Challenges in schedule management in the budget preparation process in a basic sanitation company

Milene Theodoro Silva; Fabiana da Silva Podeleski

DOI: 10.22167/2675-6528-202601239

Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.

Summary

This study analyzed schedule management in the budgeting process of an organization in the basic sanitation sector, in light of project management principles, focusing on elements that influence deadline compliance. The research, of an applied nature, adopted a qualitative approach and a case study design, in which three budget cycles were analyzed, treated as distinct projects. Data collection was carried out through triangulation of different sources of evidence, including documentary analysis of schedules, direct observations, questionnaire application, and brainstorming dynamics. The results showed the recurrent occurrence of schedule delays, associated with communication weaknesses between areas, lack of process standardization, high interdependence between activities, and limited use of the schedule as a planning and control tool. The comparative analysis of the cycles demonstrated that delays occurred consistently, regardless of the adopted work format. As a practical contribution, the study proposed guidelines for improving schedule management, aligned with the predictive approach of project management, contemplating greater detail of activities, clear definition of responsibilities, and strengthening of budget process governance.

Keywords: Budget delays; Project management; Planning and control; Budgeting process.

1. Introduction

Organizations operating in capital-intensive and highly regulated sectors, such as basic sanitation, face an environment of high operational complexity. Such contexts are characterized by the presence of multiple stakeholders and the continuous need for coordination between diverse functional areas. In this scenario, planning assumes a fundamental strategic role, especially in budgetary processes, where decisions on resource allocation directly impact the execution of activities and the achievement of organizational objectives (Kerzner, 2022).

Project management literature emphasizes the predictability and control of deadlines as crucial elements for organizational performance. The schedule, according to the Project Management Institute (PMI, 2021), is one of the main planning tools. It establishes the logical sequence of activities, their interdependencies, durations, and milestones, allowing for systematic monitoring of project progress. When used effectively, the schedule contributes to the alignment between planning and execution, reducing rework and supporting decision-making.

Although the schedule is a central tool for integrating scope, resources, and deadlines, providing greater predictability and discipline in execution (Vargas, 2018), failures in its control can lead to rework, interfunctional conflicts, and loss of efficiency. Recent studies, however, indicate that the mere formal existence of schedules does not guarantee their effectiveness. Flyvbjerg (2021) points out that recurring failures in meeting deadlines are often associated with governance deficits, coordination problems, and weaknesses in planning and control processes, transforming the schedule into a documentary artifact rather than an active management tool (Verzuh, 2016).

In the specific organizational context of a basic sanitation company, the problem addressed in this study arises from the author’s professional experience, who observed recurring difficulties in meeting deadlines during the preparation and review of the corporate budget. This environment, which involves works, asset maintenance, and essential service contracts, shows that delays are not limited to specific factors. They are, in fact, associated with structural issues related to communication between areas, the absence of process standardization, and planning governance.

The schedule management in recurring budgetary processes, such as those analyzed, requires a high degree of planning formalization, as the repetition of activities does not eliminate the need for rigorous control of deadlines and interdependencies (Meredith and Mantel, 2017). The predictive approach to project management, characterized by the advance planning of stages and the prior definition of deadlines, proves to be particularly suitable for this context, which involves recurring processes, a relatively stable scope, strong regulation, and the need for standardization (PMI, 2021; Kerzner, 2022). The practical relevance of this study lies in proposing guidelines for improving schedule management, while the academic contribution is manifested in the discussion on the application of project management principles in complex organizational environments.

Given this scenario, this study aimed to analyze schedule management in the budget preparation process of an organization in the basic sanitation sector, in light of project management principles, focusing on the elements that influence deadline compliance.

2. Material and Methods

The research developed was characterized as applied in nature, with a qualitative approach and a case study design. Its objective was to analyze the schedule management in the budget preparation process of an organization in the basic sanitation sector, in light of project management principles, focusing on the elements that influence deadline compliance. Regarding its objectives, the study was classified as descriptive.

The unit of analysis consisted of three budgetary cycles, treated as distinct projects, from a company in the basic sanitation sector. These cycles, together, represented the complete process of elaboration and revision of the organizational budget. The methodological proposal for schedule management was based on the practices of the PMBOK Guide (PMI, 2021), adopting a predictive approach to project management.

The predictive approach was chosen considering the advance planning of steps, the prior definition of deadlines, and the use of the schedule as the main tool for monitoring and control. This choice aligned with the characteristics of the organizational context studied, which involves recurring processes, a relatively stable scope, strong regulation, and the need for standardization. The analysis period of the three budgetary cycles extended from September 2024 to December 2025.

The data collection strategy was structured under the principle of triangulation, aiming to obtain robust and complementary evidence. Different sources were used, including documentary analysis, direct observations, application of questionnaires, and structured brainstorming dynamics. This approach allowed for a multifaceted understanding of the factors influencing deadline compliance.

The study participants were professionals directly involved in the preparation, consolidation, and monitoring of the budget and schedules. The ethical principles of confidentiality, anonymity, and privacy were observed, ensuring that no information allowed for the individual identification of participants or the analyzed organization.

The research fit the hypotheses for exemption from registration and evaluation by the CEP/CONEP System, according to the sole paragraph of art. 1, items I and VII, of CNS Resolution No. 510, of April 07, 2016. This exemption occurred because it involved public opinion research with unidentified participants and theoretical deepening of situations that emerge spontaneously from professional practice.

The documentary survey involved the analysis of historical records from previous budget cycles. Planned versus executed timelines, minutes of follow-up meetings, and other documentary records from budget cycle alignment meetings were examined. This stage allowed for the identification of deviations between planned and actual deadlines, as well as the occurrence of rework and communication failures.

The questionnaires were applied to five professionals who act as planning and control specialists, corresponding to the entirety of the target audience defined for this stage. The instrument, composed of closed questions with a dichotomous scale (“Yes” and “No”), sought to capture perceptions about planning, monitoring, and control practices of budgetary schedules.

The questionnaire application occurred in December 2025, at a time after the conclusion of the budgetary cycles analyzed. This allowed the respondents to retrospectively evaluate the planning, monitoring, and control processes of the schedules, as well as the difficulties encountered and the factors associated with the observed deadline deviations.

Structured brainstorming dynamics were conducted with managers from the technical and administrative areas involved in the budgetary process. The sessions took place in the format of planning meetings, with a previously defined agenda, to identify operational bottlenecks, communication failures, and difficulties related to schedule management throughout the budget planning and approval stages.

The participants’ contributions in the brainstorming sessions were recorded through structured notes and subsequently organized and consolidated. Direct observations were carried out throughout the development of the budgetary cycles, complementing the information obtained from other sources of empirical data.

The collected data were processed in three distinct stages, based on established procedures in qualitative research and case studies (Gil, 2019; Yin, 2015). Initially, the information was subjected to thematic categorization, organizing the empirical data into four structural axes: People, Processes, Technology, and Communication.

This categorization allowed for the grouping of similar evidence and the identification of the origin of the observed problems, whether behavioral, procedural, or systemic in nature. Subsequently, an interpretative synthesis of the data was carried out through the identification of emerging patterns, using the pattern matching technique described by Yin (2015).

The documentary data, the results of the questionnaires, and the records of the brainstorming dynamics were analyzed in an integrated manner, enabling the identification of recurrences. Finally, basic descriptive indicators, extracted from the documentary analysis of the schedules, such as the frequency of rework and the percentage of adherence to the originally planned deadlines, were defined to support qualitative interpretation (Gil, 2019).

3. Results and Discussion

The analyzed organization, with over fifteen years of operation in the basic sanitation sector, operates in an environment of high operational complexity, strong regulation, and growing demand for process standardization. The company, which operates in various regions of Brazil, has dedicated teams for the elaboration and consolidation of the corporate budget, including the planning and monitoring of schedules. In this context, schedule management is fundamental to align activities and coordinate the stages of the budgeting process. However, the application of this instrument as a management tool has revealed recurring weaknesses, compromising deadline compliance and increasing the incidence of rework.

The results obtained from the structured brainstorming sessions, conducted within the scope of Project 1, corroborated this initial diagnosis. Schedule restrictions associated with fixed closing milestones, critical inter-area dependencies, limitations in the use of planning support systems, and weaknesses in budget process governance were identified. Communication process failures, the absence of standardized workflows, and low adherence to the established schedule were recurrently observed, factors that compromised the fulfillment of the planned stages and resulted in systematic delays.

The budget elaboration in Project 1 occurred entirely remotely, with teams distributed in different locations. This configuration intensified communication noise and hindered alignment between areas, resulting in procedural failures, rework, and delays. The interpretive analysis indicated that remote work intensified communication noise but was not the sole cause of the delays. Evidence pointed to predominantly reactive communication and the absence of structured channels, generating inconsistent information and rework, which compromised the flow of activities. The lack of clear guidelines for information qualification led to successive revisions of deliverables, weakening schedule predictability.

Additionally, the high interdependence between areas and sequential deliveries resulted in a cascading effect of delays, hindering integrated planning. Limitations in the integration between the systems used caused delays in data consolidation, directly impacting deadline adherence. Finally, the low definition of responsibilities and occasional interferences in process governance led to misalignment between planning and execution, reducing the use of the schedule as a management tool. These findings suggest that the delays did not stem exclusively from the remote format, but from structural issues, such as the absence of standardized guidelines and the high dependence on inter-area deliveries.

In Project 2, teams began to prepare the budget in person, but the problems observed in the previous project persisted. The analysis of the documentary records from the budgetary cycle showed the frequent need to redefine deadlines and request schedule changes, indicating instability in planning and low adherence to the initial plan. Activities conditioned on the delivery of information by different organizational areas resulted in chain delays and postponed decisions, compromising the continuous flow of activities.

The existence of multiple stakeholders and the need for successive validations made coordination of deliveries difficult, fragmenting responsibilities and reducing the effectiveness of schedule execution. The mobilization of in-person efforts to correct deviations in advanced stages led to late corrections of consolidated delays, indicating that the action assumed an emergency rather than a preventive character. The combined use of corporate systems and parallel tools with rigid deadlines limited the schedule’s flexibility, directly impacting deadlines and the ability to adjust. Finally, late requests for guidelines and detailed spreadsheets resulted in rework and revisions in advanced phases, weakening schedule control from the outset.

The organization of a mandatory in-person task force, as well as the subsequent holding of meetings to discuss results, reinforces that the physical proximity of the teams was not sufficient to mitigate the structural problems of communication, governance, and definition of responsibilities. These findings indicate that, even in an in-person context, the schedule was not fully utilized as a preventive tool for planning and control, maintaining a predominantly reactive use. The recurrence of these problems, regardless of the work format, suggests that the difficulties are rooted in structural aspects of the schedule management process.

In Project 3, an attempt was made to improve schedule management by adopting a broader view of the steps and deadlines, focusing on a macro view of the process. However, the problems identified in previous cycles persisted. Holding frequent meetings with multiple managers, although indicating an effort at coordination, also revealed a high cost for schedule maintenance, suggesting the need to compensate for planning failures. Recurring requests for adjustments and validations of already executed activities maintained the schedule’s instability, which remained predominantly reactive.

The centralization of teams in in-person work for deviation correction, although it was a corrective strategy, concentrated corrections in critical periods, showing that in-person work was used as an emergency alignment mechanism. Late requests for detailed spreadsheets and information qualification hindered the monitoring of real progress, limiting effective schedule control due to the absence of operational detail. The simultaneous use of corporate systems and parallel tools with rigid deadlines reduced flexibility for deadline adjustments, directly impacting schedule execution due to systemic limitations.

The comparative analysis of the three projects shows that, despite the different operational configurations, the common problems remained. These include communication failures between areas, the absence of formalization of activity interdependencies, systematic non-compliance with schedule stages, unplanned interferences from senior management, and frequent rework. These factors were corroborated by the documentary records analyzed in Projects 1, 2, and 3, reinforcing the consistency of the empirical findings obtained from different data collection sources.

Given this context, the main variables associated with the problem analyzed in this study include internal communication processes, the level of standardization and formalization of budgetary processes, the clarity of interdependencies between activities, the performance of senior management in the flow of processes, and the degree of use of the schedule as an effective tool for planning, monitoring, and control. The identification of these variables makes it possible to understand the factors that contribute to the recurring delays observed in budgetary schedules and supports the analysis of the problem in the specific context of the organization studied.

Project management constitutes an integrating organizational competence, articulating diverse dimensions such as communication, stakeholder management, scope, schedule, quality, costs, and innovation, acting as a structuring axis for the planning and execution of activities (PMI, 2021). In the context of this study, schedule management is central, as the budgetary process directly depends on meeting deadlines and coordinating multiple areas. The predictive approach, characterized by advance planning and the use of the schedule as the main control instrument, aligns with the characteristics of the studied environment, which involves recurring processes and stable scope (Kerzner, 2022).

Schedule management involves defining and sequencing activities, identifying interdependencies, estimating durations, and continuously monitoring deadline performance. The elements considered in the study include the definition and sequencing of activities, the identification of interdependencies between areas and stages, the definition of activity durations and project milestones, adherence to planned stages, deadline monitoring, and the impacts of unplanned interferences. These elements allow for a structured analysis of the factors contributing to the recurring delays observed.

In the context of budget management, the PMO’s function plays a relevant role in supporting, guiding, and standardizing the use of the schedule. Although it does not hold direct responsibility for creating all activities, the PMO structures guidelines, proposes adjustments, and seeks to ensure adherence to the plan. However, the PMO’s performance faces challenges such as team resistance to detailing activities, communication failures, lack of continuous schedule updates, and delays that impact subsequent deliveries, in addition to requests for acceleration from senior management that alter the planned cadence (Kotter, 1996).

The analysis of the perceptions of the professionals involved, obtained through questionnaires, revealed that deadlines are often set without sufficient detail of activities, monitoring is irregular and unsystematic, and communication failures between areas are recurrent. Schedule adjustments are made reactively, and delays are perceived as recurring events, not isolated incidents. These perceptions indicate that, although the schedule formally exists, its application as a management tool is limited, especially regarding continuous monitoring and the management of interdependencies between areas.

The joint analysis of documentary data, questionnaires, and brainstorming dynamics showed convergence regarding the main factors associated with the observed delays in the schedules. The measured delays were corroborated by the professionals’ perceptions, who pointed to communication failures, lack of standardization, and low adherence to planned stages as recurring causes. Documentary records reinforced this diagnosis by identifying frequent rework and replanning as direct effects of these fragilities. The results obtained corroborate the project management literature, which highlights the schedule as a relevant element for integration between areas and for controlling temporal performance (PMI, 2021; Kerzner, 2022).

The limited use of the schedule in the studied projects indicates weaknesses in execution discipline and planning governance. The recurrence of delays, regardless of the work format (remote or in-person), suggests that the problem is not solely associated with the medium, but with structural aspects of the schedule management process, especially regarding the definition of responsibilities, management of interdependencies, and systematic monitoring of activities. These findings converge with the analyses of Shenhar et al. (2001), which indicate that organizational projects fail more frequently due to management and coordination problems than due to isolated technical limitations.

Improvement Proposal for Schedule Management

Based on the results obtained and the integrated analysis of the different data sources, it was possible to identify recurring weaknesses in schedule management, especially related to the definition of stages, the management of interdependencies between areas, deadline monitoring, and process governance. In this context, a proposal for improvement in schedule management for the budget preparation process is presented, structured based on project management practices aligned with the predictive approach and the analyzed organizational reality. The proposal aims to strengthen the use of the schedule as an effective tool for planning, monitoring, and control, in order to reduce recurring delays, minimize rework, and increase adherence between budget planning and activity execution.

The proposal is based on the principles of project management widely disseminated in the literature, especially related to the clear definition of roles and responsibilities, detailed activity planning, management of interdependencies between areas, systematic performance monitoring, and discipline in the execution of the established plan. These principles are compatible with the predictive approach adopted in the study and with the need for predictability and standardization inherent in the organization’s budgetary processes. The restructuring of the budgetary schedule into smaller intermediate deliverables, with clearly defined milestones and objective validation criteria, is proposed as the main improvement action.

This measure aims to increase the visibility of the progress of activities and allow for early identification of deviations. The proposed structure for the budgetary schedule includes stages such as Initial Planning, with the delivery of Consolidated Budgetary Guidelines, responsibility of Planning, deadline D+10 and validation by the PMO. The Consolidation stage foresees the delivery of the Preliminary Budget, responsibility of the Units, deadline D+30 and technical validation. The Review, with the delivery of the Revised Budget, is the responsibility of the Corporate, deadline D+45 and validation by the Committee. Finally, the Closing, with the delivery of the Final Budget, is the responsibility of the PMO, deadline D+60 and final approval. This structure allows for greater control over the flow of activities and reduces dependence on concentrated deliveries at the end of the process.

Another critical aspect identified refers to the lack of clarity regarding responsibility for schedule management. Thus, the formal definition of a governance structure is proposed. The PMO would be responsible for consolidating, updating, and monitoring the schedule. The Executing Areas would be responsible for executing and delivering the activities under their responsibility. Senior Management would evaluate exceptions, priorities, and relevant deviations. The Committee would monitor performance and deliberate on structural adjustments. Defining the PMO as formally responsible for the schedule contributes to centralizing management, reducing ambiguities, and strengthening execution discipline.

The proposal explicitly considers the following operational elements of schedule management, aligned with the factors identified in the results: clear definition of activity durations, logical sequencing of tasks, formal identification of interdependencies between areas, definition of control and validation milestones, objective criteria for replanning, and formal recording of changes and exceptions. These elements aim to strengthen the predictability of the process and reduce the incidence of reactive adjustments during execution. To enable the application of the proposal, a structured implementation plan in stages, with defined responsibilities and deadlines, is suggested.

The proposal implementation plan includes the Structuring stage, with the action of redefining the schedule model, responsibility of the PMO, with a deadline of T0 + 30 days. The Training foresees aligning the areas regarding the use of the schedule, also under the responsibility of the PMO, with a deadline of T0 + 45 days. The Pilot Application consists of applying the proposal in the next budget cycle, responsibility of the PMO, with a deadline of T0 + 60 days. Finally, the Evaluation aims to measure adherence and make adjustments, responsibility of the Committee, with a deadline of T0 + 90 days. This plan allows for the gradual implementation of the proposal, reducing operational risks and favoring the incorporation of the suggested practices.

In summary, the analysis of the three budgetary cycles revealed a recurrence of schedule delays, not conditioned by the work format, but rather by the reactive use of the schedule, low standardization, high inter-area dependency, and governance weaknesses. The results reinforce the importance of the schedule as an effective planning and control instrument, whose underutilization compromises the integration of areas and the execution of activities. The improvement proposal, aligned with the predictive approach, seeks to strengthen schedule management through greater detail, clear definition of responsibilities, and strengthening of governance, aiming to improve predictability and discipline in the budgetary process.

4. Conclusion

This study analyzed schedule management in the budget preparation process of an organization in the basic sanitation sector, from the perspective of project management principles, with the aim of identifying the elements that influence deadline compliance. Recurrent schedule delays were observed, which were associated with weaknesses in inter-area communication, lack of process standardization, high interdependency between activities, and limited use of the schedule as a planning and control tool. The comparative analysis of three budget cycles showed that these delays persisted consistently, regardless of the work format adopted by the teams. The findings indicated that the schedule was employed in a predominantly reactive, rather than preventive, manner, highlighting structural problems in defining responsibilities, managing interdependencies, and systematically monitoring activities. As a practical contribution, the study proposed guidelines for improving schedule management, aligned with the predictive approach of project management, including greater detail of activities, clear definition of responsibilities, and strengthening of budget process governance.

The improvement proposal, which includes restructuring the schedule into smaller intermediate deliveries and formalizing a governance structure with defined roles for the PMO, executing areas, senior management, and the committee, aims to strengthen predictability and discipline in the budgeting process. The results reinforce the project management literature by demonstrating that the schedule, when not used as an effective planning and control tool, loses its capacity to integrate areas and guide activity execution. However, the study has limitations, as it was conducted in a single organization and restricted to the analysis of three budget cycles, which limits the generalization of the results. For future studies, it is recommended to apply and monitor the proposed improvements in subsequent cycles, as well as to replicate the research in other organizational contexts, in order to broaden the understanding of schedule management in complex budgeting processes. Maturity in schedule management is achieved when the tool ceases to be merely a record of dates and effectively begins to guide organizational behavior.

Bibliographic References

FLYVBJERG, Bent. How big things get done: the surprising factors behind every successful project. London: Penguin Business, 2021.

GIL, Antônio Carlos. Métodos e técnicas de pesquisa social. 7. ed. São Paulo: Atlas, 2019.

KERZNER, Harold. Project management: a systems approach to planning, scheduling, and controlling. 13. ed. Hoboken: Wiley, 2022

KOTTER, John P. Leading change. Boston: Harvard Business School Press, 1996.

MEREDITH, Jack R.; MANTEL, Samuel J. Project management: a managerial approach. 9. ed. Hoboken: Wiley, 2017.

PROJECT MANAGEMENT INSTITUTE (PMI). A guide to the project management body of knowledge (PMBOK® Guide). 7. ed. Newtown Square, PA: PMI, 2021. Disponível em: https://www.pmi.org/pmbok-guide-standards. Acesso em: 23 mar. 2026.

SHENHAR, Aaron et al. Project success: a multidimensional strategic concept. Long Range Planning, v. 34, n. 6, p. 699–725, 2001. Disponível em: https://doi.org/10.1016/S0024-6301(01)00097-8. Acesso em: 10 abr. 2026.

VARGAS, Ricardo Viana. Gerenciamento de projetos. Rio de Janeiro: Brasport, 2018.

VERZUH, Eric. The fast forward MBA in project management. 5. ed. Hoboken: Wiley, 2016.

YIN, Robert K. Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman, 2015.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.