Success factors in the transition of managers in infrastructure projects in Brazil

Laura Rodrigues Mendes Bicalho; Flávia Priscila Dantas

DOI: 10.22167/2675-6528-202603837

Article derived from a Final Course Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

Infrastructure projects are characterized by their technical, organizational, and institutional complexity, demanding coordination among multiple actors. Given the growing turnover in the labor market, understanding the factors that contribute to success in the transition of managers in these ventures has become essential. The study aimed to identify the success factors in the transition of managers in infrastructure projects in Brazil. For this purpose, a quantitative approach was adopted, with a field survey design. A structured questionnaire was applied to professionals working in infrastructure projects, assessing the perception of the impact of different factors on the success of the transition using a Likert scale. 100 valid responses were analyzed. The results indicated greater relevance of factors related to the new manager’s competencies, the institutionalization of management, and knowledge management and project documentation. Structured succession planning, institutional articulation, and top management support showed relatively less prominence. It was observed that respondents in management positions attributed higher evaluations with less variability compared to team members. It was concluded that elements more directly linked to project execution tend to assume a central role in the perception of transition success.

Keywords: Civil construction; Project continuity; Project management; Managerial succession.

1. Introduction

The provision of infrastructure, which encompasses sectors such as energy, transportation, telecommunications, water supply, and sanitation, is widely recognized as a fundamental pillar for economic growth and social well-being, especially in developing economies (IPEA, 2022). In the Brazilian context, the importance of this sector is evidenced by significant investments, approaching R$266.80 billion, representing about 2.27% of the national Gross Domestic Product (GDP) in 2024 (CNI, 2025).

In infrastructure projects, the managers’ performance is considered crucial for the success of the ventures, given the relevance of their technical and relational leadership (Parker and Skitmore, 2005; Dubber and Pretorius, 2016). However, these projects are marked by complex challenges, including cost, deadline, and quality control, high technical complexity, multidisciplinary interfaces, management of multiple stakeholders, and compliance with environmental regulations (Hordieieva et al., 2024). In Brazil, these challenges are aggravated by sociopolitical complexity and the sector’s low technological maturity (Pereira and Gomide, 2019; BIM Fórum Brasil, 2024).

Institutional fragmentation and low coordination between government spheres compromise decision alignment and regulatory predictability (Pereira and Gomide, 2019), hindering decision-making and risk analysis. The limited adoption of technologies and the lack of standardization and integration of data and processes result in design errors, rework, and delays (BIM Fórum Brasil, 2024). Such barriers indicate that the sector needs management mechanisms that ensure continuity, integration, and knowledge transfer, not just isolated technical solutions.

The importance of effective management and planning is reinforced by data such as that from the Federal Court of Accounts (TCU), which identified recurring delays in federal highway works, associated with the absence of detailed goals and schedules and the low quality of projects (TCU, 2024). A study by Oxford Global Projects (2023) of 193 federal highway projects in Brazil, executed between 2005 and 2021, revealed an average delay of 103%, contrasting with significantly lower averages in other regions of the world. The relevance of project management is also evident in academic training, with institutions such as the Association for Project Management (APM, 2018; APM, 2025) and the Engineering Council (2025) integrating project management competencies into their curricula.

In this scenario, the turnover of managers in civil construction projects negatively impacts the progress and success of the ventures, especially when it occurs during the execution phase (Parker and Skitmore, 2005; Dubber and Pretorius, 2016; Davis et al., 2021). The consequences include communication failures, loss of focus, team overload, delays, increased costs and risks, as well as loss of information and reduced client confidence. Project management continuity, therefore, should be treated as a strategic factor. A survey by the consulting firm Robert Half (2025) indicated that 56% of salaried professionals in Brazil changed jobs in the last twelve months, highlighting a scenario of growing professional mobility.

Given this context, it becomes essential to understand how to mitigate the negative effects of manager replacement in complex ventures, such as infrastructure projects. Although the literature addresses the causes and consequences of manager replacement (Parker and Skitmore, 2005; Altamimi, 2024; Davis et al., 2021; Pinto, Davis and Turner, 2024) and there are Brazilian studies on knowledge management (Gonçalves, 2017; Souza, 2021; Almeida and Gomes, 2025), success factors (Pacagnella Junior et al., 2018; Arrotéia, 2022; Barbosa and Muÿlder, 2024), project manager competencies (Gabriel et al., 2018; Shimabuku et al., 2019; Silveira et al., 2022; Rosamilha, 2023), and causes of turnover (Gallon et al., 2021), there is a research gap that directly addresses manager turnover and continuity practices in civil construction projects in Brazil. Thus, this study is justified by the need to deepen the understanding of the conditions that favor project continuity in this process, contributing to the reduction of negative impacts and the improvement of management. Therefore, the objective of this study is to identify the success factors in manager transition in infrastructure projects in Brazil.

2. Material and Methods

The present research was characterized by its applied nature, seeking to generate practical contributions to the area of infrastructure project management. A quantitative methodological approach was adopted, considered adequate for studies that aim to measure perceptions, identify patterns, and compare results among different groups of participants through statistical analysis of the collected data (Sampieri et al., 2013).

The design employed was the field survey, known as survey, a method characterized by obtaining information directly from respondents through standardized questionnaires (Babbie, 1999). The sampling used was non-probabilistic convenience sampling, due to accessibility to participants and the time available for data collection.

The study development was structured in two main stages. In the first, an exploratory bibliographic research was carried out. This stage involved the analysis of scientific articles, books, dissertations, and theses relevant to the area of project management, with the purpose of understanding the literature’s approach to manager transition and identifying success factors and recurring difficulties in infrastructure projects in Brazil.

The findings of this bibliographic survey supported the definition of success factors to be investigated and the subsequent elaboration of the questionnaire. This phase was crucial for the construction of a data collection instrument aligned with academic discussions and the needs of the field of study.

In the second stage, a field survey was conducted by applying a structured questionnaire. The instrument was developed based on the factors identified in the literature review, aiming to assess professionals’ perception of the factors associated with the success of the transition of managers in infrastructure projects. The factors were represented by statements elaborated from the literature.

The questionnaire assertions were evaluated using a five-point Likert scale, where the value 1 indicated very low impact and the value 5, very high impact. This scale was chosen because it allowed respondents to indicate the degree of impact of each factor gradually, facilitating comparison between factors (Likert, 1932; Kusmaryono et al., 2022).

The target population of the research comprised professionals working on infrastructure projects in Brazil, including managers, supervisors, coordinators, and team members. This scope aimed to collect different perspectives on leadership transition processes. Responses were obtained from professionals from various regions of Brazil, with a concentration in the Southeast.

The questionnaire was administered online, using the Google Forms platform. During the collection, the anonymity of the participants and the confidentiality of the information provided were guaranteed. Before the final dissemination, the instrument underwent a pre-test with a small group of professionals, which allowed for verification of the clarity and coherence of the statements and for making specific adjustments to their wording.

The collected data were organized and processed with the aid of Microsoft Excel software. The analysis employed descriptive statistics, including means, medians, standard deviations, and relative frequencies, to characterize the responses obtained. Comparisons were made between respondent groups, specifically between managers and team members, to observe possible differences in perception.

The data were interpreted in light of the literature that supported the development of the questionnaire, allowing the professionals’ perceptions to be contextualized. The collected information was systematically organized by calculating the average of the assertions associated with each factor for each respondent, generating a score per factor. Subsequently, descriptive measures for these factors were calculated, considering the management and technical team groups separately.

3. Results and Discussion

The analysis of the collected data revealed that manager transition is a frequent phenomenon in infrastructure projects in Brazil, with 90.9% of the professionals who participated in the survey having already experienced this process. This finding corroborates the scenario of growing professional mobility in the country, as pointed out by the consulting firm Robert Half (2025), and reinforces the relevance of investigating the factors that contribute to the success of these transitions. The survey obtained 118 responses, of which 100 were considered valid, from professionals working in infrastructure projects.

Respondent Profile

The geographical distribution of respondents indicated a strong concentration in the Southeast region, with 92% of participants operating in this area. The North and Center-West regions represented 3% each, while the South region contributed 2% of the responses, and there were no participants from the Northeast region. This regional concentration is an important characteristic of the sample, suggesting that perceptions of success factors in manager transition should be interpreted predominantly in the context of the Brazilian Southeast. Such unequal distribution prevents robust regional comparisons, as highlighted by Muzzio (2010) and Rezende and Otsuka (2017), who point to the influence of cultural and regional differences on managerial attitudes and performance.

Regarding the function performed in the projects, the sample was composed of 65% of professionals in management positions, including supervisors, coordinators, managers, superintendents, and directors. The remaining 35% were members of technical teams, such as designers, analysts, draftsmen, engineers, architects, and specialists. This sample composition, with a higher participation of managers, may influence the perceptions captured, as different hierarchical levels may have distinct views on the success factors in leadership transition.

Presentation of Results

The success factors in the transition of managers were evaluated through a five-point Likert scale, where 1 indicated very low impact and 5, very high impact. In general, the results showed means concentrated between 3.6 and 4.2, with most medians equal to or greater than 4. This trend indicates a predominantly positive perception of the impact of the evaluated factors on the success of the transition, according to Triola’s (2010) interpretation for Likert scales.

A consistent difference was observed in the evaluations between the groups of respondents. Managers generally assigned higher averages to technical team members for most factors. Furthermore, managers’ responses showed smaller standard deviations, suggesting greater uniformity and consensus in their perceptions of the relevance of these factors for the success of the transition of managers in infrastructure projects. This distinction in perception between the groups is a relevant finding for understanding organizational dynamics.

Among the analyzed factors, the new manager’s competencies during the transition showed the highest averages, both for the technical team (4.13) and for management (4.19), indicating their high relevance. The institutionalization of project management and governance also received high ratings, with averages of 3.94 for the team and 4.10 for management. Project knowledge and documentation management followed this trend, with averages of 3.90 and 3.97, respectively, ranking among the best evaluated.

On the other hand, structured succession and handover planning, institutional articulation capacity, and top management support during the transition showed relatively lower overall averages. Notably, institutional articulation capacity and structured succession and handover planning exhibited the largest discrepancies between groups, with management assigning significantly higher averages (3.94 and 3.87, respectively) compared to the technical team (3.60 and 3.61).

The factors digitalization and the use of BIM as a facilitator of continuity and characteristics of the project team were the only ones in which the technical team attributed slightly higher average scores than management, with 3.72 versus 3.69 and 3.81 versus 3.77, respectively. This inversion, although subtle, suggests that the technical team may have a more direct and positive perception of the impact of these tools and team dynamics on the project’s daily operations and the continuity of activities.

Analysis of Results and Confrontation with Literature

The high proportion of respondents who have already experienced manager transition processes, reaching 90.9%, reinforces the frequency of this phenomenon in infrastructure projects. This data aligns with the scenario of increasing professional mobility in Brazil, as indicated by the Robert Half survey (2025). Such recurrence of manager replacement underscores the importance of analyzing the factors that contribute to the success of this process, mitigating its negative impacts and ensuring the continuity of the ventures.

The interpretation of the results must consider the regional concentration of the sample, composed mostly by professionals working in the Southeast (92%). This characteristic limits the generalization of the findings to other regions of Brazil, as cultural differences and managerial practices can vary significantly (Muzzio, 2010; Rezende and Otsuka, 2017). Thus, perceptions about success factors in the transition of managers are predominantly contextualized by the reality of the Southeast.

The new manager’s skills in the transition play a central role in success, being the best-rated factor by both respondent groups, with high averages and low variation. This result highlights a strong consensus on the relevance of the new manager’s performance for the effective conduct of the transition. Both interpersonal skills, such as communication and negotiation, and managerial skills, such as organizing priorities and decision-making, were recognized as important, with a slight predominance of managerial ones in the results of this study.

This finding partially contrasts with the literature, which tends to emphasize the role of interpersonal skills. Davis et al. (2021) highlight that failures in communication, leadership, and relationships are primary causes for manager replacement and fundamental for rebuilding trust. Parker and Skitmore (2005) also evidence the relevance of the project manager, with 97% of respondents considering them critical for success. However, the complexity and operational demands of infrastructure projects may justify the greater valuation of managerial skills in this context, suggesting that the success of the transition depends on a balanced combination of both skill sets.

The institutionalization of project management and governance stands out as one of the most relevant factors, showing high averages and low variation among respondents. This result highlights a consolidated perception of the importance of structured processes, clear definition of roles and responsibilities, and formal governance mechanisms for an organized transition. Managers assigned slightly higher ratings to this factor, which may indicate this group’s greater proximity to formal governance structures and decision-making processes.

The literature reinforces the role of organizational structures and management processes in conducting infrastructure projects. Hordieieva et al. (2024) point out that the definition of processes, roles, responsibilities, and objectives, as well as the adoption of structured planning and control practices, are central. Davis et al. (2021) highlight that the absence of these structures can lead to project disorganization. Organizational maturity in project management, which integrates formal processes and a culture that promotes empowerment, is fundamental to reducing dependence on specific managers (Karim et al., 2022).

Knowledge management and project documentation are also among the most relevant factors, presenting high averages and low variation, which indicates consensus on the importance of recording and organizing information. However, the analysis of the assertions revealed that project decision documentation is more valued than the existence of structured formal knowledge management mechanisms, such as organized repositories and formal transfer processes. This suggests that the valuation of information does not always translate into the adoption of more structured knowledge management practices.

The literature reinforces the importance of this factor, especially in handover contexts. Davis et al. (2021) highlight that the structured transfer of information, including decisions made, justifications, and project context, is essential for the continuity of activities, and that failures in this process can result in knowledge loss and damages. Souza (2021) complements this by emphasizing that knowledge management in project-based organizations depends on formal processes of creation, storage, and sharing, and that the temporary nature of projects makes knowledge retention difficult without consolidated mechanisms.

Digitalization and the use of BIM appear as elements associated with information organization, presenting intermediate relevance and relatively aligned perception between the team and management. The technical team assigned a slightly higher evaluation, which may be related to the greater contact this group has with the use of digital tools in the daily projects. The analysis of the assertions indicates that the use of digital tools for recording and tracking information is more valued than the adoption of the BIM methodology, suggesting that digitalization for information management already has greater prominence.

This reading is consistent with the literature, which points to a still heterogeneous scenario in the digital transformation process of the sector. The BIM Fórum Brasil (2024) highlights that, although there is progress in the use of digital solutions, there are still relevant limitations regarding the integration and structured use of these tools. The data indicate that 49% of professionals use repositories or collaboration platforms, while 51% still exchange information through digital files or physical media. Furthermore, 32% of professionals do not use formal tools for project planning, relying predominantly on previous experience.

Regarding BIM, a disconnect is observed between perception and practical application: although the methodology is widely recognized as positive, its adoption still occurs in a limited and poorly integrated manner. In this sense, both the literature and the results of this research indicate that digitalization, especially regarding the organization and accessibility of information, already contributes to project continuity, while BIM, as a structured and collaborative approach, is not yet fully consolidated in this context.

The characteristics of the project team showed intermediate relevance, with close averages between the team and management. The team assigned a slightly higher evaluation than management, but with a higher standard deviation, indicating less consensus on the topic. Aspects such as collaboration and professional maturity of the team were evaluated similarly. Although the literature does not directly address team characteristics as a success factor in manager transition, it highlights that manager replacement significantly impacts team dynamics.

Parker and Skitmore (2005) point out that leadership changes are associated with communication failures, loss of focus, increased workload, and reduced cooperation, indicating that the team is directly affected by this process. These effects suggest that team characteristics, such as collaboration level and professional maturity, can influence how the project responds to leadership change. In this sense, the results of this study indicate that teams with a higher level of collaboration and professional maturity tend to deal better with this process, contributing to the project’s continuity.

The capacity for institutional articulation showed moderate relevance and stood out for the greater difference in means between the team and management, being significantly more valued by management. The higher standard deviation among team respondents indicates less consensus on the topic. This difference may be related to the fact that institutional articulation tends to be more present in managerial assignments, involving dialogue with public bodies, regulators, and other external actors to the project.

Pereira and Gomide (2019) do not directly address institutional articulation as a success factor in manager transitions, but they highlight that infrastructure projects in Brazil are developed in a complex institutional environment, characterized by the action of multiple actors and interests. The need for coordination among these agents is crucial to enable project implementation, and the absence of institutional articulation can compromise results. In this sense, although the literature does not directly address manager transitions, its findings indicate that institutional articulation is a relevant element for the viability and continuity of projects.

Structured succession and handover planning has moderate relevance for the success of manager transitions, with averages lower than the best-rated factors, especially from the team’s perspective. However, the difference between management and team evaluations stands out, this being one of the factors with the greatest discrepancy between the groups, with greater appreciation from management, which indicates greater proximity of this topic to managerial duties. The analysis of the assertions indicates that the general idea of transition planning is better evaluated than more specific aspects, such as the definition of formal steps for handover.

The literature emphasizes the need for structuring the handover as an essential part of the transition of managers. Davis et al. (2021) describe this process as composed of steps that include diagnosing the project situation, aligning with stakeholders, and reviewing ongoing actions. Dubber and Pretorius (2016) highlight that the absence of a structured process can result in information loss, communication failures, and deterioration of project performance. The lower valuation of the operational and structured aspects of handover by the respondents, compared to the literature, may explain the lower averages attributed to this factor.

The support from upper management during the transition presented the lowest overall average among the analyzed factors, also being the least well-evaluated by the team. Despite this, the difference between the team and management is relatively small, and the standard deviations indicate a relatively consistent perception among respondents. This result suggests that, although the factor is recognized, it does not receive the same level of emphasis as other elements more directly related to project execution.

The analysis of the assertions indicates that the different aspects of institutional support, such as organizational support and active involvement of upper management, are evaluated similarly, with no relevant variations among them, suggesting a relatively homogeneous perception of the role of this factor in the transition process. The literature, on the other hand, attributes a central role to upper management support in guiding the transition of managers. Davis et al. (2021) highlight that institutional support is fundamental for structuring the handover, including the legitimation of the new manager, the coordinated conduct of the transition, and the creation of an environment conducive to project continuity.

Studies conducted in other South American countries indicate that some of the challenges observed in Brazil also appear in similar contexts. In Ecuador, McDermot et al. (2022) identified problems with planning, estimations, communication with stakeholders, and bureaucracy. In Peru, Cisneros-Herrera et al. (2024) point to difficulties related to planning and public management. These findings show that planning and institutional articulation issues are not exclusive to the Brazilian context, although they may manifest in different ways in each country.

There are also similarities in aspects more related to organization and management. In Chile, Serpell and Rubio (2023) identified limitations in the capacity of construction companies to apply project management in a structured way, highlighting the importance of knowledge, leadership, and teamwork. In a broader analysis of Latin America, Martinez et al. (2025) observed that, despite advances in the use of BIM and other digital technologies, there are still barriers related to data infrastructure, professional qualification, and organizational resistance. Thus, the results of this research seem to be part of a broader regional scenario.

In summary, the results of this study indicate that the success of the transition of managers in infrastructure projects in Brazil is perceived as strongly influenced by factors directly linked to project execution. The new manager’s competencies, the institutionalization of management and governance, and knowledge management and project documentation emerged as the most relevant pillars. Factors such as team characteristics and digitalization and the use of BIM have intermediate relevance, while institutional articulation, structured succession planning, and top management support, although recognized, showed less relative prominence in the professionals’ perception. These findings provide a clear overview of the elements that organizations can prioritize to ensure continuity and performance in a scenario of high professional mobility.

4. Conclusion

The present study aimed to identify the success factors in the transition of managers in infrastructure projects in Brazil. It was found that manager replacement is a recurrent phenomenon, experienced by 90.9% of the surveyed professionals, which underscores the relevance of the topic. The findings indicated that the new manager’s competencies, the institutionalization of project management and governance, and project knowledge and documentation management were perceived as the most relevant factors for the success of the transition. A slight predominance of managerial over interpersonal competencies was observed in the respondents’ perception. Factors such as team characteristics and digitalization and the use of BIM showed intermediate relevance, with digitalization for information organization being more valued than the BIM methodology itself. The capacity for institutional articulation, structured succession planning, and

transfer

, and the support from upper management during the transition were considered of lesser relative importance, especially from the perspective of the technical team, which assigned lower and more variable ratings compared to the managers.

The main contribution of this study lies in offering an overview of the elements that organizations involved in infrastructure projects can prioritize to optimize continuity and performance in scenarios of high professional mobility. It is recommended to focus on developing managers’ competencies, structuring clear governance processes, and organizing project information, as well as integrating project management practices at different hierarchical levels and expanding the use of digital solutions. Limitations include the geographical concentration of the sample in the Southeast region and the higher participation of professionals in management positions, which may influence perceptions. Furthermore, the research was based on respondents’ perceptions, without evaluating the practical application of the factors. It is suggested that future studies explore the practical application of the identified factors, evaluating their relationship with actual project performance, broaden the sample for greater regional and profile diversity, and use qualitative approaches to deepen the understanding of how these factors manifest in practice.

Bibliographic References

Confederação Nacional da Indústria [CNI]. 2025. 72% dos investimentos em infraestrutura em 2025 serão da iniciativa privada, diz estudo da CNI. Portal da Indústria. Disponível em: <https://noticias.portaldaindustria.com.br/noticias/infraestrutura/72-dos-investimentos-em-infraestrutura-em-2025-serao-da-iniciativa-privada-diz-estudo-da-cni/>. Acesso em: 22 out. 2025.

Dubber, R. J.; Pretorius, J. H. C. 2016. Investigating the effects of replacing the project manager during project execution. In: Proceedings of the 2016 IEEE International Conference on Industrial Engineering and Engineering Management, 2016, Bali, Indonesia. Anais… IEEE. Disponível em: <https://doi.org/10.1109/IEEM.2016.7798065>. Acesso em: 22 out. 2025.

Article originating from the Final Course Work of the Specialization in Project Management at POLI USP PRO

To learn more about the course, click here.

You may also like

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated automated file reading, organization of curves into current-potential matrices, generation of potential maps, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed using device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a company in the paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and improve the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used to define and identify the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Project Management

November 19, 2026

Maturity Level in Project Management in a Small Family Business

A study analyzed the project management maturity level of a small family business, operating in the electronic equipment and information technology sectors in Blumenau-SC. The objective was to propose guidelines for the improvement of its organizational processes and the evolution of this maturity level. The research was characterized as a single case study, with a qualiquantitative approach, and used the Project Management Maturity Model (Prado-MMGP). The theoretical foundation addressed the specific challenges of family Micro and Small Enterprises, marked by informality and decision-making centralization. The results indicated a maturity index of 2.0, adhering to Level 2 (Known), revealing low methodological and structural formalization. A paradox was identified: the coexistence of low formal maturity with high project success rates, attributed to the low complexity of the portfolio and the strong involvement of senior management. However, it was found that the current model compromised scalability and future predictability. Based on the diagnosis, a SWOT matrix and a Strategic Plan for Maturity Evolution were developed, with an 18-month horizon, focused on the seven competence dimensions of the Prado model. The plan prioritized low-cost, high-impact actions, seeking to balance formalization and agility, aiming to raise the maturity index to 2.8 and ensure business sustainability in the face of expected growth in the project portfolio.

Keywords: Family Business; Project Management; Project Management Maturity Index; Prado-MMGP Model; Small Businesses.

Project Management

November 19, 2026

Lean Construction Tools in industrial retrofit for conversion into logistics warehouses

An analysis of the application of Lean Construction tools in an industrial retrofit project, aimed at converting an old factory into a logistics warehouse complex in the city of São Paulo, was carried out. The objective was to investigate how these tools could improve planning, operational coordination, production flow control, and project management, facing challenges of multiple work fronts, interdependencies between disciplines, logistical constraints, and pressure for delivery deadlines. The methodology employed a comparative case study, of a mixed nature, between two industrial retrofit projects executed by the same construction company. One of the projects systematically applied tools such as Last Planner System (LPS), Line of Balance, Kanban, Visual Management (5S), and Daily Huddles, while the other served as a reference. Data collection involved direct observation, document analysis, and performance indicators, such as Percent Plan Complete (PPC). The results demonstrated significant improvements in planning reliability, operational coordination, and activity sequencing. A reduction in conflicts between teams and a decrease in the deadlines for critical activities were observed in the project that used Lean tools, compared to the reference project. The application of these tools also strengthened project management practices in areas such as scheduling, communication, quality, and knowledge management. It was concluded that the integrated use of Lean Construction tools increased activity predictability, reduced waste, improved decision-making, and promoted more efficient management in industrial retrofit projects, contributing to the literature on the application of Lean in retrofit projects.

Keywords: Logistics warehouses; Construction management; Lean Construction; Industrial retrofit.

Project Management

November 19, 2026

Earned value management of projects in companies with low data maturity

The monitoring of projects in medium-sized industrial companies with low data maturity represents a significant challenge, as the absence of structured tools compromises decision-making based on indicators. An integrated solution for project monitoring was developed, consisting of a data entry interface in Microsoft Excel and a dashboard in Microsoft Power BI, based on the Earned Value Management methodology. The solution was designed to offer cost, schedule, and operational efficiency indicators without the need to acquire commercial project management software. The research was characterized as a single case study, with an applied approach, conducted in a medium-sized multinational company manufacturing industrial machinery and equipment. Secondary data were extracted from ten projects executed between 2023 and 2026, covering costs, hours, and lifecycle milestone dates. The interface was automated by VBA macros, and the dashboard was organized with a portfolio view and individual project analysis. To objectively estimate physical progress, the weighted milestones technique was adopted. The results demonstrated that the solution generated performance indicators, allowing for the identification of deviations such as actual costs exceeding the approved budget by approximately 76% and delays of up to 118 days, in addition to enabling the monitoring of indicator evolution throughout execution. It was concluded that the solution is replicable as a proof of concept for organizations in similar contexts.

Keywords: Business Intelligence; Performance indicators; Weighted milestones; Small and medium-sized enterprises; Power BI.

Project Management

November 19, 2026

Agile methodologies in academic research project management: bibliometric evidence

The use of agile methodologies has expanded beyond software development, reaching the context of scientific research, characterized by uncertainties, iterativity, and a constant need for adaptation. The research analyzed scientific production related to the application of agile methodologies in academic research project management, identified evidence reported in the selected studies, and proposed a conceptual framework for agile management that integrated elements of Scrum and Kanban, adapted to this context. The methodology was based on a bibliometric study conducted in the Scopus database, which analyzed 72 documents published between 2007 and 2025 using the Bibliometrix (R) package. Complementarily, a qualitative analysis of 22 documents selected after a screening process and full-text availability was conducted. The results indicated a recent growth in publications and a still heterogeneous thematic structure. Among the analyzed studies, needs related to adaptation in the face of scientific uncertainty, collaboration among researchers, transparency of activities, progress monitoring, and knowledge management were identified. Based on this evidence, a conceptual framework for agile management was proposed that integrated elements of Scrum and Kanban, adapted to academic research projects.

Keywords: Bibliometrics; Academic Project Management; Kanban; Agile methodologies; Scrum.