APQP and PMBOK in the schedule management of an automotive product development project

Ana Flávia Lopes Profeta; Maria Júlia Xavier Belém

DOI: 10.22167/2675-6528-202600535

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Schedule management is crucial for efficient project execution and meeting customer demands in the automotive industry. In this context, the application of schedule planning and control practices was analyzed in the development of a stamped parts manufacturing project for the automotive backrest metal structure, using Advanced Product Quality Planning (APQP) as a basis and integrating it with the best practices of the Project Management Body of Knowledge (PMBOK) guide. The research was characterized as descriptive, with a mixed approach (quantitative and qualitative), and was developed through a case study in a medium-sized automotive industry. For the schedule elaboration, six main steps were followed: planning, definition and sequencing of activities, duration estimation, schedule development, and holding follow-up meetings. The results demonstrated that APQP contributed to the standardization and governance of the process, while PMBOK ensured greater control of deadlines in project development. The integration between APQP and PMBOK positively impacted project performance, prioritizing critical activities and milestones and favoring the implementation of action plans for success in the production of stamped parts. It was concluded that the integrated approach provided greater organization, control, and predictability, improving schedule management and assertiveness in decision-making, as well as contributing to risk reduction and greater adherence to customer requirements.

Keywords: APQP; WBS; Project management; Automotive industry; Stamped parts.

1. Introduction

The automotive industry holds significant representation in Brazil and influences the country’s economy. Data from the National Association of Automotive Vehicle Manufacturers (ANFAVEA, 2025) indicate that, in the first semester of 2025, almost one million light vehicles were registered in the domestic market and approximately 273,000 units were exported. This scenario of high competitiveness and pressure for deadlines demands effective project management to ensure operational success.

In this context, project management emerges as a fundamental discipline. According to Kerzner (2017), it is based on a systematic approach to planning, scheduling, and controlling activities, aiming to achieve specific objectives within deadlines, budgets, and quality standards. A project, by its nature, is a temporary activity with unique deliverables, requiring integrated management.

For the success of any undertaking, schedule management is a crucial performance domain, as detailed in the Project Management Body of Knowledge (PMBOK) Guide (PMI, 2021). Effective time management involves defining, organizing, and continuously monitoring activities to ensure the delivery of results within deadlines. Techniques such as the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) assist in identifying the logical sequence, interdependencies, and duration estimation, while Gantt charts are effective in representing progress and decision-making (Kerzner, 2017).

In the automotive sector, the complexity of product and process development has led to the creation of specific quality methodologies. Advanced Product Quality Planning (APQP) stands out, a structured method that guides the product development stages from conception to mass production. Developed by automakers Ford, General Motors, and Chrysler in the United States, APQP aims to standardize quality management and eliminate inconsistencies (Melo and Terazzi, 2025). Its structure is composed of five phases: Planning, Product Design and Development, Process Design and Development, Product and Process Validation, and Feedback, Assessment, and Corrective Action. It aims to identify failures and design changes in the early stages, optimizing the production process (Santos et al., 2021).

The articulation of APQP with the PMBOK guide is fundamental to align the technical product planning with internationally recognized best practices (Pissinatti et al., 2014). While APQP establishes the mandatory phases and deliverables of the project at a macro level, PMBOK complements this structure by providing detailed practices for planning, sequencing, duration estimation, and schedule control. This integration contributes to the standardization and governance of the process, ensuring greater control of deadlines and predictability, reducing risks, and increasing efficiency and quality (Lupo, 2018).

The automotive sector depends on strict adherence to deadlines to keep production synchronized with market demand and the supply chain. Effective schedule management is critical for competitiveness and meeting customer requirements. This study was conducted in a medium-sized automotive industry, specializing in the manufacturing of metal structures for seats and backrests, which adopts a project management methodology aligned with APQP and integrated with the PMBOK guide. The effectiveness of this integration in practice and its impacts on meeting deadlines and reducing deviations require analysis. Thus, the justification lies in optimizing schedule management in complex projects, where the integration of APQP and PMBOK can offer gains in predictability and control. Therefore, this work aimed to analyze the application of schedule planning and control practices for the development of a stamped parts manufacturing project for an automotive backrest metal structure, using APQP integrated with the best practices of the PMBOK guide as a basis.

2. Material and Methods

The present study was characterized as a descriptive research, with a mixed approach, combining quantitative and qualitative elements. Descriptive research, according to Gil (2017), aimed to describe the characteristics of a phenomenon or population, without necessarily investigating its causes. The mixed approach was employed to integrate numerical and descriptive data, seeking a more robust understanding of the research problem.

For the research design, the case study was adopted, a modality that allows for an in-depth analysis of a specific event or phenomenon in its natural environment (Gil, 2017). This method was considered adequate to investigate the particularities of schedule management in the real context of the automotive industry, allowing for an understanding of its complexities and internal dynamics.

The case study was conducted in a medium-sized automotive industry, located in the metropolitan region of Belo Horizonte, Minas Gerais. This company is a supplier to a car manufacturer, specializing in the production of metal structures for automotive seats and backrests, as well as welded and stamped components. The organization employs approximately 500 employees and is part of a group of national companies.

The empirical object of the research was a project in development of stamped parts for a metal structure of a car’s rear backrest, with launch scheduled for 2026. This project was managed by the Program Management department, in collaboration with other areas of the company, such as engineering, quality, production, and logistics.

For the execution of the work, several data related to the project were collected. Included were lists of activities, deadlines for the main client deliveries, and the project’s macro schedule. Specific documentation for each phase and activity of Advanced Product Quality Planning (APQP) was also analyzed.

The collection also included documentation from the stages of product planning, design, and development, process design and development, product and process validation, and feedback analysis and corrective action. Monitoring reports, meeting minutes, deadline indicators, technical details for the launch of stamped parts, and information about prototypes and production runs complemented the dataset.

The project schedule management was structured in six main stages, following the guidelines established by the Project Management Body of Knowledge (PMBOK) Guide and integrating APQP requirements. This process aimed to ensure compliance with deadlines, integration with quality processes, and efficiency in delivering project results.

The steps developed for data collection and analysis were: schedule management planning, definition of product development activities, sequencing of activities, estimation of activity durations, development of the product schedule, and holding follow-up meetings.

In the first stage, the schedule management plan was developed, which established the policies, procedures, and documentation necessary to plan, develop, control, and execute the project schedule. Tools such as the critical path method, duration estimation techniques, and milestone definition were used, as recommended by the PMBOK (Kerzner, 2017).

Additionally, the APQP requirements were considered to ensure integration between planning, quality, and production. The schedule management plan defined the approaches, criteria, and responsibilities for planning, monitoring, and supervising deadlines, promoting harmonization among stakeholders.

The second stage consisted of identifying and detailing the activities necessary for the project execution. For this, the Work Breakdown Structure (WBS) was used as the base tool, as guided by the PMBOK guide (PMI, 2021), in addition to the planning processes foreseen in the APQP. The WBS was composed of three levels of decomposition.

The first WBS level represented the main objective, which consisted of launching stamped parts for the rear seat back product. The second level dealt with the five phases of APQP: Planning; Product Design and Development; Process Design and Development; Product and Process Validation; and Feedback, Assessment, and Corrective Action. The third level listed all essential activities for launching the parts, respecting the sequence of the phases.

In the third stage, the identified activities were organized into a logical sequence, respecting their dependencies and the quality flows defined by APQP. The precedence diagram was used to represent the logical sequence of activities, identifying Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and Start-to-Finish (SF) dependencies.

The duration estimate for each activity was performed based on historical data, expert consultations, and PMBOK recommendations. The three-point estimation technique was applied, calculating the expected duration (tE) using the formula tE = (tO + tM + tP) / 3, where tO is the optimistic duration, tM the most likely, and tP the pessimistic.

The fourth stage involved the development of the complete project schedule, built using Microsoft Project software. This schedule included estimated durations, dependencies, milestones, and identified constraints, applying schedule compression techniques such as crashing or additional resource allocation, and risk analysis, aligning with APQP quality criteria.

In the fifth stage, the schedule was monitored and controlled throughout the project execution. Performance reports were generated and variance analyses were performed against the original plan. The Gantt chart was used for visualizing progress, identifying tasks, durations, start and end dates, and dependency relationships between them.

The sixth stage consisted of holding weekly follow-up meetings (FUP – follow up), with the objective of updating the schedule and monitoring the progress of activities. In these meetings, progress indicators, project milestones, and potential risks that could impact the performance of the stages were analyzed.

The Microsoft Project software supported these meetings, providing a clear view of the status of activities and facilitating decision-making. Based on the monitored data, corrective and preventive actions were applied to ensure compliance with deadlines and the achievement of defined quality milestones, ensuring the schedule’s adherence to the established plan.

3. Results and Discussion

The analysis of the application of schedule planning and control practices in the development of a stamped parts manufacturing project for automotive backrest metal structure revealed the effectiveness of the integration between Advanced Product Quality Planning (APQP) and the Project Management Body of Knowledge (PMBOK). It was observed that APQP established, at a macro level, the project phases and mandatory deliverables, outlining what should be done and when. In contrast, PMBOK complemented this structure by providing, in more detail, the practices necessary for schedule planning, development, and control, as the literature already indicated (Lupo, 2018).

This integrated approach demonstrated that APQP significantly contributed to process standardization and governance, through its structured phases and mandatory deliverables. Simultaneously, PMBOK provided the essential tools and techniques that enabled efficient management of these phases, ensuring the fulfillment of established deadlines and strict adherence to customer demands. The joint application of these methodologies, therefore, proved to be a robust and recommended practice for organizations seeking higher performance and excellence in conducting their projects in the automotive sector.

Schedule Management Planning

The stamped rear backrest parts manufacturing project, with launch scheduled for the end of the first semester of 2026, was managed based on APQP, given its nature as an automotive product. For the initial stage of schedule development, a management plan was created that established the criteria, methods, and tools to be used for the development, monitoring, and control of the schedule throughout the entire project lifecycle. This approach aimed to ensure that activities were planned, organized, estimated, and monitored in accordance with the company’s scope and strategic objectives.

The schedule management plan detailed the approaches, criteria, and responsibilities for planning, tracking, and overseeing deadlines. It described six main steps: planning schedule management, defining product development activities, sequencing activities, estimating durations, developing the product schedule, and conducting follow-up meetings. The implementation of this plan was crucial for increasing the predictability of activities, mitigating risks of delays, and promoting harmonization among stakeholders, ensuring alignment of project objectives.

The tools and techniques used in planning included “Kick-off” meetings to align expectations, the Work Breakdown Structure (WBS) to decompose the scope, the precedence diagram to visualize the order of activities, and analogous estimating based on previous projects. The planning results were documented in outputs such as the schedule management plan, the detailed activity list, the schedule network diagram, analogous duration estimates, the schedule baseline, and the update logs, all essential for project governance.

The project management responsibles included the PMO, Project/Program Manager, Plant Industrial Manager, Product and Process Engineering Coordinators, and Specialists from multidisciplinary areas, such as Product Engineering, Process Engineering, Quality, Logistics, and Sales. This structure of multidisciplinary responsibilities, aligned with the PMBOK guidelines, was fundamental to ensure that all perspectives were considered and that the project progressed in an integrated and coordinated manner, minimizing potential conflicts and optimizing resource allocation.

Definition of Product Development activities

The definition of product development activities was guided by APQP, a structured methodology required by automakers, according to IATF 16949, which accompanies the product from conception to mass production. APQP consists of five phases: Planning; Product Design and Development; Process Design and Development; Product and Process Validation; and Feedback, Assessment, and Corrective Action. This study focused on the phases relevant to the stamped parts schedule for the rear backrest.

The Work Breakdown Structure (WBS) was the central tool for identifying and detailing activities, according to PMBOK guidelines and APQP requirements. The WBS was organized into three levels: the first level represented the main objective, which was the launch of stamped parts for the rear seat back product. The second level unfolded into the APQP phases necessary to manage the launch schedule of these parts, providing a clear view of the project’s macrostructure.

The third level of the WBS consisted of the detailed listing of all essential activities for the launch of the parts, respecting the logical sequence of the APQP phases and activities. This decomposition allowed the APQP deliverables to be transformed into manageable work packages, with defined deadlines, designated responsible parties, and established milestones. The WBS, by organizing and defining all the necessary work, facilitated control, assignment of responsibilities, and progress monitoring, as recommended by the PMI (2021).

The list of deliveries and activities of the automotive APQP, which served as the basis for structuring the schedule, included several actions in each phase. In Phase 1 – Planning, customer requirements analysis, feasibility analysis, team organizational chart development, initial risk analysis, and scope definition were carried out, culminating in the initial macro schedule. These activities were crucial for establishing the project’s foundations and aligning expectations.

In Phase 2 – Product Design and Development, the deliverables involved critical design analysis, product development and approval, identification of special characteristics, DFMEA elaboration, Bill of Materials (BOM), prototype validation, product validation plan, and engineering tests. These steps are engineering and quality intensive, aiming to ensure product robustness and compliance before moving to the process phases.

Phase 3 – Process Design and Development, in turn, focused on defining the process flowchart, the production layout, machinery and devices, the PFMEA elaboration, the control plan (pre-launch), work instructions, and measurement system analysis (MSA) validation. These activities are essential to ensure that the production process is capable of manufacturing parts according to the required quality and volume specifications.

Finally, Phase 4 – Product and Process Validation, included the packaging plan, try-out, pilot run, production under real conditions, capability analysis (Cp/Cpk), process validation document, final packaging approval, PPAP submission, and customer approval. These steps are critical for the final validation of the product and process, ensuring everything is ready for the start of mass production. The list of tasks and deliverables allowed for deadline planning and risk minimization, contributing to the project’s effectiveness.

Sequencing of activities

The sequencing of activities was a crucial step for the development of the schedule, using the precedence diagram to represent the logical sequence of tasks and their interdependencies. This tool was fundamental for the correct definition of the schedule, allowing for deadline control and the identification of critical activities for project success. The PMBOK (PMI, 2021) highlights the existence of four types of dependencies: Finish-to-Start (FS), Start-to-Start (SS), Finish-to-Finish (FF), and Start-to-Finish (SF).

In the studied project, the network diagram demonstrated a predominance of the Finish-to-Start (FS) dependency, indicating that most activities could only begin after the completion of the predecessor activity. This characteristic reflects the sequential and structured logic of APQP, which requires the technical maturity of one phase for the next to be initiated. For example, the execution of the DFMEA was only possible after the clear definition of the product’s design and list of characteristics, evidencing the interdependence between deliverables.

The strong dependency on the Finish-to-Start type, although it guarantees robust quality and fault prevention by avoiding rework, resulted in a continuous sequence of activities that naturally formed the critical path of the schedule. This structure, while less flexible to changes and with little activity overlap (reduced parallelism), ensured strict control and greater predictability, enabling efficient resource allocation to the most deadline-sensitive activities.

The chaining of activities, driven by the need for technical maturity between APQP phases, such as the finalization of the product design before the execution of DFMEA and the definition of the process before PFMEA and validations, made the critical path a fundamental component in schedule management. Any delay in these activities would directly impact the project completion date, requiring closer monitoring and prioritization of efforts to keep the project on schedule.

Despite the limitations imposed by the predominance of Finish-to-Start dependencies, the company’s team demonstrated maturity in APQP and schedule management. To mitigate the impact on flexibility and total project time, concurrent engineering practices were adopted. This approach allowed for minimizing sequencing constraints without compromising quality and compliance with customer requirements, optimizing workflow and collaboration among teams.

Activity durations

The estimation of the duration of activities was carried out based on consultations with those responsible for the activities, considering the experience of the resources involved and the analysis of historical data from similar projects. Additionally, the triangular distribution estimation technique was applied, which uses three values – optimistic (tO), most likely (tM), and pessimistic (tP) – to calculate the expected duration (tE), according to the formula tE = (tO + tM + tP) / 3. This approach allowed for more concrete and realistic estimates to be obtained, absorbing possible scenarios of uncertainty.

The analysis of the estimated durations revealed that the longest project phases were Phase 2 – Product Design and Development, with an expected duration of 150 days, and Phase 3 – Process Design and Development, with 180 days. These phases concentrate the most complex and critical activities for the project’s technical maturity, involving the elaboration and review of drawings, specifications, DFMEA, PFMEA, control plans, and the definition of the production process, which require strong interaction between engineering, quality, and manufacturing.

Historically, these phases presented a higher number of revisions in previous projects, resulting in rework of tests, risk analyses, and project changes. This history contributed to the estimation of longer durations, aiming to ensure product robustness and compliance. The high dependency between Finish-to-Start activities in these phases also reduced parallelism and extended the critical path of the schedule, making them the longest within the APQP cycle.

Despite the extent of these phases, the concentration of efforts by the entire project management team on these stages was fundamental to ensuring quality and compliance. The application of three-point estimation, together with historical data analysis, allowed for a more accurate prediction of deadlines, minimizing surprises and enabling more effective planning of the resources needed for the most demanding activities.

Schedule development

For the development of the schedule, the Microsoft Project software was used, which offers robust features for creating Gantt chart-style schedules, defining task dependencies, allocating resources, and tracking costs. This tool enabled the construction of a structured view of the project, facilitating progress monitoring and the identification of deviations from the initial plan, which was essential for decision-making and replanning when necessary.

All listed activities were entered into the software with their respective deadlines, generating the Gantt chart. This visual representation, through horizontal bars, allowed for the identification of tasks, their durations, start and end dates, and dependency relationships. The visualization facilitated the understanding of the project’s logical sequence, contributing to the organization of stages and to meeting established deadlines, in addition to allowing for the monitoring of activity status to identify possible delays or deviations.

The analysis of the developed schedule demonstrated that the project was feasible and coherent, with activities logically chained and respecting the technical dependencies between the APQP stages, with a predominance of Finish-to-Start relationships. The existence of float in non-critical activities was noted, which provided some flexibility to deal with deviations without impacting the final deadline. The total project deadline proved to be compatible with the defined complexity and scope, reflecting realistic planning.

Additionally, a critical path was identified, formed by the main deliverables of product and process development, where the activities presented little or no float. Any delay in these stages would directly affect the project completion date, requiring closer monitoring and prioritization of resources. This finding reinforces the importance of constant schedule monitoring to ensure adherence to deadlines and risk reduction during project development.

Schedule timeline follow-up meetings

The follow-up meetings, known as “follow-up” (FUP), played a fundamental role in the new product launch process, especially in a context that uses structured methodologies like APQP. These weekly meetings, involving the project coordinator and the cross-functional team, had the main objective of monitoring the progress of activities, ensuring compliance with deadlines, and identifying deviations in advance, with a focus on meeting the final customer deadline.

During these meetings, progress indicators, project milestones, and potential risks that could impact the performance of the stages were analyzed. The frequent holding of meetings contributed to the improvement of schedule control, enabling early identification of deviations, rapid decision-making, and realignment of critical activities. As a result, a reduction in delays, greater adherence to established milestones, and an increase in project predictability were observed, with risks and impediments being proactively addressed.

The follow-up meetings transcended the function of a mere control instrument, acting as an effective mechanism to ensure deadline compliance and planning stability throughout the development. They also favored integration between the involved areas, such as engineering, quality, production, and logistics, promoting efficient communication and strategic alignment between teams. This alignment was essential to ensure that all phases of product development occurred in a coordinated manner, reducing rework and increasing predictability.

The status of the APQP phases in March 2026 indicated that the project was on schedule. Phases 1, 2, and 3 showed 100% completion of activities and deliverables, while phase 4 was in progress, with 75% progress, preparing for phase 5. This demonstrated that the project timeline was being met as planned, reflecting the effectiveness of the implemented monitoring and control practices.

However, a relevant challenge identified was the availability of the multifunctional team, considered a critical resource for the project’s conduction, given the lean team nature and multiple simultaneous demands. An indicator of presence in project meetings revealed that the Programs and Engineering sectors had high participation, with 100% and 95% presence, respectively. Quality and Production also showed good rates, with 87% and 89%.

In contrast, the Logistics and Commercial sectors presented lower presence rates, with 79% and 53%, respectively. The higher frequency of absences by the commercial sector and, subsequently, the logistics sector, directly impacted the quality and agility of decision-making, especially in issues that depended on specific validations from these areas. These absences caused delays in defining actions and increased the risk of schedule deviations.

The project’s greater exposure to rework, replanning, and potential impacts on deadline adherence, stemming from the lower participation of some sectors, reinforced the importance of continuous engagement from the multifunctional team as a critical factor for project stability and predictability. The Microsoft Project software was used to support these meetings, providing a clear view of activity status and facilitating decision-making, although it could not compensate for the absence of key members.

In summary, the integrated application of APQP and PMBOK best practices in managing the schedule for the stamped parts manufacturing project proved to be an effective approach for the automotive sector. It was found that this integration provided greater organization, control, and predictability, improving schedule management and assertiveness in decision-making. Process standardization, clear identification of the critical path, and continuous monitoring, despite challenges in multidisciplinary team availability, contributed to risk reduction and greater adherence to customer requirements, confirming the methodology’s relevance to project success.

4. Conclusion

The analysis of the application of schedule planning and control practices in the development of a stamped parts manufacturing project for automotive backrest metallic structure, using Advanced Product Quality Planning (APQP) integrated with the best practices of the Project Management Body of Knowledge (PMBOK) guide, revealed the effectiveness of this approach. It was verified that APQP established the mandatory project phases and deliverables at a macro level, while PMBOK complemented this structure by providing detailed practices for schedule planning, sequencing, duration estimation, and control. This integration contributed significantly to the standardization and governance of the process, ensuring greater control over deadlines and strict adherence to customer demands. The Project Breakdown Structure (WBS) was central to defining activities, and the sequencing, predominantly Finish-to-Start, formed the critical path, ensuring quality robustness and failure prevention. Duration estimates, based on historical data and triangular distribution, indicated that the Product and Process Design and Development phases were the most extensive, due to their complexity and interdependencies. The use of Microsoft Project software facilitated schedule development and monitoring, and weekly follow-up meetings were crucial for early identification of deviations and decision-making, resulting in reduced delays and increased predictability. The study’s main practical contribution lies in the improvement of schedule management in the analyzed company, evidenced by greater clarity in activity definition, deadline monitoring, and decision-making assertiveness, which resulted in risk reduction and greater adherence to customer requirements.

Despite the positive results, the availability of the multifunctional team, a critical resource for project execution, was identified as a limitation. The reduced participation of sectors such as Logistics and Sales in the follow-up meetings impacted the quality and agility of decision-making, leading to delays in defining actions and increasing the risk of schedule deviations. This situation reinforces the importance of continuous team engagement for project stability and predictability. In the academic sphere, this work contributes by demonstrating, in an applied manner, the benefits of integrating methodologies such as APQP and PMBOK in industrial environments that require a high level of quality and control, broadening the discussion on hybrid project management approaches. For future studies, it is suggested to expand this research by analyzing the application of agile methodologies in conjunction with APQP and PMBOK, as well as investigating strategies for optimizing resource management and increasing the engagement of multifunctional teams in industrial projects.

Bibliographic References

Associação Nacional dos Fabricantes de Veículos Automotores [ANFAVEA]. 2025. Edições em Excel. Disponível em: https://anfavea.com.br/site/edicoes-em-excel/. Acesso em: 14 set. 2025.

Gil, 2017 [Referência completa não encontrada no documento original]

Kerzner, H. 2017. Project management: a systems approach to planning, scheduling, and controlling. 12. ed. Hoboken: John Wiley & Sons, 2017.

LUPO, Maria Ausilia. Application of project management tools to the activities of the advanced product quality planning (APQP). Torino: Politecnico di Torino, 2018. Disponível em: https://webthesis.biblio.polito.it/7256/1/tesi.pdf . Acesso em: 28 fev. 2026.

Melo, A. J. L.; Terazzi, L. F. 2025. Gestão De Projetos Na Indústria Automotiva: Aplicações na Produção de Autopeças. Revista Interface Tecnológica 22(1): 642-653.

Pissinatti, T. P.; Franco, J. C.; Rezende, J. P.; Valente, A. M. M. P.; Satolo, E. G. 2014. Inter-relação da ferramenta APQP e do guia PMBOK para eficiência nas etapas de implementação de novos projetos na indústria automotiva. Iberoamerican Journal of Project Management 5(1): 21-41.

Project Management Institute [PMI]. 2021. Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®): uma abordagem baseada em princípios. 7ed. PMI, Newtown Square, PA, USA.

Santos, I. A. Dos; Alves, M. A.; Hamzagic, M. A. 2021. PQP e Lean Six Sigma: metodologias integradas na gestão do desenvolvimento de produto. In: XLI Encontro Nacional de Engenharia de Produção – ENEGEP, 2021, Foz do Iguaçu. Anais… Foz do Iguaçu, PR, Brasil.

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.