Improvement of the Budgeting Process in Industrial Construction
Patriny Padovani Ovidio; Felipe Miranda de Souza Almeida
DOI: 10.22167/2675-6528-202601288
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
The budgeting process in industrial works plays a strategic role in the viability of contracts and cost predictability, often marked by weaknesses in contexts of high complexity. The study analyzed the bottlenecks of the budgeting process in an organization in the industrial sector and proposed improvements to increase the agility, standardization, and reliability of commercial proposals. The research, with a qualitative and exploratory-descriptive approach, was conducted in two stages: a diagnosis of the current process, based on participant observation, semi-structured interviews with four professionals, and documentary analysis; and the structuring of improvement proposals based on empirical evidence and project management practices, following the PDCA logic. The results revealed weaknesses in the elaboration, approval, and transition of the budget, such as centralization of final approval, low standardization of cost compositions, dependence on informal consultations for productivity definition, failures in the interface with procurement, misalignment with execution, and absence of post-work feedback. Based on these findings, the use of TCPO, survey checklists, handover meetings, risk matrix, and lessons learned record were proposed. It was concluded that the improvement of the budgeting process depends on the adoption of structured mechanisms for decision support, standardization, and integration between areas, making it more robust and predictable.
Keywords: Organizational learning; Reliability; Project management; Cost management; Cross-sectoral integration.
1. Introduction
The industrial sector plays a strategic role in economic development, attracting substantial investments in the implementation, expansion, and maintenance of productive assets. These ventures are often characterized by high technical complexity, multiple operational interfaces, and a significant volume of resources. In these projects, cost predictability is a critical factor for business viability and managerial decision-making. Vargas (2018) emphasizes that complex projects require rigorous coordination of scope, cost, time, and risks, as integration failures can compromise overall performance. Kerzner (2017) reinforces that project management maturity depends on consistent articulation between planning, execution, and control, especially in environments with strong interdependencies between departments.
In the context of industrial construction, the budget transcends an initial estimate; it is an essential management tool for defining scope, forecasting resources, feasibility analysis, and financial monitoring. Mattos (2019) argues that construction budgets should be integrated into the overall project planning, as they establish premises that influence contracting, procurement, team mobilization, and cost control. This view aligns with the guidelines of the Project Management Institute [PMI] (2021), which highlight the importance of cost planning and monitoring processes to maintain adherence to the approved baseline and mitigate financial deviations. The reliability of subsequent decisions, therefore, is directly proportional to the quality of the information gathered in the budgeting phase. However, the literature indicates that estimates based on incomplete information, poorly verified assumptions, and low integration between sectors frequently result in rework, scope revisions, and economic losses. Kerzner (2017) observes that the fragmentation of communication between technical and operational areas reduces the quality of planning and the ability to respond to uncertainties. The prior identification of risks, clear definition of deliverables, and alignment among stakeholders increase predictability (PMI, 2021). In industrial works, with their specific safety requirements, technical standards, and complex interfaces, these fragilities are even more critical, as small omissions can lead to delays, emergency purchases, unproductivity, and reduced profitability.
Despite the recognized strategic importance of the budget, organizational practices often fall short of theoretical recommendations. Many companies still rely on individual experience, informal consultations, non-standardized cost compositions, and centralized approval flows, which compromise the agility and reliability of proposals. The absence of homogeneous technical criteria for quantifying, defining productivity, and analyzing risks can make the budget vulnerable to inconsistencies and rework. Mattos (2019) observes that budget quality is intrinsically linked to input information and cost composition methodology, reinforcing the need for structured procedures. Decision support tools, formal interdepartmental alignment mechanisms, and risk analysis instruments emerge as vital resources for enhancing the technical robustness of the process.
The justification for this study lies in the pressing need to address recurring problems in the budgeting process for industrial works, especially those related to the slowness in approving proposals, the difficulty in estimating costs for services of high technical complexity, the low standardization in compositions, and the fragility of intersectoral communication. Such limitations not only impact the commercial phase but reverberate throughout the entire project cycle, affecting deadlines, costs, predictability, and the company’s credibility with the client. By investigating and proposing improvements applicable to a real organizational context, this work contributes to bringing project management references closer to the daily practice of companies operating under intense pressure for agility, technical precision, and financial control. Given this scenario, the present study aimed to analyze the bottlenecks in the budgeting process for industrial works and propose technically grounded improvements to enhance the agility, standardization, and reliability of commercial proposals, based on project management best practices and the logic of continuous improvement of the Plan-Do-Check-Act cycle.
2. Material and Methods
This research was characterized as applied, with a qualitative approach and an exploratory-descriptive objective. It was classified as applied because it focused on understanding a concrete problem of the budgetary process in a company operating in industrial works, with the aim of proposing practical improvements to increase the agility, standardization, and reliability of commercial proposals. According to Gil (2002), applied research seeks to generate knowledge directed towards the solution of specific problems, while the qualitative approach favors a deep understanding of organizational phenomena inserted in their real context.
From the perspective of objectives, the study had an exploratory and descriptive character. Exploratory, because it sought to identify and understand the main bottlenecks in the current process of budget preparation, analysis, and approval; and descriptive, because it aimed to portray the characteristics of this process, the interactions between the involved sectors, and the operational effects arising from the observed failures. According to Severino (2017), research of this nature allows for greater proximity to the investigated object and favors the systematic organization of empirical evidence.
The study was developed in an organization in the industrial sector, located in the Southeast region of Brazil, which operates in the design and execution of medium and large-scale industrial works. The company operates in an environment characterized by high technical complexity, multiple interfaces between areas, and the need for rapid customer responses, especially in the stages of surveying, composition, approval, and release of commercial proposals. The specific period for data collection was not explicitly stated in the TCC, but the research was conducted to improve processes in a real organizational context.
The object of analysis focused on the budgetary process of these industrial works, understood from the receipt of the demand and the survey of technical information to the consolidation of the commercial proposal and its subsequent interface with the supply and execution sectors. In this context, the budget was not treated merely as a cost estimate, but as an organizational process that influences scope definition, resource planning, commercial decision-making, and the financial performance of the undertaking. The choice of this object was justified by its relevance to the economic feasibility of the contracts and by the existence of observed operational bottlenecks.
Thus, the object of analysis was delimited to the budgetary process as an integrated flow of activities and decisions, involving scope definition, quantity surveying, cost composition, managerial approval, and articulation with procurement and execution. The investigation focused on these stages and their critical interfaces, with the purpose of identifying bottlenecks and supporting the proposal of technically grounded improvements for the studied context. This delimitation allowed for a precise focus on the areas of greatest impact for the agility, standardization, and reliability of the proposals.
The research was conducted in two complementary and interconnected stages. The first stage involved diagnosing the current budgetary process, focusing on identifying bottlenecks related to technical surveys, cost composition, proposal approval, and information transition to procurement and execution. The second stage involved structuring the proposed improvements based on the problems identified in the diagnosis, seeking to build interventions aligned with the organization’s reality and technically sound.
In the diagnostic stage, three sources of evidence were used for data collection: participant observation of the sector’s routines, semi-structured interviews, and documentary analysis. Participant observation allowed for immersion in the organization’s daily life, capturing nuances and interactions that might not be evident in other sources. This multifaceted approach aimed to ensure a comprehensive and in-depth understanding of the challenges and particularities of the budgeting process in its real operational environment.
Semi-structured interviews were conducted with four participants directly involved in critical points of the budgetary process. The participants were selected for their strategic role and in-depth knowledge of the different phases of the flow: a partner responsible for the final approval of proposals, a budget planner, a buyer, and a site manager. Each interview lasted approximately 20 to 30 minutes, addressing aspects related to the preparation, approval, and execution of budgets, according to a pre-defined script.
The documentary analysis covered budget spreadsheets, internal records, technical documents, and support materials used in the preparation and approval of budgets. The collected information was organized by analytical categories, bringing together aspects related to approval governance, cost composition, interface with procurement, interface with execution, and post-construction feedback. This systematic organization allowed for the identification of patterns, inconsistencies, and areas for improvement, providing a solid basis for diagnosing bottlenecks.
In the second stage, improvements were formulated through the articulation between the empirical evidence from the diagnosis and good project management practices. The Project Management Body of Knowledge [PMBOK] (PMI, 2021) framework was used to support aspects related to integration between areas, risk management, communication, and process standardization. The Plan-Do-Check-Act [PDCA] cycle was employed as the organizing logic for the proposal, allowing the relationship between diagnosis, definition of actions, monitoring, and continuous adjustment.
The articulation between the two stages of the research allowed establishing a direct relationship between the identified problems, empirical evidence, and improvement proposals. Thus, the study was not limited to a generic description of management tools, but built recommendations based on the weaknesses effectively observed in the organizational context. The analysis of qualitative data, obtained through interviews and observation, was complemented by documentary review, allowing for a triangulation of information to validate bottlenecks and support the proposed solutions.
The ethical procedures were rigorously observed throughout the research. The participation of the interviewees was voluntary, and all participants signed a Free and Informed Consent Agreement (TCLE), as per Appendix A of the TCC. In it, they were informed about the study’s objectives, the procedures involved, and the guarantee of confidentiality of their identities and the information provided. The responses were treated anonymously and used exclusively for academic purposes, with no direct risks associated with participation.
As a methodological limitation, it should be noted that the research focused on a single case study, with a predominantly qualitative basis. This approach, while allowing for an in-depth understanding of the phenomenon in its specific context, restricts the broad generalization of findings to other organizations or sectors. However, the results have analytical and practical relevance, as they demonstrate how recurring weaknesses in the budgeting process can be identified, organized, and addressed through a structured logic of improvement, serving as a basis for future investigations.
3. Results and Discussion
The first stage of the research focused on the initial diagnosis of the organization’s budgeting process, with the purpose of understanding the functioning of the current flow and identifying the main bottlenecks that compromised the agility, technical accuracy, and integration among the involved sectors. This exploratory-descriptive approach, according to Gil (2002) and Severino (2017), allowed for an in-depth immersion in the organizational phenomenon, revealing nuances and interactions that would be inaccessible by less qualitative methods. The focus was on the analysis of the practices adopted from the information gathering and cost composition to the final approval of the proposal and its transfer to procurement and execution. Such a diagnosis was essential for the research not to be limited to a generic description of management tools, but to be based on concrete problems observed in the studied organizational context, providing a robust empirical basis for proposing improvements. The logic of comparison between the initial scenario and the improved process, based on specific dimensions such as scope integration, cost standardization, uncertainty management, and interface with execution, guided the analysis and discussion of the findings.
In the diagnosis, it was found that one of the main bottlenecks of the process was related to the centralization of the final approval of budgets. As reported by one of the interviewed managers, the analysis and release of proposals were concentrated in a few decision-makers, which caused the files to remain pending for up to two or three days. This delay was aggravated by the absence of a consolidated technical standard in the spreadsheets, which increased insecurity in the review and required manual investigation of the compositions and prices used. This result shows that the slowness of approval is not only due to the availability of decision-makers but also to the low confidence in the technical standard of the material submitted for validation. Decision centralization, especially in environments of high complexity and the need for quick responses, such as the industrial construction sector, can seriously compromise organizational agility and company competitiveness. Kerzner (2017) emphasizes that project management maturity is intrinsically linked to an organization’s ability to consistently articulate planning, execution, and control, and excessive centralization in final approval represents a direct obstacle to this fluidity.
The practical implications of this centralization are multifaceted. Firstly, delays in approval can result in the loss of business opportunities, as customers in a competitive market expect agile responses. Although the interviewee mentioned that this delay did not necessarily lead to immediate loss of contracts, it certainly harmed the company’s credibility and the perception of its efficiency. Secondly, the need for manual review and distrust in the technical standard of proposals generate significant rework, consuming valuable time from managers and estimators who could be dedicated to higher value-added activities. The PMI (2021) highlights the importance of well-defined cost planning and monitoring processes to keep the project aligned with the approved baseline and reduce financial deviations. The absence of standardization and the consequent need for manual validation undermine the effectiveness of these processes, increasing exposure to risks and uncertainties. The proposition of improvements for this bottleneck, therefore, should focus on creating clear validation criteria and standardizing cost compositions, allowing approval to become a more agile process based on technical confidence, rather than just individual decision-maker experience. Delegating approval responsibilities to more operational levels, based on clear guidelines, could also be a strategy to decentralize and accelerate the flow, while maintaining governance.
Another relevant bottleneck identified in this stage was the difficulty in estimating costs and defining productivity for technically more complex services. The interviewed cost estimator reported insecurity in pricing systems with many particularities and norms, in addition to frequent dependence on informal consultations with the operational sector and company partners. High time spent on manual cost research was also reported, often consuming half the day on just one item, due to the absence of a standardized reference base, such as the TCPO. Furthermore, the lack of a structured feedback flow on errors and shortcomings perceived after the work’s execution was observed, which limited organizational learning and the evolution of the budgeting process.
Table 1. Synthesis of evidence on technical survey and cost composition
|
Analyzed aspect |
Identified evidence |
Implication in the process |
|
Definition of productivities |
Insecurity in estimation in complex services |
Higher risk of parameters not adhering to execution |
|
Accessory items and complementary inputs |
Difficulty in identifying all necessary components |
Possibility of errors and underestimation of costs |
|
Informal support dependence |
Frequent queries to operations and partners |
Low technical autonomy and greater variability in composition |
|
Absence of standardized base |
Need to resort to old budgets and suppliers |
Reduction of standardization and increase of rework |
|
Lift-off time |
Possibility of spending half the day on a single item |
Slowness in development and lower responsiveness |
|
Composition traceability |
Criteria not always formalized or registered |
Difficulty of review, validation, and subsequent learning |
Source: Original research results
As presented in Table 1, insecurity in defining productivities and accessory items in complex services leads to a higher risk of parameters that are not well-aligned with execution and cost underestimation. Dependence on informal support, with frequent consultations with operations and partners, results in low technical autonomy and greater variability in composition. The absence of a standardized base, such as old budgets or suppliers, causes the need to resort to scattered sources, reducing standardization and increasing rework. The survey time is high, with the estimator spending half the day on a single item, which generates slowness and lower responsiveness. Finally, the lack of formal composition criteria hinders review, validation, and subsequent learning.
This result showed that the technical reliability of the cost composition does not depend solely on the professional experience of the person responsible for the budget, but also on the availability of standardized bases, objective criteria, and decision support mechanisms. When such elements are not formalized, the activity tends to become excessively artisanal, subject to variations between proposals and more vulnerable to omissions of items, underestimation of resources, or adoption of productivities that are not very aligned with the execution reality. Mattos (2019) observes that the quality of the budget is directly associated with the quality of the input information and the method used to compose costs, which reinforces the need for more structured procedures. The dependence on tacit knowledge and informal consultations, as observed, converges with the perspective of Meredith and Mantel (2011), who argue that unstructured processes tend to present greater variability and lower predictability, negatively impacting cost management and the accuracy of estimates.
The practical implications of low standardization and difficulty in technical surveying are profound. The lack of a structured database and reliance on informal queries generate inconsistencies between budgets, hindering comparison and performance analysis. Underestimation of costs or omission of items can lead to financial losses for the company, as, according to the interviewed partner, forgotten or poorly quantified items are absorbed by the company after contract signing, reducing the actual profit margin. Furthermore, excessive time spent on composing a single item compromises the productivity of the budgeting team and the company’s ability to respond quickly to market demands. The proposition of improvements for this bottleneck involves adopting stable technical references, such as TCPO (Table of Price Compositions for Budgets), creating surveying checklists to ensure completeness of information, and formalizing criteria for defining productivities and accessory items. The implementation of a database of standardized and updated compositions, accessible to all budgeters, would reduce reliance on individual knowledge and promote greater consistency and agility.
The diagnosis also revealed significant flaws in the integration between budget, supplies, and execution. In the purchasing department, the recurrence of requests with incomplete descriptions was verified, lacking sufficient technical specifications for adequate quotation, which generated rework and delayed the acquisition process. Furthermore, the absence of prior alignment between budget and purchasing favored urgent purchases, made under pressure and with less negotiation power, compromising the margin planned in the budget. At the interface with execution, it was found that the predicted productivities did not always correspond to the reality in the field and that the mere sending of the scope printed or by email was insufficient to convey the technical premises adopted in the proposal, generating doubts and the need for subsequent clarifications.
These communication and intersectoral integration failures are widely recognized in the project management literature as critical causes of failure. Pinto and Slevin (1987) and PMI (2021) highlight communication as one of the most critical factors for project success, and the fragmentation of communication between technical and operational areas, as observed, reduces the quality of planning and weakens the project’s responsiveness to uncertainties. Vargas (2018) reinforces that complex projects require greater rigor in coordinating the variables of time, cost, scope, and risks, and integration failures between these dimensions tend to compromise the overall performance of the undertaking. In the context of industrial works, where there are specific safety requirements, technical standards, and complex interfaces, small omissions or misalignments can result in delays, emergency purchases, low productivity, and reduced profitability.
The practical implications of these integration failures are significant. For procurement, incomplete descriptions and the lack of technical specifications result in inaccurate quotes, delays in acquiring materials and equipment, and the need for urgent purchases. Urgent purchases, in turn, are often made with less negotiation power, increasing costs and eroding the profit margin foreseen in the budget. The interviewed buyer confirmed that purchase requests often arrive with incomplete descriptions, without the standard, gauge, or brand required by the client, which generates rework and prolongs the acquisition cycle. For execution, the divergence between budgeted productivities and the reality on site, along with insufficient transmission of technical premises, causes doubts, rework, and the need for constant clarifications, impacting the efficiency and schedule of the work. The site supervisor reported that productivities predicted in the office often do not correspond to the reality on site, and that the scope sent is insufficient for understanding the execution, generating demands for four days of clarifications. The proposition of improvements for this bottleneck includes standardizing the technical specifications of purchase orders, holding formal handover meetings between budgeting and execution to clarify premises and restrictions, and creating a risk matrix to anticipate and mitigate interface problems.
Finally, an important organizational learning deficiency was identified, characterized by the absence of systematic feedback between execution and budget. The budget analyst reported that she rarely receives structured feedback from the field and that, in practice, she only becomes aware of problems when materials are missing. In parallel, the interviewed partner stated that forgotten or poorly quantified items are absorbed directly by the company after the contract is signed, reducing the actual profit margin. Together, these statements indicated the absence of a systematic closure between budget and execution that allows for the review of assumptions, recording of lessons learned, and feedback to the technical base of future proposals.
This finding directly dialogues with Nonaka and Takeuchi’s (1997) theory of organizational knowledge creation, which argues that organizational learning depends on the transformation of practical experience (tacit knowledge) into explicit and reusable knowledge. When deviations observed in the field do not return in a structured way to the planning, the process tends to repeat failures and limit organizational learning, hindering continuous improvement and the evolution of practices. The absence of a formal lessons learned system means that the errors and successes of a project are not capitalized for future projects, resulting in a vicious cycle of repeating problems and wasting resources. Kerzner (2017) also highlights the importance of Knowledge Management and organizational learning to enhance Project management maturity.
The practical implications of the absence of feedback are severe. The company loses the opportunity to refine its cost and productivity estimates, which perpetuates insecurity in the preparation of new budgets. The lack of a lessons learned register prevents the identification of root causes for recurring problems and the implementation of effective corrective actions. This not only affects the accuracy of future budgets but also impacts the company’s profitability, as errors and omissions are often absorbed, reducing profit margins. The proposal for improvements to this bottleneck includes the implementation of a lessons learned register system, periodic updating of the budget base with actual execution data, and the creation of a formal post-project feedback process. These mechanisms would allow practical experience to be transformed into explicit knowledge, enriching the company’s database and promoting a virtuous cycle of continuous improvement.
Based on the detailed diagnosis of bottlenecks, it was possible to structure a proposal for improvement directly linked to the identified problems. The delay in final approval, associated with excessive manual review, indicated the need for greater standardization of cost compositions and clearer criteria for validating proposals. The uncertainty in defining productivities and accessory items highlighted the importance of adopting more stable technical references, such as TCPO, combined with survey checklists to reduce omissions and rework. The failures in the interface with procurement justified the proposal to standardize the technical specifications of purchase orders and to align budget and procurement beforehand, in order to reduce rework in quotations and emergency purchases. The divergence between what was foreseen in the budget and the reality in the field supported the proposition of a formal handover meeting between budget and execution, aimed at clarifying premises, operational restrictions, and criteria adopted in the commercial proposal. Furthermore, the absence of systematic feedback after the completion of the works justified the proposal for recording lessons learned and periodic updating of the budget base.
The operationalization of these actions was organized according to the logic of the Plan-Do-Check-Act (PDCA) cycle, in which diagnosis underpins the planning of interventions, implementation concentrates the proposed changes, verification monitors process indicators, and corrective action promotes continuous adjustments. This methodological structure, according to Deming (1986), is fundamental for Quality Management and continuous process improvement, allowing the organization not only to identify problems but also to implement and monitor solutions systematically. The Plan (P) phase involved the diagnosis of bottlenecks and the definition of precision and standardization goals. The Do (D) phase included the implementation of tools such as TCPO, survey checklists, initial kick-off and internal handover, and risk matrix. The Check (C) phase proposed monitoring approval time, scope revisions, urgent purchases, operational doubts, and differences between planned and actual productivity. Finally, the Act (A) phase focused on recording lessons learned, reviewing compositions, updating premises, and consolidating standards.
Table 2. Alignment matrix between bottlenecks, proposed tool, and project management dimension
|
Bottleneck evidenced |
Associated tool |
GP dimension mobilized |
Predominant stage of the PDCA |
|
Slow approval and excessive manual review |
Standardization of cost compositions and approval criteria |
Integration and governance |
Planning / Execution |
|
Insecurity in the definition of productivities and accessory items |
TCPO and technical survey checklist |
Costs and scope |
Planning / Execution |
|
Incomplete specifications for purchases |
Internal kick-off for the handover and standardization of requests |
Communications and stakeholders |
From |
|
Urgent purchases and loss of bargaining power |
Anticipation of demands and release milestones for supplies |
Schedule and costs |
Check / Act |
|
Divergence between planned and executed productivity |
Technical handover and executive assumptions log |
Integration, scope, and quality |
Perform / Verify |
|
Absence of post-construction closing |
Lessons learned and update of the budgetary base |
Organizational knowledge and continuous improvement |
Action |
Source: Original research results
Table 2 presents the alignment matrix between the identified bottlenecks, the proposed tools, and the project management dimensions mobilized in each case, as well as the predominant stage of the Plan-Do-Check-Act cycle. Slow approval and excessive manual review, a governance bottleneck, is addressed by standardizing cost compositions and approval criteria, mobilizing integration and governance dimensions in the Plan/Do stage. Insecurity in defining productivities and accessory items, a cost and scope bottleneck, is handled by TCPO and technical survey checklists, mobilizing cost and scope dimensions in the Plan/Do stage. Incomplete specifications for purchases, a communication bottleneck, are addressed by internal handover meetings and standardization of requests, mobilizing communications and stakeholders in the Do stage. Urgent purchases and loss of negotiation power, a schedule and cost bottleneck, are mitigated by anticipating demands and release milestones for supplies, mobilizing schedule and costs in the Check/Act stage. The divergence between planned and executed productivity, an integration and quality bottleneck, is addressed by technical handover and recording of executive premises, mobilizing integration, scope, and quality in the Do/Check stage. Finally, the absence of post-construction closing, an organizational learning bottleneck, is resolved by lessons learned and updating the budget base, mobilizing organizational knowledge and continuous improvement in the Act stage.
This matrix demonstrates that the improvement of the budgetary process depends not only on the introduction of isolated tools, but on the restructuring of the workflow with an emphasis on standardization, intersectoral integration, risk management, and the institutionalization of learning. The results remain aligned with the objective of the work by highlighting how project management practices can contribute to making the process more agile, reliable, and consistent. The articulation between the empirical evidence from the diagnosis and the good practices of project management, according to the PMBOK (PMI, 2021), allowed for the construction of recommendations that are consistent with the organization’s reality and technically well-founded. The qualitative approach, although limited to a case study, provided an in-depth understanding of the phenomena, allowing for the identification of recurring weaknesses in the budgetary process that can be organized and addressed through a structured improvement logic.
The combination of empirical diagnosis with structured project management practices, such as integration management, cost management, communication management, and risk management, offers a viable path to make the budgeting process more robust, predictable, and aligned with the demands of the industrial environment. The implementation of these improvements has direct practical implications for the studied organization and for other companies in the sector facing similar challenges. Reduced approval time, increased accuracy of cost and productivity estimates, decreased rework and emergency purchases, and improved communication between sectors are expected benefits that can positively impact the economic viability of contracts and the company’s profit margin.
As a practical implication, the study offers a proposal applicable to organizations facing similar difficulties in the development and control of commercial proposals in contexts of high technical complexity. The research, by focusing on a single case study, based predominantly on qualitative data, restricts broad generalizations. However, the findings have analytical and practical relevance, as they demonstrate how recurring process weaknesses can be identified, organized, and addressed through a structured logic of improvement. For future studies, it is recommended to monitor the implementation of the proposed actions and measure their effects on approval time, quality of estimates, incidence of rework, and adherence between budget and execution, validating the effectiveness of the interventions and contributing to the construction of a more robust body of knowledge on budget management in industrial works.
4. Conclusion
It is concluded that the objective was achieved by analyzing the bottlenecks of the budgetary process in industrial works and proposing technically substantiated improvements to increase the agility, standardization, and reliability of commercial proposals, with the support of good project management practices and the continuous improvement logic of the PDCA cycle. The investigation revealed significant structural weaknesses, distributed from the elaboration to the transition of the budget to procurement and execution. The main bottlenecks identified included the centralization of final approval, low standardization of cost compositions, dependence on informal consultations for productivity definition, intersectoral communication failures, and the absence of a systematic post-work feedback flow. The proposed improvements, such as the adoption of TCPO, survey checklists, meetings of
transfer
and lessons learned register, demonstrated to be aligned with the problems and capable of making the process more robust, predictable, and consistent.
As a limitation, it should be noted that the research focused on a single case study, with a predominantly qualitative basis, which restricts broad generalizations. However, the findings have analytical and practical relevance, demonstrating how recurring weaknesses can be addressed by a structured logic of improvement. For future studies, it is recommended to monitor the implementation of the proposed actions and measure their effects on approval time, estimate quality, rework incidence, and adherence between budget and execution. This would validate the effectiveness of the interventions and contribute to a more robust body of knowledge on budget management in industrial works.
Bibliographic References
Deming, W.E. 1986. Out of the Crisis. Massachusetts Institute of Technology, Center for Advanced Engineering Study, Cambridge, MA, EUA. 507 р.
Gil, A.C. 2002. Como Elaborar Projetos de Pesquisa. 4ed. Atlas, São Paulo, SP, Brasil. 175 p.
Kerzner, H. 2017. Project Management: A Systems Approach to Planning, Scheduling, and Controlling. 12ed. Wiley, Hoboken, NJ, EUA. 848 p.
Mattos, A.D. 2019. Como Preparar Orçamentos de Obras. 3ed. Oficina de Textos, São Paulo, SP, Brasil.
Meredith, J.R.; Mantel Jr., S.J. 2011. Project Management: A Managerial Approach. 8ed. John Wiley & Sons, Hoboken, NJ, EUA. 589 p.
Nonaka, I.; Takeuchi, H. 1997. Criação de Conhecimento na Empresa: Como as Empresas Japonesas Geram a Dinâmica da Inovação. 9ed. Campus, Rio de Janeiro, RJ, Brasil. 358 p.
Pinto, J.K.; Slevin, D.P. 1987. Critical factors in successful project implementation. IEEE Transactions on Engineering Management 34(1): 22-27.
Project Management Institute [PMI]. 2021. A Guide to the Project Management Body of Knowledge (PMBOK Guide). 7ed. Project Management Institute, Newtown Square, PA, EUA. 370 р.
Severino, A.J. 2017. Metodologia do Trabalho Científico. Cortez, São Paulo, SP, Brasil. 320 p.
Vargas, R.V. 2018. Gerenciamento de Projetos: Estabelecendo Diferenciais Competitivos. 8ed. Brasport, Rio de Janeiro, RJ, Brasil.
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq