Earned value management of projects in companies with low data maturity
João Victor Oliveira de Jesus; Paulo Vitor Dos Santos Gonçalves
DOI: 10.22167/2675-6528-202603850
Article derived from a Final Course Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.
Summary
The monitoring of projects in medium-sized industrial companies with low data maturity represents a significant challenge, as the absence of structured tools compromises decision-making based on indicators. An integrated solution for project monitoring was developed, consisting of a data entry interface in Microsoft Excel and a dashboard in Microsoft Power BI, based on the Earned Value Management methodology. The solution was designed to offer cost, schedule, and operational efficiency indicators without the need to acquire commercial project management software. The research was characterized as a single case study, with an applied approach, conducted in a medium-sized multinational company manufacturing industrial machinery and equipment. Secondary data were extracted from ten projects executed between 2023 and 2026, covering costs, hours, and lifecycle milestone dates. The interface was automated by VBA macros, and the dashboard was organized with a portfolio view and individual project analysis. To objectively estimate physical progress, the weighted milestones technique was adopted. The results demonstrated that the solution generated performance indicators, allowing for the identification of deviations such as actual costs exceeding the approved budget by approximately 76% and delays of up to 118 days, as well as enabling the monitoring of indicator evolution throughout execution. It was concluded that the solution is replicable as a proof of concept for organizations in similar contexts.
Keywords: Business Intelligence; Performance indicators; Weighted milestones; Small and medium-sized enterprises; Power BI.
1. Introduction
In industrial companies whose business model depends on project execution, profitability is directly linked to the ability to deliver within the contracted cost and deadline. In these situations, achieving continuous profitability is not just a goal, but an essential condition for market survival. Thus, long-term profit is linked to the organization’s ability to structure and execute projects that expand its revenue potential, while controlling the associated costs (Kaufmann and Kock, 2022).
According to the Project Management Institute (2021), a project is a temporary endeavor, with a defined beginning and end, aimed at creating a unique product, service, or result. Project management is the application of knowledge, tools, and techniques to meet the defined project requirements. Key performance indicators, known by the English acronym Key Performance Indicator (KPI), are metrics used to evaluate the efficiency of a project, allowing the quantification of aspects of interest (Project Management Institute, 2021).
The interest in data analysis has been growing constantly, driven by scientific and technological development. Data analysis is recognized as an agent that generates value for organizations and drives innovation and the economy (Cao, 2017). It integrates different areas of knowledge, such as statistics and computer science, to obtain business insights that support decision-making (Bruce and Bruce, 2019). In this context, Business Intelligence (BI) represents the set of tools and methodologies designed to structure this process, facilitating access, visualization, and interpretation of information.
One of the solutions used for data visualization is dashboards, which present consolidated information on a single page, so that managers can understand complex data and make decisions dynamically (Zheng, 2017). Although a study by the International Data Corporation (IDC, 2020) indicates that Brazilian companies that use data for decisions reported a 16% increase in operational efficiency, small and medium-sized enterprises (SMEs) face significant challenges in implementing BI processes. Such challenges include resource limitations (Bouwman et al., 2019) and the disbelief of senior management regarding the advantages of using data (Božič and Dimovski, 2019). Consequently, the use of BI may not generate a significant improvement in operational efficiency if it is not implemented properly (Perdana et al., 2022).
Earned Value Management (EVM) emerges as a structured methodology for project monitoring, even in environments with limited resources. It simultaneously integrates cost and schedule dimensions into a reduced set of quantitative indicators (Project Management Institute, 2020). The methodology is based on four fundamental variables: Planned Value (PV), Actual Cost (AC), Earned Value (EV), and Budget at Completion (BAC) (Project Management Institute, 2020). However, the practical application of EVM faces operational barriers related to data collection and updating, making the development of automated systems a way to expand its applicability in industrial environments (López Pascual et al., 2021).
In this scenario, where 92% of companies use Microsoft Excel and 26% adopt Microsoft products as a basis for Business Intelligence (Fundação Getúlio Vargas, 2025), this work stems from the need of a medium-sized industrial company, with low data maturity, to monitor its projects with greater objectivity without immediately implying investment in commercial management software. The company studied recorded information in spreadsheets and documents, but without consolidation that would allow systematic project monitoring. The proposal was to build a solution from these already available tools, allowing the organization to evaluate the impact of data usage on its results before any additional investment. The present work aims to develop an integrated project monitoring solution for a medium-sized industrial company with low data maturity, consisting of a data entry interface in Microsoft Excel and a dashboard in Microsoft Power BI based on the Earned Value Management methodology, capable of offering cost, schedule, and operational efficiency indicators without requiring the acquisition of specific commercial project management software.
2. Material and Methods
The research was characterized as a single case study, of an applied nature, with the purpose of developing an integrated project monitoring solution. The study was conducted in a medium-sized multinational company, a manufacturer of industrial machinery and equipment, located in the metropolitan region of São Paulo. The company had 60 employees and presented low data maturity, recording project information dispersedly in spreadsheets and documents.
The methodological approach aimed at developing a tool capable of improving the quality of project records, promoting effective monitoring, and supporting data-driven decision-making. To this end, the research strategy employed bibliographic research and the survey of secondary data. The bibliographic research used keywords such as KPI, SME, Business Intelligence, project management, earned value management, decision making, and firm performance to support the construction of the tool.
In the secondary data collection stage, information was extracted from ten projects executed by the company between July 2023 and February 2026. The data were obtained from documents available on the company’s server, which included quotes, sales calculations, purchase orders, meeting minutes, schedules, current project status, technical acceptances, and lessons learned upon project completion.
To ensure confidentiality, information identifying clients, materials, and equipment was anonymized. The original project values were also adjusted to preserve the proportions and trends of the dataset, without representing the actual numbers. This data was organized into a structured database in Microsoft Excel, which served as the primary source for the developed solution.
The data entry interface was developed in Microsoft Excel, using platform features combined with automations programmed in Visual Basic for Applications (VBA). The choice of Microsoft Excel was justified by its wide adoption in organizations and the absence of the need to install additional software, aligning with the study’s low implementation cost proposal.
The solution in Excel was structured into four distinct tabs within a single workbook. The “Form” tab served as the data entry interface, where the project manager registered the information. The “Database” tab stored the records in a tabular format, with one row per project. The “Project History” tab recorded, at each update, the current cost and actual hours by area, along with the date and time of the record, allowing for monitoring of indicator evolution.
The “Form” was organized into four blocks of information: project identification (equipment code, type, and model), costs (estimated, current, and final), hours (planned and actual for manufacturing, installation, commissioning, coordination, and engineering), and dates (manufacturing start and end, project start and end, planned and signed technical acceptance). To standardize data entry and reduce errors, the identification fields were configured with list-type data validation, automatically updated with each new record.
The interface automation was implemented through three main macros, triggered by buttons on the spreadsheet itself: “Save Project”, “Search Project”, and “Clear”. The “Save Project” macro checked for the existence of the project code, updating fields or inserting a new row, and simultaneously registered an entry in the “Project History” tab. The “Search Project” macro retrieved data from an existing project, and the “Clear” macro erased the content of the form fields.
The dashboard was developed in Microsoft Power BI, a data visualization and analysis tool. The choice of Power BI was justified by its integration with Microsoft Excel, allowing the database to serve as a direct source, without the need for intermediate transformations. The tool enabled the creation of interactive visualizations, with automatic updating of indicators each time new data was registered in the Excel tool.
The dashboard was structured into two pages with distinct purposes, based on the Earned Value Management (EVM) method. The first page, named “Overview”, presented indicators for all projects simultaneously, offering a quick read of the portfolio. The second page, “EVM Analysis”, applied the earned value method to an individually selected project by the user, as recommended by the literature (Project Management Institute, 2020).
On the “Overview” page, indicators were presented such as total approved budget, actual cost, cost variance, planned versus actual hours by area (engineering, coordination, manufacturing, installation, commissioning), number of delayed projects, and the Hours Cost Performance Index (Hours CPI). The latter, although not an integral part of EVM, was included to monitor the efficiency of the team’s time usage, calculated by the ratio between total planned and actual project hours (Project Management Institute, 2020).
The “EVM Analysis” page applied the EVM method, based on variables such as Planned Value (PV), Actual Cost (AC), Earned Value (EV), and Estimate at Completion (EAC) (Project Management Institute, 2020). Derived indicators such as Cost Variance (CV), Schedule Variance (SV), Cost Performance Index (CPI), Schedule Performance Index (SPI), Estimate to Complete (ETC), Estimate at Completion (EAC), and Variance at Completion (VAC) were calculated. The visual organization of the EVM indicators was designed in a three-layer matrix (fact, diagnosis, and projection) and two thematic columns (cost and schedule), with color differentiation by layer, aiming to reduce the user’s cognitive load.
To estimate the physical progress of the projects, the weighted milestones technique was adopted, recognized by the Project Management Institute (2020) as an objective alternative for estimation without dependence on subjective evaluations (Fleming and Koppelman, 2010). Four milestones were defined corresponding to the project lifecycle phases of the company: manufacturing, installation, commissioning, and technical acceptance. Accumulated percentage weights were assigned to these milestones, with distinct configurations for projects with and without a manufacturing phase.
The calculation of the Earned Value (EV) was performed automatically by the formula EV = milestone percentage × Budget at Completion (BAC). The milestone percentage was determined by the most recent milestone achieved, automatically detected by the dashboard based on the planned hours for the manufacturing phase. The Planned Value (PV) was calculated based on the elapsed time relative to the total planned project duration, using the planned technical acceptance date as the expected completion milestone.
The connection between the Excel tool and Power BI was configured so that any update in the data input interface would be automatically reflected in the dashboard after the data source update. This integration ensured that the indicators presented in the dashboard reflected the most recent state of the project portfolio registered in the tool, aligning with the objective of offering indicators of cost, deadline, and operational efficiency without requiring the acquisition of specific commercial project management software.
3. Results and Discussion
The research gathered and analyzed data from ten projects executed between July 2023 and February 2026, with the objective of developing an integrated monitoring solution. Of these projects, seven included the local manufacturing phase, while three were restricted to the installation and commissioning stages. The portfolio encompassed six distinct equipment models, categorized into four types, reflecting the diversity of the company’s operations. It is important to note that projects without a manufacturing phase did not have records of hours or start and end dates for this stage, which was considered in the adaptation of the methodology.
The data entry interface, developed in Microsoft Excel, was structured into four main blocks: project identification, costs, hours, and dates. The identification block allowed for the registration of the equipment code, type, and model. The costs section captured the estimated cost, current cost, and final project cost, while the hours block detailed the planned and actual hours for the areas of manufacturing, installation, commissioning, coordination, and engineering. The planned and actual start and end dates for manufacturing and the project, as well as the planned and actual technical acceptance dates, were recorded in the dates section, providing the essential temporal milestones for monitoring.
To optimize data entry and minimize errors, project identification fields, such as equipment type and model, were configured with dynamic dropdown lists. These lists were automatically updated with newly entered values, ensuring the standardization and consistency of information. Automation was implemented through VBA macros, triggered by buttons such as “Save Project”, “Search Project”, and “Clear”, which facilitated data registration, consultation, and updating, including the history of costs and hours with each update.
The history functionality, although not validated with real data from closed projects due to the punctual collection of information, was demonstrated through a fictitious project (P014) with simulated updates. This simulation illustrated the tool’s ability to record the evolution of the current cost and accumulated actual hours by area over time. This capability is crucial for monitoring trends and anticipating deviations, allowing for more dynamic analysis of project performance before its closure, which represents a significant improvement over the company’s previous practices.
The secondary data collected, although anonymized to preserve confidentiality, were organized into a database that served as the source for the dashboard. This organization included detailed information on project identification and costs, planned and actual hours per work area, and project lifecycle milestone dates. This structuring was fundamental for feeding the calculations of cost, schedule, and operational efficiency performance indicators, according to the Earned Value Management methodology.
Page 1: Overview
The first page of the dashboard, named “Overview”, offered a consolidated perspective of the project portfolio, allowing for a quick analysis of the main indicators. It was observed that the total budget approved for the ten projects amounted to approximately R$ 5.9 million, while the actual cost reached about R$ 6 million. This difference resulted in a negative cost variance of approximately R$ 120.56 thousand for the portfolio, indicating an overall budget overrun.
The detailed analysis revealed that five out of ten projects exceeded the planned budget, with project P004 showing the largest deviation, where the actual cost surpassed the approved budget by approximately 76%. This finding underscores the importance of continuous cost monitoring to identify and correct deviations. The dashboard used conditional color formatting for cost variation, visually alerting the manager to projects with financial performance below expectations.
Regarding operational efficiency, the average Cost Performance Index for Hours (CPI Hours) for the portfolio was 0.73, indicating that, on average, the team consumed more hours than planned to complete the scope. This indicator, although not part of EVM, was included due to its relevance for industrial companies, according to Kerzner (2017), who emphasizes labor efficiency. Projects such as P009 and P008 were the least efficient, with CPI Hours of 0.41 and 0.40, respectively, demonstrating the indicator’s ability to differentiate efficiency levels.
The individual analysis of the projects revealed that P002 presented an Hours IDC of 1.50, suggesting a possible overestimation of the planned effort in the budgeting phase, rather than more efficient execution. This finding highlights the need to review the hour estimation criteria to align planning with actual execution conditions. On the other hand, project P001, which did not record manufacturing hours, showed a delay of 118 days, the longest among the analyzed projects, evidencing challenges in meeting deadlines.
The bar chart comparing the Total Approved Budget and the Actual Cost per project allowed for visual identification of projects with the largest cost deviations. Project P003, for example, showed an actual cost significantly higher than budgeted, with a negative variance of approximately R$ 141 thousand. This visualization, complemented by the Cost Variance chart, facilitated the understanding of the magnitude of financial deviations in each project.
The Project Hours chart detailed the comparison between planned and actual hours by area, allowing for the identification of specific effort deviations. In project P004, the actual commissioning hours (617.83 hours) exceeded the planned hours (367.40 hours), which may explain part of the budget overrun. This granularity in the analysis is fundamental for managers to identify the root causes of deviations and implement targeted corrective actions.
The consolidated table on the “Overview” page presented a summary of each project’s indicators, including code, status, Budget at Completion (BAC), Actual Cost (AC), Cost Variance (CV), delay in days, and Hours IDC. This table allowed for direct data consultation, confirming an 118-day delay in project P001. Together, the indicators and visualizations on this page enabled the manager to quickly identify projects with deviations in cost, schedule, or operational efficiency, without the need to apply the earned value method individually to each project in the portfolio.
Page 2: EVM Analysis
The second page of the dashboard, “EVM Analysis”, applied the Earned Value Management method to individually selected projects, as recommended by the Project Management Institute (2020) for project control. The indicators were organized into cost groups (Budget at Completion, Actual Cost, Cost Variance, Cost Performance Index, Estimate at Completion, and Estimate to Complete) and schedule/progress groups (Planned Value, Earned Value, Schedule Variance, Schedule Performance Index, and Variance at Completion).
An important distinction in “Earned Value Analysis (EVA)” is the calculation of Cost Variance (CV), which is the difference between Value Added (VA) and Actual Cost (AC), following the formal definition of the method. This differs from the CV presented in the “Overview”, which compares the Budget at Completion (BAC) with the Actual Cost (AC). This approach ensures that the indicators are interpreted in the context of the value effectively added by the project, providing a more accurate performance analysis.
To objectively estimate the physical progress of projects, without relying on subjective judgments, the weighted milestones technique was adopted, according to the Project Management Institute (2020) and Fleming and Koppelman (2010). Four milestones were defined in the project lifecycle: manufacturing, installation, commissioning, and technical acceptance, with distinct accumulated percentage weights for projects with and without a manufacturing phase. Earned Value (EV) was automatically calculated based on the percentage of the milestone achieved and the Estimate at Completion (EAC).
The application of the method was illustrated with project P004, which had already concluded in the technical acceptance phase. In this case, the Earned Value (EV) of R$ 159.45 thousand equaled the Budget at Completion (BAC), while the Actual Cost (AC) reached R$ 280.08 thousand. This relationship resulted in a negative Cost Variance (CV) of R$ 120.63 thousand and a Cost Performance Index (CPI) of 0.57, confirming that the project consumed resources significantly above the earned value, a deviation already identified in the portfolio analysis.
Regarding the deadline for project P004, the Planned Value (PV) reached R$ 195.36 thousand, exceeding the budget itself at the end. This scenario occurred because the project surpassed the planned technical acceptance date, causing the PV to exceed 100%, signaling a delay in terms of value. Consequently, the Schedule Variance (SV) was negative at R$ 35.90 thousand and the Schedule Performance Index (SPI) was 0.82, both confirming delivery later than planned, in line with the 118-day delay recorded in Table 6.
To demonstrate continuous performance monitoring, the fictitious project P014 was used, with simulated updates in different phases. In the manufacturing phase, the Added Value (AV) corresponded to 40% of the budget, totaling R$ 400 thousand, while the Actual Cost (AC) was R$ 389.02 thousand. This resulted in a positive Cost Variance (CV) of R$ 10.99 thousand and a Cost Performance Index (CPI) of 1.03, indicating that the project remained within the planned budget for that phase.
Regarding the schedule in the manufacturing phase of P014, the Schedule Performance Index (SPI) reached 3.49, a high value that indicated an advancement compared to the schedule. This result was influenced by the proximity between the reference date and the project’s start, which generated a reduced Planned Value (PV) of R$ 114.58 thousand. Projections for the project’s completion indicated an Estimate at Completion (EAC) of R$ 972.54 thousand, lower than the approved budget, with a positive Estimate at Completion Variance (EACV) of R$ 27.46 thousand, suggesting a completion within budget.
In the transition to the installation phase of project P014, the Earned Value (EV) advanced to 65% of the budget, reaching R$ 650 thousand, but the Actual Cost (AC) rose to R$ 803.05 thousand. This cost increase resulted in a negative Cost Variance (CV) of R$ 153.05 thousand and a Cost Performance Index (CPI) of 0.81, evidencing a loss of cost efficiency compared to the previous phase. The Schedule Performance Index (SPI) receded to 1.62, although the project still remained ahead of schedule, but less so.
The worsening cost performance in the installation phase of P014 was reflected in the projections: the Estimate at Completion (EAC) rose to R$ 1.24 million, exceeding the approved budget, and the Variance at Completion (VAC) became negative at R$ 235.45 thousand, indicating a possible budget overrun. This comparison between phases demonstrated the main contribution of the history functionality, which allows monitoring the trajectory of indicators throughout execution and anticipating performance deterioration, something that would not be possible in a static closure analysis.
The solution architecture, based on the integration between Microsoft Excel and Microsoft Power BI, aligns with the proposals of Kalina et al. (2025), who highlight the financial unviability of commercial Business Intelligence solutions for Small and Medium-sized Enterprises (SMEs). The choice of these tools, already widely used in the company, reduced licensing costs and the need for additional technical training, favoring the adoption and use of the tool, as pointed out by Fundação Getúlio Vargas (2025).
This approach contributed to overcoming the challenges in implementing Business Intelligence in SMEs, such as the lack of understanding about analytical tools, according to Perdana et al. (2022). By reusing familiar tools and automating the calculation of indicators, the solution reduced the dependence on specialized technical knowledge and adoption effort, directly addressing the risk factors for the success of BI implementations identified by Williams and Sheikh (2022).
The main methodological contribution of the work lay in the adoption of the weighted milestones technique for measuring the physical progress of projects. Unlike solutions that rely on subjective manager estimates, such as that described by Rosa and Alturas (2020), the proposed method allowed for the objective calculation of Earned Value. This enabled the application of Earned Value Management in a context of low data maturity, preserving the conceptual consistency of the methodology and providing more reliable indicators.
In summary, the developed solution proved effective in generating performance indicators for cost, schedule, and operational efficiency for project monitoring. The results showed significant deviations in the analyzed portfolio, such as the actual cost exceeding the approved budget by approximately 76% in a specific project and delays of up to 118 days in others. The history functionality, exemplified by the fictitious project P014, demonstrated the potential to track the evolution of indicators, allowing for the anticipation of performance deteriorations and supporting corrective decisions throughout project execution, thus responding to the objective of developing a tool that offers objective and accessible monitoring.
4. Conclusion
This study aimed to develop an integrated solution for project monitoring in a medium-sized industrial company with low data maturity, using Microsoft Excel for information input and Microsoft Power BI for a dashboard based on Earned Value Management. It was found that the solution generated cost, schedule, and operational efficiency performance indicators, revealing significant deviations in the analyzed portfolio. It was observed that five out of ten projects exceeded the budget, with one specific case exceeding the forecast by approximately 76%, and six projects experienced delays of up to 118 days. The history functionality, demonstrated through a simulated project, indicated the ability to track the evolution of indicators throughout execution, allowing for the anticipation of performance deteriorations and support for corrective decisions. The main methodological contribution lay in the adoption of the weighted milestones technique for objective measurement of physical progress, which enabled the consistent application of Earned Value Management in an environment with limited data, without the need for specific commercial software.
However, a limitation of the study was the punctual collection of secondary data, which prevented the validation of the history functionality with real records of ongoing projects. It is suggested that future research validate this functionality in continuous use and evaluate the applicability of the solution in other industrial contexts, in order to deepen the conclusions presented. By employing widely available tools already integrated into the organizational routine, the developed solution demonstrates a replication potential as a proof of concept for organizations with a similar profile, offering an accessible alternative to improve project management and data-driven decision-making.
Bibliographic References
Bouwman, H.; Nikou, S.; de Reuver, M. 2019. Digitalization, business models, and SMEs: how do business model innovation practices improve performance of digitalizing SMEs? Telecommunications Policy 43(9): 101828.
Božič, K.; Dimovski, V. 2019. Business intelligence and analytics for value creation: the role of absorptive capacity. International Journal of Information Management 46(1): 93-103.
Bruce, P.; Bruce, A. 2019. Estatística prática para cientistas de dados: 50 conceitos essenciais. 1ed. Alta Books, São Paulo, SP, Brasil.
Cao, L. 2017. Data science: a comprehensive overview. ACM Computing Surveys 50(3): 1-42.
Fleming, Q.W.; Koppelman, J.M. 2010. Earned value project management. 4ed. Project Management Institute, Newtown Square, PA, EUA.
Fundação Getúlio Vargas [FGV]; Meirelles, F. 2025. Pesquisa do uso de TI – tecnologia de informação. Disponível em: <https://eaesp.fgv.br/sites/eaesp.fgv.br/files/u68/pesti_fgvcia_2025.pdf>. Acesso em: 04 nov. 2025.
International Data Corporation [IDC]; Vesset, D. 2020. Data as the new water: the importance of investing in data and analytics pipelines. Disponível em: <https://www.polestarllp.com/docs/data-is-the-new-water.pdf>. Acesso em: 28 out. 2025.
Kalina, V.; Lhota, J.; Kalender, Z.T. 2025. Effective project portfolio management for SMEs: a conceptual framework using business intelligence tools. Procedia Computer Science 253: 745-756.
Kaufmann, C.; Kock, A. 2022. Does project management matter? The relationship between project management effort, complexity, and profitability. International Journal of Project Management 40(1): 624-633.
Kerzner, H. 2017. Project management: a systems approach to planning, scheduling, and controlling. 12ed. John Wiley & Sons, Hoboken, NJ, EUA.
López Pascual, J.; Meléndez Rodríguez, J.C.; Cruz Rambaud, S. 2021. The enhanced-earned value management (E-EVM) model: a proposal for the aerospace industry. Symmetry 13(2): 232.
Perdana, A.; Lee, H.H.; Koh, S.; Arisandi, D. 2022. Data analytics in small and mid-size enterprises: enablers and inhibitors for business value and firm performance. International Journal of Accounting Information Systems 44(1): 100547.
Project Management Institute [PMI]. 2020. The standard for earned value management. Project Management Institute, Newtown Square, PA, EUA.
Project Management Institute [PMI]. 2021. Um guia do conhecimento em gerenciamento de projetos. 7ed. Project Management Institute, Newtown Square, PA, EUA.
Rosa, M.F.; Alturas, B. 2020. Solução de business intelligence na monitorização e controlo de projetos. In: 15th Iberian Conference on Information Systems and Technologies (CISTI), 2020, Sevilha, Espanha. Anais…p. 1-6.
Williams, R.A.; Sheikh, N.J. 2022. Technical, organizational, and process impacts of business intelligence implementation failure. In: Portland International Conference on Management of Engineering and Technology (PICMET), 2022, Portland, Oregon, EUA. Anais…p. 1-13.
Zheng, J. 2017. Data visualization in business intelligence. In: Munoz, J.M. Global business intelligence. 1ed. Routledge, New York, NY, EUA.
Article originating from the Final Course Work of the Specialization in Project Management at POLI USP PRO