from the coordinators, with the approval of stakeholders, ensuring that priority decisions are strategic and aligned with the overall objectives of the project and the company. This prevents the support team from being overloaded with arbitrary prioritizations and allows for a more organized and predictable workflow.

The analysis of the interviews also revealed that the work teams have a standard number of collaborators (8 people, including an on-site installation technician, the implementation coordinator, and six support collaborators), and that these teams remain the same throughout the project. Although all members are aware of their own responsibilities, they are not always aware of the activities of other collaborators. The support supervisor (interviewee 8) exemplified that, even when working in pairs, formal or informal communication about the completion of one activity and the start of the next is often absent, causing delays in the entire commissioning stage. This gap in interdepartmental communication and task visibility is a critical point that directly impacts efficiency and deadline adherence. Sutherland (2016) highlights that, for “Scrum”, holding daily meetings to monitor adaptive projects and having teams composed of three to nine people are fundamental. The company already has standardization in team formation, with the ideal number of collaborators. However, adopting short, daily follow-up meetings is a crucial improvement proposition to enhance communication among collaborators and avoid delays, especially in commissioning.

The technical support assistant (interviewee 7) reported difficulties in identifying the next tasks to be developed, frequently resorting to the supervisor or coordinator for guidance. Deunizio (2020) highlights the relevance of visual management for the organization and development of tasks. As a proposition for improvement, the use of “Kanban” cards is suggested for the identification and monitoring of tasks by the entire team, ensuring that processes are sequential and organized. Based on the interviews and the literature review, Figure 4 illustrates a proposal for the application of the “Trello” tool for managing the implementation of the SCADA system in a plant. The methodology applied is “Scrumban”, which combines the “sprint” and “backlog” techniques of Scrum with Kanban cards.

Source: Original research results

Figure 4. Application of the Trello Tool for management

This hybrid approach allows the company to benefit from Scrum’s iterative structure and planning, while leveraging Kanban’s visibility and flow control. The visual management provided by Trello, with its boards and cards, allows all team members to have a clear understanding of the status of each task, responsibilities, and next steps. This not only improves communication and transparency, but also empowers employees to manage their own activities more autonomously, reducing the need for constant supervisor intervention. The adoption of Scrumban via Trello is a practical and low-cost solution that can transform how SCADA projects are managed, promoting greater agility, efficiency, and collaboration among teams.

In summary, the findings of this research indicate that the main challenges in schedule management for SCADA system implementation are intrinsically linked to ineffective communication between areas, inconsistent information validation with the client, and a lack of standardization in activity tracking. The proposed improvements converge towards practices aimed at increasing the integration, transparency, and adaptability of the process. The combination of elements from traditional management, such as the WBS and critical path, with agile practices, such as daily meetings, pre-mobilization checklists, detailed pending activity reports, WBS restructuring to anticipate critical activities, the adoption of a standard tool like Trello and the Scrumban methodology, and centralized priority management, proves to be an adequate approach for the analyzed scenario. These propositions not only address the identified critical points but also promote a more collaborative and efficient organizational culture, essential for success in complex and dynamic projects like the implementation of SCADA systems in photovoltaic plants. Table 4, which summarizes the identified improvement opportunities and the literature-based propositions, reinforces the robustness of the recommendations presented.

4. Conclusion

It is concluded that the objective was achieved by proposing improvements in the implementation processes of SCADA systems in photovoltaic plants, through the application of agile methods, aiming to increase productivity and organization for the fulfillment of established deadlines. The propositions include holding daily and weekly alignment meetings, adopting a pre-mobilization checklist, restructuring the Project Breakdown Structure (PBS) to anticipate critical activities, and implementing the Scrumban methodology via Trello for visual and collaborative management. These improvements aim to optimize interdepartmental communication, reduce rework, and ensure greater assertiveness in project delivery, balancing the structure of traditional management with the flexibility of agile approaches.

This study, qualitative in nature and focused on a single case, presents limitations inherent to its specificity, which restricts the direct generalization of results. For future research, it is recommended to expand the study to multiple cases in different engineering sector companies, in order to verify the applicability and consistency of improvements in various organizational contexts. It is also suggested to investigate the integration between agile and traditional methods in projects with varying levels of complexity and maturity, and to analyze the impacts of this combination on contract management and on meeting billing milestones. Finally, exploring the use of digital tools and emerging technologies in supporting hybrid project management can continuously improve the sector’s processes.

Bibliographic References

Barcaui, A. B.; Borba, Danúbio; Silva, Ivaldo M. da; Neves, Rodrigo B. 2019. Gerenciamento de cronograma em projetos. 1a ed. FGV editora.

Beck, K. et al. 2001. Manifesto for Agile Software Development. Disponível em: http://agilemanifesto.org. Acesso em: 20 out 2025.

Boyer, Stuart A. 2004. Scada: Supervisory Control and Data Acquisition. 3ed. EUA: ISA.

Deunizio, M. 2020. Métodos Ágeis: Um guia definitivo com mais de 20 metodologias ágeis utilizadas por grandes empresas para criar o produto certo. 1ed. Ebook Kindle., São Paulo, SP, Brasil.

Gido, J.; Clements, J.P.; Rose, B. 2019. Gestão de Projetos. 7ed. Cengage, São Paulo, SP, Brasil.

Gil, A.C. 2002. Como Elaborar Projetos de Pesquisa. 4ed. Atlas S.A., São Paulo, SP, Brasil.

Marques Junior, L. J. M.; Plonski, G. A. 2011. Gestão de projetos em empresas no Brasil: abordagem “tamanho único”? Gestão & Produção 18: 1-12., São Carlos, SP, Brasil.

Maschk, R. 2022. Gerenciamento de projetos: fundamentos. 1ed. Senac. São Paulo, SP, Brasil.

Mattos, A. D. 2010. Planejamento e Controle de obras. 1a ed. Pini., São Paulo, SP, Brasil.

Pahl, G.; Beitz, W.; Feldhusen, J.; Grote, K. 2005. Projeto na Engenharia. 6ed. Blucher, São Paulo, SP, Brasil

Polito, G. 2015. Gerenciamento de obras: Boas práticas para a melhoria da qualidade e da produtividade. 1a ed. Pini.

Project Management Institute (PMI). 2017. A Guide to the Project Management Body of Knowledge – PMBOK® Guide. 6ed. Pennsylvania.

Quaresma, J.; Boni, V. 2005. Aprendendo a entrevistar: como fazer entrevistas em Ciências Sociais. Revista Eletrônica dos Pós-graduandos em Sociologia Política da UFSC.

Sutherland, J. 2016. Scrum A arte de fazer o dobro na metade do tempo. 2ed. Leya, São Paulo, SP, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.