Strategic transformation with implementation of a dedicated contract management cell – Operational Services
Vinicius Paiva Ferreira; Ana Carla Fernandes Gasques
DOI: 10.22167/2675-6528-202604503
Article derived from a Business Case, with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute for textual synthesis and organization.
Summary
A multinational company in the mining sector faced significant challenges in the decentralized management of its 350 operational service contracts, which led to inefficiencies, resource waste, and increased exposure to financial and safety risks. With the objective of centralizing, standardizing, and optimizing contractual governance, a Business Case was developed. The methodology employed consisted of analyzing the current scenario and evaluating management alternatives, culminating in the proposal to create a dedicated cell, structured on the pillars of People, Processes, Technology, Structure, and Culture. The results projected recurring savings exceeding 5% of the total spending in this scope of services, with an estimated investment of R$ 2.5 million over 18 months. Projections indicated a Return on Investment (ROI) of 210% and an approximate payback of 10 months. It was concluded that the initiative represented a strategic evolution of contractual governance, which strengthened the organization’s safety, legal compliance, financial control, and operational sustainability.
Keywords: Business Case; Contract Management; Contract Governance; Cost Optimization; Operational Services.
1. Introduction
A multinational company in the mining sector, with large-scale geographically distributed operations and complex logistics, faced substantial challenges in managing its operational support services. Although these services are peripheral to the core business, they are crucial for operational continuity, directly impacting productivity, safety, and employee experience.
The organization managed approximately 350 facilities services contracts, ranging from food and transportation to maintenance and civil works. This scope involved about 250 direct employees and 15,000 outsourced workers. The decentralized management model, although historically consolidated, resulted in significant operational inefficiencies and resource waste.
The fragmented structure, developed over years of organic growth and acquisitions, led to heterogeneous practices and poorly standardized processes. This lack of standardization limited visibility into supplier performance, making it difficult to capture economies of scale and increasing exposure to financial and security risks. The management of critical contracts for business continuity was particularly impacted.
The scenario diagnosis revealed the presence of waste, duplication of efforts, and failures in financial control. In addition to direct losses, the lack of integration increased exposure to operational risks. In extreme situations, failures in these support services had the potential to paralyze production, with losses estimated at up to R$ 5,000,000 per day.
The central problem lies in the lack of standardization in hiring and management processes across different locations and directorates. This condition generated operational divergences that hindered the adoption of best practices and limited integrated management. Visibility into performance, contractual obligations, and risks was restricted, compromising the effectiveness of supervision and preventive action in the face of deviations.
Fragmentation also negatively impacted cost management, reducing negotiation power and hindering the achievement of economies of scale, which increased the probability of unoptimized spending. Historically, contract management was treated as a complementary activity, consuming about 30% of professionals’ workday, without clear criteria for the appropriate professional profile or training for efficient and strategic management.
Literature reinforces the importance of strategic contract management as a lever for efficiency and cost optimization, overcoming a purely bureaucratic view (Carvalho, 2014). The centralization of procurement, for example, allows for capturing economies of scale and reducing maverick spend, as highlighted by Monczka et al. (2020).
Given this scenario, the justification for this study lies in the urgent need to transform the dispersed operational model into an integrated and strategic management. This transformation aims not only at risk reduction and cost optimization, but also at strengthening business sustainability, improving contractual governance, security, legal compliance, financial control, and employee experience.
Thus, this work proposes the creation of a cell dedicated to the management of operational contracts, based on the pillars of People, Processes, Technology, Structure, and Culture, with the objective of centralizing, standardizing, and optimizing contractual governance.
2. Material and Methods
The present study was characterized as a research of an applied nature, with a descriptive and propositional approach, aiming at the elaboration of a Business Case. The central objective was to analyze the decentralized management model of operational contracts of a multinational company in the mining sector and to propose the creation of a dedicated cell to centralize, standardize, and optimize contractual governance. The research sought to provide subsidies for strategic decision-making, grounding the transformation of the dispersed operational model into an integrated management.
The unit of analysis consisted of the management of approximately 350 operational support service contracts, or facilities, for a multinational company in the mining sector. These contracts ranged from catering and transportation to maintenance and civil works, involving a network of about 15,000 outsourced employees and 250 direct employees. The study focused on the organization’s large-scale, geographically distributed operations and the inherent logistical complexity of the sector.
The first methodological step involved the analysis of the current situation of contract management. To deepen the understanding of the causes and impacts of the identified inefficiencies, the Ishikawa Diagram was used. This instrument allowed for the organization of contributing factors, highlighting the lack of standardized processes and the absence of dedicated managers. The cause analysis was grouped into five main categories: people, processes, technology and data, organizational structure, and culture, according to the identification of structural elements and management challenges.
Next, the identification and evaluation of management alternatives for the observed challenges were carried out. Three distinct approaches were considered: maintaining the current model with specific optimizations, creating a Center of Excellence (CoE) with shared management, and implementing a dedicated cell for contract management. Each alternative was examined for its ability to solve existing problems and generate sustainable value for the organization in the long term.
To support decision-making among the alternatives, a comparative matrix was developed. In this matrix, strategic criteria relevant to the organization were considered, to which an importance weight was assigned on a scale of 1 to 5. The alternatives were evaluated according to their adherence to these requirements, allowing for a weighted score. The criteria included cost optimization, risk reduction, operational efficiency, standardization, employee satisfaction, strategic alignment, scalability, scope, ease of implementation, and initial cost.
The economic-financial evaluation of the proposed solution was carried out through a cost-benefit analysis. This analysis was based on specific assumptions, such as estimated annual expenses in facilities contracts and projections of savings on these expenses. The necessary investment for the implementation of the cell was calculated, distributed among human capital, technology, processes, and governance, and the projected economic benefits, including optimization of contractual costs, productivity gains, and reduction of compliance fines and sanctions. From this data, financial return indicators were projected, such as Return on Investment (ROI) and payback period.
The development of the proposal included the elaboration of a detailed implementation plan for the dedicated cell. This plan was structured in three complementary phases: Planning and Structuring (People), Standardization and Technology (Processes and Technology), and Rollout and Continuous Optimization. Change management, a cross-cutting element of the project, was conceived based on the models of Kotter (1997) and Bridges (2016), aiming for leadership of the transformation and support for the individual transitions of collaborators. Objectives, deadlines, responsibilities, and deliverables were defined for each phase.
The proactive identification of risks and the formalization of mitigation strategies were crucial steps for the project’s success. The main risks considered included employee resistance to change, cultural barriers, transition costs exceeding the budget, inadequacy or failure of the Contract Lifecycle Management (CLM) system, and lack of senior leadership engagement. For each risk, specific strategies were outlined, such as the implementation of the Kotter Model, transparent communication, detailed budgeting with contingency, careful vendor selection, and the formation of a guiding coalition.
The effectiveness evaluation system for the contract management cell, once implemented, was designed to be guided by data integrity and transparency in reporting. Data collection for continuous monitoring would be centralized in the Contract Lifecycle Management (CLM) system, ensuring the traceability and reliability of the extracted information. Key performance indicators (KPIs), both quantitative and qualitative, would be used to measure the continuous alignment between operational execution and the company’s strategic objectives.
3. Results and Discussion
The analysis of operational services contract management in the mining company revealed a scenario of decentralization that generated significant inefficiencies and operational and financial risks. The fragmented structure, consolidated over years of organic growth and acquisitions, resulted in heterogeneous practices and poorly standardized processes, limiting visibility into supplier performance and the ability to capture economies of scale. This model, which involved managing approximately 350 facilities contracts and a workforce of 15,000 outsourced workers, directly impacted productivity, safety, and employee experience, in addition to exposing the organization to substantial financial losses.
The in-depth diagnosis, which included the application of the Ishikawa Diagram, identified the root causes of the problems in five main categories: people, processes, technology and data, organizational structure, and culture. Within the scope of people, the absence of an adequate professional profile and structured training was observed, resulting in reactive management and the allocation of approximately 30% of professionals’ workdays to secondary activities. This condition limited the focus and systematic monitoring of contracts, hindering the proactive identification of risks and opportunities for improvement.
Regarding the processes, the research found the existence of fragmented and redundant practices, which generated waste of time and resources. The lack of standardization in hiring and management processes compromised the consistency of deliveries and the ability to compare performance among suppliers. It was observed that managers dedicated up to ten hours per week to non-standardized routines, and problem-solving occurred 50% slower than in structured models, evidencing low operational efficiency.
The technology and data dimension revealed significant limitations, such as the lack of consolidated visibility over suppliers, which hindered accurate assessments and the effectiveness of penalties. The absence of an integrated database prevented strategic analyses and the systematic identification of optimization opportunities. The reliance on manual controls increased exposure to errors, reinforcing the need for a robust contract management system, such as Contract Lifecycle Management (CLM), to centralize and organize information.
The current organizational structure also presented fragilities, with the non-existence of a unified unit for contract administration. This dispersion favored the overlap of responsibilities, hindered coordination, and reduced the capacity for integrated action, impacting the efficiency of cost control and the loss of opportunities for negotiation at scale. Contract management, not treated as a priority, received limited investments in skills and process evolution, which corroborated Carvalho’s (2014) view on the importance of strategic management.
Culturally, decentralized management had consolidated historical roots, which favored the maintenance of local practices and generated natural resistance to standardization and centralization initiatives. The perception of contract management as an accessory activity contributed to its low institutional valuation, making it difficult to retain specialists and prioritize investments. This organizational inertia limited adaptation to new market demands and the implementation of improvements that could generate relevant gains in efficiency and performance.
The consequences of this scenario were direct and impactful. Estimates indicated that the decentralized model resulted in annual losses due to unoptimized expenses, with a potential saving of over 5% of total service costs if centralization had occurred. Failures in critical contracts, such as transportation, could interrupt mining activities, generating estimated losses of up to R$ 5,000,000 per day. The dispersion of management also increased exposure to regulatory failures and problems in essential services, with the expectation that the implementation of the specialized cell could reduce risk incidents by 20%.
Situation Analysis
The analysis of the current situation confirmed that the lack of standardization in hiring and management processes across different locations and directorates was the origin of the problem. This fragmentation generated operational divergences that hindered the adoption of best practices and limited integrated management. Restricted visibility into performance, obligations, and contractual risks compromised the effectiveness of supervision and preventive action, resulting in delays and rework in problem resolution.
Cost management was directly impacted by the lack of a centralized approach, which reduced negotiation power and hindered the achievement of economies of scale, increasing the probability of unoptimized spending. Contract management was perceived as a complementary activity, consuming a significant portion of professionals’ time without clear criteria for the necessary profile or skills. This view limited the strategic capacity of the function, making it predominantly reactive and less effective in identifying improvement opportunities.
Recommendation
Given the identified challenges, three alternative solutions were evaluated for the management of operational services contracts. The first alternative, “Maintain Current Model with Spot Optimizations,” proposed incremental improvements without altering the decentralized structure. Although it presented lower initial investment and resistance to change, this option did not eliminate the structural causes of fragmentation, maintaining low visibility, limitations in scaled negotiation, and exposure to compliance and security risks.
The second alternative, “Creation of a Center of Excellence (CoE) with Shared Management”, foresaw the centralization of governance, policies, and guidelines, but kept operational execution and oversight under the responsibility of local areas. This option would offer greater standardization and corporate visibility, with moderate transition costs. However, its effectiveness would depend on the prioritization of local teams, and the risk of gains not being fully captured would remain, potentially generating responsibility conflicts.
The third alternative, “Implementation of a Dedicated Contract Management Cell”, was the recommended solution. This proposal involved the creation of an exclusive organizational structure to manage the entire lifecycle of operational services contracts, from technical elaboration to closure. The cell would integrate governance, technical specialization, and execution into a single structure, allowing for strategic and consistent action. The benefits included standardization, strengthening of internal controls, expanded supplier monitoring, efficiency gains, regulatory compliance, risk reduction, and increased negotiation power.
The decision for alternative 3 was based on a comparative matrix that evaluated strategic criteria with relevance weights. Cost optimization and risk reduction, both with a weight of 5, were the most important criteria. Alternative 3 obtained the maximum score in both, with 5 points, while alternative 1 obtained 2 and alternative 2 obtained 3. Operational efficiency and standardization (weight 4) were also better evaluated in alternative 3, with 5 points, compared to 2 and 4 in alternatives 1 and 2, respectively.
The total weighted score of the decision matrix demonstrated the superiority of alternative 3, which achieved 124 points, surpassing alternative 2 (91 points) by 36% and alternative 1 (68 points). This analysis indicated that the dedicated cell was the most consistent option for facing the identified challenges, offering the best balance between operational robustness and financial return. In addition to financial gains, the solution would ensure the retention of critical knowledge and institutional memory regarding contracts, reducing dependence on individual talents in decentralized areas.
The creation of a dedicated cell provides the level of specialization and governance necessary to capture savings greater than 3% on contracted expenses, in addition to reducing the probability of operational failures that could disrupt operations with a daily impact of up to R$ 5 million. The solution also creates the necessary conditions for the effective implementation of improvements in people, processes, and technology, aspects that would be difficult to achieve in decentralized models. The proposal, therefore, positions contract management as a strategic competence, generating value and competitive advantage.
Cost-Benefit Analysis
The economic-financial evaluation of the recommended solution demonstrated that the potential benefits significantly outweigh the necessary investments. The assumptions used for the analysis included estimated annual expenses of R$ 400 million in facilities contracts, with a projected saving of 1.5% in year 1 (stabilization) and 3% from year 2 onwards (full operation). Additionally, a 20% reduction was foreseen in the time dedicated to administrative activities and problem-solving related to contract management.
The total estimated investment for the implementation of the dedicated cell was R$ 2.5 million over 18 months, distributed across human capital (R$ 1 million for a specialist team and training), technology (R$ 1.3 million for a robust Contract Lifecycle Management – CLM system and its integration), and processes and governance (R$ 200 thousand for consulting and change management). These investments were considered essential to establish a solid foundation for the transformation of contractual management.
The projected annual economic benefits, when the unit is in full operation, total R$ 13,750,000. Contractual cost optimization represents R$ 6,000,000 in year 1, focusing on the elimination of undue payments and renegotiations of critical contracts. From year 2 onwards, this amount doubles to R$ 12,000,000, with the full scope of the unit, focusing on the elimination of off-contract purchases and the capture of economies of scale, as Monczka et al. (2020) highlight regarding the centralization of procurement and the reduction of “maverick spend”.
Additionally, productivity gains of R$ 1,250,000 were projected, resulting from process standardization and CLM implementation, which will drastically reduce the time operational areas dedicate to bureaucracy and the resolution of basic billing and scope conflicts. The reduction of compliance fines and sanctions, estimated at R$ 500,000, will stem from centralized management that will ensure rigorous monitoring of legal deadlines, renewals, and regulatory requirements, protecting the company’s institutional image.
The project’s financial return proved attractive, with a projected Return on Investment (ROI) of approximately 210% in the first year after the completion of investments. Even with a six-month grace period for structuring, the project would deliver a return of twice the invested capital already in the first annual cycle, representing R$ 7.75 million in benefits versus R$ 2.5 million in investment. The estimated investment payback period, incorporating initial and ongoing operational costs, would be approximately 10 months, with the break-even point occurring in the tenth month of the project, an extremely positive indicator for the company.
The opportunity cost of postponing this decision was quantified at R$ 1.1 million per month in uncaptured savings after the structuring period. This amount reinforces the urgency of implementing the dedicated cell, as maintaining the current inefficient structure represents a continuous loss of value for the organization. The proposed transformation, therefore, is not just an optimization, but a strategic measure to ensure the long-term sustainability and competitiveness of the business.
Implementation Plan
The implementation of the dedicated cell will be conducted in three complementary phases, structured on the pillars of people, processes, and technology, with change management as a transversal element, based on the models of Kotter (1997) and Bridges (2016). Phase 1, “Planning and Structuring (People)”, lasting six months (Month 1 to Month 6), aims to establish the organizational and human resources base. Deliverables include the formation of the Guiding Coalition, definition of the organizational structure and initial KPIs, recruitment of the core team, development of the training program, and an initial communication and change management plan.
Phase 2, “Standardization and Technology (Processes and Technology)”, lasting eight months (Month 7 to Month 14), aims to redesign and standardize processes and implement the technological platform. Deliverables include the “As-Is” mapping and “To-Be” redesign of contract management workflows, the selection and acquisition/development of the CLM solution, its configuration, parameterization, and integration with legacy systems, the definition of detailed performance indicators, and the training of key users and initial areas to be integrated.
Phase 3, “Rollout and Continuous Optimization”, lasting four months and beyond (Month 15 to Month 18 and ongoing), aims to launch the cell, expand its scope, and ensure continuous improvement and cultural anchoring. Deliverables include the launch of the cell and start of the pilot operation, pilot evaluation and fine-tuning, expansion of scope to other areas and contract types, continuous monitoring of KPIs, regular audits, governance meetings, and continuous communication and change management actions to reinforce the cell’s value in the organizational culture.
Risks and Mitigation Strategies
The implementation of an organizational change of this magnitude involves risks that were proactively identified and for which mitigation strategies have been formalized. Resistance to change by employees, which could lead to slow adoption or refusal of new processes, will be mitigated by the implementation of the Kotter Model, which includes creating a sense of urgency, forming a guiding coalition, continuous communication, empowering and involving stakeholders in the solution design, as well as intensive training and incentive programs.
Cultural barriers, such as the perception of loss of control by local managers and disbelief in a centralized solution, will be addressed through transparent communication focused on mutual benefits (WIIFM – What’s In It For Me), creation of change ambassadors, active leadership from senior management, and demonstration of quick and visible gains. To mitigate the risk of transition costs exceeding the budget, a detailed budget with contingency, rigorous spending monitoring, efficient supplier negotiation, and phased implementation will be used.
The inadequacy or failure of the CLM system, which could generate inefficiency in contract management and user frustration, will be mitigated by a careful selection of the supplier (PoC/pilot), an IT team dedicated to integration, robust testing (UAT), adequate training, and agile technical support. The lack of senior leadership engagement, which could result in a lack of support and loss of project priority, will be combated by forming a powerful guiding coalition, regular progress reports to senior management, linking the project to the company’s strategic goals, and communicating the gains achieved.
Finally, the lack of profile or training of the cell team, which could lead to poor execution of new processes and low performance, will be mitigated by a rigorous recruitment and selection process. Furthermore, a career development and continuous training program, mentoring, and the creation of best practice manuals and guides will be implemented to ensure the team has the necessary competencies for efficient and strategic contract management.
Evaluation
The effectiveness of the Contract Management Cell will be measured through a multidimensional evaluation framework, composed of quantitative and qualitative key performance indicators (KPIs), aiming for continuous alignment between operational execution and strategic objectives. Financial and cost efficiency indicators include spending optimization (Hard Saving), with a target reduction of at least 3% on the baseline of annual facilities spending in the first 24 months of full operation, and cost avoidance, measuring eliminated waste and disputed measurements without contractual basis.
Operational and productivity performance indicators will assess the cell’s agility and delivery capacity. The target for the contracting lifecycle is a 20% reduction in lead time between the negotiation phase and the formal contract signing within the first 12 months. Team efficiency aims for a 20% increase in management capacity per analyst, enabled by workflow standardization and redundancy elimination. Strategic capacity release foresees a 50% reduction in time dedicated to non-standardized administrative routines, allowing the team to focus on critical analyses and performance monitoring.
The governance, compliance, and risk management dimension will assess the legal robustness and regulatory compliance of the operation. The compliance index (Compliance) aims to increase supplier adherence to contractual and normative obligations by 15% within a 12-month cycle. Risk incident mitigation seeks a 20% reduction in occurrences related to security failures and contractual compliance. The reduction of liabilities and litigation aims for a 10% decrease in legal actions and contractual disputes within 18 months, reflecting more balanced contracts and more assertive conflict management.
The data collection methodology and monitoring plan will ensure data integrity and transparency in reporting. Data collection will be centralized in the Contract Lifecycle Management (CLM) system, guaranteeing the traceability and reliability of the extracted information. Governance rituals, such as monthly tactical follow-up forums and quarterly meetings with the executive committee and stakeholders, will be held for course adjustments and accountability. The Management Cell’s coordination will be primarily responsible for consolidating indicators and maintaining the continuous monitoring plan, ensuring that the solution evolves according to the mining company’s strategic demands.
In summary, the research demonstrated that the decentralized management of operational services contracts in the mining company generated significant inefficiencies and risks, with the potential for financial and operational losses. The proposal to create a dedicated cell, structured in people, processes, technology, structure, and culture, emerged as the most strategic and robust solution. Financial projections indicated an investment of R$ 2.5 million with a return on investment of 210% and a payback of 10 months, evidencing the economic viability and the capacity to transform contractual management from a reactive activity into a proactive value center, strengthening the organization’s security, legal compliance, financial control, and operational sustainability.
4. Conclusion
This study aimed to centralize, standardize, and optimize the contractual governance of approximately 350 operational services contracts in a multinational mining company. It was found that the historically consolidated decentralized management model generated significant operational inefficiencies, resource waste, and increased exposure to financial and security risks. In-depth analysis identified the lack of an adequate professional profile and structured training, fragmented and redundant processes, technological and data limitations, a dispersed organizational structure, and a culture resistant to centralization as root causes. Given this scenario, the creation of a dedicated contract management cell was proposed, structured on the pillars of People, Processes, Technology, Structure, and Culture. This initiative represented the study’s main contribution, aiming to transform contract management from a reactive activity into a proactive value center.
The financial projections of the recommended solution indicated a total investment of R$ 2.5 million over 18 months, with estimated annual benefits of R$ 13,750,000 when fully operational. These values resulted in a Return on Investment (ROI) of 210% and a payback of approximately 10 months, demonstrating the economic viability of the proposal. Although the implementation of the dedicated cell demands a robust initial investment and considerable effort in change management to overcome cultural resistance and the perception of loss of autonomy by local areas, the projected financial and operational benefits significantly outweigh these challenges. The proposal, therefore, positions contract management as a strategic competence, strengthening the organization’s security, legal compliance, financial control, and operational sustainability, generating value and competitive advantage in the long term.
Bibliographic References
BRIDGES, William; BRIDGES, Susan. Managing transitions: making the most of change. 4. ed. Boston: Da Capo Press, 2016.
CARVALHO, Luiz Carlos de. Gestão de compras e contratos. 3. ed. São Paulo: Atlas, 2014.
KOTTER, John P. Liderando a mudança. Tradução de Lúcia A. L. Merlino. Rio de Janeiro: Campus, 1997.
MONCZKA, Robert M. et al. Purchasing and supply chain management. 7. ed. Boston: Cengage Learning, 2020.
Article originating from the Final Project of the Specialization in Executive Leadership and Management of the MBA USP/Esalq
To learn more about the course, click here and access the MBX Academy platform