Anticipation of logistical resources for the displacement of Offshore collaborators
Luiz Felipe Costa de Souza; Aline Gisele Zanao Benatto
DOI: 10.22167/2675-6528-202601124
Article prepared by the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute focused on synthesis and writing.
Summary
Offshore work presents significant logistical challenges in employee travel, impacting operational effectiveness and schedule adherence. The objective of this study was to apply project management principles, based on the PDCA cycle, to analyze and restructure the logistical process of anticipating and automating ticket provision, as well as the prior allocation of resources for offshore personnel transportation. The methodology adopted a qualitative, exploratory, and applied approach, structured in the PDCA phases. A detailed organizational diagnosis was performed, including documentary analysis of reimbursement controls, absence records, and operational reports, in addition to semi-structured interviews with managers, logistics analysts, and offshore employees. The analysis revealed that the previous reimbursement model constituted a critical bottleneck, leading to missed flights, employee absences, contractual breaches, financial losses of approximately R$ 9.2 million in 2023, and low employee satisfaction. The implementation of advance ticket provision, as a corrective action, resulted in a 57.8% reduction in no-show rates (from 2.63% to 1.11%) and increased employee satisfaction, with 87.1% perceiving benefits in boarding planning and 93.55% considering the process clear. It was concluded that the structured application of PDCA transformed a costly and failure-prone process into a standardized, predictable, and replicable system, optimizing operational efficiency, mitigating risks, and generating sustainable value for the organization and its clients.
Keywords: Operational efficiency; Project management; Staff mobilization; PDCA; Oil sector.
1. Introduction
The offshore sector, strategic for the global economy and an innovation driver, presents considerable logistical challenges in mobilizing and demobilizing its workforce, given the remote and complex nature of its operations. The displacement of employees from their residences to embarkation points, often distant and with restricted access, requires meticulous planning and impeccable execution to ensure safety, punctuality, and operational continuity (Ballou, 2006). Failures in this process result in significant disruptions, directly impacting productivity and profitability. Historically, transport management in critical environments has been vulnerable, with traditional models often inadequate.
In this context, the application of project management principles emerges as an essential approach to optimize complex logistical processes. The Plan-Do-Check-Act (PDCA) cycle, developed by Shewhart and popularized by Deming, constitutes a robust tool for continuous improvement and standardization (PMI, 2017). It allows for systematic structuring: planning (Plan) defines objectives and methods, execution (Do) implements, verification (Check) monitors results, and action (Act) corrects and standardizes improvements. Project management, according to Kerzner (2017), emphasizes the integrated management of scope, time, cost, and quality, recognizing personnel logistics as a critical component that affects all these pillars and demands a proactive approach in identifying and mitigating risks.
The reimbursement model, widely adopted, transfers the initial financial responsibility for travel to the employee, generating logistical vulnerabilities (Bowersox and Closs, 2006; Bowersox, Closs and Cooper, 2006). This practice disregards the socioeconomic variability of professionals and disrupts human resource planning, violating principles of predictability and control. The lack of anticipation in providing tickets and prior financial support compromises the punctuality and availability of professionals, resulting in missed flights and absences. Such failures, analyzed from the perspective of the Check phase of the PDCA, reveal direct impacts on project performance, including operational interruptions and contractual penalties. Operational inefficiency, poor interfunctional communication, and insufficient risk management aggravate the scenario of low reliability and dissatisfaction (Slack, Chambers and Johnston, 2009; Chopra and Meindl, 2019).
The magnitude of these challenges is corroborated by empirical data. In 2023, the previous reimbursement model resulted in financial losses of approximately R$ 9.2 million for the organization, stemming from flight cancellations, no-shows of professionals on board, and contractual breaches. This significant amount represents not only a direct loss of capital but also signals indirect costs such as emergency replacements, damage to the institutional image, and potential loss of new contracts. Additionally, the no-show rate, which reached an average of 2.63% in 2023, demonstrates the fragility of the logistical process and its inability to guarantee the presence of collaborators. Employee dissatisfaction, who bear initial costs and reimbursement uncertainties, impacts the organizational climate and the perception of the company’s value, underscoring the urgency to re-evaluate and restructure mobilization logistics.
Given this scenario of operational inefficiencies, significant financial losses, and low employee satisfaction, the restructuring of the offshore personnel mobilization logistics process becomes imperative. The complexity and criticality of operations demand a systematic approach based on best management practices. Thus, this study is justified by the need to transform a costly and failure-prone model into a standardized, predictable, and replicable system capable of optimizing operational efficiency and generating sustainable value for the organization and its clients. The objective of this study was to apply the principles of project management, based on the PDCA cycle, to analyze and restructure the logistics process for anticipating and automating the supply of tickets, as well as the prior granting of resources for offshore personnel transportation.
2. Material and Methods
This study adopted a qualitative, exploratory, and applied methodological approach, aiming to deepen the understanding and propose improvements in the process of providing passages and resources for the boarding of offshore collaborators. The research was systematically structured based on the principles of the Plan-Do-Check-Act (PDCA) Cycle, a project management tool that guides continuous improvement. The choice for qualitative research was justified by the need to deeply analyze the perceptions, experiences, and impacts of the reimbursement model, allowing for the capture of operational and human nuances not observable by traditional quantitative methods (Thiollent, 2011).
The study was developed in a large Brazilian company, with over 41 years of consolidated operation in the offshore service provision sector, employing more than 7500 direct employees. The unit of analysis focused on the logistical process of personnel mobilization, specifically on the provision of tickets and resources for the displacement of collaborators. The research focused on a specific contract, in effect since 2019, which involves approximately 450 professionals working offshore, with 14-day shifts. Boarding and disembarking occur exclusively through Macaé airport, in Rio de Janeiro, requiring prior displacement and overnight stay in the city.
The population of interest for this study comprised employees working offshore for the organization, who depend on a structured logistical process for their travel from their residences to the embarkation airport. The sample consisted of ninety-three offshore professionals, selected intentionally. This selection criterion aimed to ensure the participation of individuals with direct and relevant experience in mobilization logistics processes, both in the previous reimbursement model and in the resource anticipation system implemented. The intention was to collect data reflecting the operational and personal impacts of both models.
Data collection was multifaceted, starting with documentary analysis of the organization’s internal records. Documents from the Human Resources, Logistics, and Operations departments were examined, including reimbursement controls, records of absence of onboarded professionals, operational reports, and contractual penalty histories. This analysis allowed for a detailed mapping of the previous logistic process flow and the identification of critical points. Complementarily, semi-structured interviews were conducted with managers, project coordinators, logistics analysts, and offshore collaborators, seeking to capture their perceptions and experiences regarding the current model.
Additionally, an electronic form was used as a data collection instrument among the ninety-three offshore collaborators who comprised the sample. This questionnaire, detailed in Annex 1, sought to ascertain participants’ perceptions of both ticket provision models: reimbursement and advance payment. The questions were designed to capture collaborators’ experience regarding process clarity, occurrence of problems, impact on boarding planning, and the incidence of absences due to financial issues. The responses were fundamental for a comparative evaluation of the impacts of the process change.
The research execution followed the phases of the PDCA cycle. In the Plan phase, the study objectives, the scope of the analysis, and the data collection instruments were defined. An evaluation of both the previous reimbursement model and the proposed model for advance ticket provision was established, with analysis criteria focused on process efficiency, resource management, and stakeholder satisfaction. In the Do phase, data collection proceeded, which included documentary analysis, semi-structured interviews, and the application of the electronic form to offshore collaborators, as previously described.
In the Check phase, the collected data were organized and analyzed. The interview responses were thematically categorized, using the content analysis technique, to identify patterns, weaknesses, and suggestions from the participants. The electronic form data were analyzed comparatively, allowing for the identification of the impacts of the implemented changes on the logistics process performance and the collaborators’ experience. Finally, in the Act phase, based on the findings, a restructuring of the logistics process was proposed, including the standardization of financial resource provision, the integration of areas, and the prior granting of resources for travel, implemented starting in February 2024.
The treatment and analysis of the data were carried out in a way that allowed for an in-depth understanding of the problem and the evaluation of solutions. The information obtained from the semi-structured interviews was subjected to content analysis, organizing it into thematic categories to identify the subjective and operational factors that influenced the effectiveness of the logistics process. The quantitative data collected through the electronic form were comparatively analyzed, allowing for the identification of trends and the evaluation of the impact of the transition from the reimbursement model to advance provision. Additionally, a detailed mapping of process flows and the identification of critical points were performed.
Regarding the ethical aspects, it was ensured that all information collected from participants would be kept in absolute confidentiality and used exclusively for academic purposes, as explained in the research form. Concerning the methodological limitations, the study was delimited by the absence of reliable information on no-show rates prior to 2023. Furthermore, the lack of systematic control over notifications sent to clients regarding the unavailability of onboard professionals before this period restricted the scope of historical analyses, focusing them from 2023 onwards to ensure data reliability.
3. Results and Discussion
The analysis of the logistical process for supplying airline tickets to offshore employees, conducted in alignment with the *Do* (Execute) phase of the Plan-Do-Check-Act (PDCA) Cycle, revealed critical failures stemming from the adoption of the reimbursement model as the primary operational solution. Among the main problems identified were missed flights, the absence of personnel on board on the scheduled dates, and direct impacts on the delivery of offshore services, in addition to contractual breaches and their respective penalties. These failures did not represent mere isolated setbacks, but rather manifestations of an intrinsically deficient logistical system, which compromised the integrity of the project scope, schedule, and budget. The reliance on a manual process and the transfer of initial financial responsibility to the employee created an environment conducive to errors and delays, diverging from good project management practices that advocate for predictability and control (Kerzner, 2017).
The data obtained through qualitative interviews with affected collaborators supported the *Check* (Verify) stage of the PDCA and, combined with the documentary analysis of the Human Resources, Logistics, and Operations departments, evidenced the absence of planning and integration between areas, ineffective communication, and insufficient risk management. The lack of anticipation in providing travel arrangements and prior financial support was pointed out as a determining factor for the compromise of the project’s scope, time, and cost. The disarticulation between departments, the absence of a standardized information flow, and the lack of proactive mechanisms to identify and mitigate financial and operational risks resulted in a vicious cycle of problems. This scenario contradicts the principles of a well-managed supply chain, where interfunctional coordination and collaboration are essential for operational efficiency and resilience (Chopra & Meindl, 2019; Bowersox & Closs, 2006). Ineffective communication, for example, generated rework and misinformation, negatively impacting employee productivity and morale.
The research aimed to analyze, from the perspective of project management and aligned with the concepts of the PDCA cycle, the perception of the studied company’s offshore workforce regarding the process of paying for tickets for travel from residence to the airport. The study included an evaluation of the previously adopted model, based on the reimbursement of incurred costs, as well as the perception of employees after the implementation of the change in the process, characterized by the adoption of advance ticket provision, considering its impacts on process efficiency, resource management, and stakeholder satisfaction. The comparative approach was fundamental to quantify and qualify the improvements, providing a solid basis for conclusions and recommendations.
The graph presented in Figure 1 characterizes the profile of the research participants sample, providing relevant subsidies for the analysis from the project management perspective.
Source: Original research results
Figure 1. Company tenure
It is observed that approximately 50.54% of professionals have been working for more than four years at the company, indicating a high degree of organizational maturity and experience with the analyzed processes. Additionally, 36.56% of respondents have been with the organization for between three and four years, while 12.9% have been employed for one to two years. It should be noted that all participants have experienced both modalities of the ticket provision process – by reimbursement and in advance – which lends greater consistency to the comparative evaluation of the impacts of the process change. The consolidated experience of the majority of employees (87.1% with more than 3 years of tenure) is a crucial factor, as their perceptions are based on in-depth knowledge of routines and operational challenges. This increases the reliability of the collected data and the robustness of the analysis, especially regarding change management, stakeholder perception, and decision-making effectiveness in the context of projects (PMI, 2017). The ability to directly compare the two models, having experienced them, provides a valuable perspective on the implemented improvements.
The graphs presented in Figures 3 and 4 highlight the fragilities of the air ticket reimbursement process, underscoring its low efficiency and the severity of the problems faced by employees.
Source: Original research results
Figure 2. History of incidents with ticket reimbursements
The analysis of Figure 2 demonstrates that 94.62% of professionals reported the occurrence of some type of intercurrence related to ticket reimbursement, indicating that almost the entire sample was impacted by failures in the process. This alarming percentage suggests that the reimbursement model was not only inefficient but systemically flawed, generating widespread frustration and distrust among employees. Intercurrences could range from payment delays, loss of receipts, to disputes over the eligibility of expenses, culminating in an increase in the administrative burden for employees and support departments. Such a result reinforces the critical nature of the problem, especially with regard to risk management and the reliability of project-related deliverables, fundamental elements for operational continuity in high-criticality environments such as offshore (Kerzner, 2017).
Source: Original research results
Figure 3. History of shipping delays due to ticket reimbursement issues
Furthermore, as illustrated in Figure 3, 61.29% of professionals reported having already refrained from embarking due to problems related to reimbursement. This data is particularly serious, as it highlights direct impacts on schedule adherence, operational continuity, and overall project performance. The absence of an employee on an offshore platform not only generates direct costs with emergency replacements and contractual penalties but can also compromise team safety and productivity, affecting the company’s reputation with the client (Chopra & Meindl, 2019). The reliance on individual financial capacity of employees to bear travel costs, followed by a flawed reimbursement process, transferred an unacceptable risk to the workforce, resulting in significant operational losses for the organization.
The analysis of Figure 4, which addresses the clarity of the reimbursement process, corroborates the perception of inefficiency and complexity.
Source: Original research results
Figure 4. Clarity in the ticket reimbursement process
Figure 4 shows that, from the workforce perspective, the ticket reimbursement process presented a high degree of lack of clarity. It is observed that 63.44% of professionals considered the process unclear, while 24.73% rated it as somewhat unclear, whereas only 11.83% of employees perceived it as clear. This lack of clarity was a critical factor in the context of project management, as it resulted in a high volume of complaints from directly involved *stakeholders*, including formal records in the company’s ombudsman portal. The lack of clear guidelines and the complexity of manual steps contributed to ambiguity, generating uncertainties and errors. Furthermore, the ambiguity of the process negatively impacted key areas such as Logistics, Human Resources, and Operations Coordination, which began to spend significant time and resources on guiding and clarifying doubts for the workforce, compromising operational efficiency, resource allocation, and project communication. Clarity in processes is a pillar of operational efficiency, and its absence, as demonstrated, leads to bottlenecks and resource waste (Slack, Chambers & Johnston, 2009).
As presented in Table 1, the company faced substantial financial losses due to the failures of the reimbursement model.
Table 1. Monthly no-show index 2023
|
Month |
Shipments |
Absentees |
Index (%) |
Estimate of Losses (R$) |
|
Jan/23 |
3429 |
98 |
2,86% |
BRL 828,813.07 |
|
Feb/23 |
3118 |
114 |
3,66% |
BRL 1,060,295.06 |
|
Mar/23 |
3397 |
104 |
3,06% |
BRL 887,842.21 |
|
Apr/23 |
3443 |
95 |
2,76% |
BRL 800,174.27 |
|
May/23 |
3553 |
57 |
1,60% |
BRL 465,240.64 |
|
Jun/23 |
3408 |
59 |
1,73% |
BRL 502,053.99 |
|
Jul/23 |
3608 |
82 |
2,27% |
BRL 659,090.91 |
|
Aug/23 |
3374 |
79 |
2,34% |
BRL 679,016.00 |
|
Sep/23 |
3595 |
100 |
2,78% |
BRL 806,675.94 |
|
Oct/23 |
3647 |
74 |
2,03% |
BRL 588,428.85 |
|
Nov/23 |
3341 |
106 |
3,17% |
BRL 920,083.81 |
|
12/23 |
3583 |
129 |
3,60% |
BRL 1,044,097.13 |
|
Sum |
41496 |
1097 |
BRL 9,241,811.88 |
Source: Original research data
It is observed that the company failed to invoice approximately R$ 9.2 million in the year 2023 due to the non-shipment by its employees. Additionally, the insufficiency of onboard professionals resulted in the application of contractual sanctions, materialized in fines totaling around R$ 720 thousand. From a project management perspective, these financial impacts highlight significant failures in risk management, operational planning, and control of contractual deliveries. The loss of R$ 9.2 million in invoicing in a single year is a critical indicator of the inefficiency of the previous process, representing not only a direct loss of revenue but also a significant opportunity cost. The contractual fines, in turn, not only impact the financial result but also signal a failure in service delivery, potentially leading to contract reevaluation and loss of clients. Beyond the direct financial losses, the recurrence of no-shows and the unavailability of onboard personnel contributed to the deterioration of the company’s institutional image with its clients, reflected in the reduction of its evaluation indices. Maintaining this scenario would represent a strategic risk, with potential negative impact on the prospecting and sustainability of new contracts in the organization’s client portfolio, as warned by Kerzner (2017) about the importance of risk management for the reputation and viability of projects.
Due to the gravity of the identified scenario, the company’s senior management established, for the fiscal year 2024, the reformulation of the ticket payment process as a strategic objective, aiming to reduce *no-show* rates, increase stakeholder satisfaction, and mitigate revenue losses. From a project management perspective, this initiative required the structuring of an organizational change project, conducted through the establishment of a multidisciplinary commission. This commission was composed of representatives from Logistics, Operations Coordination, Management, and offshore workforce professionals, who participated in structured *brainstorming* sessions to identify alternatives and define an operationally viable solution, aligned with organizational constraints and the company’s strategic objectives. This *Plan* phase of the PDCA was crucial to ensure that the proposed solution was comprehensive and integrated, considering the diverse perspectives of *stakeholders* and the project’s scope, time, and cost objectives (PMI, 2017). The active participation of representatives from all impacted areas ensured that the new proposal was robust and had a higher probability of acceptance and success.
After conducting three structured meetings, the multidisciplinary committee reached a consensus that the most viable solution, from an operational and project management perspective, would be the implementation of advance ticket provision, based on the planning of the professionals’ monthly schedules. Thus, considering the number of trips for each employee in a given month, the finance department would make the advance payment for the tickets, always in the last week of the month preceding the month of travel. Additionally, it was decided that the financial resources allocated for this payment would be decoupled from payroll, being treated independently and made available through a benefits management application. This structure aims to ensure greater predictability, budgetary control, and efficiency in the process execution, minimizing operational risks and strengthening the satisfaction of the involved *stakeholders*. The decoupling from payroll and the use of a dedicated application represent a significant advancement in the agility and transparency of the process, eliminating bureaucracy and reducing reimbursement waiting times, which directly impacts the employee’s quality of life and financial planning. This approach aligns with best practices in cost management and value creation in projects, which seek to optimize resources and increase the predictability of results (Vargas, 2018).
In the context of implementing the new advance ticket procurement process, the Human Resources department was assigned the responsibility for creating accounts and guiding the workforce on the use of the benefits management application. The logistics department was tasked with defining and validating, together with the Operations Coordination, the updated ticket value for each employee’s travel. In turn, the Finance department, based on reports containing the number of planned trips for each professional and the costs corresponding to travel between the city of origin and the boarding location, assumed responsibility for advance payment to employees. This division of responsibilities reflects a structured project management approach, where the clear definition of roles, processes, and information flows aims at risk mitigation, operational efficiency, and the satisfaction of the *stakeholders* involved. Figure 5 illustrates the new ticket procurement flow.
Source: Original research results
Figure 5. New advance ticket supply flowchart
It is observed that, in the new early ticket supply flow, there was a significant reduction in manual interactions, especially in the Logistics and Financial sectors, where manual review of reimbursement vouchers became unnecessary. The change in the ticket supply flow in a coordinated manner and in accordance with PDCA principles brought a significant reduction in rework to the project, a result also achieved by Carmo (2025). This operational simplification resulted in the relief of teams, allowing human resources and time previously dedicated to manual control activities to be directed to other strategic fronts of the organization. Furthermore, the new process was widely communicated to the workforce throughout January 2024 and its effective implementation occurred from February 2024. This change reflects process optimization practices, effective communication with stakeholders, and efficient resource management, contributing to the reduction of operational risks and increased organizational efficiency. Clarity in defining responsibilities and the automation of critical steps are key elements for improving interfunctional communication and eliminating redundant activities, as advocated by Slack, Chambers, and Johnston (2009).
As expected in any organizational change process, the implementation of the new advance ticket supply flow presented setbacks, including difficulties for employees in using the benefits management application and in executing ticket purchases through the platform. To mitigate these challenges, a humanized and dedicated support channel was made available to clarify doubts and guide the workforce on the new process. The creation of this support channel was a strategic action in the *Act* phase of the PDCA cycle, demonstrating the organization’s ability to adapt and respond to stakeholder needs during the transition. Despite these initial difficulties, a significant positive impact was observed, evidenced by greater employee acceptance of the process, a significant reduction in complaints, and an immediate decrease in no-show cases. These results demonstrate the effectiveness of change management practices, stakeholder communication, and performance indicator monitoring in the execution of process improvement projects. Table 2 illustrates the no-show rates between February 2024 and January 2025.
Table 2. Monthly no-show index 2024-2025
|
Month |
Shipments |
Absentees |
Index (%) |
Estimate of Losses (R$) |
|
Feb/24 |
3207 |
81 |
2,53% |
BRL 1,212,347.99 |
|
March/24 |
3570 |
57 |
1,60% |
BRL 766,386.55 |
|
Apr/24 |
3542 |
49 |
1,38% |
BRL 644,031.62 |
|
may/24 |
3767 |
34 |
0,90% |
BRL 433,236.00 |
|
Jun/24 |
3426 |
41 |
1,20% |
BRL 574,430.82 |
|
Jul/24 |
3577 |
27 |
0,75% |
BRL 362,314.79 |
|
Aug/24 |
3406 |
23 |
0,68% |
BRL 324,133.88 |
|
Sep/24 |
3603 |
35 |
0,97% |
BRL 466,278.10 |
|
Oct/24 |
3752 |
16 |
0,43% |
BRL 204,690.83 |
|
Nov/24 |
3496 |
19 |
0,54% |
BRL 260,869.57 |
|
12/24 |
3693 |
61 |
1,65% |
BRL 792,851.34 |
|
Jan/25 |
3862 |
29 |
0,75% |
BRL 360,435.01 |
|
Sum |
42901 |
472 |
BRL 6,402,006.50 |
Source: Original research results
It is observed that, after the implementation of the restructuring of the ticket provision process, there was a significant reduction in the rate of boarding *no-shows*. The indicator showed a drop from the average of 2.63% recorded in 2023 (Table 1) to 1.11% in the corresponding period of 2024 and January 2025 (Table 2), representing an approximate reduction of 57.8% in occurrences. This decrease is a direct testament to the effectiveness of the new approach, translating into greater punctuality and availability of professionals for offshore operations. Furthermore, the project’s results have exceeded operational performance, reflecting positively on the mitigation of revenue losses associated with the absence of professionals on board and on the elevation of customer satisfaction levels, evidencing the generation of organizational value resulting from the initiative. The reduction in *no-shows* not only avoided the fines and revenue losses observed in 2023 but also strengthened the company’s reputation as a reliable and efficient partner.
The questionnaire applied to the company’s employees also aimed to ascertain their perceptions of the process changes, as can be seen below. The analysis of Figures 7 and 8, in particular, offers a valuable perspective on the change in the employee experience.
Source: Original research results
Figure 6. History of intercurrences with the early provision of tickets
It is observed that, after the implementation of the change in the process, 92.47% of employees stopped reporting problems related to ticket reception, while only 7.53% indicated the occurrence of some type of incident. These results highlight a significant change in the perception of internal *stakeholders*, since, as presented in Figure 2, 94.62% of professionals had previously experienced difficulties associated with the ticket reimbursement process. This evolution reflects a relevant increase in the satisfaction index and an improvement in the quality perceived by employees, who are the clients of the process, resulting from its restructuring based on PDCA principles, as also observed by Pelissari and Benatto (2020). The drastic reduction in problems from almost 95% to less than 8% demonstrates that the new methodology effectively addressed the root causes of previous dissatisfactions, promoting an environment of greater trust and predictability.
Source: Original research results
Figure 7. History of shipping delays due to problems with early ticket receipt
Additionally, the analysis of Figure 7 demonstrates that only 2.15% of respondents failed to board due to issues inherent in the new advance ticket provision process, representing a substantial reduction when compared to the 61.29% of employees who, in the previous model (Figure 3), reported boarding impediments due to failures in the reimbursement process. This sharp drop in *no-shows* for financial reasons is one of the project’s most impactful results, evidencing not only improved operational efficiency but also a positive social impact, by alleviating the financial burden on employees and ensuring their ability to meet their professional obligations.
The analysis of Figure 8 shows that the process of advance ticket provision is perceived as clear by 93.55% of the participating collaborators in the research, while 5.38% consider it unclear and only 1.08% do not perceive it as clear.
Source: Original research results
Figure 8. Clarity in the advance passage provision process
This level of understanding is directly associated with the communication strategy adopted in the project, especially with the implementation of an exclusive channel for clarifying doubts, a resource that did not exist in the previous model based on reimbursements. The clarity of the process, which went from a scenario where most considered it little or not at all clear (Figure 4) to almost total clarity, is fundamental for reducing errors, increasing employee autonomy, and decreasing the workload of support departments.
Source: Original research results
Figure 9. Employees’ perception of the change in the ticket supply process
Furthermore, as illustrated in Figure 9, 87.1% of respondents assess that the transition of the ticket payment process – from the reimbursement model to advance provision – contributed positively to the planning of their departures, while 10.75% were indifferent and only 2.15% identified no benefits. These results corroborate the significant increase in the satisfaction level of internal stakeholders, evidencing that the process change not only made the operational flow more practical but also positively impacted the project’s overall performance. The improvement in employees’ planning capacity, which was previously compromised by reimbursement uncertainty, is now a differential that contributes to punctuality and individual organization, reflecting in better collective performance.
In the context of implementing the new advance ticket procurement process, the organizational impacts were considered minimal, as the necessary resources – both human and technological – were already available and were merely reorganized to meet the project’s demands. From a financial perspective, cash flow had to be advanced to enable the early procurement of resources. However, over time, the financial flow stabilized and became predictable, a result of detailed and advance planning of all shipments, as well as precise estimation of the values involved. This experience highlights the importance of resource management and financial planning in project execution, ensuring operational sustainability and mitigating risks associated with process change. As also observed by Pelissari and Benatto (2020), the use of PDCA for standardizing the new process brought improvement in its predictability, as well as greater operational stability. The ability to reallocate existing resources and optimize cash flow, instead of incurring large investments, demonstrates efficient and strategic change management.
It should be highlighted that the analyzed organization acted as a pioneer, among companies with similar portfolios in the region, by promoting the transition of the ticket supply process from a reimbursement model to an advance supply model, within the context of a structured project management initiative. As a result of the achievements, especially the significant reduction in the *no-show* rate, the company was invited by its main client to present the motivations and critical success factors associated with the implemented change. Subsequently, the actions adopted in the project were disseminated, through the client, to other organizations in the sector, enabling the evaluation and eventual replication of the implemented practices, characterizing a process of diffusion of best practices and value generation at an interorganizational level. This external validation and the ability to become a *benchmark* reinforce the project’s success and the company’s project management maturity, transforming an operational problem into a competitive advantage and a model to be followed in the offshore industry. The systematic application of PDCA, as Carmo (2025) also observed, allowed not only the identification of weaknesses but also the proposition of structured corrective actions that promoted greater operational stability and a lasting positive impact.
4. Conclusion
It is concluded that the objective was achieved by successfully applying the principles of project management, based on the PDCA cycle, to analyze and restructure the logistical process of anticipating and automating the supply of tickets and the prior granting of resources for offshore personnel transportation. The intervention proved to be highly effective, transforming a costly and failure-prone model into a standardized and predictable system. The results obtained were significant, with a 57.8% reduction in no-show rates, a substantial increase in employee satisfaction, and the mitigation of substantial financial losses. The organization not only optimized its operational efficiency but also consolidated itself as a benchmark in the sector, demonstrating the generation of sustainable value and maturity in change management.
However, the present study presents important limitations, mainly due to the absence of reliable information on no-show rates prior to 2023 and the lack of systematic monitoring of customer notifications before this period, which restricted the scope of the analyses. For future studies, the development of robust quantitative models is suggested. These models could more accurately assess the financial impact of anticipating logistical resources, measuring the relationship between advanced planning, reduction of operational costs, and return on investment in offshore operations, deepening the understanding of the economic benefits of restructuring.
Bibliographic References
Ballou, R. H. 2006. Logística Empresarial: Transportes, Administração de Materiais e Distribuição Física. 5ed. Bookman, São Paulo, SP, Brasil.
Bowersox e Closs, 2006 [Referência completa não encontrada no documento original]
Bowersox, D. J.; Closs, D. J.; Cooper, M. B. 2006. Gestão Logística de Cadeias de Suprimentos. Bookman, Porto Alegre, RS, Brasil.
Chopra, S.; Meindl, P. 2019. Gestão da Cadeia de Suprimentos: Estratégia, Planejamento e Operação. 7ed. Pearson, São Paulo, SP, Brasil.
Kerzner, H. 2017. Gestão de Projetos: As Melhores Práticas. 3ed. Bookman, Porto Alegre, RS, Brasil.
Project Management Institute [PMI]. 2017. Guia PMBOK®: Um Guia do Conhecimento em Gerenciamento de Projetos. 6ed. PMI, Pennsylvania, EUA.
Slack, N.; Chambers, S.; Johnston, R. 2009. Administração da Produção. 3ed. Atlas, São Paulo, SP, Brasil.
Thiollent, M. 2011. Metodologia da Pesquisa-Ação. 18ed. Cortez, São Paulo, SP, Brasil
Article originating from the Final Course Project of the Specialization in Project Management of the MBA USP/Esalq