Article

October 26, 2026

Best Practices in Cost Control in Event Projects

Raquel Marques Spolidorio; Felipe Miranda de Souza Almeida

DOI: 10.22167/2675-6528-202603398

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Event projects face recurring challenges in cost control, stemming from tight deadlines, frequent scope changes, and limitations in financial planning and monitoring processes. The cost planning and control practices adopted by professionals in the event sector were analyzed, aiming to identify the main factors associated with budget deviations. The investigation was characterized as descriptive, with a quali-quantitative approach, carried out through a semi-structured questionnaire applied to professionals working in the sector nationwide. The results revealed a sample of high seniority, predominantly working in medium and large corporate events. It was observed that most professionals did not have formal certification in project management and used spreadsheets as their primary financial control tool. Tight planning deadlines and poorly defined scope were the factors most associated with budget deviations. Cost control practices were assessed as only partially efficient. The results indicated that professionals in the sector possessed consolidated technical competence, but operated without the necessary organizational infrastructure to transform this knowledge into formal, replicable, and efficient processes.

Keywords: Budget deviations; Project management; Organizational maturity; Financial planning; Event sector.

1. Introduction

The events segment holds a relevant position in the Brazilian economic dynamics, acting as a business driver and a catalyst for interconnected sectors, including tourism, hospitality, and gastronomy. According to the Brazilian Association of Event Companies (ABEOC, 2019), the activity generates billions of reais annually, creating direct and indirect impacts across different segments of the economy. Despite this relevance, the execution of projects in the events area often faces recurring obstacles in financial management, especially in cost control. The dynamic nature of these projects, characterized by tight deadlines and continuous planning adjustments, increases the risk of budget overruns, compromising the sustainability and profitability of the actions (Pires, 2018).

The events sector operates under a unique market logic: unlike other service provision segments, the project is structured around a fixed and unpostponable date, defined externally by the client even before financial planning is consolidated. This condition positions the demand generator as the central agent of the sector’s operational dynamics, as it is the client who establishes the deadline, defines and redefines the scope throughout execution, and frequently approves the budget at times that compromise the planning capacity of the responsible team. The financial management of event projects, therefore, does not occur in an environment of controlled stability, but under continuous pressure from external factors that the team does not originate and can rarely anticipate in their entirety. Understanding this dynamic is a prerequisite for interpreting the data of this research, as the identified budgetary deviations cannot be analyzed outside the context of a market that structurally imposes a reactive stance on the manager.

Within the scope of project management, cost management constitutes one of the fundamental knowledge areas. The Project Management Institute (PMI, 2017) defines this discipline as a set of processes focused on planning, estimating, budgeting, and controlling financial resources, with the objective of ensuring that the project remains within the established budgetary limits. Cost control, specifically, functions as an instrument for continuous monitoring, allowing for the review of the financial baseline and the management of any changes that may affect the budget. PMI (2018) points out that poor execution of these processes can result in significant losses on a global scale, reinforcing the relevance of the topic for project management.

Although there is a consolidated theoretical basis on the subject, the practical application of these principles in event projects still reveals gaps. Kerzner (2017) highlights that the absence of specific team qualifications and the lack of standardization in scope change management processes often cause delivery delays and exceed planned budgets. Vargas (2015) adds that poor communication between planning and execution teams intensifies these misalignments, showing that the challenges arise not only from the complexity of the projects but also from organizational and cultural vulnerabilities.

In this context, an in-depth analysis of the factors associated with budgetary deviations is crucial for the improvement of financial management in the events sector. The present study aims to analyze the factors associated with budgetary deviations in event projects, focusing on planning and cost control practices, aiming to contribute to the improvement of financial management in the sector.

2. Material and Methods

The present study was characterized as a descriptive research, with a quali-quantitative approach, aiming to analyze the factors associated with budgetary deviations in event projects. According to Gil (2019), descriptive research has the main purpose of describing the characteristics of a population or phenomenon and identifying possible relationships between variables, which aligns with the objective of improving financial management in the sector.

The choice of the quali-quantitative approach was strategic, as, according to Creswell (2014), the combination of these methodological perspectives allows for both the measurement of data and the identification of patterns, as well as the understanding of participants’ perceptions and experiences. This methodological duality sought to enrich the interpretation of the results, capturing the complexity of cost planning and control practices.

The investigated population was composed of professionals working in the events sector nationwide, with no specific geographical delimitation. Participants were selected for being directly involved in project management, planning, and financial control activities, ensuring the relevance of their contributions to the central theme of the research.

For the selection of participants, a non-probabilistic convenience sampling was adopted. This method involved accessible and available professionals during the research period, as indicated by Vergara (2016) for descriptive studies with limited access to the total population universe. This strategy allowed for the acquisition of relevant data within the operational constraints of the study.

Data collection was carried out using a semi-structured questionnaire, composed of closed and open-ended questions. The instrument was made available in digital format, using the Google Forms platform, and applied on January 27, 2026. At the end of the collection period, 101 valid responses were obtained, which constituted the empirical basis for subsequent analyses.

The questionnaire was carefully developed based on a comprehensive literature review on project management and cost control. The guidelines of the Project Management Institute (PMI, 2017, 2018), as well as the contributions of Kerzner (2017) and Vargas (2015), were fundamental in defining the variables analyzed and structuring the questions. The semi-structured nature of the questionnaire, according to Lakatos and Marconi (2017), favored the standardization of responses without restricting the participants’ freedom of expression.

The data collection instrument included closed-ended questions, which aimed to gather specific information about the cost planning, monitoring, and control practices adopted in event projects. Complementarily, open-ended questions were included, allowing participants to describe their experiences, difficulties, and perceptions of the financial processes, adding qualitative depth to the data.

The analysis of the collected data followed a mixed approach. Quantitative data, from the closed-ended questions, were treated using descriptive statistics, focusing on the presentation of relative frequencies. This technique allowed for the identification of patterns and the distribution of responses in relation to the studied variables, providing an overview of the predominant practices in the sector.

Qualitative data, obtained from the open-ended questions, were treated based on the content analysis technique, as proposed by Bardin (2016). This method enabled the identification and categorization of emerging themes related to the main challenges and perceptions about cost control in event projects, complementing the quantitative analysis with contextual insights.

Regarding the ethical aspects, the research was conducted with due observance of the principles of voluntariness and confidentiality. All participants were invited to participate voluntarily, and the acceptance of the Free and Informed Consent Form (TCLE) was a condition for participation. The information collected was treated anonymously and used exclusively for academic purposes, ensuring the privacy and security of the respondents’ data.

3. Results and Discussion

The analysis of the collected data allowed for the creation of a detailed profile of professionals working in the events sector, revealing characteristics that directly shape planning and cost control practices. It was observed that the sample was predominantly composed of Event Producers, representing 36.6% of respondents, followed by Project Managers (15.8%), Event Coordinators (14.9%), and Analysts (13.9%). Finance professionals constituted 4.0% of the sample, while other roles accounted for 14.8%, indicating a diversity of roles that reflects the operational complexity of the sector.

Regarding the length of experience, the research identified a predominance of professionals with more than six years of experience, totaling 56.4% of participants. The one to three years of experience bracket represented 25.7%, followed by four to six years (9.9%) and less than one year (7.9%). This distribution suggests a sector with high seniority, where accumulated experience plays a crucial role in project management. However, the significant presence of professionals with less time of experience also indicates a high operational turnover, requiring constant adaptation and learning.

The seniority of the sample, especially the group with more than six years of experience, is a relevant factor for understanding the sector’s resilience in the face of challenges. These professionals, throughout their careers, develop a tacit repertoire that allows them to navigate in high volatility environments. Experience, in this context, is not just an individual attribute, but intellectual capital that compensates for the absence of formalized processes, allowing for quick decision-making and adaptation to unexpected changes, as observed by Getz (2007).

Regarding the scale of the managed projects, the results indicated that participants predominantly work on medium-sized (43.6%) and large-sized (37.6%) events. Small-sized events represented 18.8% of the sample. The sum of the medium and large-sized categories, totaling 81.2%, highlights that the majority of professionals manage projects of considerable financial and operational scope. This characteristic reinforces the importance of robust cost control practices, given the magnitude of the resources involved and the potential impact of budgetary deviations.

Despite the seniority and scale of the projects, the research revealed that 81.2% of professionals lacked formal training or certification in project management. Only 18.8% reported having formal qualifications, predominantly in areas such as Communication, Advertising and Marketing, and Administration. This academic heterogeneity and low methodological formalization suggest that technical competence in the sector is often developed through practical experience, rather than standardized certifications, which can impact the consistency in applying cost management methodologies.

Regarding the area of operation, corporate events led with 68.3% of responses, followed by trade shows and exhibitions (9.9%), cultural events (7.9%), and social events (5.9%). Other categories, such as sports events, academic events, and congresses, each accounted for 4.0%. This concentration in the corporate segment is significant, as these events generally involve budgets with formal compliance and accountability requirements, which, theoretically, would demand greater budgetary rigor. However, the diversity of contexts among the segments reinforces the difficulty of standardizing financial processes, maintaining dependence on flexible tools.

The analysis on the frequency of formal budget definition before the start of event execution showed that 76.2% of respondents declared that the budget is defined “Always” (35.6%) or “Frequently” (40.6%). However, a considerable portion of 23.8% indicated that the definition occurs “Sometimes” (14.9%), “Rarely” (6.9%), or “Never” (2.0%). This data suggests that, in some projects, budget formalization is not fully consolidated before the start of execution, which can expose the project to financial risks from its initial stage.

This initial budgetary uncertainty can be attributed to the dynamics of the events sector, where the budget is often defined at the briefing stage but may undergo reductions or late approvals, especially when deadline constraints prevent waiting for full financial validation. The Project Management Institute (PMI, 2017) emphasizes the importance of an established cost baseline for financial monitoring and control. The absence of this formal parameter makes the identification and attribution of deviations more complex, particularly in an environment prone to scope changes and pressures for immediate deliverables.

The tools used for cost planning and control revealed a strong dependence on spreadsheets, mentioned by 79.2% of respondents. Company-specific tools were cited by 27.7%, project management software by 17.8%, and integrated financial systems (ERP) by 13.9%. Only 5.0% of participants declared not using any formal tool. The predominance of spreadsheets can be interpreted as a response to the need for flexibility, as the uniqueness of each event rarely allows for complete standardization of cost structures, as pointed out by Getz (2007).

The centrality of manual tools, such as spreadsheets, implies that monitoring variations and adapting to changes depend, to a large extent, on the manager’s direct intervention and experience. Flyvbjerg (2011) argues that accumulated experience can generate confidence in the individual’s ability to anticipate risks. However, the absence of automated alert mechanisms tends to increase the professional’s cognitive load in tracking deviations. Vargas (2015) emphasizes the need for systematic instruments to maintain the cost baseline, suggesting that financial control in the sector is still predominantly manual and dependent on flexible structures.

Participants’ perception of the adequacy of the initial event budget revealed that 47.5% consider it “Balanced”, meaning exactly what is needed for the idealized planning. However, a significant portion of 46.6% perceive the budget as “Insufficient” (44.6%) or “Much Insufficient” (2.0%), indicating that projects often start with resources below what is necessary for the intended scope. Only 5.9% considered the budget “Much Higher”.

This high incidence of initial deficit budgets is a critical point. Flyvbjerg (2011) differentiates technical from strategic underestimation, where budgets may be approved with insufficient values to enable initial decisions, regardless of estimation errors. The consequences of this condition, according to O’Toole (2011), manifest during execution, impacting the quality and feasibility of the event, requiring adjustments in suppliers and infrastructure. In this scenario of restriction, the experienced manager’s ability to prioritize and reallocate resources (Getz, 2007) becomes fundamental, although the stability of results may vary according to individual competence.

The main difficulties faced in estimating event costs were predominantly external to the producer’s direct action. Reduced planning deadlines were pointed out by 70.3% of respondents as the main obstacle to budget accuracy. Poorly defined scope was mentioned by 50.5% of participants. The lack of historical data from previous projects was cited by 30.7%, and the absence of a structured method by 25.7%. Reliance on individual experience was indicated by 21.8%.

The prevalence of tight deadlines and poorly defined scope as limiting factors for budget accuracy reflects the intrinsic nature of the event sector. Getz (2007) highlights that the fixed and unpostponable date of an event compresses the time for quotes, risk analysis, and validation of assumptions. O’Toole (2011) adds that scope instability compromises estimates, as the lack of clarity in deliverables prevents objective reference parameters. These external factors impose a volatile planning environment, hindering the construction of cost histories and demanding a reactive stance from professionals.

The absence of a history of previous projects and structured methods, as pointed out by Kerzner (2017), is associated with reduced levels of organizational maturity. Organizations that do not systematize data from completed projects limit their managers’ ability to calibrate future estimates. Dependence on individual experience, in this context, functions as a compensatory mechanism, where tacit knowledge accumulated over the years becomes the main management tool in the absence of formalized processes. This reinforces the need for institutionalization of processes to reduce dependence on individual factors and increase financial predictability.

The monitoring of costs during the execution of events is carried out systematically and continuously by 64.4% of respondents, suggesting consistent adherence to formal control practices. Ricardo Vargas (2015) emphasizes that the Monitoring and Controlling processes are essential for aligning the actual cost with the baseline, allowing for corrective interventions. In the context of events, the compressed lifecycle requires continuous monitoring to mitigate financial risks, as observed by Getz (2007).

However, 33.6% of participants monitor only at specific times (17.8%), informally (15.8%), or do not monitor at all (2.0%). These strata indicate greater exposure to the progressive accumulation of deviations, especially in environments that rely on non-automated tools. Although systematic monitoring is predominant, this control is mostly carried out using spreadsheets, which implies a high operational demand for the manager and reinforces the need to consolidate processes and systems that reduce dependence on individual effort.

The analysis of contributing factors to cost deviations, using a Likert scale, revealed that frequent scope changes concentrated 80.2% of the responses in scores 4 and 5, indicating the highest degree of agreement. O’Toole (2011) associates uncontrolled scope changes with cost overruns. Freeman’s (1984) stakeholder theory complements this view, explaining how multiple actors (clients, sponsors, teams) exert demands that generate successive changes, often without formal record or budget review.

Reduced deadlines also showed a similar pattern, with 68.3% of responses concentrated in scores 4 and 5, confirming their importance as an external determinant that impacts both the initial estimate and the probability of deviations. In contrast, internal factors such as lack of control in execution (46.5% in scores 4 and 5) and lack of team training (48.5% in scores 4 and 5) showed a more dispersed distribution, with relevant percentages in intermediate and low scores. This suggests that, although important, these factors are perceived as less decisive than external determinants, possibly due to managers’ experience and existing monitoring practices.

The research also investigated the moment when budget deviations are identified. The majority of respondents (67.3%) stated that they identify deviations before the end of the event, which suggests a preventive logic in management. Bowdin (2011) argues that, in the events sector, control during execution is the main window for intervention, given the ephemeral nature of the project. Maximiano (2014) reinforces that the early identification of deviations allows for the redirection of resources and renegotiation of contracts.

However, 24.8% of participants indicated identifying deviations only at the end of the event, a retrospective control pattern that, according to Meredith and Mantel (2017), has value for organizational learning but limited effectiveness in mitigating impacts on the ongoing project. Additionally, 7.9% stated they do not formally identify deviations, signaling the absence or fragility of structured control mechanisms. This reliance on manual monitoring, evidenced by the predominance of spreadsheets, reinforces the need for continuous attention to the event’s financial flow.

One of the most significant contrasts in the research lies in the frequency of formal recording of scope changes. Although scope changes were pointed out as the main factor impacting budget deviations (80.2% in notes 4 and 5), only 13.9% of respondents declared recording them “Always”. The sum of the categories “Always” and “Frequently” reaches 56.5%, indicating that slightly more than half of the sample maintains some degree of regularity in recording. However, 31.7% record “Sometimes”, and 11.8% “Rarely” or “Never”.

This inconsistency in formalization compromises budgetary traceability, as undocumented changes do not generate a formal baseline revision or contractual update, according to Gido and Clements (2014). Silvers (2008) contextualizes this behavior within the operational dynamics of the sector, where the pressure for immediate responses often leads documentary formalization to yield to the continuity of execution. The absence of consistent records limits the capacity for financial auditing and organizational learning between projects, as established by the PMI (2021) on integrated change control.

The evaluation of communication among the teams involved in event projects revealed that 66.3% of respondents classify it as “Good” (59.4%) or “Excellent” (6.9%). However, 29.7% consider it “Fair”, and 4.0% each classify it as “Poor” or “Very Poor”. Although the majority perception is positive, almost a third of the sample experiences communication limitations. Robbins (2015) observes that, in multidisciplinary teams like those in events, the perception of good communication does not always translate into effective technical alignment, potentially generating non-explicit financial discrepancies.

The perception of the impact of communication on cost control was mostly positive, with 70.3% of respondents indicating that communication “Positively Impacts”. Drucker (2001) positions communication as a central element of managerial practice for coordinating decisions. However, 12.9% identified a negative impact and 13.9% stated they did not know how to assess this relationship. Harrington (1991) argues that imprecise communication can generate non-quality costs. The combination of these data suggests that, although the majority recognize the importance of communication, the understanding of its strategic role in financial control is not yet fully homogeneous in the sector, as pointed out by Gregory (2010).

Finally, the evaluation of the efficiency of current cost control practices in events indicated that 74.3% of respondents consider them “Partially” efficient. Only 19.8% classified them as “Yes” (efficient) and 5.9% as “No” (inefficient). This distribution suggests that the predominant perception is not of total inefficiency, but of limited efficiency, where the operational model is functional but lacks full systemic consolidation. Prado (2015) associates this profile with intermediate stages of project management maturity, characterized by consolidated technical competence but dependence on non-institutionalized practices.

The integrated reading of the results reveals a systemic dynamic that connects the main factors of budgetary deviation. Reduced deadlines, pointed out by 70.3% as the main difficulty in cost estimation, compress the time for quotes and premise analysis. This temporal restriction, combined with low methodological formalization (81.2% without formal certification), makes financial control dependent on individual tacit knowledge. The result is a predominantly reactive management cycle, where decisions are imposed by deadlines, alternatives are restricted by supplier dependency, and the absence of a structured method prevents learning from being converted into an institutionalized process. The sector, therefore, operates with significant technical competence, but with still partial levels of institutionalization of financial control processes, which is manifested in recurrent budgetary deviations.

4. Conclusion

This study analyzed the factors associated with budget deviations in event projects, focusing on cost planning and control practices, aiming to improve financial management in the sector. It was found that the professionals involved have high seniority, predominantly in medium and large-scale corporate events, but operate with low methodological formalization, evidenced by the scarcity of project management certifications and reliance on spreadsheets as the main control tool. It was identified that reduced planning deadlines and poorly defined scope were the factors most associated with budget deviations, often perceived before the event’s conclusion. It was observed that, although scope changes are the main driver of deviation, their formal recording is inconsistent. The main contribution of this work lies in explicating that the consolidated technical competence of managers, while crucial, operates in an environment lacking organizational infrastructure to transform this knowledge into formal, replicable, and efficient processes, which directly impacts financial predictability.

Cost control practices were evaluated as only partially efficient, reflecting the reliance on manual tracking and the high cognitive effort required from managers. The descriptive nature of the research, with non-probabilistic convenience sampling, limits the generalization of results but offers an in-depth diagnosis of professionals’ perceptions and experiences. It is suggested that future studies explore the implementation of more structured and systematized cost management models, which can reduce reliance on individual experience and mitigate the impacts of external constraints, such as tight deadlines and volatile scope. The advancement of financial management in the event sector depends on the transition from predominantly tacit practices to more institutionalized approaches, which integrate processes, tools, and an organizational culture aligned with market dynamics.

Bibliographic References

Associação Brasileira de Empresas de Eventos [ABEOC]. 2019. Panorama do mercado de eventos no Brasil. São Paulo, SP, Brasil.

Bardin, L. 2016. Análise de conteúdo. Edições 70, São Paulo, SP, Brasil.

Bowdin, G.A.J.; Allen, J.; O’Toole, W.; Harris, R.; McDonnell, I. 2011. Events management. 3ed. Butterworth-Heinemann, Oxford, Reino Unido.

Creswell, J.W. 2014. Research design: qualitative, quantitative, and mixed methods approaches. 4ed. Sage, Thousand Oaks, CA, EUA

Drucker, P.F. 2001. O melhor de Peter Drucker: a administração. Nobel, São Paulo, SP, Brasil.

Flyvbjerg, B. 2011. Over budget, over time, over and over again: managing major projects. In: Morris, P.W.G.; Pinto, J.K.; Söderlund, J. (org.). The Oxford handbook of project management. Oxford University Press, Oxford, Reino Unido. p. 321-344.

Freeman, R.E. 1984. Strategic management: a stakeholder approach. Pitman, Boston, MA, EUA.

Getz, D. 2007. Event studies: theory, research and policy for planned events. Butterworth-Heinemann, Oxford, Reino Unido.

Gido, J.; Clements, J.P. 2014. Gestão de projetos. 5ed. Cengage Learning, São Paulo, SP, Brasil.

Gil, A.C. 2019. Métodos e técnicas de pesquisa social. 7ed. Atlas, São Paulo, SP, Brasil.

Gregory, 2010 [Referência completa não encontrada no documento original]

Harrington, H.J. 1991. Business process improvement: the breakthrough strategy for total quality, productivity, and competitiveness. McGraw-Hill, New York, NY, EUA.

Kerzner, H. 2017. Project management: a systems approach to planning, scheduling, and controlling. 12ed. John Wiley & Sons, Hoboken, NJ, EUA.

Lakatos, E.M.; Marconi, M.A. 2017. Metodologia científica. 7ed. Atlas, São Paulo, SP, Brasil.

Maximiano, A.C.A. 2014. Administração de projetos: como transformar ideias em resultados. 5ed. Atlas, São Paulo, SP, Brasil.

Meredith, J.R.; Mantel Jr., S.J. 2017. Project management: a managerial approach. 9ed. John Wiley & Sons, Hoboken, NJ, EUA.

O’Toole, W. 2011. Events feasibility and development: from strategy to operations. Butterworth-Heinemann, Oxford, Reino Unido.

Pires, V. 2018. Gestão de Eventos: Planejamento e Execução. Érica, São Paulo, SP, Brasil.

Prado, D. 2015. Maturidade em gerenciamento de projetos. 2ed. INDG, Nova Lima, MG, Brasil.

Project Management Institute [PMI]. 2017. A guide to the project management body of knowledge (PMBOK Guide). 6ed. Project Management Institute, Newtown Square, PA, EUA.

Project Management Institute [PMI]. 2018. Pulse of the profession 2018: success in disruptive times. Project Management Institute, Newtown Square, PA, EUA.

Project Management Institute [PMI]. 2021. A guide to the project management body of knowledge (PMBOK Guide). 7ed. Project Management Institute, Newtown Square, PA, EUA.

Robbins, S.P.; Judge, T.A. 2015. Comportamento organizacional. 16ed. Pearson, São Paulo, SP, Brasil.

Silvers, J.R. 2008. Risk management for meetings and events. Butterworth-Heinemann, Oxford, Reino Unido.

Vargas, R.V. 2015. Gerenciamento de projetos: como aplicar o PMBOK. 5ed. Brasport, Rio de Janeiro, RJ, Brasil.

Vergara, S.C. 2016. Projetos e relatórios de pesquisa em administração. 16ed. Atlas, São Paulo, SP, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.