Application of Six Sigma DMAIC and Gemba Walk for the analysis of mechanical availability of mobile equipment

Application of Six Sigma DMAIC and Gemba Walk for Analysis of Mechanical Availability of Mobile Equipment

Vítor de Souza Mattioli; Enise Aragão dos Santos

DOI: 10.22167/2675-6528-202602416

Article derived from a Course Conclusion Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

The inefficient management of mobile equipment maintenance routines in infrastructure works directly impacted mechanical availability indicators and productive performance. The study aimed to analyze the mechanical availability of equipment in a road superstructure work, using the Six Sigma DMAIC cycle, associated with the Gemba Walk practice. The methodology was characterized as an applied case study, with a mixed approach. It involved the collection and treatment of operational data, the calculation of mechanical availability indicators, and qualitative analysis through the Ishikawa Diagram. The results revealed that some equipment families showed performance below the acceptable level, with the asphalt plant standing out due to unavailability that affected production. The main causes identified included the absence of preventive planning, failures in maintenance management, and the lack of critical inputs. Based on this diagnosis, improvement actions and an implementation schedule were structured, aiming at the standardization of routines and systematic indicator control. It was concluded that the integrated application of the methodologies allowed for the identification of the causes of low availability and the establishment of a management model focused on operational reliability and continuous improvement.

Keywords: Operational reliability; Asset management; Performance indicators; Maintenance; Continuous improvement.

1. Introduction

The recurrence of failures during the operation of machinery and equipment compromises the efficiency and safety of civil construction projects. With increasingly tight schedules for the execution of activities, it becomes fundamental to establish processes of constant improvement, allied with Lean Manufacturing strategies, to reduce corrective stops and increase productivity rates, assisting in meeting customer delivery milestones (Zu et al., 2008; Bendoly, 2016; Gołaś et al., 2016). The combination of these resources with well-defined processes and practices can bring significant benefits to maintenance (Saleh, 2024; Al-Toubi, 2024).

In this context, the inefficient management of mobile equipment maintenance routines in infrastructure works has shown direct impacts on mechanical availability indicators and productive performance. To mitigate long idle periods and unforeseen operational costs, it is necessary to integrate resources into continuous monitoring of equipment operation, both in the field and through the analysis of strategic indicators that enable the early identification of potential failures (Mobley, 2002).

In this sense, the Six Sigma DMAIC method emerges as a relevant tool to structure a leaner approach to activity analysis, offering a simplified view of problems and directing improvements in maintenance routines. The DMAIC cycle, which comprises the Define, Measure, Analyze, Improve, and Control phases, provides a systematic structure for process improvement, from the clear description of the problem and definition of objectives (Girmanová, 2017) to the identification of root causes (Shaikh, 2015; Kazi, 2015) and continuous monitoring (Monday, 2022).

Complementarily, the Gemba Walk practice, which consists of directly observing the environment where activities occur, can be employed to ensure greater management involvement in daily operations, understanding the main obstacles to the inefficiency of the productive system (Soliman, 2020). This approach offers greater transparency and a closer relationship between management and the operational area, facilitating data collection (Taylor, 2021), although it is crucial that the conduct has a clear objective (Weber, 2018).

The integration of methodologies such as DMAIC with techniques to verify the overall equipment effectiveness has demonstrated direct contributions to raising the degree of quality of the investigated processes (Smętkowska et al., 2018). Six Sigma is efficient in root cause evaluation, organization, and integration with other management methodologies, aiming at meeting goals (Al-Mishari & Suliman, 2008; Rozak et al., 2020).

Maintenance therefore assumes great importance, especially regarding the periodic inspection of the main machine components, using work lists recommended by the manufacturer and programming in specific operating hour cycles (Erbiyik, 2022). Such preventive practices are decisive for breakdowns to be identified in advance, preserving the performance and increasing the lifespan of essential components (Mobley, 2002). In addition to affecting the mechanical availability of the equipment, corrective downtime requires immediate action from the team, diverting focus from other activities (Finigan & Humphries, 2006).

Given this scenario, the relevance of a study that proposes the analysis and improvement of maintenance management in mobile equipment becomes evident, justifying the need to identify the causes of low availability and structure a management model oriented towards operational reliability and continuous improvement. Thus, this work aimed to analyze the mechanical availability of equipment in a road superstructure construction site, through the application of the Six Sigma DMAIC cycle, associated with the Gemba Walk practice.

2. Material and Methods

The research was characterized as an applied case study, of a mixed nature, developed in a road superstructure work. The central objective was to analyze the mechanical availability of the equipment, seeking to identify the causes of low efficiency in some machine families. For this purpose, the Six Sigma DMAIC cycle was applied, associated with the Gemba Walk practice, aiming to obtain an initial diagnosis and structure improvement solutions for the operational scenario.

In the Define phase, an applied approach was used, starting with the Gemba Walk in the construction site operations. During this practice, the routines for operating equipment by the operators were mapped, and the machines stopped in the workshop were observed. Drivers of vehicles and heavy machinery recorded their activities using a mobile device, which allowed for the collection of historical data on records of mechanical losses and corrective and preventive maintenance records.

Together with the construction reporting team, primary data was collected during the technical visit, carried out between November 10 and 15, 2025. These records included information such as equipment code and type, operator identification, loss type, reporting date, and idle hours. For the asphalt plant, historical data on mechanical losses from August to October 2025 was also gathered.

In the Measure phase, the database of mechanical losses records was processed. The records were standardized in terms of time units and categorized by equipment type and family, disregarding managerial losses that do not affect mechanical availability indicators. The time records were converted to a standardized numerical format, consolidating the idle hours registered by equipment type.

Based on the consolidated data, equipment families were classified according to their performance, delimiting those with an index below 85% as critical. For this delimitation, total downtime and mechanical availability (DM) indices were calculated, using the formula that relates downtime due to mechanical failure (Tp) with the total available time in working shift hours (Tdisp). Complementarily, a basic observation checklist was applied to record pre-operation routines, preventive maintenance, team communication, and availability of parts and supplies.

In the Analyze phase, after the quantitative survey and consideration of the observed criteria, qualitative analyses were performed using the Ishikawa Diagram. This tool aided in identifying the determining factors for the low availability of the priority equipment family. Both documentary information and perceptions collected during the application of the Gemba observation checklist were considered, allowing for the structuring of the problem causes.

In the Improve phase, based on the identified causes, improvement actions were structured to reduce recurring failures and stabilize operational and maintenance routines. The initiatives focused on correcting deviations and standardizing processes, through the formalization of schedules for essential activities for asset reliability. An implementation schedule was developed, defining those responsible for each action.

The Control phase consisted of defining the continuous monitoring mechanisms, built from the management model developed during the study. Control was carried out through systematic monitoring of indicators and standardized routines, aiming to ensure that the process remained within the previously defined parameters. The objective was to guarantee the sustainability of the implemented improvements and allow for future adjustments, should deviations from the established model be observed.

The combination of documentary analysis, structured field observation, and systematic application of the DMAIC cycle allowed for the construction of a robust methodological procedure. This chaining of steps provided data for the identification of critical process factors and the design of improvement actions, aligning with the objective of analyzing mechanical availability and proposing a management model focused on operational reliability.

3. Results and Discussion

The preliminary results of this study, obtained by applying the Six Sigma DMAIC cycle in conjunction with the Gemba Walk practice, reveal a detailed diagnosis of the mechanical availability of equipment in a road superstructure construction site. The initial analysis focused on identifying findings from real data collected in the field, describing the activities developed in the stages already completed. This process allowed not only to quantify losses but also to understand the underlying causes that impact operational efficiency and adherence to project schedules, in line with the central objective of the research.

In the Define stage, during the on-site technical visit to the construction site, significant machinery idleness was observed, predominantly due to mechanical problems. It was noted that the executed workflow followed the company’s standard, with all stages duly recorded and communicated, from the start of activities to the occurrence of unplanned downtime or shift closure. However, the main bottleneck was not in the operational execution itself, but in the absence of effective indicator management and the lack of action on maintenance *backlogs* by those responsible. Although relevant operational information was available in real-time, it was underutilized in the decision-making process.

From this finding, with the support of the construction site’s reporting team, a daily survey of mechanical loss records was carried out. This data was collected during the visit period, with the objective of supporting the development of a solution for stopped machinery. The equipment family considered most critical for the continuity of the construction plan was that of 16 cubic meter dump trucks, which presented the highest total hours of downtime due to mechanical loss, totaling 73.45 hours. This initial data already indicated a concentration of problems in a specific type of asset, requiring further investigation.

Subsequently, the Measure stage involved processing the database of mechanical failure records. The records were standardized into time units and categorized by equipment type and family, disregarding managerial losses that do not directly affect mechanical availability indicators. Based on this consolidated data, the equipment families were classified according to their performance. Those with a mechanical availability index (DM) below 85% stood out, considered critical for the completion of the work stages, an acceptable technical level according to the literature (Harris et al., 2013; Peurifoy et al., 2018; Parker et al., 2009).

The calculation of the mechanical availability index revealed that the asphalt plant presented the lowest index, with 79%, followed by the loader, with 0%, and the water truck, with 83%. Other equipment such as 16 and 22 cubic meter dump trucks, skid steer loaders, asphalt recyclers, and tire tractors registered 89%, 89%, 87%, 87%, and 87% availability, respectively. These values were below the 85% threshold considered ideal for operation. In contrast, excavators and backhoe loaders achieved 100% availability, while asphalt planers and spray trucks obtained 99% and 98%, respectively, indicating satisfactory performance.

The analysis of the asphalt plant’s mechanical availability over three months (August to October 2025) showed an expressive variation. In August, availability was 99%, but it dropped to 74% in September and remained at that level in October. This trend of performance below the ideal level of 85% confirmed that the plant’s unavailability was not an isolated event, but rather a recurring problem that delayed the weekly project delivery milestones. The criticality of the asphalt plant for the asphalt application phase on the highway justified prioritizing it for a more in-depth case study, according to the DMAIC methodology.

To complement the quantitative analysis, an observation checklist was applied to those involved, focusing on aspects such as the recording of failures by operators, the execution of maintenance according to the manufacturer’s recommendation, compliance with preventive plans, communication between teams, and the availability of parts and supplies. The checklist results indicated that, although operators recorded failures and downtime, the maintenance plans were not parameterized for periodic execution, and compliance with weekly preventive plans was inadequate. Furthermore, the availability of critical parts and supplies was insufficient, and there was no periodic inspection to evaluate critical plant components.

In the Analyze stage, based on the checklist results and quantitative data, the Ishikawa Diagram was used to identify the root causes of the low availability of the asphalt plant. The causes were categorized into pillars. In the Machine pillar, significant wear of critical components and the absence of daily maintenance plans were identified. In the Labor pillar, a lack of personnel for performing maintenance outside of shifts and the need for training were verified. The Material pillar pointed to the absence of spare parts and dependence on a single external supplier, which generated delays and unavailability.

In the Measurement pillar, the causes included the absence of monitoring indicators and the underutilization of operational time tracking data, evidencing a gap in monitoring and decision-making. The Method pillar revealed the lack of maintenance *backlog* tracking and the existence of non-parameterized plans, which hindered proactive management. Finally, the Environment pillar, although with less directly mitigable factors such as dust, temperature, and humidity, also pointed to the absence of vibration monitoring, which could assist in predictive maintenance. All these causes converged towards the central effect of low availability of the asphalt plant.

With the root cause analysis, the final Improve and Control steps were carried out. In the Improve step, visual and mechanical inspection of critical plant components revealed the need to replace the mixer blades for aggregates due to wear. Additionally, the need for intervention in the blower motor was identified, which showed current peaks above 55A, its nominal limit, when seeking to increase hourly production. For the plant’s maximum production to be achieved safely and efficiently, the replacement of this component was essential, indicating a sizing failure or advanced wear.

To address the other identified causes, an eight-week implementation schedule for improvement activities was developed. This schedule focused on defining maintenance KPIs, such as MTBF (Mean Time Between Failures), MTTR (Mean Time To Repair), and availability, for more effective control. A survey of critical parts without stock and the definition of a minimum stock were foreseen, aiming to mitigate unavailability due to lack of supplies. Monitoring of maintenance backlogs and a general inspection of the plant’s equipment were also included, with defined responsibilities for each action, such as the Maintenance Controller and the Maintenance Manager.

The schedule also included consulting the manufacturer’s recommended preventive maintenance plan and defining daily maintenance routines, including cleaning the plant to mitigate the impact of dust. The creation of an indicator control and spreadsheet, the replacement of worn mixer arms and blades, and the installation and monitoring of the new blower motor were priority actions. Furthermore, efforts were made to initiate the survey of alternative material suppliers for minimum stock, aiming to reduce dependence on a single supplier and increase supply chain resilience.

Other important actions included evaluating the maintenance team’s sizing, defining off-shift maintenance when necessary, and parameterizing the preventive maintenance plan. The approval of additional suppliers, the verification and adjustments to critical plant components, and the initial analysis of operational indicators were crucial steps. The study of a vibration monitoring device was also proposed to enhance predictive maintenance. These initiatives aimed to correct identified deviations and standardize processes, increasing asset reliability.

The Control stage, in turn, consisted of defining mechanisms for continuous monitoring, built from the management model developed. Control would be carried out through systematic monitoring of indicators and standardized routines, without presenting detailed numerical results, but ensuring that the process remained within the previously defined parameters. The primary objective was to guarantee the sustainability of the implemented improvements and allow for future adjustments whenever deviations from the established model were observed, consolidating a cycle of continuous improvement in maintenance management.

In summary, the integrated application of the Six Sigma DMAIC cycle and Gemba Walk allowed the identification that the low mechanical availability of equipment, especially the asphalt plant, stems from structural failures in maintenance management. The findings revealed the absence of preventive planning, inadequate backlog control, insufficient critical spare parts in stock, and reactive corrective interventions. The proposed improvement actions, detailed in a schedule, aim to transform this reactive model into proactive, data-driven management, with the objective of increasing operational reliability and construction productivity, directly addressing the research problem and the study’s objective.

4. Conclusion

This study sought to analyze the mechanical availability of equipment in a road superstructure construction, through the application of the Six Sigma DMAIC cycle, associated with the Gemba Walk practice. It was verified that maintenance management presented significant inefficiencies, resulting in considerable machinery idleness. It was identified that the asphalt plant, with a mechanical availability index of 79%, operated below the acceptable level of 85%, directly impacting the production schedule. In-depth analysis, using the Ishikawa Diagram, revealed that the root causes of low availability were related to the absence of preventive planning, failures in maintenance management, lack of critical inputs, underutilization of operational data, and the non-existence of effective control over maintenance backlogs. The accentuated wear of critical components and the undersizing of a specific engine, which compromised the plant’s production capacity, were also observed.

The integrated application of methodologies allowed not only to diagnose the causes of low availability but also to structure a proactive management model, with the definition of an improvement action schedule. This model aims at standardizing routines, systematic control of performance indicators such as MTBF and MTTR, critical parts inventory management, and maintenance team evaluation, promoting the transition from a reactive approach to management oriented towards operational reliability and continuous improvement. However, the detailed analysis of the asphalt plant’s availability was limited to a three-month period, which may not capture seasonal or long-term variations. For future studies, it is suggested to implement and monitor the proposed KPIs, as well as investigate the feasibility of vibration monitoring devices to enhance predictive maintenance and extend the model’s application to other equipment families and projects.

Bibliographic References

Al-Mishari & Suliman, 2008 [Referência completa não encontrada no documento original]

Al-Toubi, S.S. 2024. Developing a Novel Lean Methodology with Machine Learning Approach to Improve the Productivity and Efficiency of Rotating Pumps. Tese de Doutorado em Engenharia. Glasgow Caledonian University, Glasgow, Escócia, Reino Unido. Disponível em:https://researchonline.gcu.ac.uk/en/studentTheses/7887047f-81f6-47e1-99fe-72c2731f4403. Acesso em: 27 set. 2025.

Bendoly, 2016 [Referência completa não encontrada no documento original]

Erbiyik, H. 2022. Definition of maintenance and maintenance types with due care on preventive maintenance. p. 1-26. In: Lambert-Torres, G.; Bonaldi, E.L.; Oliveira, L.E.L. Maintenance Management – Current Challenges, New Developments, and Future Directions. IntechOpen, London, UK. Disponível em: https://doi.org/10.5772/intechopen.106346. Acesso em: 01 out. 2025.

Finigan & Humphries, 2006 [Referência completa não encontrada no documento original]

Girmanová, L.; Šolc, M.; Kliment, J.; Divoková, A.; Mikloš, V. 2017. Application of Six Sigma using DMAIC methodology in the process of product quality control in metallurgical operation. Acta Technologica Agriculturae 21(4): 104-109.

Gołaś et al., 2016 [Referência completa não encontrada no documento original]

Harris, F.; McCaffer, R. 2013. Modern Construction Management. 7th ed. Oxford: Wiley-Blackwell.

Mobley, R.K. 2002. An Introduction to Predictive Maintenance. 2ed. Elsevier, Oxford, UK.

Monday, L.M. 2022. Define, measure, analyze, improve, control (DMAIC) methodology as a roadmap in quality improvement. Global Journal on Quality and Safety in Healthcare 5(2): 44-46.

Parker, H.W.; Oglesby, C.H. 2009. Productivity Improvement in Construction. New York: McGraw-Hill.

Peurifoy, R.L.; Schexnayder, C.J.; Shapira, A. 2018. Construction Planning, Equipment and Methods. 9th ed. New York: McGraw-Hill.

Rozak et al., 2020 [Referência completa não encontrada no documento original]

Saleh, 2024 [Referência completa não encontrada no documento original]

Shaikh, S.A.; Kazi, J. 2015. A Review on Six Sigma (DMAIC) Methodology. International Journal of Modern Engineering Research 5(2): 11-16.

Smętkowska, M.; Mrugalska, B. 2018. Using Six Sigma DMAIC to improve the quality of the production process: a case study. Procedia – Social and Behavioral Sciences 238: 590-596.

Soliman, M.H.A. 2017. Gemba Walks the Toyota Way: The Place to Teach and Learn Management. CreateSpace Independent Publishing Platform, USA.

Taylor, J.D. 2021. The impact of Gemba Walks on preventative maintenance productivity. Dissertação de Mestrado em Engenharia e Gestão. Western Kentucky University, Bowling Green, KY, EUA. Disponível em: https://digitalcommons.wku.edu/theses/3545. Acesso em: 01 out. 2025.

Weber, 2018 [Full reference not found in the original document]

Zu et al., 2008 [Full reference not found in the original document]

Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

November 17, 2026

Detection and Diagnosis of Diseases in Corn and Rice in Mozambique with Deep Learning

Mozambican agriculture depends on corn and rice, fundamental crops for food security, but their productivity is strongly affected by phytosanitary diseases, whose early and accurate identification remains a challenge in resource-limited contexts. The study aimed to develop and compare Deep Learning-based models for the automatic detection and diagnosis of diseases in corn and rice leaves in Mozambique. Three approaches were used: a classic Convolutional Neural Network (CNN) developed from scratch, and two transfer learning models, ResNet50 and MobileNetV2. The dataset consisted of images from public databases and collected in the field, which underwent cleaning, balancing, and artificial augmentation steps. The models were trained and evaluated with standard performance metrics, including accuracy, precision, recall, F1-score, Log Loss, and Cohen’s Kappa. The classic CNN presented the best overall performance, with 94% precision, recall, and F1-score, and 93% accuracy and Cohen’s Kappa. MobileNetV2 achieved 91% F1-score and 90% accuracy, standing out for its lower Log Loss (0.30) and training time (6h32min59s). ResNet50 reached 80% F1-score and 79% accuracy. It was concluded that Deep Learning techniques have high potential to support phytopathological diagnosis in real agricultural contexts, contributing to faster and more accurate decisions in the management of corn and rice diseases.

Keywords: Deep learning; Rice; Plant diseases; Corn; Computer vision.

November 17, 2026

Artificial intelligence in accounting operational routines and financial efficiency

The incorporation of Artificial Intelligence (AI) and automation tools has reconfigured the routines of Brazilian accounting offices, impacting productivity, error mitigation, and financial efficiency. These impacts were analyzed in a small accounting firm, specialized in serving service providers in the medical field in São Caetano do Sul, São Paulo. The research adopted a qualitative approach, with a single case study design and incorporated units of analysis. Data were collected through a structured questionnaire, applied via Google Forms between January and February 2026, to five professionals in the operational structure of the firm in a census survey. The treatment followed content analysis with a priori and emergent categories. All respondents declared the use of automated tools or tools with AI resources. The perception of reduced execution time, decreased operational errors, rework, and better use of the team’s time converged in 80% of affirmative responses and 20% partial responses. The most benefited activities were bank reconciliation, import of fiscal documents, and tax assessment, with visible gains on typing errors, duplicate entries, and incorrect classification. Human intervention remained indispensable in tax planning, scenario analysis, and verification of ancillary obligations. The overall evaluation of AI’s contribution was predominantly favorable, with moderation linked to the complexity of fiscal regulations.

Keywords: Content analysis; Process automation; Accounting 4.0; Small business; Digital transformation.

November 17, 2026

Factors influencing schedule management in sewage treatment plant “retrofit” projects

Projects involving “retrofit” in Sewage Treatment Plants (STP) are characterized by high complexity, operational restrictions, and multiple technical interfaces. The study analyzed the perception of the professionals involved regarding the management and adherence to deadlines in “retrofit” projects for sewage treatment plants, considering technical, operational, and organizational factors. The research was characterized as an applied study, with a quali-quantitative approach, designed as a field survey. Data analysis was performed using descriptive statistics and qualitative categorization, employing SWOT, risk matrix (Probability x Impact), and 5W2H action plan tools. The results indicated a high perception of clarity (77.8%) and realism of deadlines (100% agreement), evidencing consistent initial planning. However, 77.7% of respondents pointed out that rework and scope changes directly impacted deadline adherence. The integration between engineering, manufacturing, and Production Planning and Control (PPC) showed an intermediate evaluation (77.7% partial/total agreement), indicating fragility in interfunctional coordination. The risk matrix highlighted as critical: scope changes, operational limitations of the STP, and technical complexity, all with a high level. As a central improvement, the standardization of scope change control, analysis, and approval was proposed, aiming to reduce rework and increase schedule predictability.

Keywords: Performance; Integration; Planning; Rework; Risk.

November 17, 2026

B2C Acquisition in diagnostic medicine: strategic partnerships with specialized medical offices

The diagnostic medicine sector in Brazil operates with high dependence on health plan providers, which limits the financial autonomy of service providers. This study proposed and analyzed a direct patient acquisition model (B2C) for a highly complex diagnostic medicine institution, structured through partnerships with Oncology and Cardiology practices and operationalized by a personalized customer service called concierge. The investigation adopted a mixed-methods approach in three phases: a field survey with a structured questionnaire applied to 87 patients, mapping of the operational flow using “Service Blueprint”, and analysis of the conversion rate from 312 medical referrals registered in the pilot project. The results indicated that trust in medical referral achieved 92.0% agreement, establishing itself as the main factor for adherence. The convenience of performing the exam on the same day reached 78.2%, and the willingness to pay directly was 55.2%, with polarization associated with the predominance of health plan users. The “Service Blueprint” identified three critical points in the transitions between stages of the patient journey. The overall conversion rate was 51.0%, with superior performance in Oncology (58.2%) compared to Cardiology (45.0%), and the greatest loss was concentrated in the acceptance and scheduling stage (28.3%). It was concluded that the model demonstrated possible operational viability and indications of patient acceptance, conditioned by price transparency and a reduction in the interval between consultation and approach by the concierge.

Keywords: Direct payment; Patient journey; Supplementary health; Concierge service; Conversion rate.

November 17, 2026

The role of the school manager in promoting an inclusive culture: leadership and educational policies

The research analyzed the school manager’s performance in promoting an inclusive culture, considering the need to transform legal guidelines and pedagogical foundations into effective institutional practices. It was assumed that school inclusion requires planning, organization, and strategic leadership in the school’s daily operations. A qualitative approach of an applied nature was adopted, developed in three complementary stages: documentary analysis of Brazilian legislation on inclusive education, bibliographic review on school leadership and management, and data systematization using management tools such as SWOT analysis and the PDCA cycle. The results indicated that the school management’s performance directly influenced the consolidation of inclusive environments, especially in the organization of processes, continuous team training, and strengthening of a collaborative institutional culture respectful of diversity. Structural, pedagogical, and relational challenges that demanded planned interventions were also identified. Finally, a Practical Guide for School Managers was developed, with guidelines, protocols, and operational orientations for decision-making and the organization of inclusive processes. It was concluded that the construction of an inclusive culture depended on the management’s ability to articulate public policies, pedagogical practices, and institutional processes, consolidating inclusion as a permanent commitment in the school context.

Keywords: educational accessibility; educational equity; participatory management; strategic planning; institutional processes.

November 17, 2026

An AI artifact based on Design Thinking to support the elicitation of software requirements from user needs

The development of software oriented to user needs frequently faces challenges in requirements elicitation, stemming from ambiguities in natural language and communication failures. Given this, an intelligent artifact integrating Design Thinking and Artificial Intelligence was proposed and validated, focusing on the Empathy and Definition stages, to support the collection, interpretation, and structuring of user needs. The research, of an applied, qualitative, and exploratory nature, conducted a Proof of Concept in a controlled environment, employing hypothetical scenarios. The artifact operated through guided natural language interviews, organizing information into elements such as pain points, context, and impact, and generating traceable problem syntheses. The results indicated that the system organized unstructured reports, reduced ambiguities, and preserved the meaning of the original information in most cases. The ability to reorganize logically in complex scenarios was also observed, although with limitations in separating multiple problems and dependence on instructions. It was concluded that the artifact has potential as a support for requirements elicitation, improving the clarity and structuring of information, but requires supervision and contextual control.

Keywords: Design Thinking; Requirements Elicitation; Requirements Engineering; Artificial Intelligence; Natural Language Processing.

November 17, 2026

The Extinction of the Monophasic Tax System in the Pharmaceutical Industry in Light of the Tax Reform

The consumption Tax Reform, established by Constitutional Amendment No. 132/2023, introduced structural changes to the Brazilian tax system, with the replacement of the Social Integration Program (PIS) and the Social Security Financing Contribution (COFINS) by the Contribution on Goods and Services (CBS), in a dual Value Added Tax (VAT) model. The objective was to analyze the impacts of the extinction of the single-stage system on the pharmaceutical industry, in light of the new regulatory design and its economic and legal effects. A qualitative, exploratory research was conducted through a case study and documentary analysis of legislation and specialized doctrine. It was examined whether the end of the single-stage system would imply a relevant increase in the tax burden for the sector. The results indicated that, although the formal overcoming of the single-stage system has occurred, the material exemption of medicines has been preserved, mainly due to the application of reduced rates of 60% and, in certain cases, a zero rate of the Tax on Goods and Services (IBS) and CBS. The change in model may cause occasional variations in revenue collection, without characterizing a structural increase in the tax burden, tending towards neutrality over time. It was preliminarily concluded that the Tax Reform reorganized the taxation technique in the pharmaceutical industry, replacing a concentrated regime with more transparent exemption mechanisms. This approach proved compatible with the principles of neutrality, full non-cumulativeness, and fiscality, maintaining tax protection for essential medicines and aligning fiscal policy with the fundamental right to health.

Keywords: CBS; COFINS; IBS; Dual VAT; PIS.