Failures in the contracting process for service provision and impacts on fuel distribution infrastructure projects

Tiago Oliveira dos Santos; Gilmar Martinelli Junior

DOI: 10.22167/2675-6528-202604520

Article derived from a Business Case, with content based on the student’s original work and adapted to the editorial format of the E&S Magazine with the support of the ResumeAI tool, an artificial intelligence solution developed by the Pecege Institute for textual synthesis and organization.

Summary

The procurement process for services in fuel distribution infrastructure projects frequently faces challenges that compromise economic viability. This Business Case aimed to analyze the financial consequences of a unilateral contract termination in a large fuel distribution infrastructure project, located in São Luís/MA, and propose a new supplier selection methodology. To this end, the Business Case methodology was employed, with detailed financial analysis and the use of tools such as the Ishikawa Diagram and the Pareto Diagram to identify root causes. The termination of the tank assembly contract caused significant delays and financial impacts, totaling estimated additional costs of 102 million Reais, a value that exceeded the initial CAPEX and drastically reduced the project’s economic viability. The results indicated that the failures stemmed mainly from an excessive focus on cost in procurement, the absence of in-depth risk analysis, and deficiencies in project management and governance. It was concluded that there is a need to revise the governance of the supplier procurement process, promoting greater integration between areas and implementing more robust technical, financial, and operational evaluation criteria, aiming to mitigate future delays and financial impacts.

Keywords: Service contracting; Fuel distribution; Contractual failures; Project management; Infrastructure.

1. Introduction

The fuel distribution market in Brazil is characterized by a scenario of intense competitiveness among its participants. In this context, the pursuit of proprietary infrastructure, which reduces dependence on commercial contracts with third parties, emerges as a strategic differentiator. The agility in implementing new infrastructure projects and the modernization of existing assets are crucial for business sustainability. For the execution of these ventures, it is common to subcontract specialized companies in various areas, such as civil works, mechanical and electrical assembly, storage tank construction, and automation systems.

The hiring phase of service providers is, therefore, essential for the success of projects. However, there are significant challenges, such as hiring companies with low technical knowledge or limited capacity to manage complex projects, which increases the probability of non-execution or contractual disputes. In some situations, the financial fragility of the hired company can lead to the use of resources from one contract to cover deficits in others, creating an even greater risk scenario. Disputes over deadlines, scope changes, and additional costs directly impact the project, generating unbudgeted expenses and schedule delays. Such variations can compromise the financial viability of the undertaking, especially in markets with well-defined opportunity windows, such as crop exports or oil derivative imports. Thus, the process of hiring partners for infrastructure projects requires a robust structure, with comprehensive risk analysis, which considers not only technical and commercial proposals but also the supplier’s financial health, labor exposure, and delivery history.

A concrete example of these fragilities occurred in a large infrastructure project for fuel distribution, inaugurated in 2020, in São Luís, Maranhão. The venture aimed to reduce dependence on third-party infrastructure for storage and distribution, in addition to expanding the logistical influence area and optimizing the flow of biofuel exports and petroleum derivatives imports to the North, Northeast, and Center-West regions of Brazil. The expectation was to generate a financial benefit of 32 Reais per cubic meter moved, resulting in an annual saving of approximately 15 million Reais.

During the execution of the storage tank assembly, commercial disputes arose related to deadlines, scope, and additional costs. After a negotiation deadlock, the contracted company abandoned the work before the completion of services. This unilateral contract termination caused delays exceeding one year and the need for a new contract, resulting in financial impacts estimated at 102 million Reais, a value that surpassed the initial CAPEX. Consequently, the economic viability originally foreseen for the project was significantly reduced, highlighting weaknesses in the supplier selection, contracting, and monitoring processes.

Given this scenario, this Business Case aims to demonstrate the financial impacts generated by the unilateral termination of a critical equipment supply contract in this project, specifically six storage tanks, and to propose a new supplier selection methodology, focusing on mitigating delays and reducing the financial and reputational exposure of the contracting parties.

2. Material and Methods

This research was configured as a Business Case, with a qualitative and exploratory methodological approach, aiming to analyze a specific event and propose solutions. The study focused on demonstrating the financial impacts arising from a unilateral contract termination and on proposing a new methodology for selecting suppliers for infrastructure projects. The unit of analysis was an infrastructure project for fuel distribution, inaugurated in 2020, located in São Luís, Maranhão.

For data collection, documentary information and internal records related to the infrastructure project in question were used. Documents referring to the initial contracting process, the terms of the contract for the assembly of six storage tanks, records of commercial disputes, and the notification of unilateral termination were consulted. Additionally, financial and budgetary data of the project were analyzed, as well as information on the additional costs incurred after the termination.

The analysis of financial impacts was carried out by quantifying the additional costs generated by the contractual termination. These costs included expenses with third-party warehousing, rework, inflationary corrections, and the new hiring for the completion of the scope. The economic viability of the project was also assessed, considering the financial scenario after the events, to demonstrate the reduction in the initially projected profitability.

To identify the root causes of the problem, quality tools were employed. The Ishikawa Diagram, structured from the 6Ms methodology (Method, Manpower, Machine, Material, Measurement, and Environment), was used to map the factors that contributed to the failures in the hiring process and the impacts on the project. This analysis allowed for a comprehensive understanding of the interrelationships between the various variables involved.

Complementarily, the Pareto Diagram was used, adapted for a qualitative analysis of the causes identified in the Ishikawa Diagram. This procedure aimed to prioritize the factors with the greatest impact on the project’s outcome, focusing on the inadequate definition of scope, insufficient treatment of contractual risks, and limited evaluation of the contracted company’s technical and financial capacity.

The evaluation of the supplier selection process was carried out by analyzing the delivery history of competing companies (denominated A, B, and C) in relevant infrastructure projects, between the years 2015 and 2021. The financial and economic situation of the companies was also considered, using an external commercial approval process, denominated “G-CERTIFICA”, which performed a scan of credit protection, judicial, and banking systems.

The proposition of the new supplier selection methodology was based on the review of the contracting process governance. Five main dimensions were defined for the weighted evaluation of suppliers: price (30%), technical capacity (30%), financial health (15%), delivery history (20%), and management and security aspects (5%). A minimum acceptable score of 7.5 was established, classifying contracts as low, medium, or high risk.

The new methodology included the development of a risk matrix, correlating the supplier’s final evaluation score with a risk rating. Additionally, a review of CAPEX management was proposed, with the inclusion of a minimum contingency of 5% and annual monetary correction linked to indices such as the National Construction Cost Index (INCC) for labor and materials.

For contract monitoring, the proposed methodology included the definition of objective contractual milestones, continuous performance monitoring (deadline, cost, and quality), implementation of penalty and incentive clauses, and the establishment of contingency plans for supplier replacement. The implementation of the methodology was planned in stages, with a timeline that involved the review of the Integrated Management System (SIG), development of the risk matrix, pilot implementation, adjustments, and rollout.

The evaluation of the proposals’ effectiveness was outlined through the monitoring of new contracts that used the methodology. For this purpose, monitoring indicators, metrics, and follow-up frequencies were defined, covering aspects such as contract terminations, schedule adherence, budget control, contract amendments, disputes with suppliers, and delivery of the contracted scope.

3. Results and Discussion

The analysis of the results revealed that the unilateral termination of the tank assembly contract in the infrastructure project in São Luís/MA generated substantial financial impacts and severely compromised the economic viability of the undertaking. The total additional cost, directly attributable to the termination, was estimated at 102 million Reais, a value that exceeded the project’s initial CAPEX. This amount was composed of several categories of unexpected expenses, which accumulated due to the interruption of services and the need for a new contracting to complete the original scope.

The additional costs were detailed, highlighting the complexity and magnitude of the impact. Third-party warehousing represented the largest portion, with 56 million Reais for the first period and 16 million Reais for a second period. The renewal of the third-party warehousing contract, under new conditions, added 14 million Reais, and the new hiring of the company to finalize the assembly of the tanks implied an additional 12 million Reais. Expenses with quality tests and corrections, along with the inflationary adjustment of the project, totaled 2 million Reais each, summing up to the 102 million Reais of direct financial impact.

The economic viability of the project was drastically affected by these unexpected costs. A comparison between the 2021 scenario and the projection for 2025, after the termination, showed a significant deterioration. The company’s cost of capital increased from 8.50% to 11.80%, reflecting the macroeconomic scenario and the company’s financial health, impacted by problems in other projects. CAPEX, which was R$ 98,545 thousand, rose to R$ 114,546 thousand, and the Net Present Value (NPV) went from a positive R$ 111,515 thousand to a negative R$ -54,608 thousand.

The project’s Internal Rate of Return (IRR), a crucial attractiveness indicator, plummeted from 19.0% to 7.0%, while the Payout, which measures investment payback time, doubled from seven to fourteen years. Although the average EBITDA remained at high levels (R$ 41,295 thousand in 2021 and R$ 27,028 thousand in 2025), the significant reduction in IRR and NPV is a direct reflection of the project’s additional expenditures, not a decrease in volume projections or market growth in the region, confirming the commitment to profitability.

To identify the root causes of the project’s loss of viability, the Ishikawa Diagram was used, structured from the 6Ms methodology (Method, Manpower, Machine, Material, Measurement, and Milieu). This analysis revealed that the main factor was the failure in the initial hiring process, which excessively prioritized price over other critical variables. The cost-focused selection, the absence of an in-depth risk analysis, and optimistic planning were central elements in the “Method” category, contributing to the fragility of the supplier choice.

In the “Labor” category, the hired company’s low technical capacity, lack of experience in the sector, and poor communication were identified as relevant factors. In “Machinery,” limited assembly structure, inadequate equipment mobilization, and lack of quality in deliveries were pointed out. “Material” included variations in input costs and supply delays. In “Measurement,” the absence of KPIs for the supplier, insufficient schedule monitoring, and delays in developing solutions to minimize the impact of abandonment were crucial. Finally, “Environment” highlighted lengthy licensing processes and logistical and market dependence as external factors.

The analysis of the initial hiring process, which involved companies A, B, and C, demonstrated that company B, despite presenting the best price after several negotiation rounds, had a less robust profile in terms of quality and history in similar projects. The difference of over 5 million Reais between the proposals of company B and the others could not be absorbed by the project, which did not have approved contingency and had an incomplete budgetary scenario. This decision, focused on cost, ignored available information about the company’s history, which already indicated addendums in previous projects due to lack of management.

The commercial approval process, named “G-CERTIFICA”, although useful for mitigating commercial and financial risks, proved insufficient. It performed a scan of credit protection, judicial, and banking systems, but did not include issues related to the reputation of previous contracts or the delivery capacity of the analyzed company. This gap allowed a company with a history of weaknesses to be hired, directly contributing to the contract termination and subsequent financial impacts, as the risk analysis was not deep enough to consider scenarios of abandonment.

The project management also presented significant failures. Despite the available data, management did not propose hiring a second supplier considering the technical risks involved. During execution, it became evident that company B was unable to finalize the project, with the schedule detached from reality and non-compliance with safety and quality standards. The action plans for schedule recovery, reported to senior management, were not fulfilled, demonstrating ineffective management and a lack of adequate corrective measures.

After the abandonment of company B, the problem mitigation process was slow and ineffective. Although other project activities proceeded, the third-party warehousing and operation contracts were renewed at much higher values, due to the increased demand for space in the region. This resulted in the profit margin of the business in the region being almost zeroed out. The delay of more than a year to approve a “provisional” project that would allow the loading of Diesel B, using part of the new structure, further aggravated the dependence on third parties and the additional costs.

The application of the Pareto Diagram, modified to qualitatively analyze the causes identified in Ishikawa, reinforced that the critical factors for the project’s negative outcome were the inadequate definition of scope, insufficient treatment of contractual risks, and limited assessment of the contractor’s technical and financial capacity. The inadequate definition of scope represented 16% of occurrences, followed by insufficiently treated contractual risks with 11% and insufficient assessment of the contractor with 9%. Fragile contractual clauses and failures in management and monitoring also carried significant weight.

These Pareto data indicate that prioritizing actions aimed at improving selection criteria, risk analysis, and supplier monitoring has a high potential to significantly reduce the probability of similar problems occurring in future infrastructure projects. The concentration of root causes in the contracting and initial management processes underscores the need for a comprehensive review of current practices to avoid repeating scenarios with high financial and operational impact.

Given the identified failures, a complete review of the supplier evaluation and contracting process is proposed, focusing on a more robust technical and commercial analysis that goes beyond cost. The integration of this new methodology into the Integrated Management System (SIG) is recommended, specifically in the item related to third-party management, with the definition of evaluation tools and a new risk matrix, establishing a minimum compliance score for suppliers.

The proposed model considers five main dimensions in supplier evaluation: price (30%), technical capacity (30%), financial health (15%), delivery history (20%), and management and safety aspects (5%). This spreadsheet should be filled out by multidisciplinary teams, including procurement (commercial items), legal, engineering (technical), and EHS (environmental, health, and safety, and compliance with regulations). The weighted average of these items will result in a final “score”, which will be correlated with a risk classification (low, medium, high, or very high).

Scores between 5 and 7 will be classified as “high or very high risk”, between 7 and 7.5 as “medium risk”, and above 7.5 as “low or very low risk”, with 7.5 being the minimum admissible score. This approach aims to ensure that technical and commercial criteria, which carry greater weight, are rigorously followed. If a company with the best commercial proposal presents a “high or very high risk” result, with a score below 7.5, the hiring may only be approved with the endorsement of a higher hierarchical level (N+1) and will require a robust action plan to be monitored monthly.

The review of CAPEX management is equally crucial. During project approval, no provision is made for contingency or annual monetary correction, which causes the initial value to fall behind due to inflation. It is suggested that projects have annual correction linked to indices such as INCC (National Construction Cost Index) for labor and materials, in addition to a minimum contingency of 5% incorporated into the approved value. This would ensure that the initial budget is more realistic and resilient to market variations.

To strengthen contractual management, it is recommended to define contractual milestones with objective measurement criteria, continuous performance monitoring (deadline, cost, and quality), implementation of penalty clauses and performance incentives, and the establishment of contingency plans for supplier replacement. These measures would allow for faster identification of deviations, preventive action, and, in case of abandonment, a considerable reduction in impacts. The implementation of these tools does not require high investments, as many are already available and only need occasional adjustments and integration between the supply and engineering areas.

The implementation of the recommendations can be done gradually, allowing for adjustments and continuous improvement. An implementation schedule suggests steps such as the review of SIGO (9 months, 50 thousand Reais), development of the risk matrix (3 months, 15 thousand Reais), pilot implementation and monitoring (6 months, 20 thousand Reais), adjustments and final review (9 months, 5 thousand Reais), and rollout (10 months, 10 thousand Reais). The total estimated cost for these internal process reviews is 100 thousand Reais, an investment that would be justified by the mitigation of budgetary additions in the millions of Reais, already absorbed in the first large budget project.

The effectiveness of the proposals will be evaluated by monitoring the new contracts that use the methodology. The main points of analysis will include compliance with the schedule, the supplementation or amendment of the original request resulting from scope changes, and the full compliance with the contracted scope. Specific indicators were defined for monitoring, such as the number of contract terminations (target reduction of 90%), the percentage of milestones delivered on time (target of 90%), the variation between planned and actual budget (maximum deviation of 5%), the quantity of contract amendments (reduction of 50%), the number of disputes with suppliers (zero disputes), and the percentage of scope executed according to the contract (95%).

In summary, the results showed that unilateral contract termination, driven by a flawed procurement process and deficient project management, resulted in a financial impact of 102 million Reais and significantly compromised the economic viability of the undertaking. Root cause analysis, using tools such as Ishikawa and Pareto, pointed to excessive cost prioritization, lack of risk analysis, and inadequate supplier evaluation. The proposed methodology, which includes a new risk matrix and a review of CAPEX procurement and management governance, aims to mitigate future delays and financial impacts, ensuring greater predictability and robustness in the execution of infrastructure projects.

4. Conclusion

The study sought to analyze the financial consequences of a unilateral contract termination in a fuel distribution infrastructure project and to propose a new methodology for supplier selection. It was found that the termination of the tank assembly contract resulted in a financial impact of 102 million Reais, exceeding the initial CAPEX and drastically compromising the economic viability of the undertaking. Root cause analysis, using tools such as the Ishikawa Diagram and the Pareto Diagram, identified that the failures stemmed mainly from excessive focus on cost during contracting, the absence of in-depth risk analysis, and deficiencies in project management and governance. It was observed that prioritizing the lowest price, without due technical evaluation and review of the supplier’s history, led to the contracting of a company with limited capacity, resulting in significant delays and additional costs.

Given this scenario, the study’s main contribution lies in proposing a new supplier selection methodology that integrates technical, financial, operational, and management criteria, in addition to price, to mitigate future delays and financial impacts. This methodology, to be incorporated into the Integrated Management System, establishes a risk matrix and a minimum performance score, requiring multidisciplinary evaluation and robust action plans for high-risk contracts. Additionally, a review of CAPEX management was suggested, including annual contingency and monetary correction, and strengthening contractual management through objective milestones and continuous monitoring. Although the proposed methodology significantly reduces the probability of similar problems occurring, it does not entirely eliminate the risks inherent in infrastructure projects, especially those related to external and macroeconomic factors. The effectiveness of these proposals can be evaluated by monitoring new contracts that use the methodology, tracking schedule adherence and the reduction of amendments and litigation.

Bibliographic References

BANCO SAFRA. 2025. Raizen, reestruturação já mostra resultados, mas alavancagem ainda preocupa. Disponível em https://oespecialista.safra.com.br/wp-content/uploads/2025/10/PROSPECT-32630.pdf. Acesso em 11 de Dezembro 2025.

COSO – Gerenciamento de riscos corporativos – integrado com estratégia e performance – Sumário Executivo – 2017 Disponível em https://repositorio.cgu.gov.br/handle/1/74040. Acesso em 28 de Março 2026.

DESAI, Mihir A. Finanças… Simples Assim! Rio de Janeiro: Editora Alta Books, 2020. E-book. p.51. ISBN 9788550816999. Disponível em https://app.minhabiblioteca.com.br/reader/books/9788550816999/. Acesso em 11 de Dezembro 2025.

PORTO DO ITAQUI. Dados de infraestrutura Disponível em https://www.portodoitaqui.com/porto-do-itaqui/infraestrutura. Acesso em 27 de Março 2026.

RAIZEN S.A. 2025. Informações Contábeis intermediárias em 30 de Setembro 25 e relatório do auditor independente. Disponível em <https://api.mziq.com/mzfilemanager/v2/d/c016735f-1711-48ce-919f-a8c701b83c19/40815feb-690f-231a-2b46-0aa4462cfc4d?origin=1>. Acesso em 09 de Dezembro 2025.

Article originating from the Final Project of the Specialization in Executive Leadership and Management of the MBA USP/Esalq

To learn more about the course, click here and access the MBX Academy platform

You may also like

Executive Mba In Leadership And Management

November 26, 2026

Development of a digital platform for estate and succession planning

This Business Case proposed the development of a digital platform for estate and succession planning for Brazilian families, focusing on the impacts of ITCMD (State Tax on the Transfer of Property by Death) and income and wealth taxation. A growing demand was identified for technical and updatable solutions in a complex and burdensome regulatory context. The objective was to propose and analyze the viability of a B2B2C platform that would allow estate planning professionals, family offices, insurance companies, and private banks to offer an integrated journey of diagnosis, structure design, tax simulation, and family monitoring. To this end, an analysis of the situation, recommendation of the solution, and qualitative evaluation of costs, benefits, and risks were elaborated. The platform integrated artificial intelligence for document structuring, jurisprudence summarization, ITCMD calculation parameterization, and regulatory alerts. The results projected total revenue of R$ 188.3 million in the fifth year and R$ 242.0 million in the tenth year, with annual recurring revenue (ARR) of R$ 47.9 million and R$ 99.0 million, respectively. The base of recurring subscribers reached 88,629 families in the fifth year and 189,601 in the tenth. It was concluded that the implementation of the platform constitutes an alternative compliant with the regulatory environment, with the potential to consolidate itself as a reference technological infrastructure and promote a reaculturation around intergenerational succession planning in Brazil.

Keywords: Artificial intelligence; ITCMD; Estate planning; Digital platform; Succession.

Executive Mba In Leadership And Management

November 26, 2026

Digital transformation as a strategy for modernizing legacy systems

A study analyzed digital transformation as a strategy for modernizing legacy systems at Catering Fly High, a company operating in the airline catering sector. The objective was to enhance the customer service experience and improve the company’s commercial performance through the digitalization, automation, and integration of all departments. To achieve this, diagnostic tools such as the 5 Whys technique and the Ishikawa Diagram were used to identify the causes of productive inefficiency. Subsequently, a comparative analysis of three technological solutions available in the market was conducted. The results revealed that the inefficiency was caused by fragmented legacy systems, lack of integration, and manual processes. The phased implementation of the Inflightor system was proposed, an intermediate solution chosen for its cost viability, aiming to meet the most urgent operational demands. This approach included four stages, with an estimated total duration of 20 months, focusing on version equalization, system unification, new developments, and replication with training. It was concluded that digital transformation, even if partial and gradual, is essential to drive innovation, strengthen competitiveness, and ensure long-term organizational sustainability, with projections of improvement in operational efficiency, cost reduction, and optimization of customer response time.

Keywords: Airline catering; Operational efficiency; Modernization; Legacy systems; Digital transformation.

Executive Mba In Leadership And Management

November 26, 2026

Elastic capacity and productive “bench” in software consultancies

A medium-sized software consultancy was facing unproductive employee idle time and systematic margin erosion in digital transformation projects, a common challenge for the sector, but intensified by internal management practices. The study aimed to evaluate and propose an integrated set of operational and managerial practices to mitigate these losses, preserve organizational readiness, and increase realized margin. The analysis, conducted with Human Resources, Operations, and the Sales team, identified that 15% to 25% of the staff remained “on the bench” for 1 to 2 months and that the quoted margin eroded between 5 and 10 percentage points. The 5 Whys Technique and the Ishikawa Diagram revealed root causes such as lack of capacity planning, lack of estimation standardization, incomplete “handover,” and deficient scope change governance. An integrated capacity management model was proposed, including scope standardization, change governance, structured “handover,” capacity planning, productive “bench” with retraining, “flexi staffing,” and an internal “marketplace.” The first-year costs were estimated at R$ 591 thousand, with projected annual benefits of R$ 3.1 million and an investment return in about seven months. It was concluded that implementing the model is the most advantageous decision, converting idle time into organizational capacity and a source of competitive advantage.

Keywords: Productive bench; Elastic capacity; Software consultancy; Capacity management; Digital transformation.

Executive Mba In Leadership And Management

November 26, 2026

Obstacles to access and quality of cervical cancer treatment in Brazilian health institutions

Cervical cancer represents a public health problem in Brazil, characterized by high incidence and mortality, which motivated the search for improvements in treatment and access to advanced practices. This study aimed to analyze the feasibility of implementing image-guided adaptive brachytherapy (IGABT) in public and philanthropic hospitals of the Unified Health System (SUS). A critical analysis of the structural, financial, and operational barriers that limit access to advanced treatments was carried out, based on clinical evidence from the EMBRACE protocol and the reality of the Brazilian health system. It was identified that, although modern methods such as IGABT show superior results, their adoption in the SUS was restricted by inadequate infrastructure, lack of qualified professionals, logistical barriers, and underfunding. The initial costs for implementation were considered high, mainly due to equipment and tax burden, with insufficient public reimbursements to cover the actual expenses. It was concluded that the structured implementation of IGABT, aligned with scientific evidence, is a strategic opportunity to improve disease control, increase survival, reduce complications, and optimize the efficiency of the health system, despite the financial challenges. The adoption of this technology requires the engagement of managers, review of financing policies, and professional training to ensure concrete benefits for Brazilian patients.

Keywords: Health access; Brachytherapy; Cervical cancer; Public health; Unified Health System.

Executive Mba In Leadership And Management

November 26, 2026

Integrated System of Living Curricula for Internal Career Evolution

This study analyzed the challenges in managing internal mobility and talent development in a financial institution. The objective was to identify the misalignment between competencies and business demands, proposing a solution to optimize human capital allocation. The methodology employed a hybrid approach, combining qualitative analyses, based on organizational observation and internal process evaluation, with quantitative analyses, using indicators such as turnover rate, hiring cost, and time to fill vacancies. The Pareto Diagram and the comparison between the current and proposed scenarios were also used. It was identified that system fragmentation, outdated resumes, and low visibility of opportunities resulted in a high turnover rate and elevated costs. As a solution, the implementation of TalentHub S.A. was proposed, an integrated live resume platform. This platform aims to automatically update competencies, integrate performance and career data, and perform intelligent matching between professional profiles and vacancies, with an estimated investment between R$ 4 million and R$ 6 million. The solution is expected to reduce external hiring by up to 30%, decrease turnover, increase productivity, and promote a culture of continuous development and meritocracy, redefining talent management based on data.

Keywords: Live resumes; Talent management; Internal mobility; Internal recruitment; Human resources.

Executive Mba In Leadership And Management

November 26, 2026

Governance and risk management for value creation and mitigation of reputational impacts

The Business Case analyzed the challenges of reputational risk management in a large organization in the integrated services segment, whose growth strategy through expansion and acquisitions had increased operational complexity and risk exposure. The diagnosis identified vulnerabilities in process standardization, operational traceability, inter-departmental integration, and risk monitoring, compromising efficiency and value generation. The objective was to propose the implementation of an integrated Governance, Risk, and Compliance (GRC) model, aiming to transform reactive management into a data-driven, preventive approach for sustainable value generation. The methodology employed a diagnosis of the current situation, identification of structural causes, vulnerability analysis, strategic assessment, and the SARIE methodology to structure the proposal. The main result projected a reduction in non-conformities, complaints, rework, legal liabilities, and contractual penalties, in addition to an increase in operational efficiency, process predictability, and strengthening of the ESG agenda. It was concluded that the implementation of the GRC model represents a viable strategic investment, capable of mitigating risks, strengthening corporate governance, and ensuring the organization’s sustainable growth.

Keywords: Compliance; Governance; Risk management; Reputation; Integrated services.

Executive Mba In Leadership And Management

November 26, 2026

Inclusion as a Competitive Differential: Guide for Hiring and Valuing People with Disabilities and Neurodivergents

This business case addressed the critical gap in the Brazilian labor market regarding the inclusion of neurodivergent individuals and People with Disabilities (PwDs). Its objective was to propose an innovative Corporate Inclusion Manual to structure and optimize the processes of attraction, hiring, and long-term retention of these professionals. The methodology involved identifying the root causes of low inclusion effectiveness through the Ishikawa Diagram (6M) and structuring a solution based on three pillars: review of selection processes, physical and sensory adaptation of the work environment, and continuous leadership training. The implementation plan comprised diagnosis, manual development, leadership training, and continuous support, with investments in specialized consulting, assistive technologies, and ergonomic adjustments. The projected results indicated that the manual would not only ensure ethical and legal compliance but also increase team productivity by up to 30% and drive disruptive innovation. It was estimated that professionals on the autism spectrum could be up to 48% faster in technical tasks, contributing to a 36% higher probability of profitability in diverse teams. It was concluded that the implementation of the manual represents a strategic investment that transforms inclusion from mere bureaucratic compliance into a competitive advantage, strengthening the employer brand and aligning with global ESG best practices.

Keywords: Inclusion; Neurodiversity; People with Disabilities; Productivity; Recruitment.

Executive Mba In Leadership And Management

November 26, 2026

Productivity through improved resource and time management

A pharmaceutical company in the interior of São Paulo was facing a reduction in employee productivity due to cognitive overload. The objective was to improve productivity by minimizing rework and freeing up cognitive effort for strategic activities. A perception analysis of professionals was conducted through a structured questionnaire, applied to 53 employees. It was identified that informational overload and excessive interruptions were the factors with the greatest influence on the loss of efficiency and the increase in rework. Based on this diagnosis, a pilot project was proposed in the Supply Chain area, focused on improving information organization, activity management, and the use of existing resources. Recommendations included the development of guidance materials, expert follow-up, and evaluation of organizational adjustments. The project demonstrated potential to reduce rework, increase operational efficiency, improve information retrieval and sharing, and strengthen employee autonomy, without the need for new technologies. It was concluded that the progressive implementation of the proposed initiatives represents a consistent opportunity to enhance productivity and strengthen organizational efficiency, aligning with the identified needs and the institution’s strategic objectives.

Keywords: Information management; Time management; Productivity; Rework; Cognitive overload.