Influence of Communication on Stakeholder Management in Public Works

Gabriel Fernandes Ferrara; Alan Rodrigues

DOI: 10.22167/2675-6528-202603854

Article derived from a Final Course Work (TCC), with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by Instituto Pecege for textual synthesis and organization.

Summary

The study analyzed the influence of communication on stakeholder management in public housing projects of social interest in the city of São Paulo. It was assumed that communication is essential for aligning information, decision-making, conflict prevention, and strengthening relationships between public agencies, management companies, construction companies, and beneficiary communities. The objective was to understand the communication flow and identify flaws and opportunities for improvement. The research adopted a qualitative, exploratory, and descriptive approach, using a case study at the Municipal Housing Secretariat of São Paulo (SEHAB). Data collection was carried out through semi-structured interviews, documentary analysis, and direct observation. For data analysis, pattern matching and narrative analysis techniques were employed. The results indicated that communication had a direct influence on stakeholder management, being fundamental for aligning activities, transparency of information, decision-making, and project development. It was observed that the combined use of formal and informal channels, such as meetings, emails, and messaging applications, contributed to greater communication efficiency. It was concluded that opportunities for improvement were identified in the inclusion of the community in communication processes, the expansion of transparency, and the clearer definition of information flows, reinforcing communication as a determining factor for the success of public works.

Keywords: Organizational Communication; Communications Management; Project Management; Social Housing; Stakeholders.

1. Introduction

Communication is a fundamental element for the success of any organization, even preceding its formation (Pereira, 2017). In an increasingly complex, competitive, and dynamic business environment, effective communication management becomes crucial (Azeredo, 2024), being recognized as a strategic pillar that contributes to information alignment, decision-making, conflict prevention, and strengthening relationships among the various stakeholders involved (Revista Científica Foz, 2024).

Robbins (2005) characterizes the functions of communication in four essential pillars within an organization: control, motivation, emotional expression, and information. All these functions are interconnected and indispensable for good organizational performance (Azeredo, 2024). The exchange of messages in the organizational environment can occur through oral communication, such as lectures and debates; written communication, via memos and emails; non-verbal communication, through body movements; and electronic communication, using information technologies (Robbins, 2005).

For communication to be effective, it must follow a flow, where a message is transmitted from a source or sender to a receiver (Robbins, 2005). Pereira (2017) describes four communication flows: downward, which transmits information from higher hierarchical levels to lower ones; upward, which occurs in the opposite direction; horizontal, which is established between individuals of the same hierarchical level to coordinate activities; and diagonal, which uses alternative channels and can transgress traditional hierarchical chains for greater effectiveness.

In the current context, where interactions between companies and their various publics intensify, it becomes essential to understand how communication shapes relationships with project stakeholders, defined as stakeholders. According to Orth (2009), stakeholders are individuals, groups, or entities that participate in or exert influence over a project, or are impacted by its results, possessing interests that transcend the economic aspect. Stakeholder Management, a theory highlighted by Freeman (1984), focuses on analyzing the interaction of organizations with their environment, identifying all groups of people who can influence or be influenced by their actions.

Stakeholders, or publics of interest, are composed of owners, directors, employees, government, press, and communities. Clarkson (1995) classifies them into primary and secondary, with primary being subdivided into private (shareholders, employees) and public (government, communities). This diversity requires communication strategies to be elaborated with detail and caution, as inadequate communication can compromise the organization’s survival and the quality of relationships (Williams, 2017). Stakeholder analysis involves identifying their interests and power over the organization (Rocha and Goldschmidt, 2010), and a comprehensive communication program must be aligned with the organizational strategy, defining objectives, target audiences, and appropriate means (Kaplan and Norton, 1997).

This work is part of public works projects focused on social housing in the city of São Paulo, addressing social and economic problems that affect the low-income population. The difficulty of access to decent housing leads to the occupation of public areas and the formation of favelas and urban communities, which represent a significant portion of the population in the Metropolitan Region of São Paulo (IBGE, 2023). To mitigate this reality, the government, through agencies such as the São Paulo Municipal Housing Secretariat (SEHAB), carries out social work and the construction of Social Interest Housing (HIS). Stakeholders involved in these projects include SEHAB, management and construction companies, and the beneficiary communities.

The precarious situation of irregular housing, with the absence of basic sanitation, electricity, and limited access to transportation, education, and health, highlights the urgency of interventions. Faced with this scenario, the central problem of the research lies in how communication influences the management of stakeholders in these public works projects, identifying practices, strategies, and mechanisms that favor more efficient dialogue between organizations and their publics. Improving communication between public bodies, their service providers, and the low-income population of São Paulo is fundamental to enhancing social dynamics, quality of life, and promoting socioeconomic and cultural development, contributing to the reduction of social inequality.

In this context, the present study aims to analyze how communication management influences stakeholder management in public works projects, with a focus on ventures aimed at the low-income population.

2. Material and Methods

The research conducted was characterized as qualitative, of an exploratory and descriptive nature, seeking to understand, through the perception of stakeholders, how communication influenced their participation in the project. This approach was chosen because it does not use statistics in data analysis, which means that the measured events studied were not performed, allowing the questions and interests to be defined as the study developed (Godoy, 1995).

As a research strategy, the case study was employed, as advocated by Yin (2015). A detailed investigation was carried out in a public agency in the city of São Paulo, specifically at the Municipal Housing Secretariat (SEHAB). The focus was on improvement services for low-income housing, aiming to identify communication practices among stakeholders and their effectiveness.

For data collection, three main techniques were used: semi-structured interviews, documentary analysis, and direct observation, according to the methodological guidelines of Vergara (2015). The combination of these techniques allowed for data triangulation, enriching the understanding of the phenomenon studied and conferring greater rigor to the research.

The semi-structured interviews were conducted in March 2026, involving a total of 13 participants. Four public servants from the São Paulo Housing Secretariat were interviewed, two from the construction sector and two from the social sector. Additionally, two engineers and two construction supervisors from a construction company, a manager and an engineer from the management company, and three residents from the communities benefiting from the housing projects participated.

Documentary analysis involved access to corporate emails and meeting minutes, which are continuous records of project activities. These documents included technical alignment meeting minutes, social work meeting minutes, management corporate emails, social monitoring reports, and community newsletters and posters. The sources of these documents were SEHAB (construction and social sectors), the management company, the construction company, the social technical team in the field, and local leaders.

The data extracted from the analyzed documents consisted of operational deliberations, physical-financial schedule milestones, site interference resolutions, community meeting records, complaint agendas, eviction deadlines, and temporary relocation. Information was also collected on urgent information exchange, formalization of addenda, delay notifications, supply requisitions, mapping of vulnerable families, service records, and notices of supply interruption or road closures.

Direct observation was carried out *in loco*, allowing for the confrontation between information obtained from documents and interviews. This technique contributed to data validation and to a deeper understanding of the communication flow and interactions among stakeholders in the real project environment, increasing the credibility of the findings.

For the analysis of the collected data, two techniques were employed: *pattern matching* analysis and narrative analysis. The *pattern matching* technique, as elucidated by Yin (2015), consisted of linking a theoretical pattern to an observed pattern, expressed through impressions and field notes, seeking to identify relationships and combinations between them.

The second technique used was narrative analysis, as proposed by Alves and Blikstein (2006). This approach sought to investigate the participants’ human experiences, considering the sociocultural and environmental influences that shape their perceptions. Narrative analysis was achieved through observations, attentive listening, reading, and interpretation of interview texts and documents.

To ensure methodological rigor and transparency in data triangulation (Vergara, 2015), the typology of official documents collected and analyzed in the SEHAB case study was detailed. This approach allowed for the confrontation of data extracted from documents with the discourses obtained in interviews, strengthening the internal validity of the research.

3. Results and Discussion

The results of this research were obtained through an integrated analysis of documents, such as meeting minutes and emails, and field interviews, conducted with representatives of the various groups involved in a public works project. The study focused on the renovation of housing in a housing complex in the northern zone of the city of São Paulo, encompassing the public sector (City Hall), the management company, the construction company, and the local community. The inclusion of varied stakeholder profiles, from individuals with low educational levels to high-level professionals, allowed for a multifaceted analysis, aligned with R. Edward Freeman’s approach, which emphasizes the importance of considering all those involved in the organizational process.

Initially, the research identified that the project’s main target audience was composed of low-income populations, who lack decent housing and are directly impacted by the works. This finding reinforced the social nature of the undertaking and the need for effective communication practices, as highlighted by Williams (2017), who emphasizes organizational communication as essential for achieving institutional objectives. The social worker interviewed corroborated this perception, evidencing that the São Paulo Municipal Housing Secretariat (SEHAB) works to promote housing solutions and better living conditions for families in situations of social vulnerability.

Regarding communication channels, it was found that digital tools, especially WhatsApp, are widely used due to their agility and accessibility, as pointed out by the construction manager of the managing company. However, the research also highlighted the importance of formal channels, such as emails, in-person meetings, and phone calls, for formalizing processes and ensuring a comprehensive understanding of information. This combination of channels reflects the need to adapt communication strategies to the diverse profile of stakeholders, as suggested by Orth (2009) for efficient project management.

The social sector’s technique, responsible for community outreach, highlighted that the most effective initial communication occurs through collective meetings, promoting alignment and clarification from the start of activities. Furthermore, the use of posters, memos, newsletters, and instant messaging applications, such as WhatsApp, contributes significantly to making communication more accessible, rapid, and efficient for the families served. These results demonstrate the importance of integrated communication strategies adapted to the target audience, especially in social projects, corroborating Kunsch’s (2003) understanding of integrated communication as an essential tool for dialogue and relationship building.

Communication was considered an essential element for the project’s success by all respondents, including the construction company’s engineer. The data suggest that communication plays a central role in coordinating activities, decision-making, ensuring safety, and aligning stakeholders. This perception is in line with Kerzner (2017), who identifies effective communication as one of the main critical success factors in projects, integrating processes and minimizing operational failures, and with Robbins (2005), who highlights communication as indispensable for coordination, motivation, information sharing, and decision-making.

The perception of the community benefited by the intervention reinforced the importance of communication. One of the interviewed residents highlighted that communication is fundamental for residents to be constantly informed about the progress of the works, the execution stages, and the possible impacts on their routines. This account highlights the recognition of residents as the main interested parties and those affected by the project, underscoring the need for transparent, continuous, and participatory communication for stakeholder engagement and project success, as advocated by the Project Management Institute (PMI, 2017).

Regarding opportunities for improvement in communication, the interviewed resident suggested the implementation of informative murals, greater transparency about the progress of the works, and greater inclusion of the community in meetings. These findings indicate the need to expand the informational flow and make it more accessible, contributing to the reduction of uncertainties, the strengthening of trust, and the increase of engagement of the involved parties throughout the execution of the works, legitimizing the actions and minimizing resistance to the project.

This perception was corroborated by the City Hall’s construction supervisor, who proposed the implementation of collaborative notice boards, similar to a blackboard, where both the construction team and residents could post announcements and information of common interest. The proposal highlights the importance of participatory communication mechanisms, capable of promoting greater interaction among stakeholders, facilitating information dissemination, and encouraging community involvement in project activities, aligning with Kunsch’s (2003) understanding of integrated and participatory communication.

The need for greater structuring in communication management was also observed, with a clear definition of roles and responsibilities in the informational flow. This organization contributes to the reduction of communication noise and improves alignment among those involved, as defended by Williams (2017), who highlights the importance of clear and structured communication in administration for achieving institutional objectives. The absence of a defined structure can compromise communication effectiveness and generate misalignment of expectations.

The documentary analysis, carried out from corporate emails and meeting minutes, complemented the interview results, detailing the formal communication flow adopted in the project. The analyzed documents showed that communication between the City Hall (public works and social sectors), the management company, and the construction company occurs in an integrated manner. Decisions, schedules, technical alignments, and operational referrals are recorded and shared through these formal instruments, ensuring traceability and transparency in the decision-making process, in accordance with PMI (2017) best practices.

The social sector of the City Hall plays a strategic role as a link between those responsible for project execution and the beneficiary community. The analyzed documents indicated that the information discussed and deliberated in meetings or email exchanges is centralized in this team, which assumes the responsibility of relaying it to residents in a clear and accessible manner. This practice aims to ensure that information is forwarded in advance, allowing families to organize themselves in the face of impacts arising from the works, whether temporary or permanent.

The meeting minutes records also made it possible to identify that the social sector uses different strategies to ensure that information reaches all residents. Among them, periodic in-person meetings in the community for service and clarification of doubts stand out, the use of WhatsApp groups for disseminating announcements and updates on the progress of the works, and door-to-door home visits, especially to serve residents without access to electronic devices or not located through other channels.

The joint analysis of data, from interviews and documents, showed that communication directly influences stakeholder management in public works projects, corroborating the presented literature. Communication is not restricted to information transmission, but acts as a strategic tool to promote alignment, transparency, engagement, and trust among the various actors involved in the undertaking, being a determining factor for the success of public works, especially in projects with a high social impact.

Transparency has emerged as a central element for strengthening trust among stakeholders. The greater the sharing of information about the progress of activities, the higher the level of understanding and acceptance of interventions by the community tends to be. In this sense, communication assumes a strategic function not only to inform but also to legitimize the actions developed and minimize possible resistance to the project, promoting an environment of cooperation between public authorities, contracted companies, technical teams, and the benefited community.

Efficient communication favors stakeholder engagement, facilitating project administration and contributing to more assertive decision-making. Conversely, failures in the communication process can generate noise, misalignment of expectations, resistance from those involved, and difficulties in executing activities. Thus, the quality of communication directly influences project performance and stakeholders’ perception of the interventions carried out, reinforcing the importance of planned and continuous communication practices.

From the integration between the theoretical literature of Freeman (1984), Robbins (2005), and PMI (2017) with the empirical findings, a Theoretical Model of Communication Flow in Public Housing Works was developed. This model synthesizes the architecture of communication flows and highlights the crucial mediating role of the Social Sector. It organizes communication into three interdependent levels, ensuring that information flows effectively and is adapted to the needs of each audience.

The first level of the model is the Institutional and Technical Engineering, which encompasses SEHAB (Works), the Management Company, and the Construction Company. At this level, formal communication, through corporate emails and meeting minutes, ensures traceability and rigor in decisions. These channels are used for operational deliberations, physical-financial schedule milestones, and site interference resolutions, ensuring technical alignment and the handling of construction demands.

The second level is the Strategic and Translator Link, represented by the Social Sector of SEHAB. This level is responsible for translating the technical language of engineering into clear messages suitable for the residents’ profile, in addition to ensuring the timeliness of information. The Social Sector acts as a strategic mediator, facilitating the feedback loop through the ombudsman’s office, clarifying doubts, and mitigating uncertainties, thereby strengthening the population’s trust.

The third level is the Community and Housing Beneficiaries, which uses multiple channels to ensure direct, accessible, and humanized communication. It includes in-person channels, such as social support and collective meetings; digital channels, such as WhatsApp groups and agile newsletters; and inclusive channels, such as home visits and the collaborative whiteboard. This diversity of channels ensures that information reaches all residents, promoting active listening and engagement.

The analysis of empirical findings, in relation to the Technical Alignment and Coordination dimension, revealed that, although minutes and e-mails ensure legal traceability between SEHAB, the management company, and the construction company, technical information did not always reach the resident in an understandable way. The lesson learned is the need to establish formal governance between public and private primary stakeholders, ensuring that schedule milestones are formalized before community handover, guaranteeing clarity and consistency.

In the dimension of Engagement and Uncertainty Reduction, residents perceived communication as a psychosocial relief, and informational failures generated panic about the loss of housing or social rent. The lesson learned is to treat communication with the community as a Critical Success Factor (Kerzner, 2006), understanding that early transparency can transform passive resistance into active collaboration, promoting greater acceptance and participation in the project.

Regarding Mediation and Conflict Prevention, the Social Sector acted as a strategic ‘translator’ and conflict mitigator between the construction engineers and the neighborhood. The lesson learned is to empower the social management team as an integral part of the project structure (PMBOK), integrating engineering schedules with social action plans. This ensures that social concerns are considered from the planning stage, avoiding tensions and promoting a more harmonious work environment.

The dimension of the Hybrid Channels Matrix demonstrated that WhatsApp ensured daily agility, meetings promoted collective alignment, while on-call services and home visits attended to the vulnerable and digitally excluded. The lesson learned is to adopt an integrated (Kunsch, 2003) and multichannel communication strategy, combining digital speed with humanized in-person inclusion. This approach ensures that information is accessible to everyone, regardless of their educational level or access to technology.

Finally, in the dimension of Active Listening and Communicational Innovation, the proposal for a community ‘Collaborative Whiteboard/Bulletin Board’ emerged for bidirectional message recording between the construction site and families. The lesson learned is to create physical and accessible feedback mechanisms (feedback loops) on the construction site itself, institutionalizing continuous active listening. This allows the community’s demands and suggestions to be continuously considered, strengthening participation and trust in the project.

In summary, the results of this research demonstrate that communications management exerts a direct and significant influence on stakeholder management in public housing projects of social interest. Communication goes beyond the mere transmission of information, configuring itself as a strategic tool capable of promoting alignment of expectations, strengthening relationships, reducing conflicts, and expanding the participation of diverse interest groups. The adoption of diversified channels and the mediating role of the social sector are crucial for transparency, credibility, and engagement, elements that directly respond to the objective of understanding the communication flow and identifying opportunities for improvement.

4. Conclusion

This study analyzed how communication management influences stakeholder management in public housing projects of social interest in the city of São Paulo. It was found that communication exerted a direct influence on stakeholder management, being fundamental for the alignment of activities, transparency of information, decision-making, and the development of works. It was observed that the combined use of formal channels, such as emails and meetings, and informal ones, such as messaging applications, contributed to greater communication efficiency. The beneficiary community recognized communication as essential for being informed about the progress of the works and their impacts, which reduced psychosocial uncertainties. Transparency emerged as a central element for strengthening trust, legitimizing actions, and minimizing resistance. It was identified that the social sector played a crucial mediating role, translating technical language and ensuring that information reached the population clearly and in advance.

As a main contribution, a Theoretical Model of Communication Flow in Public Housing Works was developed, which synthesizes the architecture of communication flows and highlights the strategic role of the Social Sector. This model organizes communication into institutional, strategic, and community levels, offering a framework for improving governance and engagement. The research, being a specific case study, has limitations regarding the generalization of findings to other contexts. It is suggested that future studies deepen the analysis of communication management in different public works contexts, with a larger number of participants and stakeholder profiles. It is also recommended to investigate the impact of new digital technologies on community engagement and to evaluate the effectiveness of the integration between documentary, institutional, and community communication in public projects.

Bibliographic References

ALVES, Mário Aquino; BLIKSTEIN, Izidoro. Análise da narrativa. In: GODOI, Christiane Kleinübing; BANDEIRA-DE-MELLO, Rodrigo; SILVA, Anielson Barbosa da (org.). Pesquisa qualitativa em estudos organizacionais: paradigmas, estratégias e métodos. São Paulo: Saraiva, 2006. p. 403-428.

AZEREDO, Ariadne da Silva; FREITAS, Rodrigo Randow de; GOMES, Vanielle Aparecida do Patrocínio. A comunicação interna como pilar estratégico nas organizações. Revista Científica Foz, v. 7, n. 1, 2024.

CLARKSON, Max E. A stakeholder framework for analyzing and evaluating corporate social performance. Academy of Management Review, v. 20, n. 1, p. 92–117, 1995.

FREEMAN, R. Edward. Strategic management: a stakeholder approach. Boston: Pitman, 1984.

GODOY, Arilda Schmidt. Introdução à pesquisa qualitativa e suas possibilidades. Revista de Administração de Empresas, v. 35, n. 2, p. 57-63, mar./abr. 1995.

INSTITUTO BRASILEIRO DE GEOGRAFIA E ESTATÍSTICA (IBGE). Censo Demográfico 2022. Rio de Janeiro: IBGE, 2023. Disponível em:<www.ibge.gov.br>. Acesso em: 06/2026.

KAPLAN, Robert S.; NORTON, David P. A estratégia em ação: balanced scorecard. Rio de Janeiro: Campus, 1997.

KERZNER, Harold. Gestão de projetos: as melhores práticas. 2. ed. Porto Alegre: Bookman, 2006.

KUNSCH, Margarida Maria Krohling. Planejamento de relações públicas na comunicação integrada. 4. ed. São Paulo: Summus, 2003.

ORTH, Afonso I. Planejamento e gerência de projetos. Porto Alegre: EDIPUCRS, 2009.

PEREIRA, Cláudia. Planejamento de comunicação: conceitos, práticas e perspectivas. Curitiba: Intersaberes, 2017.

PROJECT MANAGEMENT INSTITUTE (PMI). Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK). 6. ed. Newtown Square, PA: Project Management Institute, 2017.

ROBBINS, Stephen P. Comportamento organizacional. 11. ed. São Paulo: Pearson Prentice Hall, 2005.

ROCHA, Thelma; GOLDSCHMIDT, Andrea (org.). Gestão dos stakeholders: como gerenciar o relacionamento e a comunicação entre a empresa e seus públicos de interesse. São Paulo: Saraiva, 2010.

VERGARA, Sylvia Constant. Métodos de pesquisa em administração. 6. ed. São Paulo: Atlas, 2015.

WILLIAMS, Chuck. ADM: princípios de administração. 2. ed. São Paulo: Cengage Learning, 2017.

YIN, Robert K. Estudo de caso: planejamento e métodos. 5. ed. Porto Alegre: Bookman, 2015.

Article originating from the Final Course Work of the Specialization in Project Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Project Management

November 19, 2026

Integrated Software for Operational Communication and Control: Practical Evidence in a Medium-Sized Company

The study analyzed the impacts of the lack of integration between commercial and operational modules of an integrated management software (ERP/CRM) in a medium-sized company in the mechanical engineering sector. The main objective was to evaluate practical evidence of communication and operational control optimization, identify bottlenecks, and formulate improvement proposals. A qualitative-quantitative approach was adopted through a single case study with documentary research, based on the extraction and filtering of historical task records from the Bitrix24 software and statistical correlation analysis between workload and allocated team. Based on the diagnosis, an action plan structured in the 5W2H tool was developed. The results revealed that 54.4% of the registered tasks consisted of duplicate, test, or practically useless records, generated by manual insertion during the scope transition between commercial CRM and engineering. It was also demonstrated that the increase in the commercial team linearly accompanied the growth of inefficient tasks, polluting the database and masking the organization’s real productive capacity. It was concluded that the automation of workflows and native integration between modules are essential to mitigate operational and financial risks, providing replicable guidelines for data governance in small and medium-sized enterprises.

Keywords: System Customization; Enterprise Resource Planning (ERP); Task Management; Management Software.

Project Management

November 19, 2026

Supervised learning in voltammetric quantification with electrochemical sensors

The application of supervised learning in the voltammetric quantification of paraquat in artificial urine was evaluated. The study aimed to quantitatively assess the predictive performance of supervised learning models compared to a univariate “baseline”, preserving the independence between devices in the training and testing sets. The research was conducted as an applied case study, processing data from four physical devices, each evaluated under a blank condition and six paraquat concentration levels, totaling 28 square wave voltammetry (SWV) curves. A computational “pipeline” integrated the automated reading of files, the organization of curves into current-potential matrices, the generation of the potential map, and device-specific blank correction. Five approaches were considered: conventional univariate calibration, predictive univariate “baseline”, partial least squares (PLS) regression, support vector regression (SVR), and random forest (RF). Predictive evaluation was performed by device-grouped cross-validation. PLS showed the best predictive performance for curves from a device not used in training, with an R² of 0.7981. RF exhibited intermediate performance, while SVR and the predictive univariate “baseline” showed inferior and similar performance between themselves. It was concluded that a compact multivariate representation of the voltammetric profile was more favorable for inter-device prediction than increasing model flexibility under the studied conditions. Grouped validation preserved independence, but the limited number of devices restricts the generalization of the results.

Keywords: Supervised learning; Paraquat; PLS; Electrochemical sensors; Square wave voltammetry.

Project Management

November 19, 2026

Improvement of Inventory Management via Lean Six Sigma: Study in the Paper Industry

Organizations seek methodologies to reduce waste, increase efficiency, and become more competitive, promoting sustainable improvements in their processes. In this context, the study aimed to apply the Lean Six Sigma methodology, through the DMAIC cycle, to improve inventory management in a paper industry manufacturing pneumatic hoses, aiming to increase the accuracy between physical and systemic inventories and enhance the visual management of parts storage. The research was developed from the collection and analysis of data extracted from the company’s ERP system. Tools such as SIPOC, Ishikawa Diagram, and 5 Whys were used for the definition and identification of the root cause of the problem. As improvement proposals, a Digital Kanban system and an adaptation of the Two-Bin system, called the Three-Bin System, were implemented, in addition to the development of standardized operating procedures and the establishment of control mechanisms. The results demonstrated a significant improvement in inventory accuracy, raising the lowest identified index from 28% to 80%, and detected discrepancies between systemic and physical records equivalent to R$ 134,335.53. It was concluded that the application of Lean Six Sigma, combined with Project Management, represented an effective approach for conducting operational improvement projects, contributed to increased reliability of inventory information, to the improvement of material control processes, and to the strengthening of the organization’s operational management.

Keywords: Inventory accuracy; DMAIC; Visual management.

Project Management

November 19, 2026

Strategic Revitalization as a Vector for Competitive Repositioning in Urban Shopping Centers

The transformation of the shopping center sector, driven by the digitalization of retail and changes in consumer behavior, required the adoption of adaptation and competitive differentiation strategies. This study evaluated how strategic revitalization can act as a vector for competitive repositioning in a medium-sized urban shopping center located in the city of São Paulo. The research was applied in nature, with a quali-quantitative approach, using a single case study complemented by a field survey. The process was structured around the DMAIC cycle, encompassing the Define, Measure, Analyze, Improve, and Control phases. Bibliographic research, document analysis, semi-structured interviews were conducted, and a questionnaire was applied to 19 consumers to measure the perception of attractiveness, experience, and return intention. The results revealed gaps between the perceived and desired positioning, notably in the food court’s location (median 2.5) and the variety of gastronomic options (median 2.7). Revitalization opportunities were identified, focusing on the repositioning of the food court, the review of the tenant mix, and operational modernization. It was concluded that strategic revitalization has the potential to positively impact the development’s attractiveness and competitiveness indicators, provided that the proposed interventions in the Improve and Control phases of the DMAIC cycle are implemented.

Keywords: DMAIC Cycle; Competitive repositioning; Strategic revitalization; Shopping center; Tenant mix.

Project Management

November 19, 2026

Application of Project Practices in the Management of Personal Goals and Life Projects

The application of project management practices in personal life planning is still limited, despite many individual goals possessing project characteristics. This study analyzed the feasibility and relevance of adapting project management practices to personal life planning, focusing on early adulthood, and proposed a practical approach to organize, prioritize, and review individual goals. An exploratory survey was conducted through an electronic questionnaire with 90 participants, and the data were analyzed with the support of bibliographies on project management, portfolio, agile methods, risk management, and personal planning. The results indicated that most respondents defined personal goals but informally tracked them, and a significant portion abandoned important goals due to a lack of organization or planning. A positive receptiveness to applying project management concepts in personal life was observed, especially among participants under 35 years old. It was concluded that the adaptation of these practices is relevant and feasible, considering human and contextual particularities. As a practical contribution, a Personal Portfolio Management Framework was proposed to support the identification, categorization, prioritization, planning, tracking, and continuous review of individual goals.

Keywords: Self-management; Individual Planning; Prioritization.

Project Management

November 19, 2026

Optimization of sequencing in cell and gene therapies: an architecture of predictive and deterministic models

The challenge of production planning and sequencing in autologous cell and gene therapies, with an emphasis on the vein-to-vein cycle of CAR-T therapies, was analyzed. The study aimed to evaluate whether a hybrid architecture, composed of a predictive Machine Learning engine and a deterministic optimization engine, could improve planning robustness in the face of biological variability and GxP environment compliance constraints. To this end, an exploratory literature review guided by PRISMA 2020, validation of the main technical references, and a computational simulation with synthetic data were used. In the simulation, a Random Forest estimated processing times from synthetic biomarkers, and a deterministic model, equivalent to a MILP formulation, solved the batch sequencing on parallel resources with cleaning/setup time. The results indicated that the hybrid policy reduced the weighted average delay penalty to 18.67 penalty points, compared to 21.84 in static MILP and 75.25 in FIFO. It was concluded that the hybrid architecture contributed to optimizing production sequencing, showing favorable performance in extreme scenarios. The findings were interpreted as conceptual validation, not as clinical or industrial proof, due to the use of synthetic data and the influence of factors such as plant layout and real demand flow. The main contribution was to indicate, in a simulated and conceptual way, that the use of predictive estimates improves decision-making compared to deterministic models.

Keywords: CAR-T; Artificial Intelligence; Production Planning; Pharma 4.0; Gene Therapy.